Monthly State Let Construction Report For San Antonio District As Of Dec 10, 2014 Page 5 Of 6

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOMAL
Highway FM 306
From 0.4 MILES EAST OF FM 3424
To JACOBS CREEK PARK ROAD
CSJ 0857-01-028
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKS
 
2.584 963415.67 0.00 943619.62 100.0
CountyCOMAL
Highway FM 306
From 0.2 MI W OF CANYON DAM ACCESS ROAD
To 1.1 MI E OF PURGATORY ROAD
CSJ 1728-02-054
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKINGS
 
6.542 2545179.77 0.00 2266257.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-28-12
Work Began 12-14-12
Work Completed 06-20-14
Time Computed 12-14-12
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 73
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0857-01-028
E-Z BEL CONSTRUCTION, LLC(1.07%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.62%)
RELMCO, INC. (6.80%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.58%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.59%)
ROADWAY SPECIALTIES, INC.(2.67%)
FLASHER EQUIPMENT COMPANY(1.96%)
EGGEMEYER LAND CLEARING, LLC (1.96%)
Contract # 10123012
Totals 3508595.44 0.00 3209877.12 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE GUIDESIGNS FY14
To .
CSJ 0915-00-155
Proj ID STP 2014(562)
Work Type DISTRICTWIDE GUIDESIGNS FY14
 
0.001 998524.12 21898.97 469792.52 47.0
Work Order 05-20-14
Work Began 00-00-00
Work Completed  
Time Computed 07-21-14
Contract Working Days 208
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 33
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143205
Totals 998524.12 21898.97 469792.52 47.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2014
To .
CSJ 0915-00-156
Proj ID STP 2014(538)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1299950.00 12851.97 569625.07 43.8
Work Order 05-01-14
Work Began 00-00-00
Work Completed  
Time Computed 07-30-14
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 19
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-156
JCD CONSTRUCTION, LLC(2.52%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.23%)
UNITED PAVEMENT & MARKINGS, LLC(0.69%)
Contract # 03143206
Totals 1299950.00 12851.97 569625.07 43.8

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-158
Proj ID STP 2012(311)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1113075.30 0.00 1057064.65 94.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-29-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 295
Working Days Charged 359
Percent Time Used 60
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-158
HEARN CO.(1.01%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (3.41%)
JCD CONSTRUCTION, LLC(3.84%)
JA&M CONSTRUCTION, LLC (1.07%)
Contract # 02123222
Totals 1113075.30 0.00 1057064.65 94.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-160
Proj ID STP 2013(404)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1179951.00 11711.62 354687.49 32.6
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 56
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-160
JND CONSTRUCTION CONSULTANTS, LLC( 13.54%)
VACA UNDERGROUND UTILITIES INC (3.44%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.69%)
BEAIRD DRILLING(0.16%)
YORK & YORK FOUNDATION DRILLING, INC.(3.55%)
JCH CONSTRUCTION, INC. (0.05%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.03%)
Contract # 02133216
Totals 1179951.00 11711.62 354687.49 32.6

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-163
Proj ID STP 2012(312)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 942875.75 0.00 984638.97 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-22-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 91
Working Days Charged 231
Percent Time Used 59
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-163
HEARN CO.(6.17%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (4.03%)
JA&M CONSTRUCTION, LLC (1.33%)
JCD CONSTRUCTION, LLC(2.82%)
Contract # 02123027
Totals 942875.75 0.00 984638.97 99.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-164
Proj ID STP 2013(405)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1218087.00 0.00 486451.86 40.1
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 49
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-164
JND CONSTRUCTION CONSULTANTS, LLC( 13.12%)
VACA UNDERGROUND UTILITIES INC (3.34%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.33%)
BEAIRD DRILLING(0.32%)
YORK & YORK FOUNDATION DRILLING, INC.(3.44%)
JCH CONSTRUCTION, INC. (0.17%)
Contract # 02133013
Totals 1218087.00 0.00 486451.86 40.1

CountyBEXAR
Highway CS
From IN SAN ANTONIO ON SOMERSET RD
To AT LEON CREEK
CSJ 0915-12-218
Proj ID BR 96(351)
Work Type REHABILITATE BRIDGE & APPROACHES
 
0.001 425301.50 19902.50 270115.00 70.7
Work Order 04-11-14
Work Began 06-11-14
Work Completed  
Time Computed 06-11-14
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 178
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-218
ABC EROSION CONTROL, INC.( 14.56%)
AMERICAN SIGNAL EQUIPMENT CO.(2.16%)
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
Contract # 03143007
Totals 425301.50 19902.50 270115.00 70.7

CountyBEXAR
Highway MH
From WURZBACH PARKWAY ON NEW LOCATION
To FROM FM 2696 TO WEST AVE
CSJ 0915-12-224
Proj ID C 915-12-224
Work Type GRAD, STRS, BASE & SURF
 
1.499 24686408.64 105.90 23966430.57 99.9
CountyBEXAR
Highway MH
From ON EAST-WEST PKWY FROM LOCKHILL-SEL
To IH 35 IN SAN ANTONIO
CSJ 8000-15-007
Proj ID RW 8000-15-7
Work Type ACQUISITION OF ROW
 
0.001 1762476.01 0.00 1649241.93 93.5
Work Order 10-07-10
Work Began 01-04-11
Work Completed  
Time Computed 01-04-11
Contract Working Days 273
Addl Days Granted 297
Working Days Charged 783
Percent Time Used 137
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-224
AUSTIN WOOD RECYCLING(0.19%)
BEAIRD DRILLING(2.68%)
COLLECTIVE CONTRACTING (6.40%)
CP REBAR AND PT INSTALLATION (1.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.45%)
F & W ELECTRICAL CONTRACTORS, INC. (3.47%)
FUQUAY, INC. (0.45%)
HIGHWAY TECHNOLOGIES, INC. (0.57%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.09%)
Z & L CONCRETE CONTRACTORS, INC. (1.19%)
TRI COUNTY SERVICES, INC.(1.19%)
MONTELONGO"S CONCRETE(0.62%)
ROADWAY SPECIALTIES, INC.(0.45%)
S BARRY SIGNATURE HOMES, INC.(1.08%)
CRIBLEY ENTERPRISES, INC.(0.03%)
GEOSOURCE, INC.(1.20%)
SCOTT DERR PAINTING CO, LLC(0.15%)
FLASHER EQUIPMENT COMPANY(0.48%)
DUSTROL, INC.(0.13%)
TEXAS STERLING CONSTRUCTION CO.( 14.73%)
ROADWAY SPECIALTIES, INC.(0.13%)
MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (0.41%)
FUQUAY, INC. (0.49%)
F & W ELECTRICAL CONTRACTORS, INC. (1.41%)
S & S BRIDGE PAINTING, INC.(0.16%)
FLASHER EQUIPMENT COMPANY(0.00%)
Contract # 08103240
Totals 26448884.65 105.90 25615672.50 99.8

CountyBEXAR
Highway VA
From IH 35 AND VARIOUS LOCATIONS_IN
To BEXAR COUNTY
CSJ 0915-12-494
Proj ID STP 2012(531)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2893180.08 50106.01 2296225.51 83.1
Work Order 07-12-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 386
Percent Time Used 157
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-494
F & W ELECTRICAL CONTRACTORS, INC. ( 17.08%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.87%)
JCD CONSTRUCTION, LLC( 46.25%)
DAVID"S QUALITY CONCRETE WORK(6.43%)
Z & L CONCRETE CONTRACTORS, INC. (2.50%)
Contract # 05123211
Totals 2893180.08 50106.01 2296225.51 83.1

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-521
Proj ID STP 2014(623)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1885777.35 71067.01 236508.66 12.5
Work Order 06-20-14
Work Began 09-18-14
Work Completed  
Time Computed 09-18-14
Contract Working Days 243
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 17
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-521
AMERICAN SIGNAL EQUIPMENT CO.(7.73%)
Contract # 05143224
Totals 1885777.35 71067.01 236508.66 12.5

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-530
Proj ID STP 2015(199)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2958588.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-530
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143225
Totals 2958588.16 0.00 0.00 0.0

CountyFRIO
Highway CR
From CR 2515 (BIEDIGER) @ SAN MIGUEL CK
To .
CSJ 0915-18-028
Proj ID BR 2012(237)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 235336.60 0.00 227542.38 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 04-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 100
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-18-028
ALTUS TRAFFIC MANAGEMENT LLC (0.74%)
VOGES DRILLING CO. (9.36%)
RICE ENVIRONMENTAL SERVICES( 18.67%)
JUST GROOVING, LTD.(0.33%)
Contract # 01143011
Totals 235336.60 0.00 227542.38 96.6

CountyUVALDE
Highway PW
From IN GARNER STATE PARK
To .
CSJ 0915-20-015
Proj ID C 915-20-15
Work Type GRAD, BASE, SURF
 
0.001 891460.49 0.00 547276.13 62.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 07-14-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 134
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-20-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143030
Totals 891460.49 0.00 547276.13 62.5

CountyGUADALUPE
Highway VA
From IN THE CITY OF SEGUIN
To ALONG WALNUT BRANCH
CSJ 0915-46-039
Proj ID STP 2011(245)TE
Work Type GRAD, BASE, SURF, STR, SIGN
 
0.001 2524283.53 182999.26 569310.97 22.5
Work Order 07-25-14
Work Began 10-06-14
Work Completed  
Time Computed 10-06-14
Contract Working Days 206
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 15
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-46-039
ROADWAY SPECIALTIES, INC.(3.90%)
S & S BRIDGE PAINTING, INC.(0.11%)
DOUBLE S PAVING, INC.(0.32%)
BACKYARD RENOVATIONS (2.79%)
EGGEMEYER LAND CLEARING, LLC (3.75%)
FUQUAY, INC. (1.43%)
TRP CONSTRUCTION GROUP, LLC(0.99%)
FLASHER EQUIPMENT COMPANY(0.34%)
W. W. FOUNDATION DRILLING, LTD.(1.50%)
GK CONSTRUCTION, LLC (0.06%)
GALO EQUIPMENT & CONSTRUCTION, LLC (2.47%)
Contract # 06143017
Totals 2524283.53 182999.26 569310.97 22.5

CountyWILSON
Highway FM 541
From US 181
To ATASCOSA / WILSON COUNTY LINE
CSJ 1011-01-035
Proj ID STP 2015(371)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
14.363 5563471.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1011-01-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143030
Totals 5563471.45 0.00 0.00 0.0

CountyATASCOSA
Highway FM 541
From IH 37
To WILSON/ATASCOSA COUNTY LINE
CSJ 1011-02-017
Proj ID STP 2014(624)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
10.896 6730083.75 0.00 476197.05 7.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-24-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 324
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 9
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1011-02-017
RICE ENVIRONMENTAL SERVICES(2.25%)
RAMI MATERIALS TRANSPORT, LLC(3.50%)
FLASHER EQUIPMENT COMPANY(2.46%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 14.39%)
Contract # 05143204
Totals 6730083.75 0.00 476197.05 7.0

CountyUVALDE
Highway RM 1050
From RM 187
To US 83
CSJ 1169-01-023
Proj ID STP 2007(845)
Work Type GRADE, BASE, SURF TREAT & STRUCTURES
 
15.899 8459160.14 0.00 8647752.23 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-11
Work Began 09-05-12
Work Completed 09-16-14
Time Computed 03-04-12
Contract Working Days 390
Addl Days Granted 12
Working Days Charged 401
Percent Time Used 99
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1169-01-023
HIGHWAY TECHNOLOGIES, INC. (1.07%)
RELMCO, INC. (9.60%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.45%)
M.V. HENKE ENTERPRISES, INC. (3.93%)
FLASHER EQUIPMENT COMPANY(2.45%)
FUQUAY, INC. (3.50%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (4.85%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.06%)
LAREDO STRIPING INC. (1.21%)
Contract # 10113002
Totals 8459160.14 0.00 8647752.23 100.0

CountyCOMAL
Highway FM 1101
From SH 46
To 0.5 MI N OF FM 306
CSJ 1272-01-016
Proj ID STP 2014(564)
Work Type BASE, GR, STR, SIDEWALK
 
2.797 6154722.50 0.00 0.00 0.0
Work Order 06-02-14
Work Began 00-00-00
Work Completed  
Time Computed 11-29-14
Contract Working Days 354
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143002
Totals 6154722.50 0.00 0.00 0.0

CountyFRIO
Highway FM 1581
From FM 117
To CR 4440
CSJ 1499-01-028
Proj ID STP 2015(372)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
3.432 1913736.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1499-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143016
Totals 1913736.35 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6