Monthly State Let Construction Report For Amarillo District As Of Sep 13, 2021 Page 2 Of 3

Last Update: Wednesday, September 15, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRANDALL
HighwayIH 27
FromWESTERN STREET
ToNORTH OF IH 27/US 60 INTERCHANGE
CSJ0168-09-165
Proj IDNH 2021(021)
Work TypeOVERLAY
 
28.0436336098.662548101.9540.2
Work Order11-19-20
Work Began00-00-00
Work Completed
Time Computed12-19-20
Contract Working Days76
Addl Days Granted4
Working Days Charged72
Percent Time Used90
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-165
H & F TRUCKING (6.01)
HJC FARMS, INC. (0.00)
FC TRAFFIC CONTROL, INC. (0.00)
TEX OP CONSTRUCTION, LP (2.58)
ALAMO BROTHERS CONCRETE INC (1.13)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.06)
BARRICADES UNLIMITED (2.23)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.40)
Contract #10203228
Totals6336098.66532446.212548101.9540.2

CountyRANDALL
HighwayIH 27
From0.058 MILES SOUTH OF 45TH AVE
ToPOTTER COUNTY LINE
CSJ0168-09-180
Proj IDSTP 2021(517)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.5215291174.650.000.0
CountyRANDALL
HighwayIH 27
From45TH AVE
ToPOTTER COUNTY LINE
CSJ0168-09-181
Proj IDF 2021(518)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
3.15625024977.76278202.891.1
CountyPOTTER
HighwayIH 27
FromRANDALL COUNTY LINE
To0.2 MILES SOUTH OF IH 40
CSJ0168-10-077
Proj IDSTP 2021(517)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.499682460.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days847
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-180
BARRICADES UNLIMITED (1.18)
SLATON BROTHERS, INC. (2.58)
H & F TRUCKING (2.17)
Contract #05213202
Totals30998613.0676831.24278202.890.8

CountyGRAY
HighwayUS 60
FromLP 171 IN PAMPA
ToROBERTS COUNTY LINE
CSJ0169-07-053
Proj IDC 169-7-53
Work TypeSUPER-2 HIGHWAY
 
12.90014712201.160.000.0
CountyGRAY
HighwayUS 60
FromTIGNOR ST
ToCOUNTY ROAD 10
CSJ0169-07-054
Proj IDC 169-7-54
Work TypeREHABILITATION OF EXISTING ROAD
 
1.4271824177.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days351
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-07-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213006
Totals16536378.970.000.000.0

CountyHARTLEY
HighwayUS 54
FromNEW MEXICO STATE LINE
To10.326 MILES NE OF FM 767
CSJ0238-01-033
Proj IDSTP 2019(410)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
39.658310777.000.000.0
CountyHARTLEY
HighwayUS 54
FromRITA BLANCA CREEK BRIDGE
ToMIDDLEWATER
CSJ0238-02-038
Proj IDNH 2019(409)
Work TypeSUPER 2 HIGHWAY
 
39.80034913009.9018361306.4152.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-19
Work Began07-08-19
Work Completed
Time Computed00-00-00
Contract Working Days465
Addl Days Granted0
Working Days Charged367
Percent Time Used78
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-01-033
HJC FARMS, INC. (1.27)
APEX HIGHWAY SERVICES, LLC (0.15)
BARRICADES UNLIMITED (1.99)
GIBSON & ASSOCIATES, INC. (1.89)
H & F TRUCKING (1.50)
SCR CIVIL CONSTRUCTION, LLC (1.04)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.16)
Contract #01193001
Totals35223786.9014400.0018361306.4152.1

CountyDALLAM
HighwayUS 54
FromTEXAS STREET IN DALHART
ToCHAMBERLAIN
CSJ0238-03-064
Proj IDNH 2020(034)
Work TypeREHABILITATION OF EXISTING ROAD
 
21.54014364733.9015967309.7699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-19
Work Began06-15-20
Work Completed
Time Computed00-00-00
Contract Working Days156
Addl Days Granted0
Working Days Charged192
Percent Time Used123
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0238-03-064
BARRICADES UNLIMITED (1.82)
DUSTROL, INC. (1.05)
BAHENA CONSTRUCTION CO.,INC. (3.92)
DK CONTRACTING, LLC (0.28)
WEST TEXAS ROCK RESOURCES, LLC (0.18)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.13)
Contract #08193009
Totals14364733.90221769.4515967309.7699.9

CountyPOTTER
HighwayIH 40
FromAT WHITAKER STREET
To.
CSJ0275-01-180
Proj IDBR 2018(359)
Work TypeREPLACE EXISTING BRIDGE
 
8.37450440638.5647293689.1993.8
Work Order02-14-18
Work Began04-02-18
Work Completed
Time Computed03-16-18
Contract Working Days696
Addl Days Granted178
Working Days Charged885
Percent Time Used101
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-180
BARRICADES UNLIMITED (1.72)
ANTIGO CONSTRUCTION, INC. (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.19)
HJC FARMS, INC. (1.10)
ALAMO BROTHERS CONCRETE, INC. (7.92)
WOLFE CONSTRUCTION GROUP, INC. (0.12)
OSCAR ORDUNO, INC. (5.20)
WILLIS ELECTRIC CO., LP (3.07)
L A FULLER & SONS CONSTRUCTION, LTD. (2.10)
MCL CONTRACTING, LLC (0.88)
SLATON BROTHERS, INC. (3.63)
MICA CORPORATION (0.88)
BOWMAN ENGINEERING & CONSULTING, INC. (0.09)
PRIMATE CONSTRUCTION, LP (0.27)
FUSION COMMUNICATIONS, LLC (0.13)
ALAMO BROTHERS CONCRETE INC (0.03)
TORO BRAVO CONSTRUCTION, LLC (0.50)
Contract #01183002
Totals50440638.561963438.9047293689.1993.8

CountyPOTTER
HighwayIH 40
FromBI 40-D
ToFM 2590 (SONCY ROAD)
CSJ0275-01-199
Proj IDNH 2020(549)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.86325360575.7716005662.5563.1
CountyPOTTER
HighwaySL 335
FromFM 2590 NORTH
ToSW 9TH
CSJ2635-04-037
Proj IDNH 2020(550)
Work TypeNEW LOCATION NON-FREEWAY
 
2.33324672131.9713559370.3754.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days575
Addl Days Granted0
Working Days Charged333
Percent Time Used57
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-199
AARON CONCRETE CONTRACTORS, L.P. (1.01)
ACT SAW CUTTING & REMOVAL (0.11)
BARRICADES UNLIMITED (0.58)
CHEROKEE SERVICES (0.09)
SCOTT DERR PAINTING CO, LLC (0.07)
SOUTHEAST GRINDING & GROOVING, LLC (0.03)
TEXOP CONSTRUCTION (0.51)
TORO BRAVO CONSTRUCTION, LLC (0.20)
WILLIAMS DITCHING, LLC (4.71)
FC TRAFFIC CONTROL, INC. (0.32)
HJC FARMS, INC. (1.69)
H & F TRUCKING (4.90)
ARTEX ELECTRIC, INC. (2.34)
FARR FOUNDATION, INC. (0.77)
ALAMO BROTHERS CONCRETE INC (3.05)
DK CONTRACTING, LLC (0.01)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.02)
DIIBS SPECIALISTS, LLC (0.02)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00)
G & L REBAR (0.00)
URBAN INFRACONSTRUCTION LLC (0.20)
G & L REBAR (0.07)
ROYAL REBAR (0.02)
Contract #02203001
Totals50032707.74689279.2129565032.9259.0

CountyPOTTER
HighwayIH 40
FromAT PARAMOUNT BLVD-JULIAN/WOLFLIN ST
To.
CSJ0275-01-205
Proj IDBR 2020(793)
Work TypeBRIDGE MAINTENANCE
 
0.53415820658.8212069068.0476.2
Work Order07-07-20
Work Began00-00-00
Work Completed
Time Computed08-06-20
Contract Working Days440
Addl Days Granted0
Working Days Charged246
Percent Time Used55
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-205
MOBILE ENTERPRISES, INC. (2.54)
MACIAS SPECIALTY CONTRACTING LLC (0.88)
J.H. PAINTING COMPANY (1.36)
V-TECH ENVIROMENTAL SERVICES (0.10)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.13)
BARRICADES UNLIMITED (1.14)
HJC FARMS, INC. (1.87)
IBCTX, LLC (27.60)
L A FULLER & SONS CONSTRUCTION, LTD. (7.83)
PENHALL COMPANY (0.22)
W.O.E. CONSTRUCTION, INC. (1.82)
WILLIS ELECTRIC CO., LP (0.68)
MCL CONTRACTING, LLC (0.00)
IVS HYDRO DEMOLITION SERVICES (WEST VIRGINIA) (2.02)
LLOYD D. NABORS DEMOLITION LLC (1.95)
Contract #05203207
Totals15820658.821646013.8112069068.0476.2

CountyPOTTER
HighwayIH 40
FromEAST OF WASHINGTON ST
ToSOUTH OSAGE ST
CSJ0275-01-215
Proj IDC 275-1-215
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4539711.252335144.7551.4
Work Order09-15-20
Work Began00-00-00
Work Completed
Time Computed10-15-20
Contract Working Days383
Addl Days Granted0
Working Days Charged180
Percent Time Used46
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-215
ALAMO BROTHERS CONCRETE INC (36.27)
DUKE ELECTRIC CO., INC. (5.34)
SCOTT DERR PAINTING CO, LLC (1.25)
STRIPE-A-ZONE, INC. (12.10)
BARRICADES UNLIMITED (4.80)
Contract #07203019
Totals4539711.25138605.002335144.7551.4

CountyCARSON
HighwayIH 40
FromPOTTER COUNTY LINE
ToBI 40-D
CSJ0275-02-070
Proj IDSTP 2020(509)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.044593602.53756832.7799.9
CountyCARSON
HighwayIH 40
FromBI 40D
ToFM2373
CSJ0275-02-072
Proj IDNH 2020(510)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.8371058810.81971112.6791.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-18-20
Work Began07-10-20
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged75
Percent Time Used92
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0275-02-070
FC TRAFFIC CONTROL, INC. (2.35)
FOX CONTRACTING KY, INC. (18.34)
WILLIAMS DITCHING, LLC (7.39)
Contract #01203205
Totals1652413.340.001727945.4499.9

CountyCARSON
HighwayIH 40
From1.6 MILES EAST OF CONWAY
To1.2 MILES EAST OF FM 2880
CSJ0275-03-066
Proj IDNH 2019(053)
Work TypeREHAB EXISTING ROADWAY
 
5.2267743120.097718882.0999.9
CountyCARSON
HighwayIH 40
From3.143 MILES EAST OF SH 207
To1.234 MILES WEST OF FM 2880
CSJ0275-03-067
Proj IDSTP 2019(054)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
3.76038840.000.000.0
CountyCARSON
HighwayIH 40
From1.2 MILES EAST OF FM 2880
To1 MILE EAST OF FM 294
CSJ0275-04-054
Proj IDNH 2019(053)
Work TypeREHAB EXISTING ROADWAY
 
6.2107282294.037009719.8596.2
CountyCARSON
HighwayIH 40
From1.234 MILES WEST OF FM 2880
To0.686 MILES WEST OF BI-40F
CSJ0275-04-056
Proj IDSTP 2019(054)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
6.26038840.0019480.0050.1
Work Order10-16-18
Work Began04-04-19
Work Completed
Time Computed11-15-18
Contract Working Days118
Addl Days Granted0
Working Days Charged231
Percent Time Used195
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0275-03-066
BARRICADES UNLIMITED (0.56)
DUSTROL, INC. (0.80)
H & F TRUCKING (0.00)
J. H. ODEN CONTRACTING COMPANY (0.20)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
Contract #09183204
Totals15103094.120.0014748081.9498.6

CountyGRAY ETC
HighwayIH 40
FromDONLEY COUNTY LINE
To0.5 MILES WEST OF ALANREED
CSJ0275-11-083
Proj IDNH 2020(353)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.38010924179.853616608.4333.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-20
Work Began07-27-20
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged148
Percent Time Used123
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-083
SILVER CREEK CONSTRUCTION, INC. (3.02)
HJC FARMS, INC. (1.75)
ALAMO BROTHERS CONCRETE INC (1.44)
BARRICADES UNLIMITED (1.53)
H & F TRUCKING (4.43)
WEST TEXAS ROCK RESOURCES, LLC (0.18)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.09)
DUSTROL, INC. (0.66)
Contract #12193011
Totals10924179.85258250.453616608.4333.4

CountyGRAY
HighwayIH 40
FromMM 134.7
ToMM 146.5
CSJ0275-11-085
Proj IDNH 2021(022)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11.8502747711.002000058.0672.7
Work Order11-19-20
Work Began05-10-21
Work Completed
Time Computed12-21-20
Contract Working Days94
Addl Days Granted0
Working Days Charged65
Percent Time Used69
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-085
GHB EQUIPMENT COMPANY, L.L.C. (13.05)
STRIPE-A-ZONE, INC. (18.39)
Contract #10203016
Totals2747711.00344972.152000058.0672.7

CountyLIPSCOMB
HighwaySH 15
FromAT DARROUZETT CREEK
To.
CSJ0355-01-050
Proj IDBR 1902(140)
Work TypeBR
 
0.0911531114.001737500.7699.9
CountyGRAY
HighwayCR
FromAT DEEP LAKE ROAD
To.
CSJ0904-13-027
Proj IDBR 1802(839)
Work TypeBR
 
0.038323916.00370595.0099.9
CountyGRAY
HighwayRM 1474
FromAT CABIN CREEK
To.
CSJ2491-01-010
Proj IDBR 1902(140)
Work TypeBR
 
1513903.001506342.0099.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began05-13-20
Work Completed
Time Computed00-00-00
Contract Working Days281
Addl Days Granted0
Working Days Charged268
Percent Time Used95
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-050
BARRICADES UNLIMITED (5.30)
SOUTH TEXAS PAINTING COMPANY (0.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.76)
TORO BRAVO CONSTRUCTION, LLC (0.50)
LANCO TURF & SEEDING, INC. (0.12)
DUININCK, INC. (1.70)
Contract #07193018
Totals3368933.00234421.503614437.7699.9

CountyCARSON
HighwaySH 207
FromBNSF RAILROAD UNDERPASS (PANHANDLE)
To.
CSJ0356-02-048
Proj IDSTP 2020(635)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.1761042468.00355712.1634.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-07-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days129
Addl Days Granted0
Working Days Charged89
Percent Time Used68
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203029
Totals1042468.001480.00355712.1634.1

CountyPOTTER
HighwaySH 136
From6.51 MI SOUTH OF MOORE COUNTY LINE
To0.5 MI NORTH OF FM 293
CSJ0379-02-032
Proj IDSTP 2B20(144)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11.8304791327.794640748.9996.8
CountyPOTTER
HighwaySH 136
From0.5 MI NORTH OF FM 293
ToFM 293
CSJ0379-02-033
Proj IDSTP 2B20(144)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.49990421.1187473.5896.7
CountyPOTTER
HighwaySH 136
FromFM 293
ToFOLSOM ROAD
CSJ0379-03-025
Proj IDSTP 2B20(144)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.1094333354.444108633.3794.8
Work Order09-16-20
Work Began00-00-00
Work Completed
Time Computed10-16-20
Contract Working Days409
Addl Days Granted0
Working Days Charged177
Percent Time Used43
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0379-02-032
BARRICADES UNLIMITED (3.62)
DUSTROL, INC. (0.87)
FC TRAFFIC CONTROL, INC. (0.44)
MARCOM"S MOWING SERVICE, LLC (1.26)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.36)
W. S. CONSTRUCTION COMPANY (2.67)
DUSTIN ALLEN, INC. (0.98)
PINNACLE GRINDING AND GROOVING LLC (0.07)
Contract #08203215
Totals9215103.34633698.328836855.9495.8

CountyPOTTER
HighwaySH 136
FromAT FM 1912
To.
CSJ0379-03-026
Proj IDSTP 2021(190)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5002861868.880.000.0
CountyPOTTER
HighwaySH 136
FromFOLSOM ROAD
To0.2 MILES SOUTH OF SL 335
CSJ0379-03-027
Proj IDF 2021(946)
Work TypeTRAFFIC CONTROL DEVICES
 
1.6413832483.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days207
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0379-03-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213011
Totals6694352.150.000.000.0

CountyGRAY
HighwaySH 152
FromUS 60
ToWHEELER CO LINE
CSJ0397-01-045
Proj IDSTP 2021(130)
Work TypeSUPER-2 HIGHWAY
 
17.99015464360.413587824.6523.2
Work Order12-11-20
Work Began02-15-21
Work Completed
Time Computed01-11-21
Contract Working Days266
Addl Days Granted0
Working Days Charged66
Percent Time Used24
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-045
BARRICADES UNLIMITED (1.50)
BIG CREEK SAND & GRAVEL, INC. (11.85)
DUSTIN ALLEN, INC. (4.69)
MARCOM"S MOWING SERVICE, LLC (0.70)
TEX OP CONSTRUCTION, LP (2.06)
W. S. CONSTRUCTION COMPANY (9.72)
WEST TEXAS ROCK RESOURCES, LLC (0.37)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.28)
Contract #11203004
Totals15464360.41426713.633587824.6523.2

CountyCARSON
HighwaySH 152
FromAT SPRING CREEK
To.
CSJ0455-02-027
Proj IDBR 2021(709)
Work TypeBRIDGE REPLACEMENT
 
0.8044283739.200.000.0
CountyCARSON
HighwaySH 152
FromAT WHITE DEER CREEK
To.
CSJ0455-02-028
Proj IDBR 2021(709)
Work TypeBRIDGE REPLACEMENT
 
0.7833941530.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days335
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0455-02-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213010
Totals8225269.800.000.000.0

CountyROBERTS ETC
HighwaySH 70
FromCANADIAN RIVER BRIDGE
To15 MILES NORTH OF GRAY COUNTY LINE
CSJ0490-04-045
Proj IDSTP 2019(727)
Work TypeOVERLAY
 
60.33223349233.8218996823.5981.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-19
Work Began01-07-20
Work Completed
Time Computed00-00-00
Contract Working Days178
Addl Days Granted0
Working Days Charged222
Percent Time Used124
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-045
BARRICADES UNLIMITED (2.69)
ALAMO BROTHERS CONCRETE INC (1.43)
Contract #04193004
Totals23349233.821634223.2018996823.5981.8

page 1 | page 2 | page 3