Monthly State Let Construction Report For San Antonio District As Of Dec 10, 2014 Page 3 Of 6

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway IH 37 ETC
From US 181
To 1.7 MI S OF US 181
CSJ 0073-08-170
Proj ID STP 2015(023)HESG
Work Type INSTALL MEDIAN BARRIER
 
29.158 2166182.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-170
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143232
Totals 2166182.00 0.00 0.00 0.0

CountyBEXAR
Highway US 281 ETC
From SP 537
To NEWELL STREET
CSJ 0073-08-171
Proj ID STP 2015(028)HESG
Work Type INSTALL PAVMT MARKING ON SHOULDERS
 
42.170 463311.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-171
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143017
Totals 463311.40 0.00 0.00 0.0

CountyBEXAR
Highway US 281
From 0.2 MI N OF STADIUM DR
To N ST MARY'S ST
CSJ 0073-08-173
Proj ID NH 2013(708)
Work Type LANDSCAPE DEVELOPMENT
 
0.600 143550.00 1000.00 114735.00 79.9
Work Order 08-12-13
Work Began 09-09-13
Work Completed  
Time Computed 09-09-13
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 50
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-173
N-LINE TRAFFIC MAINTENANCE, L.P. (4.33%)
Contract # 05133004
Totals 143550.00 1000.00 114735.00 79.9

CountyBEXAR
Highway US 281
From AT MULBERRY AND AT ST. MARYS
To .
CSJ 0073-08-179
Proj ID NH 2015(286)
Work Type TRAFFIC SIGNALS
 
0.140 498706.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-179
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143006
Totals 498706.61 0.00 0.00 0.0

CountyATASCOSA
Highway US 281A
From 0.246 MILES N. OF FM 140
To 0.170 MILES S. OF FM 1099
CSJ 0073-13-009
Proj ID STP 2015(368)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
2.566 1478559.36 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-13-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143004
Totals 1478559.36 0.00 0.00 0.0

CountyBEXAR
Highway US 181
From IH 37
To LOOP 1604
CSJ 0100-02-064
Proj ID STP 2015(288)HESG
Work Type GR, BASE, SURF, PAVMT MARKINGS
 
5.595 772166.28 0.00 0.00 0.0
CountyBEXAR
Highway SH 16
From SMITH STREET
To ATASCOSA COUNTY LINE
CSJ 0613-01-061
Proj ID STP 2015(287)HESG
Work Type GR, BASE, SURF
 
2.184 235123.34 0.00 0.00 0.0
CountyBEXAR
Highway SH 151
From LOOP 1604
To US 90
CSJ 3508-01-027
Proj ID STP 2015(289)HESG
Work Type GR, BASE, SURF, TEXT SHLDRS & PVMT MRKS
 
10.134 547672.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 141
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FENTON EXCAVATING & CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-02-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143020
Totals 1554962.12 0.00 0.00 0.0

CountyWILSON
Highway US 181
From LP 181 N OF FLORESVILLE
To PAJARITO CREEK
CSJ 0100-03-071
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
5.850 70512.50 260.00 76502.86 99.9
CountyWILSON
Highway SH 97
From SAN ANTONIO RIVER
To 0.8 MI E OF SAN ANTONIO RIVER
CSJ 0328-02-042
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
0.800 19058.60 220.00 17721.19 92.9
Work Order 06-18-12
Work Began 10-22-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 38
Addl Days Granted 10
Working Days Charged 40
Percent Time Used 83
Contractor(s)
ALTEX LANDSCAPE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-071
LONESTAR TRAFFIC SAFETY, LLC (2.84%)
Contract # 05123053
Totals 89571.10 480.00 94224.05 99.9

CountyWILSON
Highway US 181 ETC
From AT SH 97 WEST
To .
CSJ 0100-03-076
Proj ID STP 1302(005)G
Work Type TRAFFIC CONTROL DEVICE
 
0.007 507653.58 7877.30 490633.30 96.7
Work Order 10-17-13
Work Began 02-25-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 100
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-076
YORK & YORK FOUNDATION DRILLING, INC.( 12.41%)
UNITED PAVEMENT & MARKINGS, LLC(3.28%)
JND CONSTRUCTION CONSULTANTS, LLC(5.45%)
THOMPSON CONSTRUCTION(7.46%)
VACA UNDERGROUND UTILITIES INC (1.47%)
M & M STRIPING & POWER WASHING, LLC(3.94%)
Contract # 09133039
Totals 507653.58 7877.30 490633.30 96.7

CountyKENDALL
Highway RM 473 ETC
From RM 473 (WEST)
To RM 473 (EAST)
CSJ 0142-09-041
Proj ID STP 2014(222)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
200.087 5605392.71 28899.54 5521502.61 98.6
Work Order 12-10-13
Work Began 06-18-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 103
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0142-09-041
FLASHER EQUIPMENT COMPANY( 15.80%)
WEST TEXAS RUMBLE STRIP(0.08%)
VIZCAINO, L.P. (3.61%)
Contract # 11133212
Totals 5605392.71 28899.54 5521502.61 98.6

CountyWILSON
Highway US 87
From 0.5 MI S OF FM 775
To FM 539
CSJ 0143-03-042
Proj ID C 143-3-42
Work Type WIDEN RDWY TO PROVIDE PASSING LANE
 
6.263 1615779.28 17698.14 1467996.29 89.7
CountyWILSON
Highway US 87
From FM 539
To 0.5 MI E OF FM 538
CSJ 0143-04-064
Proj ID C 143-4-64
Work Type WIDEN RDWY TO PROVIDE PASSING LANES
 
9.751 1432455.49 9955.20 1280798.23 89.4
CountyWILSON
Highway US 87
From 0.5 MI E OF FM 538
To WILSON/GONZALEZ C/L
CSJ 0143-05-031
Proj ID C 143-5-31
Work Type WIDEN RDWY TO PROVIDE PASSING_LANES
 
8.970 2211388.71 15485.87 2934630.02 99.9
Work Order 09-13-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 225
Percent Time Used 89
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0143-03-042
RICE ENVIRONMENTAL SERVICES(3.75%)
MURRAY CONSTRUCTION(0.55%)
M.V. HENKE ENTERPRISES, INC. (0.38%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.20%)
HIGHWAY TECHNOLOGIES, INC. (5.69%)
RELMCO, INC. ( 13.52%)
FLASHER EQUIPMENT COMPANY(0.37%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (7.12%)
FLASHER EQUIPMENT COMPANY(5.43%)
Contract # 07123227
Totals 5259623.48 43139.21 5683424.54 99.9

CountyKERR
Highway SH 39
From 0.1 MI E OF SH 27
To NEW INGRAM LAKE DAM
CSJ 0193-02-031
Proj ID C 193-2-31
Work Type GR, STRS, BASE & SURF
 
1.267 7644985.97 184065.04 4703077.98 62.6
Work Order 10-12-12
Work Began 01-21-13
Work Completed  
Time Computed 10-28-12
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 420
Percent Time Used 121
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-031
RAMMING PAVING COMPANY ( 20.81%)
ALLEN KELLER COMPANY ( 15.12%)
F & W ELECTRICAL CONTRACTORS, INC. (2.51%)
RICE ENVIRONMENTAL SERVICES(1.39%)
W. W. FOUNDATION DRILLING, LTD.(0.89%)
FLASHER EQUIPMENT COMPANY(0.43%)
Contract # 08123027
Totals 7644985.97 184065.04 4703077.98 62.6

CountyKERR
Highway SH 39
From AT HUNT CROSSING
To .
CSJ 0193-02-038
Proj ID BR 2013(715)
Work Type REPLACE NARROW BRIDGE & APPROACHES
 
0.171 2473919.52 4000.00 4000.00 0.1
Work Order 10-28-14
Work Began 12-01-14
Work Completed  
Time Computed 11-13-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-038
VOGES DRILLING CO. (4.94%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.24%)
THE LEVY COMPANY, L.P. (4.53%)
RAMMING PAVING COMPANY (3.81%)
INTERNATIONAL TRAFFIC SAFETY SYSTEMS, - TEXAS, INC.(1.41%)
FLASHER EQUIPMENT COMPANY(1.29%)
Contract # 09143224
Totals 2473919.52 4000.00 4000.00 0.1

CountyCOMAL
Highway BS 46-C
From KERLICK LANE
To LANDA STREET
CSJ 0215-02-048
Proj ID C 215-2-48
Work Type BASE, GRAD, STR, SURF & PAV'T MRK
 
1.085 11041649.54 5679.52 310671.31 2.8
Work Order 06-03-14
Work Began 00-00-00
Work Completed  
Time Computed 11-30-14
Contract Working Days 361
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143203
Totals 11041649.54 5679.52 310671.31 2.8

CountyKENDALL
Highway SH 46
From AT HERFF ROAD
To .
CSJ 0215-06-031
Proj ID STP 2014(726)
Work Type GR, BSE, SURF, PAVT MRK
 
0.587 1830812.97 173071.04 173071.04 9.4
Work Order 07-22-14
Work Began 11-03-14
Work Completed  
Time Computed 09-21-14
Contract Working Days 181
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 9
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-031
FLASHER EQUIPMENT COMPANY(2.43%)
CARMA CONSTRUCTION, LLC(1.61%)
Contract # 06143024
Totals 1830812.97 173071.04 173071.04 9.4

CountyUVALDE
Highway SH 55
From 1.25 MI W OF US 83
To US 83
CSJ 0235-05-030
Proj ID C 235-5-30
Work Type RECONSTRUCT RDWY DRNGE & OP IMRPROV
 
1.250 2921845.37 5740.03 1264727.05 43.2
CountyUVALDE
Highway SH 55
From 1.25 MI W OF US 83
To US 83
CSJ 0235-05-033
Proj ID RW 235-5-033
Work Type ROW UTL. ADJ.
 
1.250 38957.01 0.00 5220.00 13.3
Work Order 09-20-13
Work Began 01-06-14
Work Completed  
Time Computed 11-19-13
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 188
Percent Time Used 64
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0235-05-030
RELMCO, INC. ( 42.89%)
FLASHER EQUIPMENT COMPANY(2.10%)
FUQUAY, INC. (1.63%)
MURRAY CONSTRUCTION(0.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.67%)
Contract # 07133236
Totals 2960802.38 5740.03 1269947.05 42.8

CountyUVALDE
Highway FM 117
From US 83
To 2.0 MILES NORTH OF ZAVALA C/L
CSJ 0236-01-022
Proj ID STP 2015(369)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
6.736 2075091.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0236-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143025
Totals 2075091.20 0.00 0.00 0.0

CountyCOMAL
Highway US 281
From RIVER CROSSING
To BLANCO CO LINE
CSJ 0253-03-043
Proj ID PTF 2012(530)
Work Type GR, STRS, BASE & SURF
 
5.640 22368285.39 119444.01 22635041.01 99.9
Work Order 07-12-12
Work Began 02-11-13
Work Completed  
Time Computed 01-08-13
Contract Working Days 655
Addl Days Granted 20
Working Days Charged 474
Percent Time Used 70
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-043
COWBELL TRAFFIC SERVICES, INC. (0.08%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.18%)
EGGEMEYER LAND CLEARING, LLC (1.11%)
HIGHWAY TECHNOLOGIES, INC. (1.07%)
JUST GROOVING, LTD.(0.04%)
THE LEVY COMPANY, L.P. (1.74%)
MCKINNEY DRILLING COMPANY(0.49%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
NORTH TEXAS REBAR, LLC (0.13%)
ROADWAY SPECIALTIES, INC.(1.10%)
SCOTT DERR PAINTING CO, LLC(0.04%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.69%)
CATO DRILLING COMPANY(0.06%)
CHAPMAN ROCK EXCAVATION, LLC (0.28%)
FLASHER EQUIPMENT COMPANY(1.07%)
Contract # 05123002
Totals 22368285.39 119444.01 22635041.01 99.9

CountyCOMAL
Highway US 281
From AT SH 46
To .
CSJ 0253-03-068
Proj ID C 253-3-68
Work Type CONSTRUCT TURNAROUNDS
 
0.303 3132254.40 34993.74 1719927.91 55.0
Work Order 01-09-14
Work Began 01-27-14
Work Completed  
Time Computed 01-27-14
Contract Working Days 138
Addl Days Granted 44
Working Days Charged 185
Percent Time Used 101
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-068
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
DOUBLE S PAVING, INC.(3.70%)
DUSTROL, INC.(0.44%)
FLASHER EQUIPMENT COMPANY(0.99%)
FUQUAY, INC. (0.53%)
GALO EQUIPMENT & CONSTRUCTION, LLC (0.71%)
GEOSOURCE, INC.(1.02%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(7.05%)
ROADWAY SPECIALTIES, INC.(1.58%)
SCOTT DERR PAINTING CO (0.21%)
CURTIS CONCRETE PUMPING(1.18%)
DRILL TECH DRILLING & SHORING, INC.(4.69%)
Contract # 10133225
Totals 3132254.40 34993.74 1719927.91 55.0

CountyBEXAR
Highway SS 537
From IH 410
To US 281
CSJ 0253-04-148
Proj ID NH 2015(370)
Work Type SURF, PAV'T MRKNGS
 
1.241 1046040.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-148
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143017
Totals 1046040.29 0.00 0.00 0.0

CountyBEXAR
Highway SP 536
From BUSTILLOS DRIVE
To BONNER AVENUE
CSJ 0253-06-035
Proj ID C 253-6-35
Work Type WIDEN FOR CLTL, BIKE LANES & SDWLKS
 
0.702 2509754.04 17666.94 529347.79 21.0
CountyBEXAR
Highway SP 536
From BUSTILLOS DRIVE
To BONNER AVENUE
CSJ 0253-06-036
Proj ID RW 253-6-36
Work Type ROW UTL. ADJ.
 
0.844 177538.00 0.00 0.00 0.0
Work Order 08-19-13
Work Began 06-02-14
Work Completed  
Time Computed 09-04-13
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 38
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-06-035
THE LEVY COMPANY, L.P. (2.01%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.01%)
J.D. RAMMING PAVING CO./AUSTIN MATERIALS LLC ( 32.04%)
Contract # 06133008
Totals 2687292.04 17666.94 529347.79 19.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6