Monthly Local Let Maintenance Report For Bryan District As Of Nov 10, 2024 Page 5 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBURLESON
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6471-60-001
Proj IDSUP - 647160001
Work TypePICNIC AREA MAINTENANCE
 
0.01060305.445071.568.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-60-001
RUCON, INC. (0.00)
Contract #07241734
Totals60305.442535.785071.568.4

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6471-96-001
Proj IDSUP - 647196001
Work TypeJANITORIAL MAINTENANCE
 
0.01013264.351706.1812.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-26-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged98
Percent Time Used13
Contractor(s)
WORKQUEST
TEJAS ROADRUNNERS, NON-PROFIT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6471-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241731
Totals13264.35487.481706.1812.8

CountyROBERTSON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6472-03-001
Proj IDSUP - 647203001
Work TypeSTATE USE CONTRACT
 
0.01066848.765760.028.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6472-03-001
RUCON, INC. (0.00)
Contract #07241735
Totals66848.762857.995760.028.6

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6472-99-001
Proj IDSUP - 647299001
Work TypeLITTER REMOVAL
 
0.010867121.710.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6472-99-001
RUCON, INC. (0.00)
Contract #09241730
Totals867121.710.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6473-23-001
Proj IDSUP - 647323001
Work TypeLITTER REMOVAL
 
0.010991423.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-23-001
RUCON, INC. (0.00)
Contract #09241731
Totals991423.350.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6474-23-001
Proj IDMMC - 647423001
Work TypeCUTBACK
 
0.010130320.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6474-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241701
Totals130320.000.000.000.0

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6474-24-001
Proj IDMMC - 647424001
Work TypeCUTBACK
 
0.010174960.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6474-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241702
Totals174960.000.000.000.0

CountyBRAZOS
HighwayFM0974
FromVARIOUS
ToVARIOUS
CSJ6474-81-001
Proj IDSUP - 647481001
Work TypeVEGETATION MANAGEMENT
 
0.01019152.00504.002.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6474-81-001
SAUMYA, INC (0.00)
Contract #09241732
Totals19152.00504.00504.002.6

CountyFREESTONE
HighwayIH0045
FromRM 186
ToRM 187
CSJ6475-28-001
Proj IDSUP - 647528001
Work TypeLITTER REMOVAL
 
0.01031928.001820.005.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6475-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241733
Totals31928.001820.001820.005.7

CountyBURLESON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6475-89-001
Proj IDSUP - 647589001
Work TypeJANITORIAL MAINTENANCE
 
0.01025382.960.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-24
Work Completed10-31-24
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6475-89-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #10241730
Totals25382.960.000.00100.0

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6475-91-001
Proj IDSUP - 647591001
Work TypePICNIC AREA MAINTENANCE
 
0.01054928.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6475-91-001
RUCON, INC. (0.00)
Contract #10241731
Totals54928.080.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5