Monthly State Let Construction Report For San Antonio District As Of Apr 10, 2015 Page 3 Of 6

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway IH 37
From 0.4 MI N OF LP 13
To 0.4 MI S OF LP 13
CSJ 0073-08-167
Proj ID IM 0372(085)
Work Type LANDSCAPE DEVELOPMENT
 
0.850 520750.01 0.00 500960.02 96.1
Work Order 10-18-11
Work Began 10-19-11
Work Completed  
Time Computed 01-03-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-167
DOWN UNDER CONSTRUCTION(0.96%)
LONE STAR TRAFFIC SERVICE, INC.(0.57%)
CRUZ CONTRACTING OF TEXAS, LLC (0.96%)
Contract # 08113005
Totals 520750.01 0.00 500960.02 96.1

CountyBEXAR
Highway US 281
From 0.25 MILES N OF IH 410
To 0.3 MI S OF JONES MALTSBERGER RD
CSJ 0073-08-168
Proj ID NH 2012(288)
Work Type LANDSCAPE DEVELOPMENT
 
1.150 662704.00 2000.00 649282.04 97.9
Work Order 03-16-12
Work Began 04-02-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 93
Addl Days Granted 29
Working Days Charged 116
Percent Time Used 95
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-168
LONE STAR TRAFFIC SERVICE, INC.(0.41%)
FUQUAY, INC. (1.59%)
Contract # 02123205
Totals 662704.00 2000.00 649282.04 97.9

CountyBEXAR
Highway IH 37 ETC
From US 181
To 1.7 MI S OF US 181
CSJ 0073-08-170
Proj ID STP 2015(023)HESG
Work Type INSTALL MEDIAN BARRIER
 
29.158 2166182.00 861688.20 1033343.60 47.7
Work Order 10-17-14
Work Began 01-19-15
Work Completed  
Time Computed 12-16-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 27
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-170
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143232
Totals 2166182.00 861688.20 1033343.60 47.7

CountyBEXAR
Highway US 281 ETC
From SP 537
To NEWELL STREET
CSJ 0073-08-171
Proj ID STP 2015(028)HESG
Work Type INSTALL PAVMT MARKING ON SHOULDERS
 
42.170 463311.40 0.00 475775.96 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 12-15-14
Work Completed 03-12-15
Time Computed 12-08-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 33
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-171
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143017
Totals 463311.40 0.00 475775.96 100.0

CountyBEXAR
Highway US 281
From 0.2 MI N OF STADIUM DR
To N ST MARY'S ST
CSJ 0073-08-173
Proj ID NH 2013(708)
Work Type LANDSCAPE DEVELOPMENT
 
0.600 143550.00 1000.00 118735.00 82.7
Work Order 08-12-13
Work Began 09-09-13
Work Completed  
Time Computed 09-09-13
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 50
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-173
N-LINE TRAFFIC MAINTENANCE, L.P. (4.33%)
Contract # 05133004
Totals 143550.00 1000.00 118735.00 82.7

CountyBEXAR
Highway US 281
From AT MULBERRY AND AT ST. MARYS
To .
CSJ 0073-08-179
Proj ID NH 2015(286)
Work Type TRAFFIC SIGNALS
 
0.140 498706.61 152560.56 152560.56 30.5
Work Order 12-05-14
Work Began 03-03-15
Work Completed  
Time Computed 03-03-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 15
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-179
FLASHER EQUIPMENT COMPANY(3.20%)
SIGNAL SERVICES GROUP( 12.11%)
BAY CITY TRAFFIC (8.56%)
Contract # 11143006
Totals 498706.61 152560.56 152560.56 30.5

CountyBEXAR
Highway IH 37
From S HACKBERRY STREET
To E CESAR E CHAVEZ BLVD
CSJ 0073-08-180
Proj ID NH 2015(581)
Work Type LANDSCAPE DEVELOPMENT
 
1.950 973428.36 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-180
ABM UNDERGROUND UTILITY CONSTRUCTION COMPANY (1.95%)
O & S TRAFFIC SUPPLIES (0.91%)
JTEX CONTRACTING, INC(4.27%)
Contract # 02153205
Totals 973428.36 0.00 0.00 0.0

CountyATASCOSA
Highway US 281A
From 0.246 MILES N. OF FM 140
To 0.170 MILES S. OF FM 1099
CSJ 0073-13-009
Proj ID STP 2015(368)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
2.566 1478559.36 468657.39 468657.39 31.6
Work Order 02-10-15
Work Began 03-09-15
Work Completed  
Time Computed 03-05-15
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 22
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-13-009
D&S TEXAS ICON CONSTRUCTION(2.28%)
ROADWAY SPECIALTIES, INC.(1.49%)
FLASHER EQUIPMENT COMPANY(2.57%)
Contract # 12143004
Totals 1478559.36 468657.39 468657.39 31.6

CountyBEXAR
Highway US 181
From IH 37
To LOOP 1604
CSJ 0100-02-064
Proj ID STP 2015(288)HESG
Work Type GR, BASE, SURF, PAVMT MARKINGS
 
5.595 772166.28 0.00 0.00 0.0
CountyBEXAR
Highway SH 16
From SMITH STREET
To ATASCOSA COUNTY LINE
CSJ 0613-01-061
Proj ID STP 2015(287)HESG
Work Type GR, BASE, SURF
 
2.184 235123.34 0.00 0.00 0.0
CountyBEXAR
Highway SH 151
From LOOP 1604
To US 90
CSJ 3508-01-027
Proj ID STP 2015(289)HESG
Work Type GR, BASE, SURF, TEXT SHLDRS & PVMT MRKS
 
10.134 547672.50 0.00 0.00 0.0
Work Order 01-16-15
Work Began 00-00-00
Work Completed  
Time Computed 03-17-15
Contract Working Days 141
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 7
Contractor(s)
FENTON EXCAVATING & CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-02-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143020
Totals 1554962.12 0.00 0.00 0.0

CountyWILSON
Highway US 181
From LP 181 N OF FLORESVILLE
To PAJARITO CREEK
CSJ 0100-03-071
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
5.850 70512.50 260.00 77542.86 99.9
CountyWILSON
Highway SH 97
From SAN ANTONIO RIVER
To 0.8 MI E OF SAN ANTONIO RIVER
CSJ 0328-02-042
Proj ID NH 2012(529)
Work Type LANDSCAPE DEVELOPMENT
 
0.800 19058.60 220.00 18601.19 97.5
Work Order 06-18-12
Work Began 10-22-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 38
Addl Days Granted 10
Working Days Charged 40
Percent Time Used 83
Contractor(s)
ALTEX LANDSCAPE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-071
LONESTAR TRAFFIC SAFETY, LLC (2.84%)
Contract # 05123053
Totals 89571.10 480.00 96144.05 99.9

CountyWILSON
Highway US 181 ETC
From AT SH 97 WEST
To .
CSJ 0100-03-076
Proj ID STP 1302(005)G
Work Type TRAFFIC CONTROL DEVICE
 
0.007 507653.58 34200.17 560366.79 99.9
Work Order 10-17-13
Work Began 02-25-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 100
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-03-076
YORK & YORK FOUNDATION DRILLING, INC.( 12.41%)
UNITED PAVEMENT & MARKINGS, LLC(3.28%)
JND CONSTRUCTION CONSULTANTS, LLC(5.45%)
THOMPSON CONSTRUCTION(7.46%)
VACA UNDERGROUND UTILITIES INC (1.47%)
M & M STRIPING & POWER WASHING, LLC(3.94%)
Contract # 09133039
Totals 507653.58 34200.17 560366.79 99.9

CountyKENDALL
Highway RM 473 ETC
From RM 473 (WEST)
To RM 473 (EAST)
CSJ 0142-09-041
Proj ID STP 2014(222)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
200.087 5605392.71 7245.00 5551277.59 99.0
Work Order 12-10-13
Work Began 06-18-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 146
Addl Days Granted 5
Working Days Charged 151
Percent Time Used 100
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0142-09-041
FLASHER EQUIPMENT COMPANY( 15.80%)
WEST TEXAS RUMBLE STRIP(0.08%)
VIZCAINO, L.P. (3.61%)
Contract # 11133212
Totals 5605392.71 7245.00 5551277.59 99.0

CountyKERR
Highway SH 39
From 0.1 MI E OF SH 27
To NEW INGRAM LAKE DAM
CSJ 0193-02-031
Proj ID C 193-2-31
Work Type GR, STRS, BASE & SURF
 
1.267 7644985.97 321665.16 5591153.63 75.2
Work Order 10-12-12
Work Began 01-21-13
Work Completed  
Time Computed 10-28-12
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 491
Percent Time Used 142
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-031
RAMMING PAVING COMPANY ( 20.81%)
ALLEN KELLER COMPANY ( 15.12%)
F & W ELECTRICAL CONTRACTORS, INC. (2.51%)
RICE ENVIRONMENTAL SERVICES(1.39%)
W. W. FOUNDATION DRILLING, LTD.(0.89%)
FLASHER EQUIPMENT COMPANY(0.43%)
PRESIDIO CONTRACTING, LLC(0.41%)
Contract # 08123027
Totals 7644985.97 321665.16 5591153.63 75.2

CountyKERR
Highway SH 39
From AT HUNT CROSSING
To .
CSJ 0193-02-038
Proj ID BR 2013(715)
Work Type REPLACE NARROW BRIDGE & APPROACHES
 
0.171 2473919.52 379812.26 1201354.78 48.5
Work Order 10-28-14
Work Began 12-01-14
Work Completed  
Time Computed 11-13-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 56
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-038
VOGES DRILLING CO. (4.94%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.24%)
THE LEVY COMPANY, L.P. (4.53%)
RAMMING PAVING COMPANY (3.81%)
INTERNATIONAL TRAFFIC SAFETY SYSTEMS, - TEXAS, INC.(1.41%)
FLASHER EQUIPMENT COMPANY(1.29%)
Contract # 09143224
Totals 2473919.52 379812.26 1201354.78 48.5

CountyKERR
Highway SH 39
From 2.9 MI EAST OF FM 1340
To 3.6 MI EAST OF FM 1340
CSJ 0193-02-043
Proj ID SFT 193-2-43
Work Type INSTALL ADV WARNING SIGNALS, ETC
 
0.700 49802.56 0.00 0.00 0.0
CountyKERR
Highway SH 16
From FM 1273
To 4 MI S OF FM 1273
CSJ 0291-03-065
Proj ID SFT 291-3-65
Work Type SAFETY TREAT FIXED OBJECT, ETC
 
4.000 1296470.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153211
Totals 1346273.40 0.00 0.00 0.0

CountyCOMAL
Highway BS 46-C
From KERLICK LANE
To LANDA STREET
CSJ 0215-02-048
Proj ID C 215-2-48
Work Type BASE, GRAD, STR, SURF & PAV'T MRK
 
1.085 11041649.54 106799.83 1360465.24 12.3
Work Order 06-03-14
Work Began 12-22-14
Work Completed  
Time Computed 12-22-14
Contract Working Days 361
Addl Days Granted 24
Working Days Charged 31
Percent Time Used 9
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-02-048
FLASHER EQUIPMENT COMPANY(0.58%)
ROADWAY SPECIALTIES, INC.(0.82%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.96%)
GEOSOURCE, INC.(0.10%)
AUSTIN WOOD RECYCLING(1.19%)
LONE STAR HIGHWAY PRODUCTS, INC. (5.08%)
R K STEPHENS CONSTRUCTION, LLC (2.50%)
Contract # 02143203
Totals 11041649.54 106799.83 1360465.24 12.3

CountyKENDALL
Highway SH 46
From AT HERFF ROAD
To .
CSJ 0215-06-031
Proj ID STP 2014(726)
Work Type GR, BSE, SURF, PAVT MRK
 
0.587 1830812.97 153577.62 660591.77 36.0
Work Order 07-22-14
Work Began 11-03-14
Work Completed  
Time Computed 09-21-14
Contract Working Days 181
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 52
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-031
FLASHER EQUIPMENT COMPANY(2.43%)
CARMA CONSTRUCTION, LLC(1.61%)
DOUBLE S PAVING, INC.(3.19%)
Contract # 06143024
Totals 1830812.97 153577.62 660591.77 36.0

CountyUVALDE
Highway SH 55
From 1.25 MI W OF US 83
To US 83
CSJ 0235-05-030
Proj ID C 235-5-30
Work Type RECONSTRUCT RDWY DRNGE & OP IMRPROV
 
1.250 2921845.37 180117.41 1659460.36 56.7
CountyUVALDE
Highway SH 55
From 1.25 MI W OF US 83
To US 83
CSJ 0235-05-033
Proj ID RW 235-5-033
Work Type ROW UTL. ADJ.
 
1.250 38957.01 0.00 5220.00 13.3
Work Order 09-20-13
Work Began 01-06-14
Work Completed  
Time Computed 11-19-13
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 86
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0235-05-030
RELMCO, INC. ( 42.89%)
FLASHER EQUIPMENT COMPANY(2.10%)
FUQUAY, INC. (1.63%)
MURRAY CONSTRUCTION(0.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.67%)
Contract # 07133236
Totals 2960802.38 180117.41 1664680.36 56.2

CountyUVALDE
Highway FM 117
From US 83
To 2.0 MILES NORTH OF ZAVALA C/L
CSJ 0236-01-022
Proj ID STP 2015(369)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
6.736 2075091.20 0.00 0.00 0.0
Work Order 01-13-15
Work Began 00-00-00
Work Completed  
Time Computed 03-14-15
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0236-01-022
INTERSTATE BARRICADES & MARKINGS, INC. (2.10%)
Contract # 12143025
Totals 2075091.20 0.00 0.00 0.0

CountyCOMAL
Highway US 281
From RIVER CROSSING
To BLANCO CO LINE
CSJ 0253-03-043
Proj ID PTF 2012(530)
Work Type GR, STRS, BASE & SURF
 
5.640 22368285.39 81478.96 22967371.21 99.9
Work Order 07-12-12
Work Began 02-11-13
Work Completed  
Time Computed 01-08-13
Contract Working Days 655
Addl Days Granted 20
Working Days Charged 556
Percent Time Used 82
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-043
COWBELL TRAFFIC SERVICES, INC. (0.08%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.18%)
EGGEMEYER LAND CLEARING, LLC (1.11%)
HIGHWAY TECHNOLOGIES, INC. (1.07%)
JUST GROOVING, LTD.(0.04%)
THE LEVY COMPANY, L.P. (1.74%)
MCKINNEY DRILLING COMPANY(0.49%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
NORTH TEXAS REBAR, LLC (0.13%)
ROADWAY SPECIALTIES, INC.(1.10%)
SCOTT DERR PAINTING CO, LLC(0.04%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.69%)
CATO DRILLING COMPANY(0.06%)
CHAPMAN ROCK EXCAVATION, LLC (0.28%)
FLASHER EQUIPMENT COMPANY(1.07%)
Contract # 05123002
Totals 22368285.39 81478.96 22967371.21 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6