Monthly State Let Construction Report For Amarillo District As Of Jan 10, 2023 Page 1 Of 4

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE
HighwayUS 83
FromOKLAHOMA STATE LINE
ToSH 15
CSJ0030-01-035
Proj IDF 2022(348)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.9535571551.156809780.0199.9
Work Order02-15-22
Work Began07-05-22
Work Completed
Time Computed03-17-22
Contract Working Days83
Addl Days Granted5
Working Days Charged76
Percent Time Used86
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-035
BARRICADES UNLIMITED (1.31)
DK CONTRACTING, LLC (0.73)
DUSTIN ALLEN, INC. (1.09)
H & F TRUCKING (9.68)
HUDSON, INC. SOUTH (1.01)
J. H. ODEN CONTRACTING COMPANY (0.55)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.22)
WITHERS CONSTRUCTION, LLC (1.59)
W. S. CONSTRUCTION COMPANY (2.22)
Contract #01223041
Totals5571551.15298377.726809780.0199.9

CountyOCHILTREE
HighwayUS 83
FromCR K SOUTH OF PERRYTON
ToWOLF CREEK
CSJ0030-02-052
Proj IDSTP 2019(603)
Work TypeOVERLAY
 
25.39613814377.4515783584.0899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began05-18-20
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged365
Percent Time Used272
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-052
BARRICADES UNLIMITED (1.98)
HJC FARMS, INC. (2.34)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.33)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.07)
GIBSON & ASSOCIATES, INC. (1.23)
Contract #03193005
Totals13814377.45198715.5815783584.0899.9

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromAT 15TH AVE
To.
CSJ0030-02-053
Proj IDSTP 2019(602)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
2.1522152762.701693926.6778.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-19
Work Began09-29-20
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged111
Percent Time Used60
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-053
CONCRETE CONNECTION (5.15)
FC TRAFFIC CONTROL, INC. (1.57)
LINEAR TRAFFIC MARKINGS LLC (1.67)
CONCRETE CONNECTION, LLC (5.15)
CIRCLE FOUR ENTERPRISES, LLC (1.15)
MEDELLIN HDD LLC (0.86)
BARRICADES UNLIMITED (1.80)
Contract #03193227
Totals2152762.70634718.011693926.6778.6

CountyOCHILTREE
HighwayUS 83
FromAT SL 143 (PERRYTON)
To.
CSJ0030-02-054
Proj IDSTP 2B20(146)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200203492.56213262.9699.9
CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-192
Proj IDSTP 2B20(146)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
770371.60768006.1599.9
Work Order09-08-20
Work Began00-00-00
Work Completed
Time Computed12-07-20
Contract Working Days100
Addl Days Granted0
Working Days Charged118
Percent Time Used118
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-054
LINEAR TRAFFIC MARKINGS LLC (1.87)
CONCRETE CONNECTION, LLC (9.50)
FC TRAFFIC CONTROL, INC. (0.85)
Contract #08203042
Totals973864.167260.75981269.1199.9

CountyHEMPHILL ETC
HighwayUS 60 ETC
FromAT CANADIAN RIVER
To.
CSJ0030-05-073
Proj IDBR 2022(398)
Work TypeBRIDGE MAINTENANCE
 
4.5658566511.5281525.000.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days188
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-073
ALAMO BROTHERS CONCRETE INC (0.84)
BARRICADES UNLIMITED (0.88)
FC TRAFFIC CONTROL, INC. (0.48)
HJC FARMS, INC. (0.75)
S & S BRIDGE PAINTING, INC. (1.93)
Contract #03223005
Totals8566511.520.0081525.000.9

CountyHEMPHILL ETC
HighwayUS 60 ETC
FromUS 83/ US 60 INTERCHANGE
ToBIRCH ST IN CANADIAN
CSJ0030-06-066
Proj IDF 2023(179)
Work TypeSEAL COAT
 
233.87221819571.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days97
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223002
Totals21819571.040.000.000.0

CountyHEMPHILL
HighwayUS 83
FromFM 277
ToWHEELER COUNTY LINE
CSJ0030-07-022
Proj IDF 2023(180)
Work TypeOVERLAY
 
6.9285382629.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-05-22
Work Began00-00-00
Work Completed
Time Computed01-04-23
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223025
Totals5382629.980.000.000.0

CountyDALLAM
HighwayUS 87
FromAT BU 87-B (7TH STREET)
To.
CSJ0040-03-068
Proj IDF 2021(646)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.222354993.200.000.0
CountyHARTLEY
HighwayUS 87
FromAT 16TH STREET
To.
CSJ0041-01-048
Proj IDSTP 2021(647)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200248962.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213032
Totals603955.810.000.000.0

CountyHARTLEY
HighwayUS 385
FromUS 87 IN HARTLEY
ToCHANNING
CSJ0041-02-016
Proj IDF 2021(441)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
19.9249656579.221360056.8514.0
Work Order05-20-21
Work Began11-01-21
Work Completed
Time Computed06-19-21
Contract Working Days327
Addl Days Granted0
Working Days Charged196
Percent Time Used59
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-02-016
W. S. CONSTRUCTION COMPANY (14.84)
BARRICADES UNLIMITED (2.44)
HJC FARMS, INC. (7.32)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.17)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.20)
Contract #04213207
Totals9656579.22272500.001360056.8514.0

CountyPOTTER ETC
HighwayUS 87 ETC
FromAMARILLO CREEK
ToSL 335
CSJ0041-07-111
Proj IDF 2022(118)
Work TypeSEAL COAT
 
213.69814719115.6515900526.1499.9
Work Order01-20-22
Work Began04-29-22
Work Completed
Time Computed05-16-22
Contract Working Days102
Addl Days Granted0
Working Days Charged100
Percent Time Used98
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-111
INNOVATIVE ROADWAY SOLUTIONS, LLC (10.59)
CENTERLINE TECHNOLOGIES, LLC (7.90)
FC TRAFFIC CONTROL, INC. (0.67)
LINEAR TRAFFIC MARKINGS LLC (0.00)
COX PAVING COMPANY OF TEXAS, INC. (0.00)
RED SIXTEEN CONSTRUCTION, INC (0.29)
COX PAVING OF TEXAS, INC. (20.37)
Contract #11213002
Totals14719115.656502.0015900526.1499.9

CountyARMSTRONG
HighwayUS 287
FromAT SH 207
To.
CSJ0042-03-044
Proj IDC 42-3-44
Work TypeTRAFFIC CONTROL DEVICES
 
0.0292102432.75821703.4539.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-22
Work Began08-29-22
Work Completed
Time Computed00-00-00
Contract Working Days104
Addl Days Granted0
Working Days Charged63
Percent Time Used60
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0042-03-044
ALAMO BROTHERS CONCRETE INC (10.77)
BARRICADES UNLIMITED (0.41)
DUKE ELECTRIC CO., INC. (32.89)
LINEAR TRAFFIC MARKINGS LLC (1.51)
DUSTROL, INC. (0.49)
Contract #05223237
Totals2102432.75137285.95821703.4539.0

CountyMOORE
HighwayUS 287
FromSOUTH OF FM 281
ToDUMAS
CSJ0066-04-079
Proj IDF 2021(699)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.9064229617.381627083.5339.8
Work Order08-25-21
Work Began03-30-22
Work Completed
Time Computed09-24-21
Contract Working Days137
Addl Days Granted0
Working Days Charged199
Percent Time Used145
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-04-079
MARCOM"S MOWING SERVICE, LLC (3.01)
DUSTROL, INC. (0.25)
TOTAL HIGHWAY MAINTENANCE, LLC (8.57)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.48)
LYNCO CONSTRUCTION (5.06)
LONE STAR EROSION CONTROL (2.34)
Contract #07213217
Totals4229617.3856387.701627083.5339.8

CountyMOORE
HighwayUS 87
FromSOUTH CITY LIMITS OF DUMAS
ToSH 152
CSJ0066-05-065
Proj IDNH 2013(606)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.56336473058.2828876986.6578.2
CountyMOORE
HighwayUS 87
FromAT SH 152
To.
CSJ0066-05-070
Proj IDSTP 2021(393)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.100327315.700.000.0
Work Order05-20-21
Work Began07-06-21
Work Completed
Time Computed06-19-21
Contract Working Days838
Addl Days Granted0
Working Days Charged412
Percent Time Used49
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-065
BARRICADES UNLIMITED (1.97)
JR WEST TEXAS CONCRETE LLC (8.60)
L&H ELECTRICAL, LLC (2.71)
DUSTROL, INC. (0.89)
L A FULLER & SONS CONSTRUCTION, LTD. (15.00)
PRIMATE CONSTRUCTION, LP (0.51)
RK HALL, LLC (15.08)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.04)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.10)
Contract #04213202
Totals36800373.981328285.3228876986.6577.5

CountyRANDALL
HighwayIH 27
FromSWISHER CO LINE
ToUS 60/US 87 INTERCHANGE
CSJ0067-17-036
Proj IDF 2023(244)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4296749.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0067-17-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223213
Totals4296749.450.000.000.0

CountyPOTTER ETC
HighwaySL 279 ETC
FromAT WESTERN STREET
To.
CSJ0090-05-095
Proj IDSTP 2018(815)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.8161568719.481387829.6899.9
Work Order06-14-18
Work Began00-00-00
Work Completed
Time Computed07-14-18
Contract Working Days173
Addl Days Granted3
Working Days Charged528
Percent Time Used300
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-095
ARTEX ELECTRIC, INC. (26.27)
CONCRETE CONNECTION (3.84)
BARRICADES UNLIMITED (2.13)
MEDELLIN HDD LLC (0.08)
Contract #05183244
Totals1568719.480.001387829.6899.9

CountyPOTTER
HighwayBI 40-D
FromON BI 40-D EB
ToAT BNSF RR
CSJ0090-06-044
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482915940.531517256.0352.4
CountyPOTTER
HighwayBI 40-D
FromON BI 40-D WB
ToAT BNSF RR
CSJ0090-06-045
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482291335.601851711.6580.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-21
Work Began05-03-21
Work Completed
Time Computed00-00-00
Contract Working Days364
Addl Days Granted0
Working Days Charged376
Percent Time Used103
Contractor(s)
INTEGRITY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-06-044
PINNACLE GRINDING AND GROOVING LLC (0.20)
HUNTER DEMOLITION & WRECKING CORPORATION (3.49)
BARRICADES UNLIMITED (1.90)
FC TRAFFIC CONTROL, INC. (0.47)
L&H ELECTRICAL, LLC (1.54)
RK HALL, LLC (6.23)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.41)
HJC FARMS, INC. (1.85)
A BROTHERS MILLING, LLC (0.35)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.36)
TORO BRAVO CONSTRUCTION, LLC (0.32)
TORO BRAVO CONSTRUCTION, LLC (0.91)
AARON CONCRETE CONTRACTORS, L.P. (3.17)
PENHALL COMPANY (0.16)
Contract #01213007
Totals5207276.1339094.103368967.6864.9

CountyDEAF SMITH
HighwayUS 60
FromTIERRA BLANCA CREEK
ToCASTRO COUNTY LINE
CSJ0168-05-041
Proj IDF 2022(056)
Work TypeOVERLAY
 
5.4645275866.955543008.2699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted3
Working Days Charged101
Percent Time Used120
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-05-041
ALAMO BROTHERS CONCRETE INC (1.12)
BARRICADES UNLIMITED (2.71)
DK CONTRACTING, LLC (3.11)
DUSTIN ALLEN, INC. (0.78)
FC TRAFFIC CONTROL, INC. (0.24)
TEXOP CONSTRUCTION (1.36)
WEST TEXAS ROCK RESOURCES, LLC (0.21)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.16)
W. S. CONSTRUCTION COMPANY (2.49)
Contract #10213203
Totals5275866.95151857.215543008.2699.9

CountyDEAF SMITH
HighwayUS 60
From.9 MILES SW OF FM 2943
To.5 MILES NE OF FM 2943
CSJ0168-07-047
Proj IDF 2021(869)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1.7403379277.553138972.9992.8
CountyDEAF SMITH
HighwayUS 60
FromAT FM 2943
To.
CSJ0168-07-048
Proj IDSTP 2021(870)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200310437.2580356.9025.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-27-22
Work Began05-02-22
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged139
Percent Time Used99
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-047
ALAMO BROTHERS CONCRETE INC (3.19)
BARRICADES UNLIMITED (2.94)
HJC FARMS, INC. (4.53)
WILLIS ELECTRIC CO., LP (0.00)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.15)
FUSION COMMUNICATIONS, LLC (0.00)
H & F TRUCKING (1.31)
TRP CONSTRUCTION GROUP, LLC (1.02)
Contract #08213239
Totals3689714.80675299.653219329.8987.2

CountyDEAF SMITH
HighwayUS 60
FromEAST OF FM 2943 SOUTH
ToRANDALL COUNTY LINE
CSJ0168-07-049
Proj IDF 2021(708)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5647434.204060479.4973.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-21
Work Began11-08-21
Work Completed
Time Computed00-00-00
Contract Working Days181
Addl Days Granted0
Working Days Charged250
Percent Time Used138
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-049
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.11)
BARRICADES UNLIMITED (4.48)
DUSTIN ALLEN, INC. (2.26)
DUSTROL, INC. (1.81)
MARCOM"S MOWING SERVICE, LLC (5.39)
GHC TRANSPORT, L.L.C. (0.15)
Contract #07213016
Totals5647434.201385485.004060479.4973.2

CountyDEAF SMITH
HighwayUS 60
FromEAST OF HEREFORD
ToRANDALL COUNTY LINE
CSJ0168-07-050
Proj IDC 168-7-50
Work TypeREHABILITATION OF EXISTING ROAD
 
26.39023784485.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days194
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233202
Totals23784485.600.000.000.0

page 1 | page 2 | page 3 | page 4