Monthly State Let Construction Report For Amarillo District As Of Sep 13, 2021 Page 3 Of 3

Last Update: Wednesday, September 15, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCARSON
HighwayFM 293
From1.183 MI W OF SH 207
ToSH 207
CSJ0753-02-022
Proj IDSTP 2020(739)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.183799569.38147380.6818.4
Work Order07-27-20
Work Began00-00-00
Work Completed
Time Computed08-26-20
Contract Working Days90
Addl Days Granted0
Working Days Charged69
Percent Time Used76
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0753-02-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06203231
Totals799569.3835668.18147380.6818.4

CountyHUTCHINSON
HighwayRM 687
FromRM 1319
ToSH 152
CSJ0791-06-011
Proj IDSTP 2B20(145)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.3731901330.821982658.3299.9
CountyHUTCHINSON
HighwayRM 687
FromFM 3395
ToRM 1319 IN SANFORD
CSJ2437-01-027
Proj IDSTP 2B20(145)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.707577651.30535877.5092.7
Work Order09-18-20
Work Began01-04-21
Work Completed
Time Computed10-19-20
Contract Working Days45
Addl Days Granted0
Working Days Charged101
Percent Time Used224
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0791-06-011
ALAMO BROTHERS CONCRETE INC (0.00)
Contract #08203032
Totals2478982.1234205.502518535.8299.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICT WIDE
To.
CSJ0904-00-187
Proj IDF 2021(385)
Work TypeSEAL COAT
 
100.000844332.480.000.0
CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-196
Proj IDC 904-00-196
Work TypeSEAL COAT
 
84973.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-187
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213219
Totals929306.250.000.000.0

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-188
Proj IDSTP 2020(551)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.0001274691.70736545.6257.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-07-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days214
Addl Days Granted0
Working Days Charged96
Percent Time Used44
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-188
FC TRAFFIC CONTROL, INC. (2.97)
TX DOWN UNDER CONSTRUCTION, LLC (0.00)
TALON/LPE, LTD. (0.00)
Contract #02203224
Totals1274691.700.00736545.6257.7

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICT WIDE
To.
CSJ0904-00-194
Proj IDC 904-00-194
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2739960.822653428.0796.8
Work Order07-27-20
Work Began00-00-00
Work Completed
Time Computed11-24-20
Contract Working Days260
Addl Days Granted0
Working Days Charged206
Percent Time Used79
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-194
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (12.77)
BARRICADES UNLIMITED (0.00)
FC TRAFFIC CONTROL, INC. (0.00)
TRAFFIC TECH SOLUTIONS, LLC (26.12)
RANSOM DRILLING SERVICES, LLC (1.40)
Contract #06203023
Totals2739960.82148796.882653428.0796.8

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS ON IH 40
To.
CSJ0904-00-195
Proj IDC 904-00-195
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3940370.901382862.3735.0
Work Order07-13-20
Work Began09-21-20
Work Completed
Time Computed08-12-20
Contract Working Days171
Addl Days Granted0
Working Days Charged134
Percent Time Used78
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-195
FC TRAFFIC CONTROL, INC. (0.98)
Contract #05203009
Totals3940370.90441850.931382862.3735.0

CountyPOTTER
HighwayVA
FromMM 15+00.94
ToMM 64
CSJ0904-00-197
Proj IDF 2021(874)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
50.0854796527.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-197
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213225
Totals4796527.000.000.000.0

CountyPOTTER
HighwayVA
FromUS 87 (BUCHANAN ST)
ToGRAND ST
CSJ0904-02-045
Proj IDNH 2021(373)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.900315057.00282934.1989.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days61
Addl Days Granted0
Working Days Charged31
Percent Time Used50
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-045
FUSION COMMUNICATIONS, LLC (1.90)
LINEAR TRAFFIC MARKINGS LLC (1.58)
FC TRAFFIC CONTROL, INC. (1.67)
ALAMO BROTHERS CONCRETE INC (5.98)
Contract #02213034
Totals315057.00129379.55282934.1989.8

CountyHANSFORD
HighwayCR
FromON CR 13
ToAT FARWELL CREEK
CSJ0904-08-004
Proj IDBR 2018(472)
Work TypeREPLACE EXISTING BRIDGE
 
0.010428959.00477504.4699.9
CountyHANSFORD
HighwayCR
FromON CR Z
ToAT HORSE CREEK
CSJ0904-08-005
Proj IDBR 2018(462)
Work TypeREPLACE EXISTING BRIDGE
 
0.010309162.00312826.0099.9
CountyCARSON
HighwayCR
FromON CR 25
ToAT SPRING CREEK
CSJ0904-12-022
Proj IDBR 2018(242)
Work TypeREPLACE EXISTING BRIDGE
 
0.010560506.16556195.0099.2
CountyCARSON
HighwayCS
FromON NEWCOME STREET IN GROOM
ToAT DRAW
CSJ0904-12-023
Proj IDBR 1802(172)
Work TypeREPLACE EXISTING BRIDGE
 
0.010446956.00476590.6099.9
Work Order05-14-19
Work Began10-07-19
Work Completed
Time Computed06-13-19
Contract Working Days176
Addl Days Granted11
Working Days Charged183
Percent Time Used97
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-08-004
TEXAS ALTERNATIVE GRASSER INCORPORATED (1.67)
BARRICADES UNLIMITED (2.14)
Contract #04193225
Totals1745583.1612950.001823116.0699.9

CountyRANDALL
HighwayFM 1541
From900' SOUTH OF SL 335 EB FRONTAGE ROAD
To1100' SOUTH OF FM 1151
CSJ1480-02-036
Proj IDF 2021(875)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5305311.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days158
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1480-02-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213022
Totals5305311.140.000.000.0

CountyLIPSCOMB
HighwayFM 1920
FromRM 3260
ToHEMPHILL COUNTY LINE
CSJ1819-01-015
Proj IDSSW 1819-1-15
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.07616356130.413208104.0519.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-09-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days441
Addl Days Granted0
Working Days Charged102
Percent Time Used23
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1819-01-015
BARRICADES UNLIMITED (5.90)
GREGORY PILE DRIVING, INC. (0.31)
PRIMATE CONSTRUCTION, LP (0.10)
SCOTT DERR PAINTING CO, LLC (0.11)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.78)
Contract #04203203
Totals16356130.41147369.803208104.0519.6

CountyGRAY
HighwayRM 1321
FromAT SAND CREEK
To.
CSJ1861-02-024
Proj IDBR 2021(648)
Work TypeBRIDGE REPLACEMENT
 
0.0851287349.040.000.0
CountyGRAY
HighwayRM 1321
FromCANTONMENT CREEK
To.
CSJ1861-02-025
Proj IDBR 2021(648)
Work TypeBRIDGE REPLACEMENT
 
0.1222190990.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days273
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1861-02-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213214
Totals3478339.720.000.000.0

CountyHUTCHINSON
HighwayRM 2277
FromAT COTTONWOOD CREEK
To.
CSJ2127-01-010
Proj IDBR 2021(394)
Work TypeBRIDGE REPLACEMENT
 
0.0473371388.86346780.0010.2
Work Order04-08-21
Work Began07-27-21
Work Completed
Time Computed05-08-21
Contract Working Days230
Addl Days Granted0
Working Days Charged25
Percent Time Used10
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2127-01-010
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
BARRICADES UNLIMITED (0.33)
Contract #03213213
Totals3371388.86316180.00346780.0010.2

CountyPOTTER
HighwayRM 2381
FromAT RM 1061 INTERSECTION
To.
CSJ2494-01-015
Proj IDF 2021(650)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2407611.820.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days174
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2494-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213226
Totals2407611.820.000.000.0

CountyPOTTER
HighwaySL 335
FromIH 40
ToSOUTH OF SH 136 (DIVIDED SECTION)
CSJ2635-01-038
Proj IDNH 2020(079)
Work TypeOVERLAY
 
7.96610715637.225893709.0355.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days99
Addl Days Granted0
Working Days Charged180
Percent Time Used181
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2635-01-038
BAHENA CONSTRUCTION CO.,INC. (3.54)
DK CONTRACTING, LLC (1.21)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.03)
BARRICADES UNLIMITED (1.69)
DUSTROL, INC. (5.81)
DUSTIN ALLEN, INC. (4.27)
HJC FARMS, INC. (0.35)
CHEROKEE SERVICES (0.07)
APEX HIGHWAY SERVICES, LLC (0.00)
PINNACLE GRINDING AND GROOVING LLC (0.00)
Contract #10193009
Totals10715637.223348184.545893709.0355.9

CountyRANDALL
HighwaySL 335
FromFM 2590
ToWEST OF COULTER
CSJ2635-03-024
Proj IDC 2635-3-24
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
0.90125974526.559225952.7835.5
Work Order01-08-21
Work Began00-00-00
Work Completed
Time Computed02-07-21
Contract Working Days684
Addl Days Granted0
Working Days Charged129
Percent Time Used18
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-03-024
BARRICADES UNLIMITED (0.98)
H & F TRUCKING (0.00)
J. H. ODEN CONTRACTING COMPANY (0.35)
ALAMO BROTHERS CONCRETE INC (2.17)
ARTEX ELECTRIC, INC. (3.96)
URBAN INFRACONSTRUCTION LLC (1.12)
WILLIAMS DITCHING, LLC (7.31)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.40)
TORO BRAVO CONSTRUCTION, LLC (0.04)
SLATON BROTHERS, INC. (1.63)
TORO BRAVO CONSTRUCTION, LLC (0.25)
DUSTROL, INC. (0.99)
JB PINNACLE GROUP, LLC (0.45)
DUSTIN ALLEN, INC. (0.04)
PRIMATE CONSTRUCTION, LP (0.05)
SCOTT DERR PAINTING CO, LLC (0.04)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.38)
Contract #12203003
Totals25974526.55817039.799225952.7835.5

CountyRANDALL
HighwaySL 335
FromFM 2186
ToPOTTER COUNTY LINE
CSJ2635-05-001
Proj IDNH 2019(411)
Work TypeNEW LOCATION NON-FREEWAY
 
5.57545797690.5436003405.0378.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-20-19
Work Began05-01-19
Work Completed
Time Computed00-00-00
Contract Working Days764
Addl Days Granted6
Working Days Charged586
Percent Time Used76
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-05-001
WILLIAMS DITCHING, LLC (9.54)
H & F TRUCKING (2.81)
ARTEX ELECTRIC, INC. (0.27)
BOWMAN ENGINEERING & CONSULTING, INC. (0.11)
DK CONTRACTING, LLC (0.48)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.59)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00)
BUILDER"S ENVIRONMENTAL SERVICES, LLC (0.06)
HJC FARMS, INC. (0.63)
TEXOP CONSTRUCTION (0.21)
BOWMAN ENGINEERING & CONSULTING, INC. (0.00)
BARRICADES UNLIMITED (0.50)
ALAMO BROTHERS CONCRETE INC (3.28)
Contract #01193201
Totals45797690.54793950.7636003405.0378.6

page 1 | page 2 | page 3