Monthly State Let Construction Report For San Antonio District As Of Nov 20, 2014 Page 3 Of 6

Last Update: Thursday, November 20, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway US 281 ETC
From SP 537
To NEWELL STREET
CSJ 0073-08-171
Proj ID STP 2015(028)HESG
Work Type INSTALL PAVMT MARKING ON SHOULDERS
 
42.170 463311.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-171
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143017
Totals 463311.40 0.00 0.00 0.0

CountyBEXAR
Highway US 281
From 0.2 MI N OF STADIUM DR
To N ST MARY'S ST
CSJ 0073-08-173
Proj ID NH 2013(708)
Work Type LANDSCAPE DEVELOPMENT
 
0.600 143550.00 0.00 113735.00 79.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-12-13
Work Began 09-09-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 50
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-173
N-LINE TRAFFIC MAINTENANCE, L.P. (4.33%)
Contract # 05133004
Totals 143550.00 0.00 113735.00 79.2

CountyBEXAR
Highway US 281
From AT MULBERRY AND AT ST. MARYS
To .
CSJ 0073-08-179
Proj ID NH 2015(286)
Work Type TRAFFIC SIGNALS
 
0.140 498706.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-179
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143006
Totals 498706.61 0.00 0.00 0.0

CountyBEXAR
Highway US 181
From IH 37
To LOOP 1604
CSJ 0100-02-064
Proj ID STP 2015(288)HESG
Work Type GR, BASE, SURF, PAVMT MARKINGS
 
5.595 772166.28 0.00 0.00 0.0
CountyBEXAR
Highway SH 16
From SMITH STREET
To ATASCOSA COUNTY LINE
CSJ 0613-01-061
Proj ID STP 2015(287)HESG
Work Type GR, BASE, SURF
 
2.184 235123.34 0.00 0.00 0.0
CountyBEXAR
Highway SH 151
From LOOP 1604
To US 90
CSJ 3508-01-027
Proj ID STP 2015(289)HESG
Work Type GR, BASE, SURF, TEXT SHLDRS & PVMT MRKS
 
10.134 547672.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 141
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FENTON EXCAVATING & CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-02-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143020
Totals 1554962.12 0.00 0.00 0.0

CountyWILSON
Highway US 181
From LP 181 N OF FLORESVILLE
To PAJARITO CREEK
CSJ 0100-03-071
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
5.850 70512.50 260.00 76242.86 99.9
CountyWILSON
Highway SH 97
From SAN ANTONIO RIVER
To 0.8 MI E OF SAN ANTONIO RIVER
CSJ 0328-02-042
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
0.800 19058.60 220.00 17501.19 91.8
Work Order 06-18-12
Work Began 10-22-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 38
Addl Days Granted 10
Working Days Charged 40
Percent Time Used 83
Contractor(s)
ALTEX LANDSCAPE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-071
LONESTAR TRAFFIC SAFETY, LLC (2.84%)
Contract # 05123053
Totals 89571.10 480.00 93744.05 99.9

CountyWILSON
Highway US 181 ETC
From AT SH 97 WEST
To .
CSJ 0100-03-076
Proj ID STP 1302(005)G
Work Type TRAFFIC CONTROL DEVICE
 
0.007 507653.58 142011.71 482756.00 95.0
Work Order 10-17-13
Work Began 02-25-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 164
Percent Time Used 99
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-076
YORK & YORK FOUNDATION DRILLING, INC.( 12.41%)
UNITED PAVEMENT & MARKINGS, LLC(3.28%)
JND CONSTRUCTION CONSULTANTS, LLC(5.45%)
THOMPSON CONSTRUCTION(7.46%)
VACA UNDERGROUND UTILITIES INC (1.47%)
M & M STRIPING & POWER WASHING, LLC(3.94%)
Contract # 09133039
Totals 507653.58 142011.71 482756.00 95.0

CountyKENDALL
Highway RM 473 ETC
From RM 473 (WEST)
To RM 473 (EAST)
CSJ 0142-09-041
Proj ID STP 2014(222)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
200.087 5605392.71 71432.31 5492603.07 98.0
Work Order 12-10-13
Work Began 06-18-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 103
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0142-09-041
FLASHER EQUIPMENT COMPANY( 15.80%)
WEST TEXAS RUMBLE STRIP(0.08%)
VIZCAINO, L.P. (3.61%)
Contract # 11133212
Totals 5605392.71 71432.31 5492603.07 98.0

CountyWILSON
Highway US 87
From 0.5 MI S OF FM 775
To FM 539
CSJ 0143-03-042
Proj ID C 143-3-42
Work Type WIDEN RDWY TO PROVIDE PASSING LANE
 
6.263 1615779.28 0.00 1438130.68 89.0
CountyWILSON
Highway US 87
From FM 539
To 0.5 MI E OF FM 538
CSJ 0143-04-064
Proj ID C 143-4-64
Work Type WIDEN RDWY TO PROVIDE PASSING LANES
 
9.751 1432455.49 0.00 1270843.03 88.7
CountyWILSON
Highway US 87
From 0.5 MI E OF FM 538
To WILSON/GONZALEZ C/L
CSJ 0143-05-031
Proj ID C 143-5-31
Work Type WIDEN RDWY TO PROVIDE PASSING_LANES
 
8.970 2211388.71 0.00 2919144.15 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 225
Percent Time Used 89
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0143-03-042
RICE ENVIRONMENTAL SERVICES(3.75%)
MURRAY CONSTRUCTION(0.55%)
M.V. HENKE ENTERPRISES, INC. (0.38%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.20%)
HIGHWAY TECHNOLOGIES, INC. (5.69%)
RELMCO, INC. ( 13.52%)
FLASHER EQUIPMENT COMPANY(0.37%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (7.12%)
FLASHER EQUIPMENT COMPANY(5.43%)
Contract # 07123227
Totals 5259623.48 0.00 5628117.86 99.9

CountyKERR
Highway SH 39
From 0.1 MI E OF SH 27
To NEW INGRAM LAKE DAM
CSJ 0193-02-031
Proj ID C 193-2-31
Work Type GR, STRS, BASE & SURF
 
1.267 7644985.97 315489.76 4519012.94 60.0
Work Order 10-12-12
Work Began 01-21-13
Work Completed  
Time Computed 10-28-12
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 406
Percent Time Used 117
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-031
RAMMING PAVING COMPANY ( 20.81%)
ALLEN KELLER COMPANY ( 15.12%)
F & W ELECTRICAL CONTRACTORS, INC. (2.51%)
RICE ENVIRONMENTAL SERVICES(1.39%)
W. W. FOUNDATION DRILLING, LTD.(0.89%)
FLASHER EQUIPMENT COMPANY(0.43%)
Contract # 08123027
Totals 7644985.97 315489.76 4519012.94 60.0

CountyKERR
Highway SH 39
From AT HUNT CROSSING
To .
CSJ 0193-02-038
Proj ID BR 2013(715)
Work Type REPLACE NARROW BRIDGE & APPROACHES
 
0.171 2473919.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-14
Work Began 00-00-00
Work Completed  
Time Computed 11-12-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143224
Totals 2473919.52 0.00 0.00 0.0

CountyCOMAL
Highway BS 46-C
From KERLICK LANE
To LANDA STREET
CSJ 0215-02-048
Proj ID C 215-2-48
Work Type BASE, GRAD, STR, SURF & PAV'T MRK
 
1.085 11041649.54 26921.64 304991.79 2.7
Work Order 06-03-14
Work Began 00-00-00
Work Completed  
Time Computed 11-30-14
Contract Working Days 361
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143203
Totals 11041649.54 26921.64 304991.79 2.7

CountyKENDALL
Highway SH 46
From AT HERFF ROAD
To .
CSJ 0215-06-031
Proj ID STP 2014(726)
Work Type GR, BSE, SURF, PAVT MRK
 
0.587 1830812.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 181
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-031
FLASHER EQUIPMENT COMPANY(2.43%)
Contract # 06143024
Totals 1830812.97 0.00 0.00 0.0

CountyUVALDE
Highway SH 55
From 1.25 MI W OF US 83
To US 83
CSJ 0235-05-030
Proj ID C 235-5-30
Work Type RECONSTRUCT RDWY DRNGE & OP IMRPROV
 
1.250 2921845.37 36524.43 1258987.02 43.0
CountyUVALDE
Highway SH 55
From 1.25 MI W OF US 83
To US 83
CSJ 0235-05-033
Proj ID RW 235-5-033
Work Type ROW UTL. ADJ.
 
1.250 38957.01 5220.00 5220.00 13.3
Work Order 09-20-13
Work Began 01-06-14
Work Completed  
Time Computed 11-19-13
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 174
Percent Time Used 60
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0235-05-030
RELMCO, INC. ( 42.89%)
FLASHER EQUIPMENT COMPANY(2.10%)
FUQUAY, INC. (1.63%)
MURRAY CONSTRUCTION(0.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.67%)
Contract # 07133236
Totals 2960802.38 41744.43 1264207.02 42.6

CountyCOMAL
Highway US 281
From RIVER CROSSING
To BLANCO CO LINE
CSJ 0253-03-043
Proj ID PTF 2012(530)
Work Type GR, STRS, BASE & SURF
 
5.640 22368285.39 2843097.78 22515597.00 99.9
Work Order 07-12-12
Work Began 02-11-13
Work Completed  
Time Computed 01-08-13
Contract Working Days 655
Addl Days Granted 20
Working Days Charged 456
Percent Time Used 67
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-043
COWBELL TRAFFIC SERVICES, INC. (0.08%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.18%)
EGGEMEYER LAND CLEARING, LLC (1.11%)
HIGHWAY TECHNOLOGIES, INC. (1.07%)
JUST GROOVING, LTD.(0.04%)
THE LEVY COMPANY, L.P. (1.74%)
MCKINNEY DRILLING COMPANY(0.49%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
NORTH TEXAS REBAR, LLC (0.13%)
ROADWAY SPECIALTIES, INC.(1.10%)
SCOTT DERR PAINTING CO, LLC(0.04%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.69%)
CATO DRILLING COMPANY(0.06%)
CHAPMAN ROCK EXCAVATION, LLC (0.28%)
FLASHER EQUIPMENT COMPANY(1.07%)
Contract # 05123002
Totals 22368285.39 2843097.78 22515597.00 99.9

CountyCOMAL
Highway US 281
From AT SH 46
To .
CSJ 0253-03-068
Proj ID C 253-3-68
Work Type CONSTRUCT TURNAROUNDS
 
0.303 3132254.40 137488.76 1684934.17 53.7
Work Order 01-09-14
Work Began 01-27-14
Work Completed  
Time Computed 01-27-14
Contract Working Days 138
Addl Days Granted 44
Working Days Charged 167
Percent Time Used 91
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-068
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
DOUBLE S PAVING, INC.(3.70%)
DUSTROL, INC.(0.44%)
FLASHER EQUIPMENT COMPANY(0.99%)
FUQUAY, INC. (0.53%)
GALO EQUIPMENT & CONSTRUCTION, LLC (0.71%)
GEOSOURCE, INC.(1.02%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(7.05%)
ROADWAY SPECIALTIES, INC.(1.58%)
SCOTT DERR PAINTING CO (0.21%)
CURTIS CONCRETE PUMPING(1.18%)
DRILL TECH DRILLING & SHORING, INC.(4.69%)
Contract # 10133225
Totals 3132254.40 137488.76 1684934.17 53.7

CountyBEXAR
Highway SP 536
From BUSTILLOS DRIVE
To BONNER AVENUE
CSJ 0253-06-035
Proj ID C 253-6-35
Work Type WIDEN FOR CLTL, BIKE LANES & SDWLKS
 
0.702 2509754.04 139607.24 511680.85 20.3
CountyBEXAR
Highway SP 536
From BUSTILLOS DRIVE
To BONNER AVENUE
CSJ 0253-06-036
Proj ID RW 253-6-36
Work Type ROW UTL. ADJ.
 
0.844 177538.00 0.00 0.00 0.0
Work Order 08-19-13
Work Began 06-02-14
Work Completed  
Time Computed 09-04-13
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 32
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-06-035
THE LEVY COMPANY, L.P. (2.01%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.01%)
J.D. RAMMING PAVING CO./AUSTIN MATERIALS LLC ( 32.04%)
Contract # 06133008
Totals 2687292.04 139607.24 511680.85 19.0

CountyFRIO
Highway US 57
From FM 140
To IH 35 WB FRONTAGE ROAD
CSJ 0276-07-029
Proj ID STP 1402(014)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
13.066 5946630.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 11-02-14
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0276-07-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143050
Totals 5946630.34 0.00 0.00 0.0

CountyKERR
Highway SH 16
From KERR/GILLESPIE COUNTY LINE
To IH 10
CSJ 0291-02-034
Proj ID STP 2013(718)
Work Type GR, BSE, SURF, PAVT MRK
 
5.647 2985558.94 0.00 253119.37 8.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 239
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 7
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0291-02-034
FLASHER EQUIPMENT COMPANY(3.92%)
AUSTIN WOOD RECYCLING(3.89%)
HUNTER INDUSTRIES, LTD.( 22.66%)
ROADWAY SPECIALTIES, INC.(5.01%)
Contract # 06143049
Totals 2985558.94 0.00 253119.37 8.4

CountyKERR
Highway SH 16
From SH 173
To 0.2 MI. SOUTH OF RIVER HILLS BLVD.
CSJ 0291-03-057
Proj ID STP 2014(016)
Work Type GRAD, BASE, EMBANK, STR, SURF & PAV MRK
 
1.540 1866572.26 76389.50 503424.93 26.9
CountyKERR
Highway SH 16
From FROM SPUR 98
To SH 173
CSJ 0291-03-061
Proj ID STP 2014(016)
Work Type OVERLAY AND PAVEMENT MARKINGS
 
0.803 637966.90 291054.76 563902.69 88.3
Work Order 12-05-13
Work Began 03-05-14
Work Completed  
Time Computed 03-05-14
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 87
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0291-03-057
J.D. RAMMING PAVING CO., LTD.( 43.64%)
ROADWAY SPECIALTIES, INC.(9.17%)
E-Z BEL CONSTRUCTION, LLC(4.38%)
D. I. J. CONSTRUCTION, INC.(2.19%)
FLASHER EQUIPMENT COMPANY(0.55%)
CHEROKEE SERVICES(0.20%)
PENHALL COMPANY (AUSTIN) (0.00%)
CHEROKEE BRIDGE AND ROAD, LTD. (5.78%)
AARON CONCRETE CONTRACTORS, L.P. (1.20%)
SAECO ELECTRIC & UTILITY, LTD. (0.03%)
PERFORMANCE EQUIPMENT SERVICE(1.86%)
Contract # 09133025
Totals 2504539.16 367444.26 1067327.62 42.6

CountyATASCOSA
Highway SH 97
From BROWN AVENUE
To FM 3510
CSJ 0328-04-042
Proj ID STP 1402(015)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
2.020 5025776.24 0.00 0.00 0.0
CountyATASCOSA
Highway SH 97
From SH 16
To BROWN AVENUE
CSJ 0328-05-043
Proj ID STP 1402(015)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
0.122 304963.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-04-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143244
Totals 5330739.44 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6