The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Polk County (FY 2022)

CCSJ: 0176-04-056

District:LUFKINLet Date:May 2022
Highway:US 59Let Status:Tentative
Project ID:NH 2013(222)CSJ:0176-04-056
Description:HIGHWAY IMPROVEMENTHandling
Code:
 
Limits From:3.4 MI N OF US 287Fund Cat:11
Limits To:US 287ESTIMATE:$93,500,000
Length:3.8Actual$0
 
District:LUFKINLet Date:May 2022
Highway:US 59Let Status:Tentative
Project ID:NH 2013(221)CSJ:0176-05-104
Description:HIGHWAY IMPROVEMENTHandling
Code:
 
Limits From:US 287Fund Cat:11
Limits To:3.0 MI S OF US 287ESTIMATE:$69,600,001
Length:3.3Actual$0
 
Back...
Totals for 0176-04-056
Length:7.1
Estimate:$163,100,001
Actual:

CCSJ: 0911-04-089

District:LUFKINLet Date:Jun 2022
Highway:CRLet Status:Tentative
Project ID:BR 2B20(098)CSJ:0911-04-089
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:KELLEY RD AT BLUFF CREEKFund Cat:6
Limits To:.ESTIMATE:$675,000
Length:0.0Actual$0
 
Back...
Totals for 0911-04-089
Length:0
Estimate:$675,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let