Letting Schedule for December, 2003 (FY 2004)
Letting Schedule for December, 2003 (FY 2004) | ||||
Last Update: Tuesday, August 17, 2004 |
December, 2003 (FY 2004) | (see Links) |
SEP 2003 | OCT 2003 | NOV 2003 | DEC 2003 | JAN 2004 | FEB 2004 | MAR 2004 | APR 2004 | MAY 2004 | JUN 2004 | JUL 2004 | AUG 2004 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0910-08-041 | Anderson/ Tyler |
VA | Actual | $236,961 | 9 | RELOCATE AND RENOVATE RAILROAD DEPOT |
0073-04-045 | Atascosa/ San Antonio |
US 281 | Actual | $4,735,371 | 1 | SEAL COAT & PAVEMENT MARKINGS |
0915-12-351 | Bexar/ San Antonio |
CS | Actual | 7 | INSTALL BIKE RACKS AT APPROXIMATELY 50 VARIOUS LOCATIONS | |
0179-02-063 | Brazoria/ Houston |
SH 35 | Actual | $9,983,678 | 2 | WIDEN TO 4 - LANE DIVIDED RURAL |
1684-01-018 | Brazoria/ Houston |
FM 1128 | Actual | $2,199,099 | 8 | ACP OVERLAY AND WIDEN SHOULDERS AND ADD TURN LANES AT CR 91 |
0144-06-021 | Calhoun/ Yoakum |
SH 185 | Actual | $1,825,799 | 1 | SEAL COAT |
0220-04-032 | Cameron/ Pharr |
US 281 | Actual | $1,542,381 | 1 | SEAL COAT |
0220-05-062 | Cameron/ Pharr |
SH 48 | Actual | $5,729,567 | 1 | ACP OVERLAY |
0031-05-038 | Childress/ Childress |
US 62 | Actual | $2,739,355 | 1 | OVERLAY |
0016-04-091 | Comal/ San Antonio |
IH 35 | Actual | $48,817,391 | ROW | UPGRADE TO 8 LANE FREEWAY (MAINLANES & FRONTAGE RDS) #4 |
1187-01-024 | Coryell/ Waco |
FM 929 | Actual | $1,961,035 | 1 | EMULSION |
0918-00-070 | Dallas/ Dallas |
VA | Actual | $1,552,609 | 1 | SEALCOAT |
0918-45-292 | Dallas/ Dallas |
CS | Actual | $178,693 | 5 | 2 INTERSECTION IMPROVEMENTS |
0918-45-321 | Dallas/ Dallas |
CS | Actual | $115,829 | 5 | INTERSECTION IMPROVEMENTS |
0918-45-472 | Dallas/ Dallas |
CS | Actual | $3,328,442 | 7 | WIDEN 2 LANE FACILITY TO 4 LANE FACILITY |
0918-45-577 | Dallas/ Dallas |
CS | Actual | $900,000 | 7 | RIGHT OF WAY ACQUISITION, RELOCATION ASSISTANCE AND UTILITY |
0918-45-629 | Dallas/ Dallas |
CS | Actual | $344,908 | 5 | RIGHT OF WAY ACQUISITION |
0918-45-630 | Dallas/ Dallas |
CS | Actual | $256,849 | 5 | RIGHT OF WAY ACQUISITION |
0918-45-679 | Dallas/ Dallas |
CS | Actual | $142,643 | 5 | ACQUISITION, UTILITIES AND RELOCATION FOR 5 INTERSECTION |
0918-45-684 | Dallas/ Dallas |
VA | Actual | $344,030 | 1 | REPLACING OLD SIGNS, DELINEATORS AND OBJECT MARKERS |
0918-46-081 | Denton/ Dallas |
CS | Actual | $407,905 | 10 | RECONSTRUCT CITY STREET |
0007-04-102 | Eastland/ Brownwood |
SH 6 | Actual | $6,367,475 | 1 | SEAL COAT |
0924-06-160 | El Paso/ El Paso |
CS | Actual | $1,804,741 | 9 | MISSION TRAILS ENHANCEMENT PROJECT, PHASE II |
0092-03-045 | Ellis/ Dallas |
IH 45 | Actual | $192,027 | 1 | SIGN REFURBISHING |
1159-01-021 | Ellis/ Dallas |
FM 875 | Actual | $150,000 | 11 | INSTALLATION OF RAILROAD WARNING SIGNALS AND GATES |
1211-02-015 | Ellis/ Dallas |
FM 984 | Actual | $160,000 | 11 | INSTALLATION OF RAILROAD WARNING SIGNALS AND GATES |
0334-08-030 | Fayette/ Yoakum |
FM 154 | Actual | $2,067,617 | 10 | RESTORE ROADWAY |
0027-06-050 | Fort Bend/ Houston |
US 90A | Actual | $1,818,598 | 1 | MILLING, ADDING SHOULDERS AND ACP OVERLAY |
1683-01-031 | Fort Bend/ Houston |
FM 1640 | Actual | $2,624,633 | 1 | BASE REPAIR, PLANING, ACP OVERLAY AND PAVEMENT MARKINGS |
0010-04-018 | Franklin/ Paris |
US 67 | Actual | $1,642,374 | 1 | SEAL COAT |
0057-02-027 | Freestone/ Bryan |
BU 84-R | Actual | $1,268,849 | 1 | SEAL COAT CONSISTING OF A ONE COURSE SURFACE TREATMENT AND |
0389-11-055 | Galveston/ Houston |
LP 197 | Actual | $233,942 | 1 | FULL DEPTH REPAIR AND ACP OVERLAY |
1607-01-046 | Galveston/ Houston |
FM 1764 | Actual | $141,496 | 8 | REHABILITATE SERVICES AND LUMINAIRES |
0071-06-053 | Gillespie/ Austin |
US 87 | Actual | $477,419 | 1 | SEALCOAT |
0045-04-056 | Grayson/ Paris |
SH 56 | Actual | $1,554,199 | 1 | SEAL COAT |
0138-01-083 | Gregg/ Tyler |
US 259 | Actual | $5,924,318 | 1 | REPLACE BRIDGE AND APPROACHES |
0424-03-020 | Gregg/ Tyler |
FM 349 | Actual | $5,728,256 | 1 | RECONSTRUCT AS 4 - LN DIVIDED HIGHWAY |
0813-03-033 | Hardin/ Beaumont |
FM 421 | Actual | $758,798 | 1 | ADD A CONTINUOUS LEFT TURN LANE AND OVERLAY ROADWAY |
0028-01-078 | Harris/ Houston |
US 90 | Actual | $1,814,148 | 6 | REPLACE BRIDGE AND APPROACHES |
0271-16-118 | Harris/ Houston |
IH 610 | Actual | $331,447 | 11 | CONSTRUCT SOUND WALL |
0500-03-517 | Harris/ Houston |
IH 45 | Actual | $286,941 | 1 | DRAINAGE IMPROVEMENTS |
0508-01-308 | Harris/ Houston |
IH 10 | Actual | $4,073,314 | 1 | CLEAN AND SEAL JOINTS AND PAVEMENT REPAIR |
0976-01-031 | Harris/ Houston |
FM 865 | Actual | $316,762 | 1 | FULL DEPTH ACP REPAIR AND JOINT / CRACK SEAL |
0108-04-031 | Henderson/ Tyler |
SH 19 | Actual | $46,871 | 10 | GOVERNOR'S AWARD LANDSCAPE PROJECT |
1668-01-019 | Henderson/ Tyler |
SH 198 | Actual | $2,725,097 | 1 | REHABILITATE ROADWAY, ADD LEFT TURN LANE, WIDEN SHOULDERS |
0219-01-044 | Hidalgo/ Pharr |
FM 1016 | Actual | $256,720 | 10 | LANDSCAPE DEVELOPMENT WITH IRRIGATION SYSTEM |
0014-07-091 | Hill/ Waco |
IH 35 | Actual | $10,064,875 | 4 | INSTALL MEDIAN BARRIER WALL |
0009-13-138 | Hunt/ Paris |
IH 30 | Actual | $2,199,650 | 1 | SEAL COAT |
0028-06-064 | Jefferson/ Beaumont |
US 90 | Actual | $4,704,966 | 1 | SEAL COAT |
0014-04-071 | Johnson/ Fort Worth |
SH 81 | Actual | $35,923 | 1 | INSTALL TRAFFIC SIGNAL |
0918-11-037 | Kaufman/ Dallas |
CR | Actual | $543,106 | 6 | REPLACE BR & APPRS |
0045-09-083 | Lamar/ Paris |
US 82 | Actual | $1,753,987 | 1 | SEAL COAT |
0813-01-088 | Liberty/ Beaumont |
FM 787 | Actual | $3,262,169 | 1 | REHABILITATE EXISTING ROADWAY |
0905-06-029 | Lubbock/ Lubbock |
CS | Actual | $6,066,321 | 11 | THE WIDENING OF A NON - FREEWAY FACILITY |
1188-02-069 | Midland/ Odessa |
LP 250 | Actual | $182,045 | 1 | BRIDGE MAINTENANCE |
2897-01-011 | Montgomery/ Houston |
FM 830 | Actual | $2,635,583 | 1 | WIDEN SUBGRADE, O.C.S.T.AND ACP OVERLAY |
0995-01-021 | Navarro/ Dallas |
FM 637 | Actual | $160,000 | 11 | INSTALLATION OF RAILROAD WARNING SIGNALS AND GATES |
3325-01-010 | Navarro/ Dallas |
FM 3243 | Actual | $150,000 | 11 | INSTALLATION OF RAILROAD WARNING SIGNALS AND GATES |
0916-35-092 | Nueces/ Corpus Christi |
CR | Actual | $382,540 | 6 | REPLACE BRIDGE AND APPROACHES |
0226-02-027 | Oldham/ Amarillo |
US 385 | Actual | $10,289,793 | 1 | REPLACE BRIDGE AND APPROACHES |
0388-01-037 | Polk/ Lufkin |
SH 146 | Actual | $2,330,783 | 1 | REHABILITATE EXISTING PAVEMENT AND ADD SHOULDERS |
1015-01-017 | Rockwall/ Dallas |
FM 549 | Actual | $180,000 | 11 | INSTALLATION OF RAILROAD WARNING SIGNALS AND GATES |
1016-01-021 | Rockwall/ Dallas |
FM 551 | Actual | $180,000 | 11 | INSTALLATION OF RAILROAD WARNING SIGNALS AND GATES |
1290-03-019 | Rockwall/ Dallas |
SH 276 | Actual | $924,636 | 1 | MICROSURFACING OF THE MAIN LANES AND SHOULDERS |
0087-03-026 | San Patricio/ Corpus Christi |
SH 359 | Actual | $2,754,733 | 11 | UPGRADE TO 5 LANE CURB & GUTTER |
0053-10-037 | Scurry/ Abilene |
US 84 | Actual | $4,972,163 | 1 | MILL, SUBGRADE WIDENING, LIME TREAT SUBGRADE & BASE, NEW BASE, |
0063-06-087 | Shelby/ Lufkin |
US 96 | Actual | $7,665,119 | 1 | SEAL COAT |
0011-08-023 | Stephens/ Brownwood |
US 180 | Actual | $2,851,422 | 9 | GRADING, CONCRETE PAVEMENT, CURB AND GUTTER, SIDEWALK |
0902-48-504 | Tarrant/ Fort Worth |
CS | Actual | $349,839 | 6 | REPLACE BRIDGE AND APPROACHES |
0902-48-517 | Tarrant/ Fort Worth |
CS | Actual | $411,173 | 7 | INTERSECTION IMPROVEMENTS; ADD NB / SB LEFT TURN LANE |
0015-13-312 | Travis/ Austin |
IH 35 | Actual | $1,979,027 | 1 | OVERALY AND UPGRADE SAFETY APPURTENANCES |
0151-06-121 | Travis/ Austin |
LP 111 | Actual | $1,389,594 | 1 | FULL DEPTH REPAIR & OVERLAY |
2298-01-012 | Upton/ Odessa |
RM 2401 | Actual | $959,283 | 1 | REHABILITATE EXIST. ROAD |
0022-10-047 | Val Verde/ Laredo |
US 90 | Actual | $347,182 | 1 | IMPROVE TRAFFIC SIGNAL AND SAFETY LIGHTING AT INTERSECTION |
2477-01-007 | Van Zandt/ Tyler |
FM 1395 | Actual | $1,484,434 | 1 | REHABILITATE ROADWAY |
2350-01-035 | Victoria/ Yoakum |
US 77 | Actual | $7,957,297 | 6 | CONSTRUCT GRADE SEPARATION INTERCHANGE |
0271-09-017 | Waller/ Houston |
US 90 | Actual | $388,932 | 1 | PLANING, BASE REPAIR, ONE COURSE SURFACE TREATMENT, POROUS |
0523-01-024 | Waller/ Houston |
FM 1098 | Actual | $210,751 | 1 | BASE REPAIR AND ACP OVERLAY AND / OR CRACKSEAL |
0338-10-018 | Washington/ Bryan |
FM 390 | Actual | $1,135,288 | 1 | SEAL COAT CONSISTING OF A ONE COURSE SURFACE TREATMENT AND |
0397-02-033 | Wheeler/ Childress |
SH 152 | Actual | $2,594,454 | 1 | OVERLAY |
0043-17-019 | Wichita/ Wichita Falls |
BU 287J | Actual | $2,971,051 | 6 | REPLACE BRIDGE AND APPROACHES |
0327-06-023 | Willacy/ Pharr |
BU 77-W | Actual | $1,031,337 | 1 | MICRO SURFACE |
1378-02-022 | Williamson/ Austin |
RM 1431 | Actual | $6,523,602 | 11 | RECONST TO 6 - LANE ROADWAY (MAD6) |
1378-02-028 | Williamson/ Austin |
RM 1431 | Actual | $253,741 | 10 | ADD ACCELERATION / DECELERATION LANE |
|
|