Detail Letting Schedule for Hays County (FY 2002)
![]() |
![]() |
![]() |
![]() |
![]() |
Detail Letting Schedule for Hays County (FY 2002) | ||||
Last Update: Thursday, September 5, 2002 | ||||
Updated from Design & Construction Information System (DCIS) on: August 30, 2002 |
Hays County (FY 2002) |
CCSJ: 0016-02-096 | |||
District: | Austin | Let Date: | MAR 2002 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | IM 35-3(224) | CSJ: | 0016-02-096 |
Description: | CONVERT TO ONE WAY FRONTAGE ROADS | Handling Code: |
|
Limits From: | LP 4 | Fund Cat: | 1 |
Limits To: | FM 2001 | Estimate: | $307,715 |
Length: | 1.0 Miles | Actual: | $198,515 |
Back... |
Totals for 0016-02-096 | ||
---|---|---|---|
Length: | 1.0 Miles | ||
Estimate: | $307,715 | ||
Actual: | $198,515 | ||
CCSJ: 0113-07-040 | |||
District: | Austin | Let Date: | FEB 2002 |
Highway: | US 290 | Let Status: | Actual |
Project ID: | NH 2001(143) | CSJ: | 0113-07-040 |
Description: | RECONST TO 5 - LN URBAN RDWY | Handling Code: |
|
Limits From: | 0.92 MI W OF RM 12 | Fund Cat: | 1 |
Limits To: | 0.524 MI E OF RM 12 | Estimate: | $2,723,941 |
Length: | 1.4 Miles | Actual: | $2,749,034 |
Back... |
Totals for 0113-07-040 | ||
Length: | 1.4 Miles | ||
Estimate: | $2,723,941 | ||
Actual: | $2,749,034 | ||
CCSJ: 0286-01-046 | |||
District: | Austin | Let Date: | JAN 2002 |
Highway: | RM 12 | Let Status: | Actual |
Project ID: | STP 2001(939)RXH | CSJ: | 0286-01-046 |
Description: | UPGRADE RRX WARNING DEVICES | Handling Code: |
XX |
Limits From: | IN SAN MARCOS AT UPRR | Fund Cat: | 8 |
Limits To: | #415507U | Estimate: | $200,000 |
Length: | 0.0 Miles | Actual: | $200,000 |
Back... |
Totals for 0286-01-046 | ||
Length: | 0.0 Miles | ||
Estimate: | $200,000 | ||
Actual: | $200,000 | ||
CCSJ: 0471-02-037 | |||
District: | Austin | Let Date: | DEC 2001 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2001(638)R | CSJ: | 0471-02-037 |
Description: | WIDEN TO 4 LANES AND ADD SHOULDERS | Handling Code: |
|
Limits From: | SH 80 | Fund Cat: | 1 |
Limits To: | S OF FM 1966 | Estimate: | $4,234,376 |
Length: | 3.3 Miles | Actual: | $3,465,112 |
Back... |
Totals for 0471-02-037 | ||
Length: | 3.3 Miles | ||
Estimate: | $4,234,376 | ||
Actual: | $3,465,112 | ||
CCSJ: 0471-02-039 | |||
District: | Austin | Let Date: | JUL 2002 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | MG 2002(710) | CSJ: | 0471-02-035 |
Description: | CONSTRUCT GRADE SEPARATION | Handling Code: |
|
Limits From: | AT SH 80 | Fund Cat: | 4 |
Limits To: | . | Estimate: | $3,385,324 |
Length: | 0.7 Miles | Actual: | $3,001,578 |
District: | Austin | Let Date: | JUL 2002 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2001(574)HES | CSJ: | 0471-02-039 |
Description: | REALIGN INTERSECTION | Handling Code: |
|
Limits From: | AT SH 80 IN SAN MARCOS | Fund Cat: | 8 |
Limits To: | . | Estimate: | $1,019,958 |
Length: | 0.2 Miles | Actual: | $882,451 |
Back... |
Totals for 0471-02-039 | ||
Length: | 0.9 Miles | ||
Estimate: | $4,405,282 | ||
Actual: | $3,884,029 | ||
CCSJ: 0511-03-010 | |||
District: | Austin | Let Date: | JUL 2002 |
Highway: | RM 12 | Let Status: | Actual |
Project ID: | STP 2002(759)RM | CSJ: | 0285-03-037 |
Description: | FULL DEPTH PAVEMENT REPAIR (SPOT) | Handling Code: |
|
Limits From: | SAN MARCOS C.L. | Fund Cat: | 1 |
Limits To: | HOLLAND ST | Estimate: | $44,880 |
Length: | 1.5 Miles | Actual: | $33,222 |
District: | Austin | Let Date: | JUL 2002 |
Highway: | SH 80 | Let Status: | Actual |
Project ID: | STP 2002(759)RM | CSJ: | 0286-01-045 |
Description: | 1 - CST, OVERLAY & MILLING | Handling Code: |
|
Limits From: | IH 35 SB FRONTAGE RD | Fund Cat: | 1 |
Limits To: | BLANCO RIVER BRIDGE | Estimate: | $154,605 |
Length: | 0.7 Miles | Actual: | $128,181 |
District: | Austin | Let Date: | JUL 2002 |
Highway: | RM 32 | Let Status: | Actual |
Project ID: | STP 2002(759)RM | CSJ: | 0511-03-010 |
Description: | OVERLAY AND EDGE REPAIR | Handling Code: |
|
Limits From: | COMAL C/L | Fund Cat: | 1 |
Limits To: | RM 12 | Estimate: | $662,542 |
Length: | 3.1 Miles | Actual: | $396,120 |
Back... |
Totals for 0511-03-010 | ||
Length: | 5.3 Miles | ||
Estimate: | $862,027 | ||
Actual: | $557,523 | ||
CCSJ: 0805-01-011 | |||
District: | Austin | Let Date: | JUL 2002 |
Highway: | RM 150 | Let Status: | Actual |
Project ID: | STP 2002(711)RM | CSJ: | 0805-01-011 |
Description: | RECONSTRUCT TO 3 - LN RURAL ROAD FACILITY | Handling Code: |
|
Limits From: | CR 203 | Fund Cat: | 1 |
Limits To: | SH 21 | Estimate: | $1,175,851 |
Length: | 1.8 Miles | Actual: | $900,310 |
Back... |
Totals for 0805-01-011 | ||
Length: | 1.8 Miles | ||
Estimate: | $1,175,851 | ||
Actual: | $900,310 | ||
CCSJ: 2293-01-014 | |||
District: | Austin | Let Date: | JUN 2002 |
Highway: | FM 2439 | Let Status: | Actual |
Project ID: | STP 2002(312)UM | CSJ: | 2293-01-014 |
Description: | RECONSTRUCT TO 5 LANES | Handling Code: |
|
Limits From: | S OF SAN MARCOS MIDDLE SCHOOL | Fund Cat: | 11 |
Limits To: | 0.07 MI S OF CENTER POINT RD | Estimate: | $6,130,457 |
Length: | 2.1 Miles | Actual: | $6,111,688 |
Back... |
Totals for 2293-01-014 | ||
Length: | 2.1 Miles | ||
Estimate: | $6,130,457 | ||
Actual: | $6,111,688 |