Monthly Local Let Maintenance Report For Bryan District As Of Nov 10, 2024 Page 2 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6444-14-001
Proj IDMMC - 644414001
Work TypeFLOWABLE FILL
 
0.010246560.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-28-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6444-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231709
Totals246560.000.000.000.0

CountyFREESTONE
HighwayIH0045
FromVARIOUS
ToVA
CSJ6444-22-001
Proj IDMMC - 644422001
Work TypeFLOWABLE FILL
 
0.010224560.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6444-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231710
Totals224560.000.000.000.0

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6444-24-001
Proj IDMMC - 644424001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010259500.001250415.0399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-28-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged462
Percent Time Used85
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231711
Totals259500.0078049.401250415.0399.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6444-30-001
Proj IDMMC - 644430001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010136752.00165708.9699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-16-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged382
Percent Time Used52
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231703
Totals136752.003432.63165708.9699.9

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6444-98-001
Proj IDRMC - 644498001
Work TypePICNIC AREA MAINTENANCE
 
0.01055759.0067546.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-11-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged446
Percent Time Used61
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6444-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231708
Totals55759.004825.0067546.0099.9

CountyWALKER
HighwaySH0019
FromVARIOUS
ToVARIOUS
CSJ6447-48-001
Proj IDBPM - 644748001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010163498.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-04-24
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241705
Totals163498.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromBRYAN DISTRICT HQ
ToBRYAN DISTRICT HQ
CSJ6447-62-001
Proj IDSUP - 644762001
Work TypeVEGETATION MANAGEMENT
 
0.010127621.7640964.2632.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-23
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged508
Percent Time Used69
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6447-62-001
SAUMYA, INC (0.00)
Contract #06231730
Totals127621.76596.6640964.2632.0

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6451-67-001
Proj IDSUP - 645167001
Work TypePICNIC AREA MAINTENANCE
 
0.01082234.4049868.0260.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged458
Percent Time Used62
Contractor(s)
WORKQUEST
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6451-67-001
JUNCTION FIVE-O-FIVE (0.00)
Contract #07231730
Totals82234.403478.9649868.0260.6

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6454-31-001
Proj IDMMC - 645431001
Work TypeROCK/RIPRAP
 
0.010184900.009780.965.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged336
Percent Time Used62
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231704
Totals184900.009780.969780.965.2

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6454-91-001
Proj IDRMC - 645491001
Work TypeDEBRIS REMOVAL
 
0.010248160.001247708.4599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6454-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231701
Totals248160.00121100.001247708.4599.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6455-57-001
Proj IDMMC - 645557001
Work TypeEMULSION
 
0.010167600.00110801.7866.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged336
Percent Time Used62
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231705
Totals167600.0026396.32110801.7866.1

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6456-05-001
Proj IDRMC - 645605001
Work TypeRAISED PAVEMENT MARKERS
 
0.010137285.00132051.0896.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-06-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged331
Percent Time Used45
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231703
Totals137285.00117149.92132051.0896.1

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6456-29-001
Proj IDMMC - 645629001
Work TypeCUTBACK
 
0.010149280.0098360.5365.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged336
Percent Time Used62
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6456-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231706
Totals149280.0041183.1798360.5365.8

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6456-31-001
Proj IDMMC - 645631001
Work TypeEMULSION
 
0.010193320.00391779.5299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged336
Percent Time Used62
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6456-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231707
Totals193320.0035060.32391779.5299.9

CountyFREESTONE
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6456-33-001
Proj IDMMC - 645633001
Work TypeEMULSION
 
0.010163760.00126903.2077.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged336
Percent Time Used62
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6456-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231708
Totals163760.000.00126903.2077.4

CountyFREESTONE
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6456-35-001
Proj IDMMC - 645635001
Work TypeROCK/RIPRAP
 
0.010163600.0031591.8019.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged336
Percent Time Used62
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231709
Totals163600.000.0031591.8019.3

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6457-63-001
Proj IDSUP - 645763001
Work TypeJANITORIAL MAINTENANCE
 
0.010140699.3674409.8352.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged397
Percent Time Used54
Contractor(s)
WORKQUEST
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6457-63-001
JUNCTION FIVE-O-FIVE (0.00)
Contract #09231730
Totals140699.364808.1874409.8352.8

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6459-10-001
Proj IDRMC - 645910001
Work TypeTREE REMOVAL
 
0.010395100.00320036.0081.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged259
Percent Time Used35
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6459-10-001
ORTEGA"S LAWN AND LANDSCAPING, LLC (0.00)
Contract #12231702
Totals395100.000.00320036.0081.0

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6459-17-001
Proj IDRMC - 645917001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010188790.05104401.9955.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged259
Percent Time Used70
Contractor(s)
AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6459-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231703
Totals188790.059416.86104401.9955.3

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6459-23-001
Proj IDRMC - 645923001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010185248.60106107.2057.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged268
Percent Time Used36
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6459-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231704
Totals185248.600.00106107.2057.2

page 1 | page 2 | page 3 | page 4 | page 5