Monthly Local Let Maintenance Report For Bryan District As Of Sep 13, 2021 Page 2 Of 6

Last Update: Wednesday, September 15, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6367-00-001
Proj IDRMC - 636700001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.001104331.9627794.4826.6
Work Order12-09-20
Work Began12-09-20
Work Completed
Time Computed12-09-20
Contract Working Days365
Addl Days Granted0
Working Days Charged266
Percent Time Used72
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6367-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201703
Totals104331.960.0027794.4826.6

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6367-01-001
Proj IDRMC - 636701001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.001111763.0020286.0018.1
Work Order01-14-21
Work Began01-14-21
Work Completed
Time Computed01-14-21
Contract Working Days365
Addl Days Granted0
Working Days Charged230
Percent Time Used63
Contractor(s)
SWEEPING CORPORATION OF AMERICA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6367-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201704
Totals111763.008399.0020286.0018.1

CountyMILAM
HighwayFM0486
FromAT LITTLE RIVER SLOUGH
ToAT LITTLE RIVER SLOUGH
CSJ6370-12-001
Proj IDBPM - 637012001
Work TypeSTONE RIP RAP AND SCOUR COUNTERMEASURES
 
1.00072031.2071296.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-26-21
Work Completed08-16-21
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged3
Percent Time Used20
Contractor(s)
DOUBLE L CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6370-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12201703
Totals72031.20750.0071296.00100.0

CountyBRAZOS
HighwaySH0006
FromAT BURTON CREEK, ETC.
ToAT BURTON CREEK, ETC.
CSJ6370-13-001
Proj IDBPM - 637013001
Work TypeSCOUR REPAIR
 
0.100204920.00212830.6099.9
Work Order04-12-21
Work Began04-12-21
Work Completed
Time Computed04-12-21
Contract Working Days57
Addl Days Granted0
Working Days Charged45
Percent Time Used78
Contractor(s)
EVERYTHING IRRIGATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6370-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12201701
Totals204920.00131295.57212830.6099.9

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6370-23-001
Proj IDSUP - 637023001
Work TypeBUILDING JANITORIAL ROBERTSON COUNTY
 
0.01035164.5216314.9046.3
Work Order09-01-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6370-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201730
Totals35164.52912.3316314.9046.3

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6370-82-001
Proj IDSUP - 637082001
Work TypeBUILDING JANITORIAL
 
0.00149227.3625875.9252.5
Work Order09-01-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6370-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201737
Totals49227.361420.0225875.9252.5

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6370-99-001
Proj IDSUP - 637099001
Work TypePICNIC AREA AND WEIGHT STATION MAINT
 
0.01057929.4028492.0749.1
Work Order09-01-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged364
Percent Time Used49
Contractor(s)
WORKQUEST
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6370-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201732
Totals57929.402409.5128492.0749.1

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6371-01-001
Proj IDSUP - 637101001
Work TypeYARD MAINTENANCE
 
0.01053604.8614543.8927.1
Work Order09-01-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201733
Totals53604.862473.9414543.8927.1

CountyBURLESON
HighwayFM0050
FromVARIOUS
ToVARIOUS
CSJ6371-09-001
Proj IDSUP - 637109001
Work TypePICNIC AND CARPOOL MAINT. BURLESON CTY
 
0.00164664.6432742.4250.6
Work Order09-01-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201734
Totals64664.643064.3032742.4250.6

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6371-10-001
Proj IDSUP - 637110001
Work TypePICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.001106656.0047900.0044.9
Work Order09-01-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201735
Totals106656.004159.0047900.0044.9

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6371-14-001
Proj IDSUP - 637114001
Work TypePICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.00182270.0041947.5250.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-20
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201736
Totals82270.003880.0841947.5250.9

CountyMADISON
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6371-28-001
Proj IDSUP - 637128001
Work TypeMADISON COUNTY BUILDING JANITORIAL
 
0.01022045.9013542.4861.4
Work Order08-31-20
Work Began08-31-20
Work Completed
Time Computed08-31-20
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201738
Totals22045.90426.8413542.4861.4

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6371-29-001
Proj IDSUP - 637129001
Work TypeGRIMES COUNTY BUILDING JANITORIAL
 
0.00126578.5616635.7762.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-20
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201739
Totals26578.562273.6916635.7762.5

CountyWASHINGTON
HighwaySH0036
FromSEE PLAN SHEETS
ToSEE PLAN SHEET
CSJ6372-58-001
Proj IDMMC - 637258001
Work TypeHYDRAULIC CEMENT (MATERIALS ONLY)
 
0.00144266.2056861.3799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-04-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged240
Percent Time Used66
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6372-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201705
Totals44266.206540.8056861.3799.9

CountyBRAZOS
HighwaySH0006
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6372-59-001
Proj IDMMC - 637259001
Work TypeHYDRAULIC CEMENT (MATERIALS ONLY)
 
0.001103043.60199932.9299.9
Work Order12-09-20
Work Began12-09-20
Work Completed
Time Computed12-09-20
Contract Working Days120
Addl Days Granted240
Working Days Charged266
Percent Time Used73
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6372-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201706
Totals103043.606496.00199932.9299.9

CountyWALKER
HighwayIH0045
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6372-60-001
Proj IDMMC - 637260001
Work TypeHYDRAULIC CEMENT (MATERIALS ONLY)
 
0.001143208.20110208.8776.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-15-20
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged260
Percent Time Used72
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6372-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201707
Totals143208.200.00110208.8776.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6372-65-001
Proj IDMMC - 637265001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001276100.00373118.6399.9
Work Order12-16-20
Work Began12-16-20
Work Completed
Time Computed12-16-20
Contract Working Days120
Addl Days Granted240
Working Days Charged259
Percent Time Used71
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6372-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201708
Totals276100.00109625.47373118.6399.9

CountyBURLESON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6372-66-001
Proj IDMMC - 637266001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001258000.00823883.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-25-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged240
Percent Time Used66
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6372-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201709
Totals258000.00162754.79823883.0299.9

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6372-67-001
Proj IDMMC - 637267001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001279900.00525496.2699.9
Work Order02-10-21
Work Began02-10-21
Work Completed
Time Computed02-10-21
Contract Working Days120
Addl Days Granted120
Working Days Charged203
Percent Time Used84
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6372-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201710
Totals279900.00253726.44525496.2699.9

CountyGRIMES
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6372-68-001
Proj IDMMC - 637268001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001252000.00362349.0099.9
Work Order12-16-20
Work Began12-16-20
Work Completed
Time Computed12-16-20
Contract Working Days120
Addl Days Granted240
Working Days Charged259
Percent Time Used71
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6372-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201711
Totals252000.0080995.20362349.0099.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6