Monthly Local Let Maintenance Report For Bryan District As Of Sep 13, 2021 Page 3 Of 6

Last Update: Wednesday, September 15, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6372-69-001
Proj IDMMC - 637269001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001256000.00559092.4899.9
Work Order12-10-20
Work Began12-10-20
Work Completed
Time Computed12-10-20
Contract Working Days120
Addl Days Granted240
Working Days Charged265
Percent Time Used73
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6372-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201712
Totals256000.00110196.48559092.4899.9

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6372-70-001
Proj IDMMC - 637270001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001224000.00214863.3695.9
Work Order02-10-21
Work Began02-10-21
Work Completed
Time Computed02-10-21
Contract Working Days120
Addl Days Granted120
Working Days Charged203
Percent Time Used84
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6372-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201713
Totals224000.0040680.96214863.3695.9

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6372-71-001
Proj IDMMC - 637271001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001254000.00660136.3199.9
Work Order03-25-21
Work Began03-25-21
Work Completed
Time Computed03-25-21
Contract Working Days120
Addl Days Granted120
Working Days Charged160
Percent Time Used66
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6372-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201714
Totals254000.00159962.85660136.3199.9

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6372-72-001
Proj IDMMC - 637272001
Work TypeDENSE-GRADED HOT-MIX ASPHALT (SM QTY)
 
0.001282750.00320652.8799.9
Work Order12-16-20
Work Began12-16-20
Work Completed
Time Computed12-16-20
Contract Working Days120
Addl Days Granted240
Working Days Charged259
Percent Time Used71
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6372-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201715
Totals282750.00110310.96320652.8799.9

CountyWALKER
HighwayIH0045
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6372-73-001
Proj IDMMC - 637273001
Work TypeDENSE-GRADED HOT-MIX ASPHALT
 
0.001255000.001238410.1099.9
Work Order02-10-21
Work Began02-10-21
Work Completed
Time Computed02-10-21
Contract Working Days120
Addl Days Granted240
Working Days Charged203
Percent Time Used56
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6372-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201716
Totals255000.00295259.161238410.1099.9

CountyWASHINGTON
HighwayUS0290
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6372-74-001
Proj IDMMC - 637274001
Work TypeDENSE-GRADED HOT-MIX ASPHALT
 
0.001292500.00955924.7699.9
Work Order12-31-20
Work Began12-31-20
Work Completed
Time Computed01-04-21
Contract Working Days120
Addl Days Granted240
Working Days Charged244
Percent Time Used67
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6372-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201717
Totals292500.00261094.98955924.7699.9

CountyWASHINGTON
HighwayUS0290
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-09-001
Proj IDMMC - 637309001
Work TypeASPHALTIC PATCHING (MATERIAL ONLY)
 
0.00112877.5922471.2099.9
Work Order12-09-20
Work Began12-10-20
Work Completed
Time Computed12-10-20
Contract Working Days120
Addl Days Granted240
Working Days Charged265
Percent Time Used73
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6373-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201702
Totals12877.592585.2622471.2099.9

CountyBRAZOS
HighwaySH0006
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-10-001
Proj IDMMC - 637310001
Work TypeASPHALTIC CONCRETE PATCHING MATERIAL
 
0.00129613.2414868.6950.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-14-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged230
Percent Time Used63
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6373-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201703
Totals29613.240.0014868.6950.2

CountyWALKER
HighwayIH0045
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-11-001
Proj IDMMC - 637311001
Work TypeASPHALTIC CONCRETE PATCHING MATERIAL
 
0.00123688.7555525.9499.9
Work Order12-23-20
Work Began12-23-20
Work Completed
Time Computed12-23-20
Contract Working Days120
Addl Days Granted240
Working Days Charged252
Percent Time Used70
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6373-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201704
Totals23688.755103.8555525.9499.9

CountyBRAZOS
HighwaySH0006
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-13-001
Proj IDMMC - 637313001
Work TypeTYPE II BRINE SALT(MATERIALS ONLY)
 
0.00123600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAHAN FOUNDATION & CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6373-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201701
Totals23600.000.000.000.0

CountyWASHINGTON
HighwayUS0290
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-30-001
Proj IDMMC - 637330001
Work TypeFLEXIBLE BASE(MATERIALS ONLY)
 
0.00127275.0023719.3886.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-10-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged203
Percent Time Used56
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6373-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201705
Totals27275.004598.1623719.3886.9

CountyBRAZOS
HighwaySH0006
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-31-001
Proj IDMMC - 637331001
Work TypeFLEXIBLE BASE(MATERIALS ONLY)
 
0.001140250.00114609.0881.7
Work Order01-07-21
Work Began01-07-21
Work Completed
Time Computed01-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged237
Percent Time Used65
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6373-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201706
Totals140250.000.00114609.0881.7

CountyWALKER
HighwayIH0045
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-32-001
Proj IDMMC - 637332001
Work TypeFLEXIBLE BASE(MATERIALS ONLY)
 
0.00181587.5077573.1095.0
Work Order01-29-21
Work Began01-28-21
Work Completed
Time Computed01-29-21
Contract Working Days120
Addl Days Granted240
Working Days Charged216
Percent Time Used60
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6373-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201707
Totals81587.5019793.5277573.1095.0

CountyROBERTSON
HighwaySH0006
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-34-001
Proj IDMMC - 637334001
Work TypeAGGREGATE SURFACE(MATERIALS ONLY)
 
0.00172050.000.00100.0
Work Order04-14-21
Work Began04-14-21
Work Completed09-07-21
Time Computed04-14-21
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6373-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201709
Totals72050.000.000.00100.0

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6373-71-001
Proj IDSUP - 637371001
Work TypeLITTER PICKUP & DISPOSAL
 
0.0011661448.22812412.0348.8
Work Order11-30-20
Work Began12-01-20
Work Completed
Time Computed12-01-20
Contract Working Days365
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6373-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10201732
Totals1661448.2270376.86812412.0348.8

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6373-88-001
Proj IDMMC - 637388001
Work TypeCEMENT & FLOWABLE FILL (MATERIAL ONLY)
 
0.01042720.001118.002.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-22-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged163
Percent Time Used67
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6373-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211701
Totals42720.000.001118.002.6

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6373-89-001
Proj IDMMC - 637389001
Work TypeCEMENT & FLOWABLE FILL (MATERIAL ONLY)
 
0.01042720.000.000.0
Work Order04-07-21
Work Began04-06-21
Work Completed
Time Computed04-07-21
Contract Working Days120
Addl Days Granted120
Working Days Charged148
Percent Time Used61
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6373-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211702
Totals42720.000.000.000.0

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6373-90-001
Proj IDMMC - 637390001
Work TypeCEMENT & FLOWABLE FILL (MATERIAL ONLY)
 
0.01079200.000.000.0
Work Order04-12-21
Work Began04-12-21
Work Completed
Time Computed04-12-21
Contract Working Days120
Addl Days Granted120
Working Days Charged142
Percent Time Used59
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6373-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211703
Totals79200.000.000.000.0

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6373-91-001
Proj IDMMC - 637391001
Work TypeCEMENT & FLOWABLE FILL (MATERIAL ONLY)
 
0.01042720.007420.0017.3
Work Order04-14-21
Work Began04-14-21
Work Completed
Time Computed04-14-21
Contract Working Days120
Addl Days Granted120
Working Days Charged140
Percent Time Used58
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6373-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211704
Totals42720.004240.007420.0017.3

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6373-92-001
Proj IDMMC - 637392001
Work TypeCEMENT & FLOWABLE FILL (MATERIAL ONLY)
 
0.01042720.000.000.0
Work Order04-14-21
Work Began04-14-21
Work Completed
Time Computed04-14-21
Contract Working Days120
Addl Days Granted120
Working Days Charged140
Percent Time Used58
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6373-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211705
Totals42720.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6