Detail Letting Schedule for Shelby County (FY 2016)

Last Update: Wednesday, September 17, 2014
Shelby County (FY 2016)

CCSJ: 0063-06-096

District: Lufkin Let Date: JAN 2016
Highway: US 96 Let Status: Tentative
Project ID: NH ( ) CSJ: 0063-06-096
Description: PLANE EXISTING SURFACE AND OVERLAY Handling
Code:
 
Limits From: 1.46 MI N OF SH 87 IN CENTER Fund Cat: 1
Limits To: SH 87 IN CENTER Estimate: $1,200,000
Length: 1.5 Miles Actual:  
 
District: Lufkin Let Date: JAN 2016
Highway: US 96 Let Status: Tentative
Project ID: NH ( ) CSJ: 0809-02-067
Description: PLANE EXISTING SURFACE AND OVERLAY Handling
Code:
 
Limits From: SH 87 IN CENTER Fund Cat: 1
Limits To: 0.18 MI S OF SH 7 IN CENTER Estimate: $1,485,000
Length: 1.8 Miles Actual:  
 
Back...

Totals for 0063-06-096
Length: 3.3 Miles
Estimate: $2,685,000
Actual:  

CCSJ: 0809-01-029

District: Lufkin Let Date: MAR 2016
Highway: FM 699 Let Status: Tentative
Project ID: STP ( ) CSJ: 0809-01-029
Description: RECONSTRUCT AND WIDEN PAVEMENT Handling
Code:
 
Limits From: 0.19 MI NORTH OF FM 2468 Fund Cat: 1
Limits To: 0.22 MI SOUTH OF TIMBER ROCK RR Estimate: $1,700,000
Length: 0.6 Miles Actual:  
 
Back...

Totals for 0809-01-029
Length: 0.6 Miles
Estimate: $1,700,000
Actual:  

CCSJ: 0911-39-038

District: Lufkin Let Date: MAY 2016
Highway: CR Let Status: Tentative
Project ID: BR ( ) CSJ: 0911-39-038
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: CR 4059 AT POOR JOE CREEK Fund Cat: 6
Limits To: . Estimate: $238,500
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0911-39-038
Length: 0.1 Miles
Estimate: $238,500
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract