Monthly State Let Construction Report For San Antonio District As Of Dec 10, 2014 Page 2 Of 6

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMEDINA
Highway US 90
From AVENUE C IN HONDO
To 1.6 MILES EAST OF SH 173
CSJ 0024-05-095
Proj ID NH 2014(361)
Work Type OVERLAY & PAVEMENT MARKINGS
 
1.398 911816.80 0.00 1018176.97 99.9
Work Order 02-14-14
Work Began 06-30-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 102
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0024-05-095
PERFORMANCE EQUIPMENT(3.47%)
DUSTROL, INC.(0.64%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.83%)
ROADWAY SPECIALTIES, INC.(4.86%)
TRP CONSTRUCTION GROUP, LLC(3.70%)
Contract # 01143018
Totals 911816.80 0.00 1018176.97 99.9

CountyBEXAR
Highway IH 10
From S PINE STREET
To ROLAND AVENUE
CSJ 0025-02-194
Proj ID C 25-2-194
Work Type MILL, RETAINING WALL, SURFACE
 
0.800 12027793.24 675724.99 7450030.45 61.9
Work Order 06-14-13
Work Began 08-12-13
Work Completed  
Time Computed 08-12-13
Contract Working Days 349
Addl Days Granted 75
Working Days Charged 202
Percent Time Used 47
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-194
ANGEL BROTHERS ENTERPRISES, LTD. ( 22.61%)
DANRIDGE CONSTRUCTION, LLC.(0.67%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.79%)
FLASHER EQUIPMENT COMPANY(0.75%)
HALL AND SONS TRANSPORT, INC.(7.88%)
RICE ENVIRONMENTAL SERVICES(0.60%)
THE LEVY COMPANY, L.P. ( 12.82%)
LIGHT IT UP ELECTRIC (0.22%)
TEXSTAR ENTERPRISES, INC.(1.62%)
ANTIGO CONSTRUCTION, INC.(0.20%)
CALAME CONTRACTING, LLC(1.95%)
DU-MOR ENTERPRISES_INC.(0.81%)
WEBBER BARRIER SERVICES, LLC.(0.41%)
BEAIRD DRILLING(0.03%)
Contract # 04133217
Totals 12027793.24 675724.99 7450030.45 61.9

CountyBEXAR
Highway IH 10
From IH 35
To 0.1 MI W. OF S. NEW BRAUNFELS AVE.
CSJ 0025-02-196
Proj ID NH 2014(853)
Work Type OVERLAY AND PAVEMENT MARKINGS
 
2.990 4673604.88 0.00 0.00 0.0
CountyBEXAR
Highway IH 10
From 0.1 MI E. OF S. WALTERS ST
To IH 410 EAST
CSJ 0025-02-197
Proj ID NH 2014(853)
Work Type BASE REPAIR, MILL, OV & PVMT MRKING
 
4.530 5828747.87 0.00 0.00 0.0
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 11-08-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-196
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143004
Totals 10502352.75 0.00 0.00 0.0

CountyBEXAR
Highway IH 10 ETC
From 0.2 MI WEST OF GRAYTOWN
To 0.2 MI EAST OF PFEIL
CSJ 0025-02-201
Proj ID STP 2015(195)HESG
Work Type SAFETY LIGHTING
 
13.723 2712741.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-201
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143002
Totals 2712741.65 0.00 0.00 0.0

CountyBEXAR
Highway FM 78 ETC
From AT WALZEM
To .
CSJ 0025-09-075
Proj ID STP 2014(981)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.703 356499.50 0.00 8516.00 2.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143045
Totals 356499.50 0.00 8516.00 2.3

CountyGUADALUPE
Highway FM 78
From SANTA CLARA CREEK, WEST OF MARION
To SANTA CLARA CREEK, EAST OF MARION
CSJ 0025-10-073
Proj ID STP 2013(348)
Work Type GRAD, STRS, BASE & SURF
 
1.080 4136146.75 412760.65 1902583.42 45.9
Work Order 07-16-13
Work Began 11-11-13
Work Completed  
Time Computed 11-11-13
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 46
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-073
FLASHER EQUIPMENT COMPANY(0.31%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (2.51%)
E-Z BEL CONSTRUCTION, LLC(1.02%)
MURRAY CONSTRUCTION(0.53%)
RICE ENVIRONMENTAL SERVICES(0.56%)
C & C ALCOSER TRUCKING (0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.53%)
VEGETATION MANAGEMENT SERVICES, LLC(0.00%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.00%)
Contract # 01133220
Totals 4136146.75 412760.65 1902583.42 45.9

CountyKENDALL
Highway IH 10
From SH 46
To 0.4 MI WEST OF US 87
CSJ 0072-06-071
Proj ID NH 2015(020)
Work Type BASE, GR, STR, SURF, SIGN & PAV MRK
 
1.044 3536440.57 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143211
Totals 3536440.57 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-059
Proj ID IM 4104(382)
Work Type SC, STRIPING, BASE
 
7.406 18426875.59 0.00 0.00 0.0
CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-065
Proj ID RW 72-7-65
Work Type ADJUSTMENT OF UTILITIES
 
7.406 915396.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 376
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143204
Totals 19342271.59 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From FM 3351 (RALPH FAIR RD)
To BOERNE STAGE RD
CSJ 0072-07-060
Proj ID C 72-7-60
Work Type GRAD, BS, STR, PVMT MRKG
 
0.871 6345951.80 156694.51 3358998.00 52.9
Work Order 08-06-13
Work Began 03-24-14
Work Completed  
Time Computed 08-22-13
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 48
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-060
J.D. RAMMING PAVING CO., LTD.( 15.45%)
SIEMENS INDUSTRY, INC. (3.77%)
PRESIDIO CONTRACTING, LLC(2.35%)
FARR FOUNDATION, INC.(2.29%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.90%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.44%)
D GUERRA CONSTRUCTION, LLC (1.68%)
FLASHER EQUIPMENT COMPANY(1.19%)
VOGES DRILLING CO. (1.20%)
A-Z REBAR CONTRACTOR (0.37%)
SCOTT DERR PAINTING CO (0.08%)
STAR OPERATIONS, INC.(4.42%)
TEXAS HIGHWAY WALLS(5.43%)
PENNTEX MILLING INC. (0.60%)
Contract # 06133205
Totals 6345951.80 156694.51 3358998.00 52.9

CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-120
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
2.513 25923457.53 950457.54 16786522.54 63.8
CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-125
Proj ID NH 1102(524)
Work Type UTIL & UTIL IN CONSTR CONTRACT
 
3.980 408971.75 0.00 364462.91 89.1
CountyBEXAR
Highway IH 10
From 1.0 MI N OF HUEBNER RD
To S. OF HUEBNER RD
CSJ 0072-12-179
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
1.464 9635856.12 103585.17 4597449.93 47.7
Work Order 10-19-11
Work Began 01-02-12
Work Completed  
Time Computed 11-03-14
Contract Working Days 698
Addl Days Granted 73
Working Days Charged 721
Percent Time Used 93
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-120
LONE STAR TRAFFIC SERVICE, INC.(0.20%)
FUQUAY, INC. (0.07%)
ROADWAY SPECIALTIES, INC.(0.69%)
SITESAFE PRODUCTS TEXAS(0.99%)
PRIMATE CONSTRUCTION, INC. (0.03%)
J. R. (JOE) RAMON & SONS, INC. (0.60%)
GEOSOURCE, INC.(0.50%)
FARR FOUNDATION, INC.(1.09%)
DUSTROL, INC.(0.20%)
BEAIRD DRILLING(0.37%)
CP REBAR AND PT INSTALLATION (0.25%)
COLLECTIVE CONTRACTING (1.01%)
FLASHER EQUIPMENT COMPANY(1.35%)
STAR OPERATIONS, INC.( 15.22%)
S & S BRIDGE PAINTING, INC.(0.16%)
A & L UNDERGROUND, INC.(0.03%)
DU-MOR ENTERPRISES_INC.(0.55%)
DRILL TECH DRILLING & SHORING, INC.(2.82%)
T & D SOLUTIONS, LTD (1.55%)
WEBBER, LLC(113.59%)
FARR FOUNDATION, INC.(1.25%)
TEXAS HIGHWAY WALLS(2.73%)
BEAIRD DRILLING(0.35%)
FLASHER EQUIPMENT COMPANY(1.25%)
STAR OPERATIONS, INC.( 10.76%)
GIBSON & ASSOCIATES, INC.(0.13%)
HOLES OF SAN ANTONIO (0.01%)
M & M CONTRACTING, LTD.(1.04%)
TEXAS CURB CUT, LP (0.07%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 36.16%)
WEBBER BARRIER SERVICES, LLC.(2.34%)
HOUSTON SAWING & DRILLING(0.02%)
CP REBAR AND PT INSTALLATION (0.14%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.48%)
CRAIG OLDEN, INC.(0.99%)
PENHALL COMPANY (AUSTIN) (0.00%)
SAECO ELECTRIC & UTILITY, LTD. (0.03%)
DCCS, LLC(1.66%)
RDI FOUNDATION DRILLING(0.13%)
LOU MAC SERVICES (0.00%)
ROADWAY SPECIALTIES, INC.(0.35%)
Contract # 08113003
Totals 35968285.40 1054042.71 21748435.38 59.7

CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-122
Proj ID HP 1102(265)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.150 10850899.11 0.00 224423.38 100.0
CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-134
Proj ID RW 72-8-134
Work Type UTILITY ADJUSTMENTS
 
0.150 1291148.18 0.00 0.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-11
Work Began 00-00-00
Work Completed 10-13-14
Time Computed 00-00-00
Contract Working Days 382
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-122
C-3 ENVIRONMENTAL SPECIALTIES, LP(0.10%)
BADECO, INC(0.53%)
FUQUAY, INC. (0.19%)
AUSTIN WOOD RECYCLING(0.40%)
FLASHER EQUIPMENT COMPANY(0.66%)
PRIMATE CONSTRUCTION, INC. (0.02%)
COLLECTIVE CONTRACTING (7.78%)
DU-MOR ENTERPRISES_INC.(1.58%)
SITE-SAFE PRODUCTS OF TEXAS, L.P.(0.60%)
DUSTROL, INC.(0.44%)
F & W ELECTRICAL CONTRACTORS, INC. (3.25%)
CERTIFIED PLACERS LLC(2.14%)
Contract # 08113201
Totals 12142047.29 0.00 224423.38 100.0

CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-134
Proj ID RW 72-8-134
Work Type ROW UTL. ADJ.
 
0.150 1621558.09 0.00 1432225.76 88.3
CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-136
Proj ID HP 1102(265)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.150 12261538.68 419289.09 8565549.35 69.2
Work Order 06-26-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 342
Percent Time Used 85
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-136
CP REBAR AND PT INSTALLATION (0.26%)
AUSTIN WOOD RECYCLING(0.35%)
BADECO, INC(1.64%)
C & C ALCOSER TRUCKING (1.39%)
DU-MOR ENTERPRISES_INC.(1.69%)
DUSTROL, INC.(0.11%)
FLASHER EQUIPMENT COMPANY(0.18%)
FUQUAY, INC. (0.26%)
HOUSTON SAWING & DRILLING(0.03%)
KELLYSTONE, INC(0.20%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.59%)
SCOTT DERR PAINTING CO, LLC(0.05%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.10%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.48%)
STAR OPERATIONS, INC.(3.74%)
W. W. FOUNDATION DRILLING, LTD.( 10.27%)
RDI FOUNDATION DRILLING(1.18%)
Contract # 04133032
Totals 13883096.77 419289.09 9997775.11 71.4

CountyKENDALL
Highway US 87
From AT CIBOLO CREEK
To .
CSJ 0072-14-024
Proj ID C 72-14-24
Work Type WIDEN NARROW BRIDGE AND APPROACHES
 
0.238 943105.79 3570.00 930189.68 99.9
Work Order 08-21-12
Work Began 01-07-13
Work Completed  
Time Computed 09-07-13
Contract Working Days 166
Addl Days Granted 15
Working Days Charged 318
Percent Time Used 175
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-14-024
BEAIRD DRILLING(3.82%)
O & S TRAFFIC SUPPLIES (1.27%)
J.D. RAMMING PAVING CO., LTD.(8.58%)
FLASHER EQUIPMENT COMPANY(1.73%)
S & S BRIDGE PAINTING, INC.(0.90%)
Contract # 07123021
Totals 943105.79 3570.00 930189.68 99.9

CountyBEXAR
Highway US 281 ETC
From LP 1604
To BEXAR/ATASCOSA C/L
CSJ 0073-02-069
Proj ID NH 2015(284)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
113.302 4909119.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-14
Work Began 00-00-00
Work Completed  
Time Computed 12-21-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0073-02-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143205
Totals 4909119.80 0.00 0.00 0.0

CountyBEXAR
Highway US 281
From FM 1937
To ATASCOSA COUNTY LINE
CSJ 0073-02-070
Proj ID STP 2015(285)HES
Work Type CTB, SURF & TEXTURIZE SHOULDERS
 
11.368 7142617.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-02-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143210
Totals 7142617.69 0.00 0.00 0.0

CountyATASCOSA
Highway US 281
From BEXAR COUNTY LINE
To 0.443 MI N OF FM 3006
CSJ 0073-03-063
Proj ID STP 2015(021)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
8.668 167947.99 0.00 0.00 0.0
CountyBEXAR
Highway SS 122
From LP 13
To IH 410
CSJ 0100-02-061
Proj ID STP 2015(022)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
3.020 310980.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 88
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0073-03-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143012
Totals 478928.85 0.00 0.00 0.0

CountyATASCOSA
Highway IH 37
From 1.1 MI SOUTH OF US 281
To ATASCOSA RIVER
CSJ 0073-05-065
Proj ID IM 0372(088)
Work Type MILL, BS, SURF, SC, OV & PAV MRK (SBML)
 
11.482 4592624.13 0.00 4610102.28 99.9
CountyATASCOSA
Highway IH 37
From 0.9 MILES NORTH OF US 281
To 1.1 MILES SOUTH OF US 281
CSJ 0073-10-050
Proj ID IM 0372(088)
Work Type MILL, SURF, SC, OV & PAV MRK
 
2.000 803126.55 0.00 1102518.59 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 09-11-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 147
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-05-065
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
FLASHER EQUIPMENT COMPANY(1.00%)
PAVEOVER, INC( 15.72%)
SCR CONSTRUCTION CO., INC. ( 17.44%)
Contract # 07133049
Totals 5395750.68 0.00 5712620.87 99.9

CountyATASCOSA
Highway IH 37
From ATASCOSA RIVER
To LIVE OAK/ATASCOSA COUNTY LINE
CSJ 0073-06-046
Proj ID IM 0372(090)
Work Type MILL, BS, SURF, SC, OV & PAV MRK (SBML)
 
7.623 3571178.36 0.00 653088.84 18.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-19-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 11
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-06-046
FLASHER EQUIPMENT COMPANY(1.33%)
R.P.V. CONSTRUCTION(8.99%)
WEST TEXAS RUMBLE STRIP(0.17%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (1.38%)
Contract # 01143205
Totals 3571178.36 0.00 653088.84 18.2

CountyBEXAR
Highway IH 37
From 0.4 MI N OF LP 13
To 0.4 MI S OF LP 13
CSJ 0073-08-167
Proj ID IM 0372(085)
Work Type LANDSCAPE DEVELOPMENT
 
0.850 520750.01 0.00 500960.02 96.1
Work Order 10-18-11
Work Began 10-19-11
Work Completed  
Time Computed 01-03-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-167
DOWN UNDER CONSTRUCTION(0.96%)
LONE STAR TRAFFIC SERVICE, INC.(0.57%)
CRUZ CONTRACTING OF TEXAS, LLC (0.96%)
Contract # 08113005
Totals 520750.01 0.00 500960.02 96.1

CountyBEXAR
Highway US 281
From 0.25 MILES N OF IH 410
To 0.3 MI S OF JONES MALTSBERGER RD
CSJ 0073-08-168
Proj ID NH 2012(288)
Work Type LANDSCAPE DEVELOPMENT
 
1.150 662704.00 2000.00 641282.04 96.7
Work Order 03-16-12
Work Began 04-02-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 93
Addl Days Granted 29
Working Days Charged 116
Percent Time Used 95
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-168
LONE STAR TRAFFIC SERVICE, INC.(0.41%)
FUQUAY, INC. (1.59%)
Contract # 02123205
Totals 662704.00 2000.00 641282.04 96.7