Monthly State Let Construction Report For San Antonio District As Of Jul 11, 2014 Page 2 Of 5

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGUADALUPE
Highway FM 78
From SANTA CLARA CREEK, WEST OF MARION
To SANTA CLARA CREEK, EAST OF MARION
CSJ 0025-10-073
Proj ID STP 2013(348)
Work Type GRAD, STRS, BASE & SURF
 
1.080 4136146.75 167912.45 1156666.54 27.9
Work Order 07-16-13
Work Began 11-11-13
Work Completed  
Time Computed 11-11-13
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 17
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-073
FLASHER EQUIPMENT COMPANY(0.31%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (2.51%)
E-Z BEL CONSTRUCTION, LLC(1.02%)
MURRAY CONSTRUCTION(0.53%)
RICE ENVIRONMENTAL SERVICES(0.56%)
C & C ALCOSER TRUCKING (0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.53%)
VEGETATION MANAGEMENT SERVICES, LLC(0.00%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.00%)
Contract # 01133220
Totals 4136146.75 167912.45 1156666.54 27.9

CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-059
Proj ID IM 4104(382)
Work Type SC, STRIPING, BASE
 
7.406 18426875.59 0.00 0.00 0.0
CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-065
Proj ID RW 72-7-65
Work Type ADJUSTMENT OF UTILITIES
 
7.406 915396.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 376
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143204
Totals 19342271.59 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From FM 3351 (RALPH FAIR RD)
To BOERNE STAGE RD
CSJ 0072-07-060
Proj ID C 72-7-60
Work Type GRAD, BS, STR, PVMT MRKG
 
0.871 6345951.80 408048.64 2199888.97 34.6
Work Order 08-06-13
Work Began 03-24-14
Work Completed  
Time Computed 08-22-13
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 15
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-060
J.D. RAMMING PAVING CO., LTD.( 15.45%)
SIEMENS INDUSTRY, INC. (3.77%)
PRESIDIO CONTRACTING, LLC(2.35%)
FARR FOUNDATION, INC.(2.29%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.90%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.44%)
D GUERRA CONSTRUCTION, LLC (1.68%)
FLASHER EQUIPMENT COMPANY(1.19%)
VOGES DRILLING CO. (1.20%)
A-Z REBAR CONTRACTOR (0.37%)
SCOTT DERR PAINTING CO (0.08%)
STAR OPERATIONS, INC.(4.42%)
TEXAS HIGHWAY WALLS(5.43%)
PENNTEX MILLING INC. (0.60%)
Contract # 06133205
Totals 6345951.80 408048.64 2199888.97 34.6

CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-120
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
2.513 25923457.53 0.00 11358090.08 43.8
CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-125
Proj ID NH 1102(524)
Work Type UTIL & UTIL IN CONSTR CONTRACT
 
3.980 408971.75 0.00 364462.91 89.1
CountyBEXAR
Highway IH 10
From 1.0 MI N OF HUEBNER RD
To S. OF HUEBNER RD
CSJ 0072-12-179
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
1.464 9635856.12 0.00 3937526.06 40.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-11
Work Began 01-02-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 698
Addl Days Granted 73
Working Days Charged 617
Percent Time Used 80
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-120
LONE STAR TRAFFIC SERVICE, INC.(0.20%)
FUQUAY, INC. (0.07%)
ROADWAY SPECIALTIES, INC.(0.69%)
SITESAFE PRODUCTS TEXAS(0.99%)
PRIMATE CONSTRUCTION, INC. (0.03%)
J. R. (JOE) RAMON & SONS, INC. (0.60%)
GEOSOURCE, INC.(0.50%)
FARR FOUNDATION, INC.(1.09%)
DUSTROL, INC.(0.20%)
BEAIRD DRILLING(0.37%)
CP REBAR AND PT INSTALLATION (0.25%)
COLLECTIVE CONTRACTING (1.01%)
FLASHER EQUIPMENT COMPANY(1.35%)
STAR OPERATIONS, INC.( 15.22%)
S & S BRIDGE PAINTING, INC.(0.16%)
A & L UNDERGROUND, INC.(0.03%)
DU-MOR ENTERPRISES_INC.(0.55%)
DRILL TECH DRILLING & SHORING, INC.(2.82%)
T & D SOLUTIONS, LTD (1.55%)
WEBBER, LLC(112.09%)
FARR FOUNDATION, INC.(1.25%)
TEXAS HIGHWAY WALLS(2.73%)
BEAIRD DRILLING(0.35%)
FLASHER EQUIPMENT COMPANY(1.25%)
STAR OPERATIONS, INC.( 10.76%)
GIBSON & ASSOCIATES, INC.(0.13%)
HOLES OF SAN ANTONIO (0.01%)
M & M CONTRACTING, LTD.(1.04%)
TEXAS CURB CUT, LP (0.07%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 36.16%)
WEBBER BARRIER SERVICES, LLC.(2.34%)
HOUSTON SAWING & DRILLING(0.02%)
CP REBAR AND PT INSTALLATION (0.14%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.48%)
CRAIG OLDEN, INC.(0.99%)
PENHALL COMPANY (AUSTIN) (0.00%)
SAECO ELECTRIC & UTILITY, LTD. (0.03%)
Contract # 08113003
Totals 35968285.40 0.00 15660079.05 43.5

CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-122
Proj ID HP 1102(265)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.150 10850899.11 0.00 196048.38 1.8
CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-134
Proj ID RW 72-8-134
Work Type UTILITY ADJUSTMENTS
 
0.150 1291148.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-11
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 382
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-122
C-3 ENVIRONMENTAL SPECIALTIES, LP(0.10%)
BADECO, INC(0.53%)
FUQUAY, INC. (0.19%)
AUSTIN WOOD RECYCLING(0.40%)
FLASHER EQUIPMENT COMPANY(0.66%)
PRIMATE CONSTRUCTION, INC. (0.02%)
COLLECTIVE CONTRACTING (7.78%)
DU-MOR ENTERPRISES_INC.(1.58%)
SITE-SAFE PRODUCTS OF TEXAS, L.P.(0.60%)
DUSTROL, INC.(0.44%)
F & W ELECTRICAL CONTRACTORS, INC. (3.25%)
CERTIFIED PLACERS LLC(2.14%)
Contract # 08113201
Totals 12142047.29 0.00 196048.38 1.6

CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-134
Proj ID RW 72-8-134
Work Type ROW UTL. ADJ.
 
0.150 1621558.09 0.00 1298000.65 80.0
CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-136
Proj ID HP 1102(265)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.150 12261538.68 0.00 5537572.18 45.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-26-13
Work Began 09-24-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 54
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-136
CP REBAR AND PT INSTALLATION (0.26%)
AUSTIN WOOD RECYCLING(0.35%)
BADECO, INC(1.64%)
C & C ALCOSER TRUCKING (0.00%)
DU-MOR ENTERPRISES_INC.(1.69%)
DUSTROL, INC.(0.11%)
FLASHER EQUIPMENT COMPANY(0.18%)
FUQUAY, INC. (0.26%)
HOUSTON SAWING & DRILLING(0.03%)
KELLYSTONE, INC(0.20%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.59%)
SCOTT DERR PAINTING CO, LLC(0.05%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.10%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.48%)
STAR OPERATIONS, INC.(3.74%)
W. W. FOUNDATION DRILLING, LTD.( 10.27%)
RDI FOUNDATION DRILLING(1.18%)
Contract # 04133032
Totals 13883096.77 0.00 6835572.83 49.2

CountyBEXAR
Highway IH 10
From S. OF HUEBNER RD
To IH 410
CSJ 0072-12-190
Proj ID IM 0352(340)
Work Type SURF, PAV MRK, BASE REPAIR
 
2.892 3140320.00 0.00 3542961.58 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-13
Work Began 09-24-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 12
Working Days Charged 59
Percent Time Used 76
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-12-190
STAR OPERATIONS, INC.(3.75%)
LIGHT IT UP ELECTRIC (2.85%)
INTERSTATE BARRICADES & MARKINGS, INC. (4.56%)
Contract # 12123215
Totals 3140320.00 0.00 3542961.58 99.9

CountyKENDALL
Highway US 87
From AT CIBOLO CREEK
To .
CSJ 0072-14-024
Proj ID C 72-14-24
Work Type WIDEN NARROW BRIDGE AND APPROACHES
 
0.238 943105.79 34374.00 891255.68 99.9
Work Order 08-21-12
Work Began 01-07-13
Work Completed  
Time Computed 09-07-13
Contract Working Days 166
Addl Days Granted 15
Working Days Charged 318
Percent Time Used 175
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-14-024
BEAIRD DRILLING(3.82%)
O & S TRAFFIC SUPPLIES (1.27%)
J.D. RAMMING PAVING CO., LTD.(8.58%)
FLASHER EQUIPMENT COMPANY(1.73%)
S & S BRIDGE PAINTING, INC.(0.90%)
Contract # 07123021
Totals 943105.79 34374.00 891255.68 99.9

CountyATASCOSA
Highway IH 37
From 1.1 MI SOUTH OF US 281
To ATASCOSA RIVER
CSJ 0073-05-065
Proj ID IM 0372(088)
Work Type MILL, BS, SURF, SC, OV & PAV MRK (SBML)
 
11.482 4592624.13 0.00 2605775.55 56.7
CountyATASCOSA
Highway IH 37
From 0.9 MILES NORTH OF US 281
To 1.1 MILES SOUTH OF US 281
CSJ 0073-10-050
Proj ID IM 0372(088)
Work Type MILL, SURF, SC, OV & PAV MRK
 
2.000 803126.55 0.00 737643.79 91.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 09-11-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 100
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-05-065
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
FLASHER EQUIPMENT COMPANY(1.00%)
PAVEOVER, INC( 15.72%)
SCR CONSTRUCTION CO., INC. ( 17.44%)
Contract # 07133049
Totals 5395750.68 0.00 3343419.34 61.9

CountyATASCOSA
Highway IH 37
From ATASCOSA RIVER
To LIVE OAK/ATASCOSA COUNTY LINE
CSJ 0073-06-046
Proj ID IM 0372(090)
Work Type MILL, BS, SURF, SC, OV & PAV MRK (SBML)
 
7.623 3571178.36 0.00 150623.20 4.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-19-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-06-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143205
Totals 3571178.36 0.00 150623.20 4.2

CountyBEXAR
Highway IH 37
From 0.4 MI N OF LP 13
To 0.4 MI S OF LP 13
CSJ 0073-08-167
Proj ID IM 0372(085)
Work Type LANDSCAPE DEVELOPMENT
 
0.850 520750.01 1200.00 498560.02 95.7
Work Order 10-18-11
Work Began 10-19-11
Work Completed  
Time Computed 01-03-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-167
DOWN UNDER CONSTRUCTION(0.96%)
LONE STAR TRAFFIC SERVICE, INC.(0.57%)
CRUZ CONTRACTING OF TEXAS, LLC (0.96%)
Contract # 08113005
Totals 520750.01 1200.00 498560.02 95.7

CountyBEXAR
Highway US 281
From 0.25 MILES N OF IH 410
To 0.3 MI S OF JONES MALTSBERGER RD
CSJ 0073-08-168
Proj ID NH 2012(288)
Work Type LANDSCAPE DEVELOPMENT
 
1.150 662704.00 0.00 631282.04 95.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-12
Work Began 04-02-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 93
Addl Days Granted 29
Working Days Charged 116
Percent Time Used 95
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-168
LONE STAR TRAFFIC SERVICE, INC.(0.41%)
FUQUAY, INC. (1.59%)
Contract # 02123205
Totals 662704.00 0.00 631282.04 95.2

CountyBEXAR
Highway US 281
From 0.2 MI N OF STADIUM DR
To N ST MARY'S ST
CSJ 0073-08-173
Proj ID NH 2013(708)
Work Type LANDSCAPE DEVELOPMENT
 
0.600 143550.00 0.00 109735.00 76.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-12-13
Work Began 09-09-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 50
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-173
N-LINE TRAFFIC MAINTENANCE, L.P. (4.33%)
Contract # 05133004
Totals 143550.00 0.00 109735.00 76.4

CountyWILSON
Highway US 181
From LP 181 N OF FLORESVILLE
To PAJARITO CREEK
CSJ 0100-03-071
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
5.850 70512.50 260.00 75202.86 99.9
CountyWILSON
Highway SH 97
From SAN ANTONIO RIVER
To 0.8 MI E OF SAN ANTONIO RIVER
CSJ 0328-02-042
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
0.800 19058.60 220.00 16621.19 87.2
Work Order 06-18-12
Work Began 10-22-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 38
Addl Days Granted 10
Working Days Charged 40
Percent Time Used 83
Contractor(s)
ALTEX LANDSCAPE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123053
Totals 89571.10 480.00 91824.05 99.9

CountyWILSON
Highway US 181 ETC
From AT SH 97 WEST
To .
CSJ 0100-03-076
Proj ID STP 1302(005)G
Work Type TRAFFIC CONTROL DEVICE
 
0.007 507653.58 79664.19 260818.49 51.3
Work Order 10-17-13
Work Began 02-25-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 47
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-076
YORK & YORK FOUNDATION DRILLING, INC.( 12.41%)
UNITED PAVEMENT & MARKINGS, LLC(3.28%)
JND CONSTRUCTION CONSULTANTS, LLC(5.45%)
THOMPSON CONSTRUCTION(7.46%)
VACA UNDERGROUND UTILITIES INC (1.47%)
Contract # 09133039
Totals 507653.58 79664.19 260818.49 51.3

CountyKENDALL
Highway RM 473 ETC
From RM 473 (WEST)
To RM 473 (EAST)
CSJ 0142-09-041
Proj ID STP 2014(222)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
200.087 5605392.71 4034663.51 4428299.39 79.0
Work Order 12-10-13
Work Began 06-18-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 37
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0142-09-041
FLASHER EQUIPMENT COMPANY( 20.04%)
WEST TEXAS RUMBLE STRIP(0.08%)
Contract # 11133212
Totals 5605392.71 4034663.51 4428299.39 79.0

CountyWILSON
Highway US 87
From 0.5 MI S OF FM 775
To FM 539
CSJ 0143-03-042
Proj ID C 143-3-42
Work Type WIDEN RDWY TO PROVIDE PASSING LANE
 
6.263 1615779.28 2815.40 1407755.68 87.1
CountyWILSON
Highway US 87
From FM 539
To 0.5 MI E OF FM 538
CSJ 0143-04-064
Proj ID C 143-4-64
Work Type WIDEN RDWY TO PROVIDE PASSING LANES
 
9.751 1432455.49 2970.05 1270843.03 88.7
CountyWILSON
Highway US 87
From 0.5 MI E OF FM 538
To WILSON/GONZALEZ C/L
CSJ 0143-05-031
Proj ID C 143-5-31
Work Type WIDEN RDWY TO PROVIDE PASSING_LANES
 
8.970 2211388.71 2970.40 2919144.15 99.9
Work Order 09-13-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 225
Percent Time Used 89
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0143-03-042
RICE ENVIRONMENTAL SERVICES(3.75%)
MURRAY CONSTRUCTION(0.55%)
M.V. HENKE ENTERPRISES, INC. (0.38%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.20%)
HIGHWAY TECHNOLOGIES, INC. (5.69%)
RELMCO, INC. ( 13.52%)
FLASHER EQUIPMENT COMPANY(0.37%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (7.12%)
FLASHER EQUIPMENT COMPANY(5.43%)
Contract # 07123227
Totals 5259623.48 8755.85 5597742.86 99.9

CountyKERR
Highway SH 39
From 0.1 MI E OF SH 27
To NEW INGRAM LAKE DAM
CSJ 0193-02-031
Proj ID C 193-2-31
Work Type GR, STRS, BASE & SURF
 
1.267 7644985.97 392397.22 3175658.59 41.5
Work Order 10-12-12
Work Began 01-21-13
Work Completed  
Time Computed 10-28-12
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 325
Percent Time Used 94
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-031
J.D. RAMMING PAVING CO., LLC ( 20.81%)
ALLEN KELLER COMPANY ( 15.12%)
F & W ELECTRICAL CONTRACTORS, INC. (2.51%)
RICE ENVIRONMENTAL SERVICES(1.39%)
W. W. FOUNDATION DRILLING, LTD.(0.89%)
FLASHER EQUIPMENT COMPANY(0.43%)
Contract # 08123027
Totals 7644985.97 392397.22 3175658.59 41.5

CountyCOMAL
Highway BS 46-C
From KERLICK LANE
To LANDA STREET
CSJ 0215-02-048
Proj ID C 215-2-48
Work Type BASE, GRAD, STR, SURF & PAV'T MRK
 
1.085 11041649.54 82517.27 82517.27 0.7
Work Order 06-03-14
Work Began 00-00-00
Work Completed  
Time Computed 11-30-14
Contract Working Days 361
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143203
Totals 11041649.54 82517.27 82517.27 0.7

CountyKENDALL
Highway SH 46
From AT HERFF ROAD
To .
CSJ 0215-06-031
Proj ID STP 2014(726)
Work Type GR, BSE, SURF, PAVT MRK
 
0.587 1830812.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 181
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143024
Totals 1830812.97 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5