Monthly State Let Construction Report For San Antonio District As Of Apr 10, 2015 Page 2 Of 6

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMEDINA
Highway US 90
From AVENUE C IN HONDO
To 1.6 MILES EAST OF SH 173
CSJ 0024-05-095
Proj ID NH 2014(361)
Work Type OVERLAY & PAVEMENT MARKINGS
 
1.398 911816.80 0.00 1018176.97 99.9
Work Order 02-14-14
Work Began 06-30-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 102
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0024-05-095
PERFORMANCE EQUIPMENT(3.47%)
DUSTROL, INC.(0.64%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.83%)
ROADWAY SPECIALTIES, INC.(4.86%)
TRP CONSTRUCTION GROUP, LLC(3.70%)
Contract # 01143018
Totals 911816.80 0.00 1018176.97 99.9

CountyBEXAR
Highway IH 10
From S PINE STREET
To ROLAND AVENUE
CSJ 0025-02-194
Proj ID C 25-2-194
Work Type MILL, RETAINING WALL, SURFACE
 
0.800 12027793.24 1354642.58 11374126.33 90.8
Work Order 06-14-13
Work Began 08-12-13
Work Completed  
Time Computed 08-12-13
Contract Working Days 349
Addl Days Granted 75
Working Days Charged 292
Percent Time Used 68
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-194
ANGEL BROTHERS ENTERPRISES, LTD. ( 22.61%)
DANRIDGE CONSTRUCTION, LLC.(0.67%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.79%)
FLASHER EQUIPMENT COMPANY(0.75%)
HALL AND SONS TRANSPORT, INC.(7.88%)
RICE ENVIRONMENTAL SERVICES(0.60%)
THE LEVY COMPANY, L.P. ( 12.82%)
LIGHT IT UP ELECTRIC (0.22%)
TEXSTAR ENTERPRISES, INC.(1.62%)
ANTIGO CONSTRUCTION, INC.(0.20%)
CALAME CONTRACTING, LLC(1.95%)
DU-MOR ENTERPRISES_INC.(0.81%)
WEBBER BARRIER SERVICES, LLC.(0.41%)
BEAIRD DRILLING(0.03%)
Contract # 04133217
Totals 12027793.24 1354642.58 11374126.33 90.8

CountyBEXAR
Highway IH 10
From IH 35
To 0.1 MI W. OF S. NEW BRAUNFELS AVE.
CSJ 0025-02-196
Proj ID NH 2014(853)
Work Type OVERLAY AND PAVEMENT MARKINGS
 
2.990 4673604.88 0.00 0.00 0.0
CountyBEXAR
Highway IH 10
From 0.1 MI E. OF S. WALTERS ST
To IH 410 EAST
CSJ 0025-02-197
Proj ID NH 2014(853)
Work Type BASE REPAIR, MILL, OV & PVMT MRKING
 
4.530 5828747.87 0.00 0.00 0.0
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 11-08-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-196
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143004
Totals 10502352.75 0.00 0.00 0.0

CountyBEXAR
Highway IH 10 ETC
From 0.2 MI WEST OF GRAYTOWN
To 0.2 MI EAST OF PFEIL
CSJ 0025-02-201
Proj ID STP 2015(195)HESG
Work Type SAFETY LIGHTING
 
13.723 2712741.65 126936.35 260473.64 9.6
Work Order 11-14-14
Work Began 02-17-15
Work Completed  
Time Computed 02-12-15
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 10
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-201
DS TEXAS ICON CONSTRUCTION (0.59%)
FLASHER EQUIPMENT COMPANY(0.51%)
Contract # 10143002
Totals 2712741.65 126936.35 260473.64 9.6

CountyBEXAR
Highway IH 10 ETC
From AT IH 35
To .
CSJ 0025-02-202
Proj ID STP 2015(723)HES
Work Type TEXTURIZE SHOULDERS
 
63.761 1108928.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 04-13-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-202
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153236
Totals 1108928.80 0.00 0.00 0.0

CountyBEXAR
Highway FM 78 ETC
From AT WALZEM
To .
CSJ 0025-09-075
Proj ID STP 2014(981)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.703 356499.50 80190.00 144847.68 40.6
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 11-18-14
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-075
ALAMO CRANE SERVICE, INC.(1.82%)
HEARN CO.(1.45%)
CATO ELECTRIC COMPANY(2.83%)
FLASHER EQUIPMENT COMPANY(3.83%)
Contract # 07143045
Totals 356499.50 80190.00 144847.68 40.6

CountyBEXAR
Highway FM 78
From AT LP 1604
To .
CSJ 0025-09-076
Proj ID STP 2015(580)HES
Work Type GR, BASE, SURF, PAVMT MRKRS, SIGNALS
 
0.106 2187618.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153004
Totals 2187618.06 0.00 0.00 0.0

CountyGUADALUPE
Highway FM 78
From SANTA CLARA CREEK, WEST OF MARION
To SANTA CLARA CREEK, EAST OF MARION
CSJ 0025-10-073
Proj ID STP 2013(348)
Work Type GRAD, STRS, BASE & SURF
 
1.080 4136146.75 675028.07 3844909.72 92.9
Work Order 07-16-13
Work Began 11-11-13
Work Completed  
Time Computed 11-11-13
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 174
Percent Time Used 85
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-073
FLASHER EQUIPMENT COMPANY(0.31%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (2.51%)
E-Z BEL CONSTRUCTION, LLC(1.02%)
MURRAY CONSTRUCTION(0.53%)
RICE ENVIRONMENTAL SERVICES(0.56%)
C & C ALCOSER TRUCKING (0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.53%)
VEGETATION MANAGEMENT SERVICES, LLC(0.00%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.00%)
Contract # 01133220
Totals 4136146.75 675028.07 3844909.72 92.9

CountyKENDALL
Highway IH 10
From SH 46
To 0.4 MI WEST OF US 87
CSJ 0072-06-071
Proj ID NH 2015(020)
Work Type BASE, GR, STR, SURF, SIGN & PAV MRK
 
1.044 3536440.57 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-071
DOUBLE S PAVING, INC.( 25.74%)
DRILL TECH DRILLING & SHORING, INC.(5.25%)
SAECO ELECTRIC & UTILITY, LTD. (4.55%)
ENVIRONMENTAL SAFETY SERVICES, INC.(2.82%)
FLASHER EQUIPMENT COMPANY(1.06%)
Contract # 09143211
Totals 3536440.57 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-059
Proj ID IM 4104(382)
Work Type SC, STRIPING, BASE
 
7.406 18426875.59 39560.10 39560.10 0.2
CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-065
Proj ID RW 72-7-65
Work Type ADJUSTMENT OF UTILITIES
 
7.406 915396.00 0.00 0.00 0.0
Work Order 10-02-14
Work Began 03-10-15
Work Completed  
Time Computed 03-10-15
Contract Working Days 376
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 3
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-059
FUQUAY, INC. (0.61%)
RELMCO, INC. (4.88%)
BADECO, INC(0.66%)
THE LEVY COMPANY, L.P. (6.41%)
K.L. DURHAM CONSTRUCTION, LLC(0.28%)
ROADWAY SPECIALTIES, INC.(2.51%)
VINSON CONSTRUCTION, LLC.(0.79%)
GOSNEY BROTHERS, LLC.(4.16%)
OSCAR ORDUNO, INC. (3.00%)
FLASHER EQUIPMENT COMPANY(0.66%)
MICKIE SERVICE, INC. (0.06%)
MCL CONTRACTING, LLC (0.14%)
Contract # 07143204
Totals 19342271.59 39560.10 39560.10 0.2

CountyBEXAR
Highway IH 10
From FM 3351 (RALPH FAIR RD)
To BOERNE STAGE RD
CSJ 0072-07-060
Proj ID C 72-7-60
Work Type GRAD, BS, STR, PVMT MRKG
 
0.871 6345951.80 251412.41 4687802.05 73.8
Work Order 08-06-13
Work Began 03-24-14
Work Completed  
Time Computed 08-22-13
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 231
Percent Time Used 74
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-060
J.D. RAMMING PAVING CO., LTD.( 15.45%)
SIEMENS INDUSTRY, INC. (3.77%)
PRESIDIO CONTRACTING, LLC(2.35%)
FARR FOUNDATION, INC.(2.29%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.90%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.44%)
D GUERRA CONSTRUCTION, LLC (1.68%)
FLASHER EQUIPMENT COMPANY(1.19%)
VOGES DRILLING CO. (1.20%)
A-Z REBAR CONTRACTOR (0.37%)
SCOTT DERR PAINTING CO (0.08%)
STAR OPERATIONS, INC.(4.42%)
TEXAS HIGHWAY WALLS(5.43%)
PENNTEX MILLING INC. (0.60%)
GEOSOURCE, INC.(0.35%)
Contract # 06133205
Totals 6345951.80 251412.41 4687802.05 73.8

CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-120
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
2.513 25923457.53 1148903.58 21391658.09 81.7
CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-125
Proj ID NH 1102(524)
Work Type UTIL & UTIL IN CONSTR CONTRACT
 
3.980 408971.75 0.00 364462.91 89.1
CountyBEXAR
Highway IH 10
From 1.0 MI N OF HUEBNER RD
To S. OF HUEBNER RD
CSJ 0072-12-179
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
1.464 9635856.12 521076.16 5582178.47 57.9
Work Order 10-19-11
Work Began 01-02-12
Work Completed  
Time Computed 11-03-11
Contract Working Days 698
Addl Days Granted 105
Working Days Charged 796
Percent Time Used 99
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-120
LONE STAR TRAFFIC SERVICE, INC.(0.20%)
FUQUAY, INC. (0.07%)
ROADWAY SPECIALTIES, INC.(0.69%)
SITESAFE PRODUCTS TEXAS(0.99%)
PRIMATE CONSTRUCTION, INC. (0.03%)
J. R. (JOE) RAMON & SONS, INC. (0.60%)
GEOSOURCE, INC.(0.50%)
FARR FOUNDATION, INC.(1.09%)
DUSTROL, INC.(0.20%)
BEAIRD DRILLING(0.37%)
CP REBAR AND PT INSTALLATION (0.25%)
COLLECTIVE CONTRACTING (1.01%)
FLASHER EQUIPMENT COMPANY(1.35%)
STAR OPERATIONS, INC.( 15.22%)
S & S BRIDGE PAINTING, INC.(0.16%)
A & L UNDERGROUND, INC.(0.03%)
DU-MOR ENTERPRISES_INC.(0.55%)
DRILL TECH DRILLING & SHORING, INC.(2.82%)
T & D SOLUTIONS, LTD (1.55%)
WEBBER, LLC(113.59%)
FARR FOUNDATION, INC.(1.25%)
TEXAS HIGHWAY WALLS(2.73%)
BEAIRD DRILLING(0.35%)
FLASHER EQUIPMENT COMPANY(1.25%)
STAR OPERATIONS, INC.( 10.76%)
GIBSON & ASSOCIATES, INC.(0.13%)
HOLES OF SAN ANTONIO (0.01%)
M & M CONTRACTING, LTD.(1.04%)
TEXAS CURB CUT, LP (0.07%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 36.16%)
WEBBER BARRIER SERVICES, LLC.(2.34%)
HOUSTON SAWING & DRILLING(0.02%)
CP REBAR AND PT INSTALLATION (0.14%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.48%)
CRAIG OLDEN, INC.(0.99%)
PENHALL COMPANY (AUSTIN) (0.00%)
SAECO ELECTRIC & UTILITY, LTD. (0.03%)
DCCS, LLC(1.66%)
RDI FOUNDATION DRILLING(0.13%)
LOU MAC SERVICES (0.00%)
ROADWAY SPECIALTIES, INC.(0.35%)
GEOSOURCE, INC.(1.07%)
M & M STRIPING & POWER WASHING, LLC(0.36%)
ODUM SERVICES, L.P.(0.00%)
SAN ANTONIO TELEPHONE COMPANY INC. (0.35%)
Contract # 08113003
Totals 35968285.40 1669979.74 27338299.47 75.4

CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-134
Proj ID RW 72-8-134
Work Type ROW UTL. ADJ.
 
0.150 1621558.09 0.00 1432225.76 88.3
CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-136
Proj ID HP 1102(265)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.150 12261538.68 417284.83 10187198.27 83.7
Work Order 06-26-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 426
Percent Time Used 106
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-136
CP REBAR AND PT INSTALLATION (0.26%)
AUSTIN WOOD RECYCLING(0.35%)
BADECO, INC(1.64%)
C & C ALCOSER TRUCKING (1.39%)
DU-MOR ENTERPRISES_INC.(1.69%)
DUSTROL, INC.(0.11%)
FLASHER EQUIPMENT COMPANY(0.18%)
FUQUAY, INC. (0.26%)
HOUSTON SAWING & DRILLING(0.03%)
KELLYSTONE, INC(0.20%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.59%)
SCOTT DERR PAINTING CO, LLC(0.05%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.10%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.48%)
STAR OPERATIONS, INC.(3.74%)
W. W. FOUNDATION DRILLING, LTD.( 10.27%)
RDI FOUNDATION DRILLING(1.18%)
Contract # 04133032
Totals 13883096.77 417284.83 11619424.03 84.2

CountyKENDALL
Highway US 87
From AT CIBOLO CREEK
To .
CSJ 0072-14-024
Proj ID C 72-14-24
Work Type WIDEN NARROW BRIDGE AND APPROACHES
 
0.238 943105.79 1829.85 933219.53 100.0
Work Order 08-21-12
Work Began 01-07-13
Work Completed 04-08-15
Time Computed 09-07-13
Contract Working Days 166
Addl Days Granted 15
Working Days Charged 318
Percent Time Used 175
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-14-024
BEAIRD DRILLING(3.82%)
O & S TRAFFIC SUPPLIES (1.27%)
J.D. RAMMING PAVING CO., LTD.(8.58%)
FLASHER EQUIPMENT COMPANY(1.73%)
S & S BRIDGE PAINTING, INC.(0.90%)
Contract # 07123021
Totals 943105.79 1829.85 933219.53 100.0

CountyBEXAR
Highway US 281 ETC
From LP 1604
To BEXAR/ATASCOSA C/L
CSJ 0073-02-069
Proj ID NH 2015(284)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
113.302 4909119.80 14721.41 164101.19 3.3
Work Order 12-05-14
Work Began 00-00-00
Work Completed  
Time Computed 12-21-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0073-02-069
FLASHER EQUIPMENT COMPANY( 14.60%)
WEST TEXAS RUMBLE STRIP(0.09%)
Contract # 11143205
Totals 4909119.80 14721.41 164101.19 3.3

CountyBEXAR
Highway US 281
From FM 1937
To ATASCOSA COUNTY LINE
CSJ 0073-02-070
Proj ID STP 2015(285)HES
Work Type CTB, SURF & TEXTURIZE SHOULDERS
 
11.368 7142617.69 0.00 37500.00 0.5
Work Order 01-26-15
Work Began 00-00-00
Work Completed  
Time Computed 02-11-15
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-02-070
ROADWAY SPECIALTIES, INC.(0.66%)
FENTON EXCAVATING & CONSTRUCTION, INC. ( 19.62%)
FOX ENTERPRISES, INC.(3.64%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.72%)
DUSTROL, INC.( 29.77%)
Contract # 11143210
Totals 7142617.69 0.00 37500.00 0.5

CountyATASCOSA
Highway US 281
From BEXAR COUNTY LINE
To 0.443 MI N OF FM 3006
CSJ 0073-03-063
Proj ID STP 2015(021)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
8.668 167947.99 43068.08 83830.47 49.9
CountyBEXAR
Highway SS 122
From LP 13
To IH 410
CSJ 0100-02-061
Proj ID STP 2015(022)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
3.020 310980.86 65141.44 87451.65 28.1
Work Order 10-09-14
Work Began 02-17-15
Work Completed  
Time Computed 12-08-14
Contract Working Days 88
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 35
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0073-03-063
ROADWAY SPECIALTIES, INC.(2.82%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) ( 10.77%)
FLASHER EQUIPMENT COMPANY(1.22%)
WEBB & BEXAR CONSTRUCTION, LLC ( 23.38%)
Contract # 09143012
Totals 478928.85 108209.52 171282.12 35.7

CountyATASCOSA
Highway IH 37
From 1.1 MI SOUTH OF US 281
To ATASCOSA RIVER
CSJ 0073-05-065
Proj ID IM 0372(088)
Work Type MILL, BS, SURF, SC, OV & PAV MRK (SBML)
 
11.482 4592624.13 0.00 4610102.28 99.9
CountyATASCOSA
Highway IH 37
From 0.9 MILES NORTH OF US 281
To 1.1 MILES SOUTH OF US 281
CSJ 0073-10-050
Proj ID IM 0372(088)
Work Type MILL, SURF, SC, OV & PAV MRK
 
2.000 803126.55 0.00 1102518.59 99.9
Work Order 08-02-13
Work Began 09-11-13
Work Completed  
Time Computed 09-11-13
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 147
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-05-065
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
FLASHER EQUIPMENT COMPANY(1.00%)
PAVEOVER, INC( 15.72%)
SCR CONSTRUCTION CO., INC. ( 17.44%)
Contract # 07133049
Totals 5395750.68 0.00 5712620.87 99.9

CountyATASCOSA
Highway IH 37
From 0.4 MI SOUTH OF US 281
To 0.2 MI SOUTH OF FM 541
CSJ 0073-05-068
Proj ID STP 2015(733)HES
Work Type GR, BASE & PAVEMENT MARKINGS
 
6.067 2293599.14 0.00 0.00 0.0
CountyATASCOSA
Highway IH 37
From 1.1 MI SOUTH OF US 281
To 0.2 MI NORTH OF SP 199
CSJ 0073-10-051
Proj ID STP 2015(734)HES
Work Type GRADE, BASE, SURF, PAVMT MARKINGS
 
1.810 1352503.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-05-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153010
Totals 3646103.10 0.00 0.00 0.0

CountyATASCOSA
Highway IH 37
From ATASCOSA RIVER
To LIVE OAK/ATASCOSA COUNTY LINE
CSJ 0073-06-046
Proj ID IM 0372(090)
Work Type MILL, BS, SURF, SC, OV & PAV MRK (SBML)
 
7.623 3571178.36 32996.77 1119318.36 31.3
Work Order 02-19-14
Work Began 10-20-14
Work Completed  
Time Computed 04-20-14
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 11
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-06-046
FLASHER EQUIPMENT COMPANY(1.33%)
R.P.V. CONSTRUCTION(8.99%)
WEST TEXAS RUMBLE STRIP(0.17%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (1.38%)
Contract # 01143205
Totals 3571178.36 32996.77 1119318.36 31.3

page 1 | page 2 | page 3 | page 4 | page 5 | page 6