Monthly State Let Construction Report For Amarillo District As Of Nov 10, 2024 Page 3 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCARSON
HighwaySH 152
FromAT SPRING CREEK
To.
CSJ0455-02-027
Proj IDBR 2021(709)
Work TypeBRIDGE REPLACEMENT
 
0.8044283739.203719259.4395.6
CountyCARSON
HighwaySH 152
FromAT WHITE DEER CREEK
To.
CSJ0455-02-028
Proj IDBR 2021(709)
Work TypeBRIDGE REPLACEMENT
 
0.7833941530.603894733.0598.8
Work Order08-25-21
Work Began11-19-21
Work Completed
Time Computed09-24-21
Contract Working Days335
Addl Days Granted0
Working Days Charged618
Percent Time Used184
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0455-02-027
ALAMO BROTHERS CONCRETE INC (2.88)
BARRICADES UNLIMITED (1.20)
HJC FARMS, INC. (2.76)
PRIMATE CONSTRUCTION, LP (0.22)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.61)
G & L REBAR (0.23)
DUSTROL, INC. (0.76)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.10)
TORO BRAVO CONSTRUCTION, LLC (1.34)
GRIT LOGISTICS, L.L.C. (0.73)
TRP CONSTRUCTION GROUP, LLC (1.20)
PINNACLE GRINDING AND GROOVING LLC (0.22)
Contract #07213010
Totals8225269.802144.857613992.4897.1

CountyCARSON
HighwaySH 152
FromHUTCHINSON CO LINE
ToGRAY CO LINE
CSJ0455-02-031
Proj IDF 2B23(295)
Work TypeSUPER-2 HIGHWAY
 
13.01314702486.149933215.4767.5
CountyCARSON
HighwaySH 152
FromHUTCHINSON COUNTY LINE
ToGRAY COUNTY LINE
CSJ0455-02-032
Proj IDSTP 2B23(296)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1772018.221263649.2671.3
Work Order12-05-23
Work Began02-15-24
Work Completed
Time Computed01-04-24
Contract Working Days202
Addl Days Granted0
Working Days Charged169
Percent Time Used83
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0455-02-031
BAHENA CONSTRUCTION CO.,INC. (6.95)
DUSTIN ALLEN, INC. (0.52)
INDUSTRIAL FABRICS, INC. (8.94)
MURRAY CONSTRUCTION (0.72)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.18)
TEX OP CONSTRUCTION, LP (1.23)
TRP CONSTRUCTION GROUP, LLC (2.96)
WITHERS CONSTRUCTION, LLC (0.79)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.27)
FC TRAFFIC CONTROL, INC. (0.15)
Contract #11233203
Totals16474504.361219838.0011196864.7367.9

CountyGRAY
HighwaySH 152
FromCARSON CO LINE
ToSH 70
CSJ0455-03-038
Proj IDF 2B24(078)
Work TypeSUPER-2 HIGHWAY
 
6.42517457097.335814148.7833.3
Work Order06-12-24
Work Began07-08-24
Work Completed
Time Computed07-12-24
Contract Working Days193
Addl Days Granted0
Working Days Charged75
Percent Time Used38
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0455-03-038
BAHENA CONSTRUCTION CO.,INC. (3.16)
BARRICADES UNLIMITED (0.17)
DK CONTRACTING, LLC (0.25)
DUSTIN ALLEN, INC. (0.58)
INDUSTRIAL FABRICS, INC. (4.69)
PROFESSIONAL TRAFFIC CONTROL LLC (0.08)
TEXOP CONSTRUCTION (1.15)
TRP CONSTRUCTION GROUP, LLC (1.91)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.10)
W. S. CONSTRUCTION COMPANY (6.84)
Contract #05243009
Totals17457097.332243668.395814148.7833.3

CountyDONLEY
HighwayFM 291
From@ WHITEFISH CREEK
To.
CSJ0795-05-010
Proj IDBR 2023(281)
Work TypeBRIDGE REPLACEMENT
 
3892082.003331774.0088.1
Work Order01-12-23
Work Began05-30-23
Work Completed
Time Computed02-11-23
Contract Working Days210
Addl Days Granted0
Working Days Charged317
Percent Time Used150
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0795-05-010
FC TRAFFIC CONTROL, INC. (0.47)
A-CORE CONCRETE CUTTING, INC. (0.18)
LANCO TURF & SEEDING, INC. (0.37)
TRP CONSTRUCTION GROUP, LLC (1.04)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.00)
G & L REBAR (0.30)
L A FULLER & SONS CONSTRUCTION, LTD. (1.71)
TEX OP CONSTRUCTION, LP (0.00)
Contract #12223015
Totals3892082.00232933.253331774.0088.1

CountyDEAF SMITH
HighwayFM 809
FromAT FM 1062
To.
CSJ0801-02-022
Proj IDSTP 2023(691)HES
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.200404030.05389196.7898.7
CountyPOTTER
HighwayVA
FromIH 40 WEST
To.
CSJ0904-00-218
Proj IDSTP 2023(965)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1957418.441806338.8092.2
Work Order06-14-23
Work Began02-01-24
Work Completed
Time Computed10-12-23
Contract Working Days100
Addl Days Granted0
Working Days Charged112
Percent Time Used112
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0801-02-022
GOMEZ PROPERTY SOLUTIONS LLC (6.92)
FC TRAFFIC CONTROL, INC. (0.74)
Contract #05233032
Totals2361448.4941662.652195535.5893.3

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-188
Proj IDSTP 2020(551)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.0001274691.701376210.1899.9
Work Order07-07-20
Work Began11-16-20
Work Completed
Time Computed11-04-20
Contract Working Days214
Addl Days Granted0
Working Days Charged214
Percent Time Used100
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-188
FC TRAFFIC CONTROL, INC. (0.00)
TX DOWN UNDER CONSTRUCTION, LLC (0.00)
TALON/LPE, LTD. (0.00)
CANNON ASPHALT GROUP LLC (1.12)
D. E. RICE CONSTRUCTION COMPANY, INC. (0.00)
LINEAR TRAFFIC MARKINGS LLC (0.00)
Contract #02203224
Totals1274691.700.001376210.1899.9

CountyPOTTER
HighwayVA
FromDISTRICT WIDE
To.
CSJ0904-00-207
Proj IDF 2024(137)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3292241.773330582.3399.9
Work Order11-30-23
Work Began03-19-24
Work Completed
Time Computed12-30-23
Contract Working Days93
Addl Days Granted0
Working Days Charged121
Percent Time Used130
Contractor(s)
CENTERLINE TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-207
RED SIXTEEN CONSTRUCTION, INC (0.00)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.00)
Contract #10233213
Totals3292241.77628607.573330582.3399.9

CountyPOTTER
HighwayVA
FromVARIOUS
To.
CSJ0904-00-214
Proj IDSTP 2B24(237)VRUG
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
640275.00142780.0022.2
Work Order08-14-24
Work Began00-00-00
Work Completed
Time Computed11-13-24
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-214
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243030
Totals640275.00142780.00142780.0022.2

CountyPOTTER
HighwayVA
FromNEW MEXICO STATE LINE
ToWHEELER COUNTY
CSJ0904-00-220
Proj IDF 2B24(460)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3354582.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIGHT IT UP ELECTRIC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-220
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243219
Totals3354582.500.000.000.0

CountyPOTTER
HighwayVA
FromPOTTER CO LINE
ToWHEELER CO LINE
CSJ0904-00-223
Proj IDF 2B24(226)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2357139.5018750.000.7
Work Order07-10-24
Work Began00-00-00
Work Completed
Time Computed10-08-24
Contract Working Days77
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-223
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243259
Totals2357139.5018750.0018750.000.7

CountyDEAF SMITH
HighwayFM 1259
FromTIERRA BLANCA CREEK
To.
CSJ1243-02-031
Proj IDBR 2023(820)
Work TypeBRIDGE REPLACEMENT
 
0.0495827413.204403499.6376.9
Work Order07-19-23
Work Began02-02-24
Work Completed
Time Computed08-19-23
Contract Working Days145
Addl Days Granted0
Working Days Charged187
Percent Time Used128
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1243-02-031
ALAMO BROTHERS CONCRETE INC (4.93)
FC TRAFFIC CONTROL, INC. (0.15)
HJC FARMS, INC. (0.34)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.90)
PRIMATE CONSTRUCTION, LP (0.19)
TRP CONSTRUCTION GROUP, LLC (0.30)
TORO BRAVO CONSTRUCTION, LLC (0.37)
Contract #06233008
Totals5827413.20191340.514403499.6376.9

CountyPOTTER
HighwayRM 1061
FromRM 2381
ToN COULTER STREET
CSJ1245-02-049
Proj IDF 2022(374)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.16812755021.4113227049.9999.9
Work Order03-11-22
Work Began06-06-22
Work Completed
Time Computed04-10-22
Contract Working Days288
Addl Days Granted10
Working Days Charged311
Percent Time Used104
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-049
ALAMO BROTHERS CONCRETE INC (0.68)
BARRICADES UNLIMITED (1.48)
DK CONTRACTING, LLC (1.31)
DUSTIN ALLEN, INC. (1.67)
J. H. ODEN CONTRACTING COMPANY (0.28)
W. S. CONSTRUCTION COMPANY (6.06)
AMARILLO ARBORLOGICAL, INC. (0.46)
DUSTROL, INC. (0.90)
TRP CONSTRUCTION GROUP, LLC (1.48)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.09)
Contract #02223226
Totals12755021.4122078.9813227049.9999.9

CountyLIPSCOMB
HighwaySH 23
From11 MI NORTH OF US 83
ToUS 83
CSJ1337-02-012
Proj IDF 2022(057)
Work TypeREHABILITATION OF EXISTING ROAD
 
11.0507414243.898223584.6499.9
Work Order11-17-21
Work Began07-28-22
Work Completed
Time Computed12-17-21
Contract Working Days257
Addl Days Granted8
Working Days Charged265
Percent Time Used100
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1337-02-012
BARRICADES UNLIMITED (3.15)
HJC FARMS, INC. (3.56)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.29)
H & F TRUCKING (1.70)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (3.03)
Contract #10213006
Totals7414243.890.008223584.6499.9

CountyLIPSCOMB
HighwayFM 1454
FromWOLF CREEK BRIDGE .
To.
CSJ1339-02-028
Proj IDBR 2023(457)
Work TypeBRIDGE REPLACEMENT
 
0.2288532873.457148451.3784.1
CountyLIPSCOMB
HighwayFM 1920
FromLITTLE SAND CREEK BRIDGE
To.
CSJ1819-01-016
Proj IDBR 2023(457)
Work TypeBRIDGE REPLACEMENT
 
0.0841892138.901941640.0599.9
Work Order03-16-23
Work Began07-05-23
Work Completed
Time Computed04-15-23
Contract Working Days315
Addl Days Granted2
Working Days Charged321
Percent Time Used101
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1339-02-028
FC TRAFFIC CONTROL, INC. (0.27)
LINEAR TRAFFIC MARKINGS LLC (0.39)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.07)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.95)
S&S BRIDGE PAINTING (0.31)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.40)
TORO BRAVO CONSTRUCTION, LLC (0.32)
L A FULLER & SONS CONSTRUCTION, LTD. (12.41)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.17)
Contract #02233012
Totals10425012.354732.009090091.4287.4

CountyMOORE
HighwayFM 281
FromHARTLEY COUNTY LINE
ToUS 287
CSJ1727-02-024
Proj IDC 1727-2-24
Work TypeREHABILITATION OF EXISTING ROAD
 
9.38741097397.1010759091.6326.1
Work Order05-03-24
Work Began07-08-24
Work Completed
Time Computed06-02-24
Contract Working Days299
Addl Days Granted0
Working Days Charged73
Percent Time Used24
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1727-02-024
BARRICADES UNLIMITED (0.12)
HJC FARMS, INC. (0.43)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.06)
TRP CONSTRUCTION GROUP, LLC (0.79)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.10)
Contract #02243203
Totals41097397.104365869.6310759091.6326.1

CountyLIPSCOMB
HighwayFM 1920
FromRM 3260
ToHEMPHILL COUNTY LINE
CSJ1819-01-015
Proj IDSSW 1819-1-15
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.07616356130.4118043954.9799.9
Work Order06-09-20
Work Began03-15-21
Work Completed
Time Computed07-09-20
Contract Working Days441
Addl Days Granted10
Working Days Charged450
Percent Time Used99
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1819-01-015
BARRICADES UNLIMITED (5.90)
GREGORY PILE DRIVING, INC. (0.31)
PRIMATE CONSTRUCTION, LP (0.10)
SCOTT DERR PAINTING CO, LLC (0.11)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.78)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (1.26)
Contract #04203203
Totals16356130.410.0018043954.9799.9

CountyGRAY
HighwayRM 1321
FromAT SAND CREEK
To.
CSJ1861-02-024
Proj IDBR 2021(648)
Work TypeBRIDGE REPLACEMENT
 
0.0851287349.04927164.7799.9
CountyGRAY
HighwayRM 1321
FromCANTONMENT CREEK
To.
CSJ1861-02-025
Proj IDBR 2021(648)
Work TypeBRIDGE REPLACEMENT
 
0.1222190990.682316891.6799.9
Work Order07-22-21
Work Began09-27-21
Work Completed
Time Computed08-23-21
Contract Working Days273
Addl Days Granted0
Working Days Charged717
Percent Time Used262
Contractor(s)
UNITED FIRE & CASUALTY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1861-02-024
BARRICADES UNLIMITED (0.71)
FARR FOUNDATION, INC. (9.18)
HJC FARMS, INC. (2.55)
HUNTER DEMOLITION & WRECKING CORPORATION (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.92)
PINNACLE GRINDING AND GROOVING LLC (0.38)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.36)
TORO BRAVO CONSTRUCTION, LLC (1.81)
PENHALL COMPANY (0.59)
TEX OP CONSTRUCTION, LP (0.43)
RK HALL, LLC (8.76)
COPPELL CONSTRUCTION CO., INC. (64.99)
TRP CONSTRUCTION GROUP, LLC (0.36)
Contract #06213214
Totals3478339.72357660.003244056.4499.9

CountyRANDALL
HighwayFM 2590
FromSL 335
ToUS 60 (CANYON)
CSJ2614-01-024
Proj IDSTP 2B24(144)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.41714662276.85147940.001.0
CountyRANDALL
HighwayFM 2590
FromSL 335
ToUS 60 (CANYON)
CSJ2614-01-025
Proj IDF 2B24(145)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.4173875375.000.000.0
CountyRANDALL
HighwayFM 2590
FromSL 335
ToUS 60 (CANYON)
CSJ2614-01-026
Proj IDF 2B24(145)
Work TypeOVERLAY
 
9.0499949399.600.000.0
Work Order08-02-24
Work Began00-00-00
Work Completed
Time Computed09-01-24
Contract Working Days290
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2614-01-024
APOLLO CONSTRUCTORS, INC. (5.33)
HJC FARMS, INC. (0.92)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.08)
TRP CONSTRUCTION GROUP, LLC (0.95)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
W. S. CONSTRUCTION COMPANY (13.87)
Contract #06243005
Totals28487051.450.00147940.000.5

CountyRANDALL
HighwaySL 335
FromEASTERN STREET
ToFARMERS AVENUE
CSJ2635-02-038
Proj IDSTP 2B24(243)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.5466927098.5361257.270.8
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed09-23-24
Contract Working Days97
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-038
PROFESSIONAL TRAFFIC CONTROL LLC (0.18)
URBAN HEIGHTS INVESTMENTS LLC (0.21)
BARRICADES UNLIMITED (0.20)
DK CONTRACTING, LLC (0.65)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.65)
TRP CONSTRUCTION GROUP, LLC (1.60)
Contract #07243031
Totals6927098.530.0061257.270.8

CountyRANDALL
HighwaySL 335
FromFM 2590
ToWEST OF COULTER
CSJ2635-03-024
Proj IDC 2635-3-24
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
0.90125974526.5524883532.1697.3
Work Order01-08-21
Work Began03-01-21
Work Completed
Time Computed02-07-21
Contract Working Days684
Addl Days Granted40
Working Days Charged858
Percent Time Used118
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-03-024
BARRICADES UNLIMITED (0.98)
H & F TRUCKING (0.00)
J. H. ODEN CONTRACTING COMPANY (0.35)
ALAMO BROTHERS CONCRETE INC (2.17)
ARTEX ELECTRIC, INC. (3.96)
URBAN INFRACONSTRUCTION LLC (1.12)
WILLIAMS DITCHING, LLC (7.31)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.40)
TORO BRAVO CONSTRUCTION, LLC (0.04)
SLATON BROTHERS, INC. (1.63)
TORO BRAVO CONSTRUCTION, LLC (0.25)
DUSTROL, INC. (0.99)
JB PINNACLE GROUP, LLC (0.45)
DUSTIN ALLEN, INC. (0.04)
PRIMATE CONSTRUCTION, LP (0.05)
SCOTT DERR PAINTING CO, LLC (0.04)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.38)
GHC TRANSPORT, L.L.C. (0.00)
TEC"S (0.19)
CHEROKEE SERVICES (0.10)
ARANDA TRANSPORT LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.77)
APOLLO CONSTRUCTORS, INC. (0.63)
HJC FARMS, INC. (0.51)
Contract #12203003
Totals25974526.55753107.5724883532.1697.3

page 1 | page 2 | page 3 | page 4