Monthly Local Let Maintenance Report For Bryan District As Of Sep 13, 2021 Page 4 Of 6

Last Update: Wednesday, September 15, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6374-10-001
Proj IDSUP - 637410001
Work TypePICNIC AREA MAINTENANCE
 
0.00153328.0019486.5036.5
Work Order11-01-20
Work Began11-01-20
Work Completed
Time Computed11-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged304
Percent Time Used41
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201730
Totals53328.002079.5019486.5036.5

CountyBURLESON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6374-17-001
Proj IDSUP - 637417001
Work TypeBURLESON COUNTY BUILDING JANITORIAL
 
0.00131139.9210607.5034.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-20
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged304
Percent Time Used41
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201731
Totals31139.921044.2510607.5034.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6374-26-001
Proj IDRMC - 637426001
Work TypeILLUMINATION MAINTENANCE WORK
 
0.001143995.00169803.3099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-05-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12201704
Totals143995.0099054.12169803.3099.9

CountyFREESTONE
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6374-28-001
Proj IDRMC - 637428001
Work TypeROADSIDE MOWING
 
0.001147859.8568638.6746.4
Work Order01-25-21
Work Began01-25-21
Work Completed
Time Computed06-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged219
Percent Time Used60
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6374-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12201706
Totals147859.850.0068638.6746.4

CountyROBERTSON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6374-32-001
Proj IDRMC - 637432001
Work TypeROADSIDE MOWING
 
0.001181358.7076468.0242.1
Work Order03-24-21
Work Began03-31-21
Work Completed
Time Computed03-31-21
Contract Working Days365
Addl Days Granted0
Working Days Charged154
Percent Time Used42
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6374-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12201707
Totals181358.700.0076468.0242.1

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6375-70-001
Proj IDMMC - 637570001
Work TypeEMULSION
 
0.010166744.06155656.6293.3
Work Order03-24-21
Work Began03-24-21
Work Completed
Time Computed03-24-21
Contract Working Days120
Addl Days Granted120
Working Days Charged161
Percent Time Used67
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6375-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211706
Totals166744.0630700.49155656.6293.3

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6375-71-001
Proj IDMMC - 637571001
Work TypeEMULSION
 
0.010200199.87196679.7798.2
Work Order03-17-21
Work Began03-17-21
Work Completed
Time Computed03-17-21
Contract Working Days120
Addl Days Granted120
Working Days Charged168
Percent Time Used70
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6375-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211707
Totals200199.8733222.76196679.7798.2

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6375-72-001
Proj IDMMC - 637572001
Work TypeEMULSION
 
0.01041023.98159969.0899.9
Work Order03-25-21
Work Began03-25-21
Work Completed
Time Computed03-25-21
Contract Working Days120
Addl Days Granted120
Working Days Charged160
Percent Time Used66
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6375-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211708
Totals41023.9812981.44159969.0899.9

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6375-86-001
Proj IDMMC - 637586001
Work TypeAGGREGATE
 
0.010239300.0063581.5826.5
Work Order03-30-21
Work Began03-31-21
Work Completed
Time Computed03-30-21
Contract Working Days120
Addl Days Granted240
Working Days Charged155
Percent Time Used43
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6375-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211709
Totals239300.000.0063581.5826.5

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6375-87-001
Proj IDMMC - 637587001
Work TypeAGGREGATE
 
0.010213400.00208528.3097.7
Work Order04-08-21
Work Began04-08-21
Work Completed
Time Computed04-08-21
Contract Working Days120
Addl Days Granted120
Working Days Charged146
Percent Time Used60
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6375-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211710
Totals213400.000.00208528.3097.7

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6375-88-001
Proj IDMMC - 637588001
Work TypeAGGREGATE
 
0.010105090.0047218.0044.9
Work Order05-20-21
Work Began05-20-21
Work Completed
Time Computed05-20-21
Contract Working Days120
Addl Days Granted120
Working Days Charged104
Percent Time Used43
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6375-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211711
Totals105090.0027142.7647218.0044.9

CountyWALKER
HighwayFM0247
FromFM 247 & FM 2821
ToFM 247 & FM 2821
CSJ6376-21-001
Proj IDSUP - 637621001
Work TypeSTATE USE PROJECT
 
0.01010067.683079.7530.5
Work Order03-10-21
Work Began03-01-21
Work Completed
Time Computed03-10-21
Contract Working Days730
Addl Days Granted0
Working Days Charged184
Percent Time Used25
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01211730
Totals10067.68544.563079.7530.5

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6376-82-001
Proj IDSUP - 637682001
Work TypeJANITORIAL MAINTENANCE
 
0.01038903.568231.9421.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged212
Percent Time Used29
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-82-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #01211731
Totals38903.561702.268231.9421.1

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6377-03-001
Proj IDSUP - 637703001
Work TypeJANITORIAL MAINTENANCE
 
0.01047763.6017282.5136.1
Work Order02-01-21
Work Began02-01-21
Work Completed
Time Computed02-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged212
Percent Time Used29
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01211732
Totals47763.601724.0417282.5136.1

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6377-94-001
Proj IDSUP - 637794001
Work TypeJANITORIAL MAINTENANCE
 
0.01092178.1616975.4418.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-30-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-94-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #02211730
Totals92178.161562.8516975.4418.4

CountyMADISON
HighwayFM1372
FromVARIOUS
ToVARIOUS
CSJ6379-12-001
Proj IDBPM - 637912001
Work TypeBRIDGE REPAIR
 
0.010132492.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days27
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
12TWELVE ROAD AND BRIDGE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08211701
Totals132492.000.000.000.0

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6379-98-001
Proj IDMMC - 637998001
Work TypeROCK/RIPRAP
 
0.010176909.0058287.6532.9
Work Order06-30-21
Work Began06-30-21
Work Completed
Time Computed06-30-21
Contract Working Days120
Addl Days Granted0
Working Days Charged63
Percent Time Used52
Contractor(s)
TEXCON GENERAL CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6379-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06211701
Totals176909.0038488.7258287.6532.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6379-99-001
Proj IDMMC - 637999001
Work TypeROCK/RIPRAP
 
0.010170447.00158312.2392.8
Work Order06-29-21
Work Began06-29-21
Work Completed
Time Computed06-29-21
Contract Working Days120
Addl Days Granted0
Working Days Charged64
Percent Time Used53
Contractor(s)
TEXCON GENERAL CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6379-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06211702
Totals170447.00127837.11158312.2392.8

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6380-00-001
Proj IDMMC - 638000001
Work TypeROCK/RIPRAP
 
0.010218500.0022165.6910.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-28-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged35
Percent Time Used29
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6380-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06211703
Totals218500.0022165.6922165.6910.1

CountyFREESTONE
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6380-67-001
Proj IDRMC - 638067001
Work TypeTREE REMOVAL
 
0.010212190.800.000.0
Work Order07-20-21
Work Began07-20-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged43
Percent Time Used11
Contractor(s)
SERNA CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6380-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06211704
Totals212190.800.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6