Letting Schedule for July, 2016 (FY 2016)

Last Update: Tuesday, July 19, 2016
July, 2016 (FY 2016) (see Links)
SEP 2015 | OCT 2015 | NOV 2015 | DEC 2015 | JAN 2016 | FEB 2016 | MAR 2016 | APR 2016 | MAY 2016 | JUN 2016 | JUL 2016 | AUG 2016
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0548-05-048 Andrews/
Odessa
SH 176 Actual $10,506,608 1 REHABILITATION OF EXISTING ROAD
0911-38-070 Angelina/
Lufkin
CR Actual $460,228 6 REPLACE BRIDGE AND APPROACHES
0507-04-041 Aransas/
Corpus Christi
FM 1069 Actual $340,987 8 TEXTURIZE SHOULDERS, (ROLL OR MILL IN) , CENTERLINE TEXTURING
2176-01-008 Bastrop/
Austin
FM 1209 Actual $1,990,498 1 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0088-01-067 Bee/
Corpus Christi
US 59 Actual $3,243,062 1 HOT RUBBER SEAL
1198-03-009 Bell/
Waco
FM 2670 Actual $521,758 8 SAFETY TREAT FIXED OBJECTS
2304-02-036 Bell/
Waco
FM 2410 Actual $6,800,753 1 WIDEN FROM TWO TO FOUR LANES WITH CONTINUOUS LEFT TURN LANE
0024-08-133 Bexar/
San Antonio
US 90 Actual $1,069,800 10 LANDSCAPE DEVELOPMENT
0073-08-188 Bexar/
San Antonio
US 281 Actual $2,131,726 1 MILL, SC, OVERLAY & PAVEMENT MARKINGS
0915-12-537 Bexar/
San Antonio
VA Actual $1,552,147 3 IMPROVING OLD TOWN HELOTES - BICYLCLE AND PEDESTRIAN
0192-02-050 Brazoria/
Houston
SH 6 Actual $4,942,809 1 CONSTRUCT ACCESS MANAGEMENT IMPROVEMENTS (MEDIAN,
0912-31-301 Brazoria/
Houston
VA Actual $920,524 10 LANDSCAPE DEVELOPMENT
0917-29-130 Brazos/
Bryan
VA Actual $8,200 3 MISCELLANEOUS WORK CONSISTING OF INSTALLING SIGNS ALONG
0713-01-032 Burleson/
Bryan
FM 60 Actual $2,429,598 1 REHABILITATE EXISTING ROAD CONSISTING OF GRADING, STRUCTURES
0914-22-068 Caldwell/
Austin
CR Actual $4,879,112 3 GRADING, ASPHALTIC CEMENT PAVEMENT & MARKINGS FOR CR 222
0919-00-073 Cass/
Atlanta
VA Actual $680,959 1 2016 DISTRICT SEAL COAT PAVEMENT MARKINGS
1728-02-059 Comal/
San Antonio
FM 306 Actual $5,996,508 1 EXPAND 2 TO 4 LANES WITH CONTINUOUS LEFT TURN LANE, BIKE
0567-01-027 Coryell/
Waco
FM 1996 Actual $2,775,914 1 REHABILITATE ROADWAY
0140-11-043 Crockett/
San Angelo
IH 10 Actual $14,033,551 1 PLANE, EMULSION TREAT, SURFACE TREATMENT, AND ACP OVERLAY
0009-11-233 Dallas/
Dallas
IH 30 Actual $2,254,488 8 CONSTRUCT PREFAB PEDESTRIAN BRIDGE
0095-02-102 Dallas/
Dallas
US 80 Actual $10,441,948 7 RAMP MODIFICATIONS & ADDITION OF AUXILIARY LANE ON FRONTAGE
1047-03-070 Dallas/
Dallas
FM 1382 Actual $6,048,901 5 INSTALL TRAFFIC SIGNAL
0353-02-074 Denton/
Fort Worth
SH 114 Actual $24,897,375 1 WIDEN FREEWAY FROM 4 LANES TO 6 LANES
0816-02-076 Denton/
Dallas
FM 455 Actual $4,986,229 1 CONSTRUCT PAVED SHOULDERS (1 - 4FT)
0918-46-272 Denton/
Dallas
CS Actual $6,719,415 3 BICYCLE AND PEDESTRIAN FACILITY - 10 WIDE CONCRETE PATH AND
0913-17-041 Dewitt/
Yoakum
CR Actual $323,694 6 REPLACE BRIDGE AND APPROACHES
1113-01-026 Dewitt/
Yoakum
FM 766 Actual $4,871,849 11 RESTORE ROADWAY
0007-04-113 Eastland/
Brownwood
IH 20 Actual $278,880 3 CRASH WALLS
0924-06-511 El Paso/
El Paso
CS Actual $674,447 3 CONSTRUCTION OF SIDEWALKS, DUAL USE PATHS, AND ACCESSIBLE CU
2121-04-098 El Paso/
El Paso
IH 10 Actual $12,915,902 2M WIDEN ROADWAY TO 8 LANES
0027-12-151 Fort Bend/
Houston
IH 69 Actual $1,458,610 10 LANDSCAPE DEVELOPMENT
0089-09-067 Fort Bend/
Houston
US 59 Actual $37,743,799 4 WIDEN TO 6 MAIN LANES WITH 2 - LANE FRONTAGE ROADS, GRADE
0081-07-023 Grayson/
Paris
US 377 Actual $1,372,923 8 TEXTURIZE SHOULDERS, ROLLED OR MILLED IN, CENTERLINE AND
0500-03-603 Harris/
Houston
IH 45 Actual $2,369,011 10 LANDSCAPE DEVELOPMENT
0912-00-506 Harris/
Houston
VA Actual $6,000,000 5 DEVELOPING TRANSIT MARKET FLEET EXPANSION PROGRAM YEAR 2
0113-07-067 Hays/
Austin
US 290 Actual $816,443 1 OVERLAY
2612-01-011 Hemphill/
Amarillo
RM 2654 Actual $5,653,752 8 SAFETY WIDENING OF ROADWAY
0921-02-252 Hidalgo/
Pharr
CR Actual $967,447 6 REPLACE BRIDGE & RECONST APPROACHES
0014-23-032 Hill/
Waco
IH 35W Actual $1,948,180 8 SAFETY TREAT FIXED OBJECTS
0901-28-088 Hopkins/
Paris
CR Actual $565,396 6 REPLACE BRIDGE AND APPROACHES
0911-28-040 Houston/
Lufkin
CR Actual $1,080,977 6 REPLACE BRIDGE AND APPROACHES
0764-02-011 Hunt/
Paris
FM 272 Actual $3,455,817 1 REHABILITATION OF EXISTING ROAD
0368-04-028 Jefferson/
Beaumont
SH 124 Actual $162,353 6 REPAIR BRIDGE SUBSTRUCTURE
2118-02-019 Johnson/
Fort Worth
FM 1902 Actual $6,740,440 1 WIDEN PAVEMENT AND ADD SHOULDERS
0901-29-079 Lamar/
Paris
VA Actual $638,645 3 BICYCLE & PEDESTRIAN FACILITIES
0335-01-031 Leon/
Bryan
SH 7 Actual $25,152,378 8 REHABILITATE EXISTING ROAD CONSISTING OF PAVEMENT REPAIRS,
1067-01-026 Liberty/
Beaumont
FM 686 Actual $1,690,130 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0380-01-085 Lubbock/
Lubbock
US 62 Actual $17,312,700 1 WIDEN FREEWAY FROM 4 LANES TO 6 LANES
0569-03-021 Marion/
Atlanta
SH 43 Actual $1,204,182 1 REPLACE STEEL GRATE SPAN
0258-09-124 McLennan/
Waco
SH 6 Actual $14,733,503 1 WIDEN TO FOUR LANE FREEWAY - PHASE 1 OF 3
0074-06-226 Nueces/
Corpus Christi
IH 37 Actual $6,667,564 1 MILL, SEAL AND OVERLAY
0475-11-031 Polk/
Lufkin
FM 356 Actual $7,653,712 11 RECONSTRUCT AND WIDEN PAVEMENT WITH TWO WAY CONTINUOUSLEFT
0911-04-083 Polk/
Lufkin
CR Actual $812,182 6 REPLACE BRIDGE AND APPROACHES
0773-01-018 Red River/
Paris
FM 412 Actual $2,884,882 10 REHABILITATION OF EXISTING ROAD
3371-01-009 Red River/
Paris
FM 3390 Actual $298,222 6 REPLACE BRIDGE AND APPROACHES
0350-01-016 Refugio/
Corpus Christi
SH 239 Actual $179,858 8 TEXTURIZE SHOULDERS (ROLL OR MILL IN) CENTERLINE TEXTURING
0911-39-054 Shelby/
Lufkin
CR Actual $552,048 6 REPLACE BRIDGE AND APPROACHES
0424-01-053 Smith/
Tyler
SH 31 Actual $1,795,044 1 PLANE AND RESURFACE ROADWAY
0077-06-098 Tom Green/
San Angelo
US 67 Actual $3,805,304 1 GRADING, BASE, STRUCTURES, TRAFFIC SIGNALS
0907-24-044 Tom Green/
San Angelo
VA Actual $469,578 6 UPGRADE BRIDGE AND APPROACH RAILING / ADD SAFETY END TREATMENT
0015-13-378 Travis/
Austin
IH 35 Actual $42,617,265 ROW ADD SHOULDERS, AUXILIARY LNS, RAMP IMPROVEMENTS, PAVEMENT
0914-00-368 Travis/
Austin
VA Actual $1,041,313 1 FY 2016 SITE - SPECIFIC SIGNALS
0914-00-392 Travis/
Austin
VA Actual $339,000 3 2045 REGIONAL ACTIVE TRANSPORTATION PLAN
0914-04-298 Travis/
Austin
VA Actual $1,177,598 10 LANDSCAPING AND IRRIGATION
0023-01-087 Val Verde/
Laredo
US 90 Actual $5,319,276 1 OVERLAY
0495-03-061 Van Zandt/
Tyler
IH 20 Actual $4,570,487 1 REALIGN WB EXIT RAMP
0143-10-050 Victoria/
Yoakum
US 87 Actual $10,878,661 2U CONSTRUCT 4 - LANE OVERPASS AT INTERSECTION OF FM 447
0432-02-088 Victoria/
Yoakum
SH 185 Actual $193,412 8 INSTALL TRAFFIC SIGNAL
0086-01-084 Webb/
Laredo
US 83 Actual $4,395,788 1 OVERLAY
0089-06-085 Wharton/
Yoakum
US 59 Actual $1,880,242 6 REHABILITATE BRIDGE
0913-09-067 Wharton/
Yoakum
CR Actual $289,824 6 REPLACE BRIDGE AND APPROACHES
0802-02-066 Wichita/
Wichita Falls
FM 369 Actual $2,496,814 1 IMPROVE INTERSECTIONS
0015-08-146 Williamson/
Austin
IH 35 Actual $730,891 10 LANDSCAPING AND IRRIGATION
0204-01-067 Williamson/
Austin
US 79 Actual $265,696 1 MEDIAN MODIFICATIONS
0320-03-093 Williamson/
Austin
SH 95 Actual $1,507,709 3 CONSTRUCT PEDESTRIAN AND BIKE PATH
0914-05-188 Williamson/
Austin
CS Actual $263,500 3 WILLIAMS DRIVE CORRIDOR & CENTERS PLAN FOR MULTIMODAL AND
1604-02-016 Wise/
Fort Worth
FM 1655 Actual $299,998 8 INSTALL CHEVRON SIGNS WITH MOTION ACTIVATED LED LIGHTS


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract