Letting Schedule for Wichita Falls District (FY 2006)
| Letting Schedule for Wichita Falls District (FY 2006) | ||||
| Last Update: Monday, August 28, 2006 | 
| Wichita Falls District (FY 2006) | 
| Archer | Baylor | Clay | Cooke | Montague | Wichita | Wilbarger | Young | ||||||
| Archer County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
|---|---|---|---|---|---|---|
| 0133-07-023 | SH 114 | Actual | OCT 2005 | $9,693,312 | 1 | SEAL COAT | 
| Baylor County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
| 0125-01-038 | US 183 | Actual | JAN 2006 | $705,696 | 6 | REPLACE BRIDGE AND APPROACHES | 
| 0156-06-040 | US 277 | Actual | JAN 2006 | $43,978,969 | 4 | UPGRADE TO 4 LANE DIVIDED FACILITY | 
| 0156-06-046 | US 82 | Actual | MAY 2006 | $5,197,446 | 1 | HOT MIX OVERLAY | 
| Clay County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
| 0044-02-075 | US 82 | Actual | JAN 2006 | $409,912 | 8 | INSTALL MEDIAN BARRIER | 
| 0224-02-040 | US 287 | Actual | SEP 2005 | $5,502,827 | 1 | HEAVY HOT MIX OVERLAY | 
| 0282-01-015 | SH 79 | Actual | DEC 2005 | $3,714,294 | 1 | HOT MIX OVERLAY | 
| 0681-03-009 | FM 171 | Actual | SEP 2005 | $743,582 | 1 | IMPROVE VERTICAL AND HORIZONTAL ALIGNMENT | 
| Cooke County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
| 0045-01-052 | US 82 | Actual | DEC 2005 | $2,484,465 | 1 | HOT MIX OVERLAY | 
| 0194-02-075 | IH 35 | Actual | AUG 2006 | $14,790,001 | 1 | REHAB US 82 RAMP AND FRONTAGE ROADS | 
| 0194-02-084 | IH 35 | Actual | SEP 2005 | $416,753 | 1 | INTALL DYNAMIC MESSAGE SIGNS | 
| 0823-02-017 | FM 373 | Actual | FEB 2006 | $2,752,919 | 11 | WIDEN PAVED SURFACE | 
| 0903-15-062 | CR | Actual | MAR 2006 | $572,134 | 6 | BRIDGE REPLACEMENT | 
| 0903-15-069 | CR | Actual | JAN 2006 | $711,452 | 6 | REPLACE BRIDGE AND APPROACHES | 
| Montague County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
| 0013-05-053 | US 81 | Actual | OCT 2005 | $2,345,025 | 1 | HOT MIX OVERLAY | 
| 0903-28-024 | CR | Actual | JAN 2006 | $778,905 | 6 | REPLACE BRIDGE AND APPROACHES | 
| 1352-01-015 | FM 677 | Actual | APR 2006 | $1,655,728 | 11 | REPLACE BRIDGE AND APPROACHES | 
| Wichita County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
| 0043-09-107 | IH 44 | Actual | MAR 2006 | $1,184,104 | 1 | CONCRETE PAVEMENT REPAIR | 
| 0043-09-108 | US 287 | Actual | JAN 2006 | $209,299 | 11 | LANDSCAPING | 
| 0043-14-022 | LP 11 | Actual | OCT 2005 | $583,748 | 1 | UPGRADE GUARDRAIL AND SGT'S | 
| 0043-17-023 | BU 287J | Actual | JUN 2006 | $621,617 | 1 | WIDEN DRAINAGE STRUCTURES | 
| 0156-03-042 | SH 240 | Actual | OCT 2005 | $2,478,743 | 1 | HOT MIX OVERLAY | 
| 0681-04-034 | FM 367 | Actual | DEC 2005 | $2,407,478 | 1 | HOT MIX OVERLAY | 
| 1615-01-011 | FM 1740 | Actual | JAN 2006 | $2,733,706 | 11 | WIDEN PAVED SURFACE, EXTEND CULVERTS AND ADD SHOULDERS | 
| Wilbarger County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
| 0043-05-101 | US 287 | Actual | MAR 2006 | $1,815,106 | 1 | SEAL COAT AND DENSE - GRADED HOT - MIX ASPHALT | 
| 0043-06-076 | US 287 | Actual | SEP 2005 | $285,823 | 8 | INSTALL MEDIAN BARRIER | 
| 0043-06-077 | US 287 | Actual | MAY 2006 | $1,711,258 | 1 | HMAC OVERLAY | 
| 0043-07-103 | US 287 | Actual | SEP 2005 | $229,491 | 1 | INSTALL INTERSECTION FLASHING BEACONS | 
| 0124-02-027 | US 283 | Actual | SEP 2005 | $12,528,656 | 1 | WIDEN PAVEMENT AND STRUCTURES | 
| 0702-01-011 | FM 91 | Actual | JUN 2006 | $780,049 | 11 | REPLACE BRIDGE AND APPROACHES | 
| 0903-30-020 | CR | Actual | APR 2006 | $287,656 | 6 | REPLACE BRIDGE AND APPROACHES | 
| Young County | ||||||
| CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | 
| 0134-02-045 | SH 16 | Actual | MAR 2006 | $655,000 | 1 | UPGRADE TRAFFIC SIGNALS | 
| 0444-01-030 | SH 114 | Actual | DEC 2005 | $4,730,594 | 1 | HOT MIX OVERLAY | 
| 
 | 
|  |