August, 2004 (FY 2004) | (see Links) |
SEP 2003 | OCT 2003 | NOV 2003 | DEC 2003 | JAN 2004 | FEB 2004 | MAR 2004 | APR 2004 | MAY 2004 | JUN 2004 | JUL 2004 | AUG 2004 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0911-00-053 | Angelina/ Lufkin |
VA | Approved | $221,254 | 11 | CONSTRUCT CURB RAMPS TO MEET THE TEXAS ACCESSIBILITY |
0911-00-055 | Angelina/ Lufkin |
VA | Approved | $224,509 | 11 | CONSTRUCT CURB RAMPS TO MEET THE TEXAS ACCESSIBILITY AND |
0911-38-057 | Angelina/ Lufkin |
VA | Approved | $455,000 | 9 | CONSTRUCT SIDE WALKS AND ADA RAMPS |
0073-05-060 | Atascosa/ San Antonio |
IH 37 | Approved | $10,162,586 | 1 | REHABILITATE AND WIDEN NARROW PAVEMENT |
0187-03-052 | Austin/ Yoakum |
SH 36 | Approved | $1,190,771 | 11 | DRAINAGE IMPROVEMENTS |
0291-04-019 | Bandera/ San Antonio |
SH 16 | Approved | $825,815 | 10 | FLOOD DAMAGE REPAIR |
0291-06-039 | Bandera/ San Antonio |
SH 16 | Approved | $2,462,006 | 1 | CONSTRUCT LEFT TURN LANE, ACCELLERATION / DECELERATION LANES & |
0792-04-036 | Bandera/ San Antonio |
FM 470 | Tentative | $18,362 | 10 | REMOVE & REPLACE RIPRAP & DEBRIS REMOVAL |
0088-01-056 | Bee/ Corpus Christi |
US 59 | Approved | $1,442,645 | 1 | IMPROVE HORIZONTAL ALIGNMENT |
0231-03-114 | Bell/ Waco |
US 190 | Approved | $1,160,375 | 11 | RELOCATE RAMPS AND ADD AUXILIARY LANE |
0320-05-012 | Bell/ Waco |
LP 363 | Approved | $2,802,243 | 1 | SEAL COAT AND ASPHALT CONCRETE PAVEMENT OVERLAY |
0113-04-019 | Blanco/ Austin |
US 290 | Approved | $1,228,621 | 1 | MILL, ULTRA THIN BONDED WEARING COURS |
1020-01-044 | Bowie/ Atlanta |
FM 559 | Approved | $416,252 | 6 | REHABILITATE BRIDGE AND APPROACHES |
0050-01-060 | Brazos/ Bryan |
BS 6-R | Approved | $14,302,246 | ROW | THE WIDENING OF A NON - FREEWAY FACILITY CONSISTING OF GRADING |
0116-04-090 | Brazos/ Bryan |
SH 21 | Approved | $134,707 | 10 | MISCELLANEOUS WORK CONSISTING OF LANDSCAPE DEVELOPMENT |
0054-06-084 | Brown/ Brownwood |
US 67 | Approved | $286,191 | 10 | LANDSCAPE DEVELOPMENT |
0116-02-027 | Burleson/ Bryan |
SH 21 | Approved | $25,811,084 | 8 | WIDEN NON - FREEWAY FACILITY CONSISTING OF GRADING, STRUCTURES |
0700-01-025 | Burnet/ Austin |
SH 71 | Approved | $2,223,009 | 6 | REPLACE BRIDGE AND APPROACHES |
0914-24-008 | Burnet/ Austin |
CR | Approved | $187,992 | 6 | REPLACE BRIDGE AND APPROACHES |
0152-02-061 | Caldwell/ Austin |
US 183 | Approved | $3,529,857 | 1 | SEAL COAT AND LEVEL - UP |
0921-06-177 | Cameron/ Pharr |
CS | Approved | $835,447 | 10 | ROAD IMPROVEMENTS |
1019-02-022 | Camp/ Atlanta |
FM 557 | Approved | $964,237 | 8 | IMPROVE HORIZONTAL ALIGNMENT ON 2 - LANE RURAL HIGHWAY |
0446-03-046 | Colorado/ Yoakum |
US 90A | Approved | $1,051,978 | 1 | ASPHALTIC CONCRETE PAVEMENT |
0194-02-082 | Cooke/ Wichita Falls |
IH 35 | Approved | $2,081,034 | 1 | INSTALL MEDIAN BARRIER |
0231-02-046 | Coryell/ Waco |
US 190 | Approved | $2,511,180 | 1 | ULTRA THIN BONDED WEARING COURSE |
0047-07-192 | Dallas/ Dallas |
US 75 | Tentative | $225,000 | 1 | REHABILITATE VARIOUS PIECES OF VIDEO TRANSMISSION EQUIPT. |
0047-07-199 | Dallas/ Dallas |
US 75 | Tentative | $1,500,000 | 1 | REHABILITATE VIDEO EQUIPMENT |
0196-03-236 | Dallas/ Dallas |
IH 35E | Approved | $1,613,763 | 1 | PLANING AND OVERLAY |
0261-03-050 | Dallas/ Dallas |
US 67 | Approved | $1,494,643 | 1 | SURFACE TEXTURING |
0261-03-051 | Dallas/ Dallas |
US 67 | Approved | $276,701 | 1 | FULL DEPTH PVMT REPAIR |
0918-00-078 | Dallas/ Dallas |
VA | Approved | $1,030,538 | 1 | NON - SITE SPECIFIC TRAFFIC SIGNAL CONTRACT |
0918-45-441 | Dallas/ Dallas |
CS | Approved | $95,892 | 8 | TRAFFIC SIGNAL INSTALLATION |
0918-45-619 | Dallas/ Dallas |
CS | Approved | $515,988 | 5 | 1 OFF SYSTEM INTERSECTION IMPROVEMENT |
0918-45-676 | Dallas/ Dallas |
CS | Tentative | 5 | ACQUISITION AND UTILITIES | |
0195-03-064 | Denton/ Dallas |
IH 35E | Approved | $277,628 | 1 | REPLACE SAFETY LIGHTING SYSTEMS |
0196-01-092 | Denton/ Dallas |
IH 35E | Approved | $947,245 | 11 | SWITCH EXISTING SOUTHBOUND ENTRANCE AND EXIT RAMPS |
0042-07-051 | Donley/ Childress |
US 287 | Approved | $2,402,125 | 11 | OVERLAY |
0007-05-008 | Eastland/ Brownwood |
LP 254 | Approved | $1,636,163 | 1 | ACP, CURB & GUTTER, TRAFFIC SIGNAL, ILLUMINATION & RR |
0923-09-039 | Eastland/ Brownwood |
VA | Approved | $899,429 | 1 | REHABILITATE SAFETY LIGHTING |
0005-01-095 | Ector/ Odessa |
BI 20-E | Approved | $386,860 | 1 | BRIDGE REHABILITATION |
2296-01-044 | Ector/ Odessa |
SH 191 | Approved | $45,273 | 9 | CONSTRUCT PEDESTRIAN CROSSINGS |
0924-00-036 | El Paso/ El Paso |
VA | Approved | $3,859,868 | 10 | BRIDGE OF THE AMERICAS PORT OF ENTRY BORDER SAFETY |
0924-06-163 | El Paso/ El Paso |
CS | Approved | $1,229,652 | 7 | RECONSTRUCT MAGOFFIN AVE. |
0924-06-221 | El Paso/ El Paso |
CS | Approved | $4,765,366 | 5 | TRAFFIC LIGHT SYNCHRONIZATION PHASES IV |
2121-02-114 | El Paso/ El Paso |
IH 10 | Approved | $10,277,455 | 1 | REMOVE E - 3 RAIL AND REPLACE WITH CTB |
0260-02-036 | Ellis/ Dallas |
US 67 | Approved | $1,279,017 | 1 | MILLING OF MAIN LANES, 1" ACP OVERLAY AND NOVACHIP SEAL OF |
0442-03-031 | Ellis/ Dallas |
IH 35E | Approved | $49,588,953 | 11 | RECONSTRUCT AND ADD 2 MAIN LANES |
0314-04-032 | Erath/ Fort Worth |
IH 20 | Approved | $19,814,136 | 1 | REHABILITATION OF THE EXISTING MAIN LANES AND SHOULDERS |
0913-28-047 | Fayette/ Yoakum |
CS | Approved | $182,000 | 9 | RESTORE HISTORIC TRAIN DEPOT |
0027-08-108 | Fort Bend/ Houston |
US 90A | Approved | $36,089,258 | 6 | WIDEN TO 8 - LANE DIVIDED WITH IMPROVEMENTS AT DITCH "H" |
0389-06-087 | Galveston/ Houston |
SH 146 | Approved | $6,500,391 | 1 | GRADE SEPARATION |
0113-02-049 | Gillespie/ Austin |
US 290 | Approved | $1,313,972 | 1 | SEAL COAT |
0901-19-128 | Grayson/ Paris |
CR | Approved | $737,314 | 6 | REPLACE BRIDGE AND APPROACHES |
1763-03-031 | Gregg/ Tyler |
LP 281 | Approved | $3,786,670 | 3 | WIDEN TO 6 LANES DIVIDED W / CHANNELIZED INTERSECTION |
0216-02-043 | Guadalupe/ San Antonio |
SH 46 | Approved | $4,528,844 | 11 | RECONSTRUCT & EXPAND 2 TO 4 LANE URBAN W / CLTL |
3107-02-026 | Guadalupe/ San Antonio |
FM 3009 | Approved | $434,209 | 1 | SURF, CONC MEDIAN / PAVERS, PAV MRKRS, TRAF SIGNAL |
0912-71-654 | Harris/ Houston |
CS | Approved | $823,281 | 8 | INSTALL SIDEWALKS |
0912-71-796 | Harris/ Houston |
CS | Approved | $505,701 | 9 | NASA PARKWAY SCENIC BEAUTIFICATION IN NASSAU BAY |
0912-71-857 | Harris/ Houston |
VA | Approved | $974,965 | 1 | REPLACE PAVEMENT MARKINGS AND RAISED REFLECTIVE PAVEMENT |
0096-07-035 | Harrison/ Atlanta |
US 80 | Approved | $994,119 | 8 | SAFETY TREAT DRAINAGE STRUCTURES, SAFETY LIGHTING AND |
0157-09-001 | Haskell/ Abilene |
US 277 | Approved | $16,782,373 | 10 | RELOCATE AND RECONTRUCT EXISTING HIGHWAY TO A 4 - LANE |
0805-04-018 | Hays/ Austin |
RM 150 | Approved | $138,410 | 8 | SAFETY TREAT DRAINAGE STRUCTURES |
0805-04-019 | Hays/ Austin |
RM 150 | Approved | $159,815 | 10 | ADD LEFT TURN LANE |
0039-18-086 | Hidalgo/ Pharr |
US 83 | Approved | $62,936,590 | 2 | WIDEN TO 6 LANES |
0909-37-039 | Hill/ Waco |
VA | Approved | $489,787 | 11 | CONSTRUCT / RECONSTRUCT ADA RAMPS |
0902-51-013 | Hood/ Fort Worth |
VA | Approved | $37 | 9 | CONSTRUCT TRAIL; MOMENTS IN TIME TRAIL |
0901-28-043 | Hopkins/ Paris |
CR | Approved | $616,727 | 6 | REPLACE BRIDGE AND APPROACHES |
0336-01-036 | Houston/ Lufkin |
SH 7 | Approved | $4,650,266 | 10 | WIDEN CROWN, ADD PAVED SHOULDERS, SAFETY TREAT STRUCTURES |
0940-01-015 | Houston/ Lufkin |
FM 357 | Approved | $804,915 | 6 | BRIDGE REPLACEMENT |
0768-01-046 | Hunt/ Paris |
SH 24 | Approved | $117,576 | 1 | INSTALL TRAFFIC SIGNAL AND ADVANCE BEACON |
0391-06-017 | Jack/ Fort Worth |
SH 148 | Approved | $4,274,760 | 1 | REPLACE BRIDGE |
0515-01-058 | Jackson/ Yoakum |
FM 616 | Approved | $924,672 | 6 | REPLACE BIRDGE AND APPROACHES |
0913-18-014 | Jackson/ Yoakum |
CR | Approved | $896,522 | 6 | REPLACE BRIDGE AND APPROACHES |
0065-02-045 | Jasper/ Beaumont |
US 96 | Approved | $19,342,390 | 4 | WIDEN & RECONSTRUCT TO 4 LANE DIVIDED RURAL |
0104-02-024 | Jeff Davis/ El Paso |
SH 17 | Approved | $7,005,299 | 11 | CULVERT WIDENING AND PAVEMENT RESTORATION |
1181-02-029 | Johnson/ Fort Worth |
FM 917 | Approved | $231,765 | 8 | CONSTRUCT LEFT TURN LANE AND INSTALL SIGNAL |
1181-04-031 | Johnson/ Fort Worth |
FM 917 | Approved | $6,734,036 | 11 | REALIGN EXISTING FACILITY TO TIE - IN WITH HERITAGE PARKWAY |
0133-03-037 | Knox/ Childress |
US 82 | Approved | $178,106 | 8 | SAFETY TREAT DRAINAGE STRUCTURES & WIDEN |
0018-01-061 | La Salle/ Laredo |
IH 35 | Approved | $806,000 | 9 | REALIGN FRONTAGE ROAD CONSISTING OF GRAD STRUCT BASE & SURF |
0483-01-038 | La Salle/ Laredo |
SH 97 | Approved | $1,851,099 | 1 | FOR THE CONSTRUCTION OF THE REHABILITATION OF A BRIDGE |
0652-04-046 | La Salle/ Laredo |
FM 624 | Approved | $4,705,390 | 1 | RECONSTRUCT EXISTING ROADWAY |
1452-02-008 | Lamar/ Paris |
FM 1508 | Approved | $1,317,896 | 1 | RESTORATION OF EXISTING ROADWAY |
0996-02-012 | Limestone/ Waco |
FM 638 | Approved | $1,392,353 | 1 | WIDEN ROADWAY, BASE OVERLAY, TWO COURSE SURFACE TREATMENT |
0700-04-033 | Llano/ Austin |
SH 71 | Approved | $367,706 | 11 | IMPROVE GUARDRAIL, SAFETY TREAT DRAINAGE STRUCTURES AND |
0005-04-063 | Martin/ Odessa |
IH 20 | Approved | $323,649 | 1 | BRIDGE REPAIRS |
0071-03-035 | Mason/ Austin |
US 87 | Approved | $756,539 | 1 | MILL, SEAL, 2" HMACP IN - LAY |
0014-10-057 | McLennan/ Waco |
BU 77-L | Approved | $3,088,950 | 1 | JOINT REPAIR AND TEXTURE CONCRETE PAVEMENT |
0015-01-163 | McLennan/ Waco |
IH 35 | Approved | $29,867,558 | 10 | RECONSTRUCT EXISTING INTERCHANGE TO A 3 LEVEL AND PARTLY |
0015-01-198 | McLennan/ Waco |
IH 35 | Approved | $541,973 | 1 | ADD RIGHT TURN LANE |
0209-07-040 | McLennan/ Waco |
FM 933 | Approved | $3,995,714 | 1 | UPGRADE TO TWO LANE STANDARD |
0567-04-018 | McLennan/ Waco |
FM 185 | Approved | $1,395,713 | 1 | UPGRADE TO TWO LANE STANDARD WITH SHOULDERS, CURB AND |
0013-05-052 | Montague/ Wichita Falls |
US 287 | Approved | $628,915 | 10 | CONSTRUCTION OF RELOCATION OF EXISTING FRONTAGE ROADS |
1986-01-015 | Montgomery/ Houston |
FM 1314 | Approved | $8,943,668 | 1 | WIDEN FROM 2 LANES TO 4 - LANE DIVIDED |
2664-02-001 | Nacogdoches/ Lufkin |
FM 2435 | Approved | $7,396,701 | 4 | CONSTRUCT NEW FARM TO MARKET HIGHWAY |
0074-06-198 | Nueces/ Corpus Christi |
IH 37 | Approved | $1,239,124 | 1 | IMPROVE CONNECTOR RAMP FROM WESTBOUND_SH 358 TO NORTHBOUND |
0916-35-072 | Nueces/ Corpus Christi |
VA | Approved | $1,354,870 | 7 | ADA ACCESSIBILITY |
0247-03-021 | Panola/ Atlanta |
US 79 | Approved | $242,645 | 8 | SAFETY TREAT FIXED OBJECTS |
0008-03-086 | Parker/ Fort Worth |
IH 20 | Approved | $2,593,991 | 1 | REHABILITATION OF EXISTING ROADWAY; INSTALL TURNAROUNDS, |
0902-38-039 | Parker/ Fort Worth |
CR | Approved | $760,984 | 6 | REPLACE BRIDGE |
0902-38-045 | Parker/ Fort Worth |
CR | Approved | $412,719 | 6 | REPLACE BRIDGE AND APPROACHES |
1849-03-016 | Rains/ Paris |
SH 276 | Approved | $9,102,566 | 8 | UPGRADE TO NON - FREEWAY STANDARDS |
0046-01-041 | Red River/ Paris |
US 82 | Approved | $7,862,264 | 4 | CONSTRUCT 2 LANES OF ULT 4 LN DIVIDED ON NEW LOCATION |
0911-29-025 | Sabine/ Lufkin |
CR | Approved | $237,839 | 6 | BRIDGE REPLACEMENT |
0911-29-026 | Sabine/ Lufkin |
CR | Approved | $202,913 | 6 | BRIDGE REPLACEMENT |
0101-04-077 | San Patricio/ Corpus Christi |
US 181 | Approved | $20,767,873 | 4 | CONSTRUCT RAILROAD GRADE SEPARATION AND APPROACHES |
0908-19-012 | Scurry/ Abilene |
CR | Approved | $359,703 | 6 | REPLACE BRIDGE AND APPROACHES |
0059-05-033 | Shelby/ Lufkin |
SH 7 | Approved | $3,634,992 | 6 | REPLACE EXISTING RAILROAD UNDERPASS_AND APPROACHES |
0014-16-246 | Tarrant/ Fort Worth |
IH 35W | Tentative | $181,670 | 10 | INSTALL CRASH WALLS AT DOT#789553D RAMP 629.9 |
0171-04-061 | Tarrant/ Fort Worth |
SH 199 | Approved | $24,844,817 | 11 | CONSTRUCT FRONTAGE ROADS |
0172-09-027 | Tarrant/ Fort Worth |
US 287 | Approved | $1,176,872 | 8 | INSTALL CONCRETE MEDIAN BARRIER ON SHOULDER |
0364-01-123 | Tarrant/ Fort Worth |
SH 121 | Approved | $258,750 | 8 | INSTALL MEDIAN BARRIER |
0902-00-096 | Tarrant/ Fort Worth |
VA | Approved | $2,421,619 | 1 | REMOVAL AND REPLACEMENT OF BUTTON COPY FREEWAY GUIDE SIGNS |
0902-00-097 | Tarrant/ Fort Worth |
VA | Approved | $2,302,287 | 1 | INSTALL WIRE ROPE MEDIAN BARRIER ON IH 20 FROM FM 1884 |
0902-48-194 | Tarrant/ Fort Worth |
CS | Approved | $2,838,016 | 7 | CONSTRUCT 4 LANES ON NEW LOCATION |
0902-48-432 | Tarrant/ Fort Worth |
VA | Approved | $1,960,903 | 5 | INSTALL DETECTION, DIGITAL MESSAGE SIGN, CCTV, ETC |
0902-48-442 | Tarrant/ Fort Worth |
VA | Approved | $2,262,575 | 5 | INTEGRATION OF ALTERNATE DETECTION COMMUNICATIONS INTO |
0902-48-561 | Tarrant/ Fort Worth |
VA | Tentative | $917,500 | 5 | PHASING |
0902-48-575 | Tarrant/ Fort Worth |
CS | Approved | $6,376,160 | 7 | WIDEN FROM 2 LANES TO 4 LANES |
0902-48-584 | Tarrant/ Fort Worth |
VA | Approved | $2,383,480 | 1 | REMOVAL AND REPLACEMENT OF BUTTON COPY FREEWAY GUIDE SIGNING |
0902-48-586 | Tarrant/ Fort Worth |
VA | Approved | $452,035 | 5 | SIGNAL COORDINATION - SPREAD SPECTRUM TECHNIQUE |
2266-02-095 | Tarrant/ Fort Worth |
SH 360 | Approved | $20,738,105 | 11 | CONSTRUCT 6 MAIN LANES |
3125-01-015 | Tarrant/ Fort Worth |
FM 3029 | Approved | $114,326 | 1 | TRAFFIC SIGNALS |
0152-01-063 | Travis/ Austin |
US 183 | Approved | $2,400,000 | 1 | MILL, SEAL COAT AND OVERLAY |
0683-02-049 | Travis/ Austin |
RM 620 | Approved | $1,741,794 | 1 | SPOT MILL, SEAL COAT AND OVERLAY |
0683-02-050 | Travis/ Austin |
RM 620 | Approved | $3,088,347 | 1 | 1 - CST AND 2" OVERLAY |
0914-00-162 | Travis/ Austin |
VA | Tentative | $20,000 | 1 | REHABILITATE DMS SUBSYSTEM |
0914-04-137 | Travis/ Austin |
CS | Approved | $1,118,207 | 7 | DESIGN & INSTALL 6' WIDE BIKE LANES |
0914-04-171 | Travis/ Austin |
VA | Approved | $500,000 | 7 | CONSTRUCT CONCRETE TRAIL |
1149-01-020 | Travis/ Austin |
FM 812 | Approved | $64,418 | 8 | INSTALL CONTINUOUS TURN LN, ADD LEFT TURN LN, & CONST PAVED SHL |
1186-01-054 | Travis/ Austin |
FM 969 | Approved | $8,074,550 | ROW | EXTEND 5 - LANE SECTION |
1186-01-062 | Travis/ Austin |
FM 969 | Approved | $265,736 | 11 | CONSTRUCT LEFT TURN LANES AND SHOULDERS |
3136-01-137 | Travis/ Austin |
LP 1 | Approved | $1,148,519 | 1 | MILL, SPOT REPAIR, NOVACHIP, SGT'S |
0380-12-017 | Upton/ Odessa |
SH 349 | Approved | $32,779 | 9 | ADD CROSSWALK, FLASHING BEACONS, PAV MRKS |
0022-09-047 | Val Verde/ Laredo |
US 90 | Approved | $5,433,022 | 11 | CLEANING AND PAINTING OF A STRUCTURAL STEEL BRIDGE |
0299-01-058 | Val Verde/ Laredo |
US 277 | Approved | $4,935,000 | 4 | REHABILITATION OF EXISTING ROADWAY |
0542-01-039 | Webb/ Laredo |
US 59 | Approved | $17,274,041 | 1 | CONSTRUCT URBAN SECTION OF ROADWAY |
0709-02-041 | Wharton/ Yoakum |
FM 102 | Approved | $2,958,721 | 1 | WIDEN ROADWAY |
0044-01-086 | Wichita/ Wichita Falls |
US 287 | Approved | $4,876,351 | 1 | ILLUMINATION |
0903-30-013 | Wilbarger/ Wichita Falls |
CR | Approved | $411,995 | 6 | BRIDGE REPLACEMENT |
0320-04-020 | Williamson/ Austin |
FM 397 | Approved | $552,009 | 10 | CONSTRUCT CTL AND DECELERATION LANES |
0914-05-125 | Williamson/ Austin |
VA | Tentative | $17,500 | 10 | TRAFFIC SIGNAL |
2690-01-026 | Williamson/ Austin |
FM 971 | Approved | $718,593 | 8 | SAFETY TREAT DRAINAGE STRUCTURE |
0902-20-060 | Wise/ Fort Worth |
CR | Approved | $674,431 | 6 | REPLACE BRIDGE |
1568-01-013 | Wise/ Fort Worth |
FM 407 | Approved | $2,560,261 | 1 | HMAC OVERLAY, PAVEMENT REHABILITATION TO INCLUDE 4' SHOULDER |
0910-35-026 | Wood/ Tyler |
VA | Approved | $544,400 | 9 | RENOVATE DEPOT FOR USE AS A MULTI - TRANSPORTATION CENTER |
0276-04-020 | Zavala/ Laredo |
US 57 | Tentative | $1,668,685 | 1 | FOR THE CONSTRUCTION OF OVERLAY TYPE OF WORK (FY 2005) |
|
|