Detail Letting Schedule for Polk County (FY 2006)
Detail Letting Schedule for Polk County (FY 2006) | ||||
Last Update: Monday, August 28, 2006 |
Polk County (FY 2006) |
CCSJ: 0176-05-135 | |||
District: | Lufkin | Let Date: | SEP 2005 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2000(305)TE | CSJ: | 0176-05-135 |
Description: | RENOVATION OF SAFETY REST AREA | Handling Code: |
NC |
Limits From: | AT REST AREAS 1.5 MI N OF LEGGET | Fund Cat: | 10 |
Limits To: | . | Estimate: | $8,429,203 |
Length: | 0.0 Miles | Actual: | $7,382,393 |
District: | Lufkin | Let Date: | SEP 2005 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | C 176-5-153 | CSJ: | 0176-05-153 |
Description: | HMA OVERLAY | Handling Code: |
|
Limits From: | AT REST AREAS 1.5 MI N OF LEGGET | Fund Cat: | 11 |
Limits To: | . | Estimate: | $392,892 |
Length: | 0.8 Miles | Actual: | $392,507 |
Back... |
Totals for 0176-05-135 | ||
---|---|---|---|
Length: | 0.8 Miles | ||
Estimate: | $8,822,095 | ||
Actual: | $7,774,900 | ||
CCSJ: 0177-01-082 | |||
District: | Lufkin | Let Date: | FEB 2006 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | SFT 177-1-82 | CSJ: | 0177-01-082 |
Description: | CONSTRUCT INTERCHANGE | Handling Code: |
|
Limits From: | .1MI N OF FM 1988 | Fund Cat: | 11 |
Limits To: | .1MI S OF LP 393 | Estimate: | $6,038,011 |
Length: | 1.1 Miles | Actual: | $7,489,697 |
Back... |
Totals for 0177-01-082 | ||
Length: | 1.1 Miles | ||
Estimate: | $6,038,011 | ||
Actual: | $7,489,697 | ||
CCSJ: 0213-03-090 | |||
District: | Lufkin | Let Date: | JAN 2006 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | C 213-3-90 | CSJ: | 0213-03-090 |
Description: | NEW TRAFFIC SIGNALS, IMPROVE TRAFFIC SIGNALS, AND | Handling Code: |
|
Limits From: | FM 356 | Fund Cat: | 1 |
Limits To: | FM 3459 | Estimate: | $137,056 |
Length: | 0.9 Miles | Actual: | $118,449 |
Back... |
Totals for 0213-03-090 | ||
Length: | 0.9 Miles | ||
Estimate: | $137,056 | ||
Actual: | $118,449 | ||
CCSJ: 0388-01-039 | |||
District: | Lufkin | Let Date: | AUG 2006 |
Highway: | SH 146 | Let Status: | Actual |
Project ID: | C 388-1-39 | CSJ: | 0388-01-039 |
Description: | REHABILITATE EXISTING PAVEMENT AND ADD SHOULDERS | Handling Code: |
|
Limits From: | 0.253 MI S OF FM 2610 | Fund Cat: | 1 |
Limits To: | LIBERTY COUNTY LINE | Estimate: | $5,205,015 |
Length: | 4.3 Miles | Actual: | $5,314,122 |
Bid Tabulations Award Status Back... |
Totals for 0388-01-039 | ||
Length: | 4.3 Miles | ||
Estimate: | $5,205,015 | ||
Actual: | $5,314,122 | ||
CCSJ: 0911-04-042 | |||
District: | Lufkin | Let Date: | JUN 2006 |
Highway: | VA | Let Status: | Actual |
Project ID: | C 911-4-42 | CSJ: | 0911-04-042 |
Description: | INSTALL COUNTY ROAD ADVANCE SIGNING | Handling Code: |
|
Limits From: | VARIOUS LOCATIONS IN POLK COUNTY | Fund Cat: | 1 |
Limits To: | . | Estimate: | $368,765 |
Length: | 0.1 Miles | Actual: | $307,205 |
Bid Tabulations Back... |
Totals for 0911-04-042 | ||
Length: | 0.1 Miles | ||
Estimate: | $368,765 | ||
Actual: | $307,205 | ||
CCSJ: 1408-01-021 | |||
District: | Lufkin | Let Date: | JUL 2006 |
Highway: | FM 1276 | Let Status: | Actual |
Project ID: | SFT 1408-1-21 | CSJ: | 1408-01-021 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | US 190 | Fund Cat: | 1 |
Limits To: | FM 943 | Estimate: | $4,373,133 |
Length: | 13.5 Miles | Actual: | $5,733,383 |
District: | Lufkin | Let Date: | JUL 2006 |
Highway: | FM 2610 | Let Status: | Actual |
Project ID: | SFT 2591-1-9 | CSJ: | 2591-01-009 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | SH 146 | Fund Cat: | 11 |
Limits To: | LIBERTY COUNTY LINE | Estimate: | $1,498,985 |
Length: | 5.0 Miles | Actual: | $1,928,462 |
District: | Lufkin | Let Date: | JUL 2006 |
Highway: | FM 3126 | Let Status: | Actual |
Project ID: | SFT 3160-3-6 | CSJ: | 3160-03-006 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | US 190 | Fund Cat: | 11 |
Limits To: | FM 2457 | Estimate: | $1,011,351 |
Length: | 2.7 Miles | Actual: | $1,301,834 |
Bid Tabulations Back... |
Totals for 1408-01-021 | ||
Length: | 21.2 Miles | ||
Estimate: | $6,883,469 | ||
Actual: | $8,963,679 | ||
CCSJ: 3036-01-004 | |||
District: | Lufkin | Let Date: | APR 2006 |
Highway: | FM 222 | Let Status: | Actual |
Project ID: | C 395-4-15 | CSJ: | 0395-04-015 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | FM 3278 | Fund Cat: | 11 |
Limits To: | 1.8 MI SOUTH OF FM 3278 | Estimate: | $604,357 |
Length: | 1.8 Miles | Actual: | $574,488 |
District: | Lufkin | Let Date: | APR 2006 |
Highway: | FM 2969 | Let Status: | Actual |
Project ID: | SFT 3036-1-4 | CSJ: | 3036-01-004 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | 2.6 MI W | Fund Cat: | 8 |
Limits To: | FM 1988 | Estimate: | $810,679 |
Length: | 2.6 Miles | Actual: | $823,033 |
District: | Lufkin | Let Date: | APR 2006 |
Highway: | FM 222 | Let Status: | Actual |
Project ID: | SFT 3038-1-10 | CSJ: | 3038-01-010 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | 6.4 MI N OF SH 150 | Fund Cat: | 8 |
Limits To: | SH 150 | Estimate: | $1,621,142 |
Length: | 6.5 Miles | Actual: | $1,740,900 |
District: | Lufkin | Let Date: | APR 2006 |
Highway: | FM 3278 | Let Status: | Actual |
Project ID: | SFT 3198-2-11 | CSJ: | 3198-02-011 |
Description: | SAFETY TREAT FIXED OBJECTS AND WIDEN LANES | Handling Code: |
|
Limits From: | FM 222 | Fund Cat: | 1 |
Limits To: | CR 184 | Estimate: | $557,403 |
Length: | 1.4 Miles | Actual: | $602,255 |
Back... |
Totals for 3036-01-004 | ||
Length: | 12.3 Miles | ||
Estimate: | $3,593,581 | ||
Actual: | $3,740,676 |
|
|