Monthly State Let Construction Report For Amarillo District As Of Nov 10, 2024 Page 4 Of 4
Last Update: Sunday, November 10, 2024
 |
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | POTTER |
Highway | SL 335 |
From | SW 9TH |
To | FM 1719 |
CSJ | 2635-04-031 |
Proj ID | F 2023(243) |
Work Type | WIDEN NON-FREEWAY |
|
| 6.010 | 133890000.00 | | 97341628.57 | 72.7 |
Work Order | 06-01-23 |
Work Began | 06-12-23 |
Work Completed | |
Time Computed | 09-01-23 |
Contract Working Days | 890 |
Addl Days Granted | 0 |
Working Days Charged | 355 |
Percent Time Used | 39 |
Contractor(s) |
WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 2635-04-031 ADRIAN CONTRACTING, INC (0.02) APOLLO CONSTRUCTORS, INC. (2.48) BARRICADES UNLIMITED (0.16) DUSTIN ALLEN, INC. (0.73) GIBSON & ASSOCIATES, INC. (0.99) HJC FARMS, INC. (0.34) J. LEE MILLIGAN, INC. (29.66) PRIMATE CONSTRUCTION, LP (0.03) S & S BRIDGE PAINTING, INC. (0.10) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.38) TORO BRAVO CONSTRUCTION, LLC (1.14) TRP CONSTRUCTION GROUP, LLC (0.37) V-TECH ENVIROMENTAL SERVICES (0.50) A BROTHERS MILLING, LLC (0.53) M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00) TURKEY CREEK HDD, LLC (0.69) TORO BRAVO CONSTRUCTION, LLC (0.05) GP7 CONSTRUCTION INC. (7.00) H & F TRUCKING (0.00) FLOVERA CONSTRUCTION SERVICES, LLC (1.36) ALAMO BROTHERS CONCRETE INC (0.30)
|
Contract # | 12223001 |
| Totals | 133890000.00 | 1414655.22 | 97341628.57 | 72.7 |
|