Monthly Local Let Maintenance Report For Amarillo District As Of Sep 13, 2023 Page 4 Of 4
Last Update: Thursday, September 14, 2023
 |
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | RANDALL |
Highway | US0060 |
From | SEE PLAN SHEETS |
To | SEE PLAN SHEETS |
CSJ | 6451-21-001 |
Proj ID | SUP - 645121001 |
Work Type | JANITORIAL MAINTENANCE |
|
| 0.010 | 16527.46 | | 1184.01 | 7.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 31 |
Percent Time Used | 8 |
Contractor(s) |
WORKQUEST WORLD TECHNICAL SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6451-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07230420 |
| Totals | 16527.46 | 1184.01 | 1184.01 | 7.1 |
|
County | RANDALL |
Highway | IH0027 |
From | VARIOUS LOCATIONS ~ SEE PLAN SHEETS |
To | VARIOUS LOCATIONS ~ SEE PLAN SHEETS |
CSJ | 6453-40-001 |
Proj ID | SUP - 645340001 |
Work Type | JANITORIAL MAINTENANCE |
|
| 0.010 | 83294.66 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
WORKQUEST WORLD TECHNICAL SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-40-001 WORLD TECHNICAL SERVICES, INC. (0.00)
|
Contract # | 08230420 |
| Totals | 83294.66 | 0.00 | 0.00 | 0.0 |
|
County | RANDALL |
Highway | FM1541 |
From | VARIOUS LOCATIONS ~ SEE PLAN SHEETS |
To | VARIOUS LOCATIONS ~ SEE PLAN SHEETS |
CSJ | 6453-42-001 |
Proj ID | SUP - 645342001 |
Work Type | JANITORIAL MAINTENANCE |
|
| 0.010 | 22535.52 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
WORKQUEST WORLD TECHNICAL SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-42-001 WORLD TECHNICAL SERVICES, INC. (0.00)
|
Contract # | 08230421 |
| Totals | 22535.52 | 0.00 | 0.00 | 0.0 |
|
County | MOORE |
Highway | FM2203 |
From | VARIOUS LOCATIONS ~ SEE PLAN SHEETS |
To | VARIOUS LOCATIONS ~ SEE PLAN SHEETS |
CSJ | 6453-44-001 |
Proj ID | SUP - 645344001 |
Work Type | JANITORIAL MAINTENANCE |
|
| 0.010 | 15802.08 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
WORKQUEST WORLD TECHNICAL SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-44-001 WORLD TECHNICAL SERVICES, INC. (0.00)
|
Contract # | 08230422 |
| Totals | 15802.08 | 0.00 | 0.00 | 0.0 |
|