Detail Letting Schedule for Ellis County (FY 2006)
Detail Letting Schedule for Ellis County (FY 2006) | ||||
Last Update: Monday, August 28, 2006 |
Ellis County (FY 2006) |
CCSJ: 0092-03-047 | |||
District: | Dallas | Let Date: | JAN 2006 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | IM 0453(125) | CSJ: | 0092-02-115 |
Description: | INSTALL WIRE ROPE MEDIAN BARRIER | Handling Code: |
|
Limits From: | DALLAS/ELLIS COUNTY LINE | Fund Cat: | 1 |
Limits To: | NORTH OF MALLOY BRIDGE | Estimate: | $214,545 |
Length: | 1.1 Miles | Actual: | $163,369 |
District: | Dallas | Let Date: | JAN 2006 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | STP 2006(094)SFT | CSJ: | 0092-03-047 |
Description: | INSTALL WIRE ROPE MEDIAN BARRIER | Handling Code: |
|
Limits From: | BRUSHY CREEK | Fund Cat: | 8 |
Limits To: | DALLAS COUNTY LINE | Estimate: | $1,143,496 |
Length: | 5.4 Miles | Actual: | $869,126 |
District: | Dallas | Let Date: | JAN 2006 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | STP 2006(094)SFT | CSJ: | 0092-04-068 |
Description: | INSTALL A WIRE ROPE MEDIAN BARRIER | Handling Code: |
|
Limits From: | SH 34 | Fund Cat: | 8 |
Limits To: | BRUSHY CREEK | Estimate: | $1,441,932 |
Length: | 10.1 Miles | Actual: | $1,084,592 |
District: | Dallas | Let Date: | JAN 2006 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | STP 2006(094)SFT | CSJ: | 0092-05-045 |
Description: | INSTALL WIRE ROPE MEDIAN BARRIER | Handling Code: |
|
Limits From: | NAVARRO COUNTY LINE | Fund Cat: | 8 |
Limits To: | SH 34 | Estimate: | $1,078,309 |
Length: | 7.1 Miles | Actual: | $779,705 |
Back... |
Totals for 0092-03-047 | ||
---|---|---|---|
Length: | 23.7 Miles | ||
Estimate: | $3,878,282 | ||
Actual: | $2,896,792 | ||
CCSJ: 0172-05-104 | |||
District: | Dallas | Let Date: | JUL 2006 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2006(689) | CSJ: | 0172-05-104 |
Description: | MICROSURFACING, MILLING AND OVERLAY | Handling Code: |
|
Limits From: | 0.70 MI SOUTH OF FM 878 | Fund Cat: | 1 |
Limits To: | 0.82 MI SOUTH OF BU 287R | Estimate: | $429,310 |
Length: | 2.3 Miles | Actual: | $345,260 |
District: | Dallas | Let Date: | JUL 2006 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2006(689) | CSJ: | 0172-07-024 |
Description: | MICROSURFACING, MILLING AND OVERLAY | Handling Code: |
|
Limits From: | 0.82 MI SOUTH OF BU 287R | Fund Cat: | 1 |
Limits To: | EAST OF COTTONWOOD CREEK | Estimate: | $658,121 |
Length: | 3.5 Miles | Actual: | $538,932 |
District: | Dallas | Let Date: | JUL 2006 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2006(689) | CSJ: | 0172-08-051 |
Description: | MICROSURFACING, MILLING AND OVERLAY | Handling Code: |
|
Limits From: | EAST OF COTTONWOOD CREEK | Fund Cat: | 1 |
Limits To: | WEST OF YORKSTOWN DRIVE IN ENNIS | Estimate: | $568,178 |
Length: | 5.3 Miles | Actual: | $444,186 |
District: | Dallas | Let Date: | JUL 2006 |
Highway: | BU 287S | Let Status: | Actual |
Project ID: | STP 2006(689) | CSJ: | 0172-12-003 |
Description: | MICROSURFACING, MILLING AND OVERLAY | Handling Code: |
|
Limits From: | WEST OF YORKSTOWN DRIVE | Fund Cat: | 1 |
Limits To: | BI 45-J (KAUFMAN STREET) | Estimate: | $1,118,483 |
Length: | 1.7 Miles | Actual: | $1,410,083 |
Bid Tabulations Back... |
Totals for 0172-05-104 | ||
Length: | 12.8 Miles | ||
Estimate: | $2,774,092 | ||
Actual: | $2,738,461 | ||
CCSJ: 0260-02-039 | |||
District: | Dallas | Let Date: | SEP 2005 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | STP 2005(897)SFT | CSJ: | 0260-02-039 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | SOUTH OF WARD ROAD | Fund Cat: | 8 |
Limits To: | US 287 IN MIDLOTHIAN | Estimate: | $328,102 |
Length: | 2.4 Miles | Actual: | $311,521 |
District: | Dallas | Let Date: | SEP 2005 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | STP 2005(897)SFT | CSJ: | 0261-01-038 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | US 287 IN MIDLOTHIAN | Fund Cat: | 8 |
Limits To: | DALLAS COUNTY LINE | Estimate: | $647,210 |
Length: | 5.3 Miles | Actual: | $618,306 |
District: | Dallas | Let Date: | SEP 2005 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | STP 2005(897)SFT | CSJ: | 0261-02-063 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | ELLIS COUNTY LINE | Fund Cat: | 8 |
Limits To: | WHEATLAND ROAD | Estimate: | $1,077,845 |
Length: | 8.8 Miles | Actual: | $1,013,751 |
District: | Dallas | Let Date: | SEP 2005 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | STP 2005(897)SFT | CSJ: | 0261-03-052 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | WHEATLAND ROAD | Fund Cat: | 1 |
Limits To: | CAMP WISDOM ROAD | Estimate: | $164,928 |
Length: | 1.3 Miles | Actual: | $165,977 |
Back... |
Totals for 0260-02-039 | ||
Length: | 17.8 Miles | ||
Estimate: | $2,218,085 | ||
Actual: | $2,109,555 | ||
CCSJ: 0261-01-036 | |||
District: | Dallas | Let Date: | FEB 2006 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 2006(281) | CSJ: | 0260-02-037 |
Description: | CONSTRUCT TURNAROUNDS AND RELOCATE RAMP | Handling Code: |
|
Limits From: | BUS US 287 | Fund Cat: | 1 |
Limits To: | 0.15 MI SOUTH OF US 287 | Estimate: | $724,363 |
Length: | 0.1 Miles | Actual: | $692,774 |
District: | Dallas | Let Date: | FEB 2006 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 2006(281) | CSJ: | 0261-01-036 |
Description: | CONSTRUCT TURNAROUNDS AND RELOCATE RAMP | Handling Code: |
|
Limits From: | 0.30 MI NORTH OF US 287 | Fund Cat: | 1 |
Limits To: | BUS US 287 | Estimate: | $2,262,646 |
Length: | 0.3 Miles | Actual: | $1,747,169 |
Back... |
Totals for 0261-01-036 | ||
Length: | 0.4 Miles | ||
Estimate: | $2,987,009 | ||
Actual: | $2,439,943 | ||
CCSJ: 0747-06-011 | |||
District: | Dallas | Let Date: | AUG 2006 |
Highway: | FM 157 | Let Status: | Actual |
Project ID: | SFT 747-6-11 | CSJ: | 0747-06-011 |
Description: | ADD 3 FOOT PAVED SHOULDERS | Handling Code: |
|
Limits From: | 0.5 MILES NORTH OF MAYPEARL ROAD | Fund Cat: | 1 |
Limits To: | FM 875 | Estimate: | $3,759,772 |
Length: | 6.6 Miles | Actual: | $4,469,465 |
District: | Dallas | Let Date: | AUG 2006 |
Highway: | FM 157 | Let Status: | Actual |
Project ID: | C 747-6-12 | CSJ: | 0747-06-012 |
Description: | ADD SHOULDERS AND GUARD FENCE, UPGRADE CULVERT AND BRIDGE | Handling Code: |
|
Limits From: | JOHNSON COUNTY LINE (NEAR FM 1807) | Fund Cat: | 1 |
Limits To: | FM 66 | Estimate: | $2,225,461 |
Length: | 8.5 Miles | Actual: | $3,120,559 |
Bid Tabulations Award Status Back... |
Totals for 0747-06-011 | ||
Length: | 15.1 Miles | ||
Estimate: | $5,985,233 | ||
Actual: | $7,590,024 | ||
CCSJ: 0918-22-097 | |||
District: | Dallas | Let Date: | SEP 2005 |
Highway: | CR | Let Status: | Actual |
Project ID: | STP 2005(991)RXH | CSJ: | 0918-22-097 |
Description: | INSTALLATION OF RAILROAD WARNING SIGNALS AND GATES | Handling Code: |
XX |
Limits From: | S. OF FERRIS ON RISINGER RD @ UP RR | Fund Cat: | 10 |
Limits To: | DOT NO. 765452Y | Estimate: | $170,000 |
Length: | 0.0 Miles | Actual: | $170,000 |
Back... |
Totals for 0918-22-097 | ||
Length: | 0.0 Miles | ||
Estimate: | $170,000 | ||
Actual: | $170,000 | ||
CCSJ: 1048-01-020 | |||
District: | Dallas | Let Date: | JUN 2006 |
Highway: | FM 983 | Let Status: | Actual |
Project ID: | SFT 1048-1-20 | CSJ: | 1048-01-020 |
Description: | ADD 3 FOOT PAVED SHOULDERS | Handling Code: |
|
Limits From: | BRUSHY CREEK | Fund Cat: | 8 |
Limits To: | 0.5 MILES EAST OF BATCHLER ROAD | Estimate: | $1,586,254 |
Length: | 2.9 Miles | Actual: | $2,373,149 |
District: | Dallas | Let Date: | JUN 2006 |
Highway: | FM 983 | Let Status: | Actual |
Project ID: | C 1048-1-21 | CSJ: | 1048-01-021 |
Description: | ADD SHOULDERS AND GUARD FENCE, UPGRADE CULVERT AND BRIDGE | Handling Code: |
|
Limits From: | FM 813 | Fund Cat: | 1 |
Limits To: | WOOD ST IN FERRIS | Estimate: | $3,662,449 |
Length: | 7.6 Miles | Actual: | $5,266,695 |
Bid Tabulations Back... |
Totals for 1048-01-020 | ||
Length: | 10.5 Miles | ||
Estimate: | $5,248,703 | ||
Actual: | $7,639,844 |
|
|