Monthly State Let Construction Report For San Antonio District As Of Nov 20, 2014 Page 5 Of 6

Last Update: Thursday, November 20, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-160
Proj ID STP 2013(404)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1179951.00 18855.00 342975.87 31.6
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 172
Percent Time Used 53
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-160
JND CONSTRUCTION CONSULTANTS, LLC( 13.54%)
VACA UNDERGROUND UTILITIES INC (3.44%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.69%)
BEAIRD DRILLING(0.16%)
YORK & YORK FOUNDATION DRILLING, INC.(3.55%)
JCH CONSTRUCTION, INC. (0.05%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.03%)
Contract # 02133216
Totals 1179951.00 18855.00 342975.87 31.6

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-163
Proj ID STP 2012(312)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 942875.75 0.00 984638.97 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-22-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 91
Working Days Charged 231
Percent Time Used 59
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-163
HEARN CO.(6.17%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (4.03%)
JA&M CONSTRUCTION, LLC (1.33%)
JCD CONSTRUCTION, LLC(2.82%)
Contract # 02123027
Totals 942875.75 0.00 984638.97 99.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-164
Proj ID STP 2013(405)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1218087.00 1976.62 486451.86 40.1
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 44
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-164
JND CONSTRUCTION CONSULTANTS, LLC( 13.12%)
VACA UNDERGROUND UTILITIES INC (3.34%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.33%)
BEAIRD DRILLING(0.32%)
YORK & YORK FOUNDATION DRILLING, INC.(3.44%)
JCH CONSTRUCTION, INC. (0.17%)
Contract # 02133013
Totals 1218087.00 1976.62 486451.86 40.1

CountyBEXAR
Highway CS
From IN SAN ANTONIO ON SOMERSET RD
To AT LEON CREEK
CSJ 0915-12-218
Proj ID BR 96(351)
Work Type REHABILITATE BRIDGE & APPROACHES
 
0.001 425301.50 0.00 250212.50 63.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 06-11-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 153
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-218
ABC EROSION CONTROL, INC.( 14.56%)
AMERICAN SIGNAL EQUIPMENT CO.(2.16%)
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
Contract # 03143007
Totals 425301.50 0.00 250212.50 63.6

CountyBEXAR
Highway MH
From WURZBACH PARKWAY ON NEW LOCATION
To FROM FM 2696 TO WEST AVE
CSJ 0915-12-224
Proj ID C 915-12-224
Work Type GRAD, STRS, BASE & SURF
 
1.499 24686408.64 0.00 23966324.67 99.9
CountyBEXAR
Highway MH
From ON EAST-WEST PKWY FROM LOCKHILL-SEL
To IH 35 IN SAN ANTONIO
CSJ 8000-15-007
Proj ID RW 8000-15-7
Work Type ACQUISITION OF ROW
 
0.001 1762476.01 0.00 1649241.93 93.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-10
Work Began 01-04-11
Work Completed  
Time Computed 00-00-00
Contract Working Days 273
Addl Days Granted 297
Working Days Charged 783
Percent Time Used 137
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-224
AUSTIN WOOD RECYCLING(0.19%)
BEAIRD DRILLING(2.68%)
COLLECTIVE CONTRACTING (6.40%)
CP REBAR AND PT INSTALLATION (1.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.45%)
F & W ELECTRICAL CONTRACTORS, INC. (3.47%)
FUQUAY, INC. (0.45%)
HIGHWAY TECHNOLOGIES, INC. (0.57%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.09%)
Z & L CONCRETE CONTRACTORS, INC. (1.19%)
TRI COUNTY SERVICES, INC.(1.19%)
MONTELONGO"S CONCRETE(0.62%)
ROADWAY SPECIALTIES, INC.(0.45%)
S BARRY SIGNATURE HOMES, INC.(1.08%)
CRIBLEY ENTERPRISES, INC.(0.03%)
GEOSOURCE, INC.(1.20%)
SCOTT DERR PAINTING CO, LLC(0.15%)
FLASHER EQUIPMENT COMPANY(0.48%)
DUSTROL, INC.(0.13%)
TEXAS STERLING CONSTRUCTION CO.( 14.73%)
ROADWAY SPECIALTIES, INC.(0.13%)
MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (0.41%)
FUQUAY, INC. (0.49%)
F & W ELECTRICAL CONTRACTORS, INC. (1.41%)
S & S BRIDGE PAINTING, INC.(0.16%)
FLASHER EQUIPMENT COMPANY(0.00%)
Contract # 08103240
Totals 26448884.65 0.00 25615566.60 99.8

CountyBEXAR
Highway VA
From IH 35 AND VARIOUS LOCATIONS_IN
To BEXAR COUNTY
CSJ 0915-12-494
Proj ID STP 2012(531)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2893180.08 0.00 2246119.50 81.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 09-10-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 155
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-494
F & W ELECTRICAL CONTRACTORS, INC. ( 17.08%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.87%)
JCD CONSTRUCTION, LLC( 46.25%)
DAVID"S QUALITY CONCRETE WORK(6.43%)
Z & L CONCRETE CONTRACTORS, INC. (2.50%)
Contract # 05123211
Totals 2893180.08 0.00 2246119.50 81.2

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-521
Proj ID STP 2014(623)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1885777.35 0.00 165441.65 8.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 09-18-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 243
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 12
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-521
AMERICAN SIGNAL EQUIPMENT CO.(7.73%)
Contract # 05143224
Totals 1885777.35 0.00 165441.65 8.7

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-530
Proj ID STP 2015(199)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2958588.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-530
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143225
Totals 2958588.16 0.00 0.00 0.0

CountyFRIO
Highway CR
From CR 2515 (BIEDIGER) @ SAN MIGUEL CK
To .
CSJ 0915-18-028
Proj ID BR 2012(237)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 235336.60 0.00 227542.38 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 04-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 100
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-18-028
ALTUS TRAFFIC MANAGEMENT LLC (0.74%)
VOGES DRILLING CO. (9.36%)
RICE ENVIRONMENTAL SERVICES( 18.67%)
JUST GROOVING, LTD.(0.33%)
Contract # 01143011
Totals 235336.60 0.00 227542.38 96.6

CountyUVALDE
Highway PW
From IN GARNER STATE PARK
To .
CSJ 0915-20-015
Proj ID C 915-20-15
Work Type GRAD, BASE, SURF
 
0.001 891460.49 197285.68 547276.13 62.5
Work Order 04-15-14
Work Began 07-14-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 134
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-20-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143030
Totals 891460.49 197285.68 547276.13 62.5

CountyGUADALUPE
Highway VA
From IN THE CITY OF SEGUIN
To ALONG WALNUT BRANCH
CSJ 0915-46-039
Proj ID STP 2011(245)TE
Work Type GRAD, BASE, SURF, STR, SIGN
 
0.001 2524283.53 0.00 386311.71 15.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-25-14
Work Began 10-06-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 206
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 9
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-46-039
ROADWAY SPECIALTIES, INC.(3.90%)
S & S BRIDGE PAINTING, INC.(0.11%)
DOUBLE S PAVING, INC.(0.32%)
BACKYARD RENOVATIONS (2.79%)
EGGEMEYER LAND CLEARING, LLC (3.75%)
FUQUAY, INC. (1.43%)
TRP CONSTRUCTION GROUP, LLC(0.99%)
FLASHER EQUIPMENT COMPANY(0.34%)
W. W. FOUNDATION DRILLING, LTD.(1.50%)
Contract # 06143017
Totals 2524283.53 0.00 386311.71 15.3

CountyATASCOSA
Highway FM 541
From IH 37
To WILSON/ATASCOSA COUNTY LINE
CSJ 1011-02-017
Proj ID STP 2014(624)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
10.896 6730083.75 0.00 435386.52 6.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-24-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 324
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 6
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1011-02-017
RICE ENVIRONMENTAL SERVICES(2.25%)
RAMI MATERIALS TRANSPORT, LLC(3.50%)
FLASHER EQUIPMENT COMPANY(2.46%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 14.39%)
Contract # 05143204
Totals 6730083.75 0.00 435386.52 6.4

CountyUVALDE
Highway RM 1050
From RM 187
To US 83
CSJ 1169-01-023
Proj ID STP 2007(845)
Work Type GRADE, BASE, SURF TREAT & STRUCTURES
 
15.899 8459160.14 0.00 8647752.23 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-11
Work Began 09-05-12
Work Completed 09-16-14
Time Computed 03-04-12
Contract Working Days 390
Addl Days Granted 12
Working Days Charged 401
Percent Time Used 99
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1169-01-023
HIGHWAY TECHNOLOGIES, INC. (1.07%)
RELMCO, INC. (9.60%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.45%)
M.V. HENKE ENTERPRISES, INC. (3.93%)
FLASHER EQUIPMENT COMPANY(2.45%)
FUQUAY, INC. (3.50%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (4.85%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.06%)
LAREDO STRIPING INC. (1.21%)
Contract # 10113002
Totals 8459160.14 0.00 8647752.23 100.0

CountyCOMAL
Highway FM 1101
From SH 46
To 0.5 MI N OF FM 306
CSJ 1272-01-016
Proj ID STP 2014(564)
Work Type BASE, GR, STR, SIDEWALK
 
2.797 6154722.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 354
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143002
Totals 6154722.50 0.00 0.00 0.0

CountyFRIO
Highway FM 1582
From SP 581
To SH 85
CSJ 1500-01-023
Proj ID STP 2013(717)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
9.939 8831027.89 0.00 103628.80 1.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 338
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 4
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1500-01-023
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33%)
A BROTHERS MILLING, LLC(1.74%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (4.83%)
FUQUAY, INC. (1.66%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.48%)
Contract # 06143245
Totals 8831027.89 0.00 103628.80 1.1

CountyBEXAR
Highway PA 1502
From O'CONNER
To WETMORE
CSJ 1502-03-002
Proj ID NH 2014(625)
Work Type SURF, PAV'T MRKINGS
 
4.762 2894774.15 0.00 2177476.87 75.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-14
Work Began 08-18-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 55
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1502-03-002
A BROTHERS MILLING, LLC(6.25%)
FLASHER EQUIPMENT COMPANY(6.35%)
Contract # 04143235
Totals 2894774.15 0.00 2177476.87 75.2

CountyUVALDE
Highway FM 481
From AT NUECES RIVER
To .
CSJ 1590-01-021
Proj ID BR 2012(755)
Work Type GRAD, STRS, BASE & SURF
 
0.332 2663512.88 66613.00 2039823.73 79.8
Work Order 09-24-12
Work Began 05-15-13
Work Completed  
Time Computed 10-10-12
Contract Working Days 231
Addl Days Granted 21
Working Days Charged 363
Percent Time Used 144
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1590-01-021
W. W. FOUNDATION DRILLING, LTD.(2.16%)
FLASHER EQUIPMENT COMPANY(0.50%)
O & S TRAFFIC SUPPLIES (0.33%)
Contract # 08123039
Totals 2663512.88 66613.00 2039823.73 79.8

CountyCOMAL
Highway FM 306
From 0.5 MI NORTH OF HUNTER ROAD
To IH 35
CSJ 1728-02-037
Proj ID STP 2012(694)
Work Type GRAD, STR, BASE, SURF
 
2.046 6197894.34 -242706.14 7057023.29 99.9
CountyCOMAL
Highway FM 306
From IN NEW BRAUNFELS AT UPRR CROSSING
To DOT 415536E
CSJ 1728-02-049
Proj ID STP 2012(695)RGS
Work Type CONSTRUCT RR GRADE SEPARATION STR &
 
0.500 7368312.94 312608.86 5407034.84 73.3
CountyCOMAL
Highway FM 306
From IN NEW BRAUNFELS AT UPRR CROSSING
To .
CSJ 1728-02-050
Proj ID STP 2012(695)RGS
Work Type CONSTRUCT RR GRADE SEPARATION STR &
 
0.530 9572658.52 201869.13 5880426.81 61.4
Work Order 10-24-12
Work Began 03-12-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 587
Addl Days Granted 0
Working Days Charged 415
Percent Time Used 70
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-037
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.91%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.10%)
GK CONSTRUCTION, LLC (0.35%)
PRIMATE CONSTRUCTION, INC. (0.05%)
THE LEVY COMPANY, L.P. (1.15%)
R K STEPHENS CONSTRUCTION, LLC (2.90%)
ROADWAY SPECIALTIES, INC.(0.18%)
SCOTT DERR PAINTING CO, LLC(0.17%)
VOGES DRILLING CO. (1.00%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.57%)
CATO DRILLING COMPANY(0.01%)
FLASHER EQUIPMENT COMPANY(0.88%)
Contract # 08123202
Totals 23138865.80 271771.85 18344484.94 79.2

CountyFRIO
Highway FM 462
From MOORE (STA 0+15)
To FM 472 IN BIG FOOT
CSJ 1729-01-015
Proj ID STP 2013(106)
Work Type GRAD, STR, BASE, SURF
 
8.382 4686835.06 0.00 4298855.56 91.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-13
Work Began 08-26-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 287
Percent Time Used 79
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1729-01-015
ROADWAY SPECIALTIES, INC.(1.86%)
MURRAY CONSTRUCTION(1.11%)
FLASHER EQUIPMENT COMPANY(2.75%)
M.V. HENKE ENTERPRISES, INC. (0.73%)
RELMCO, INC. ( 12.71%)
W. W. FOUNDATION DRILLING, LTD.(0.97%)
VOGES DRILLING CO. (0.96%)
Contract # 10123218
Totals 4686835.06 0.00 4298855.56 91.7

CountyATASCOSA
Highway FM 2504
From SH 173
To 1.8 MI S OF FM 476
CSJ 1738-02-013
Proj ID C 1738-2-13
Work Type GRADE, BASE & SURF
 
7.750 3839024.80 0.00 3702977.69 97.5
CountyATASCOSA
Highway FM 2504
From 1.8 MI S OF FM 476
To FM 476
CSJ 1740-02-028
Proj ID C 1740-2-28
Work Type GRADE, BASE & SURF
 
1.841 1065719.82 0.00 1085442.28 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-12
Work Began 10-15-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 186
Addl Days Granted 8
Working Days Charged 238
Percent Time Used 122
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1738-02-013
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.21%)
M.V. HENKE ENTERPRISES, INC. (0.40%)
TEXAS ALTERNATIVE GRASSER, INC.(1.51%)
E-Z BEL CONSTRUCTION, LLC(0.53%)
FLASHER EQUIPMENT COMPANY(3.30%)
RICE ENVIRONMENTAL SERVICES(2.73%)
RELMCO, INC. (3.73%)
Contract # 06123204
Totals 4904744.62 0.00 4788419.97 98.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6