Detail Letting Schedule for Houston County (FY 2010)
Detail Letting Schedule for Houston County (FY 2010) | ||||
Last Update: Tuesday, November 2, 2010 |
Houston County (FY 2010) |
CCSJ: 0109-03-030 | |||
District: | Lufkin | Let Date: | APR 2010 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2010(767) | CSJ: | 0109-03-030 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | 0.25 MI S OF BU 287-V | Fund Cat: | 11 |
Limits To: | 3.63 MI S | Estimate: | $428,502 |
Length: | 3.6 Miles | Actual: | $418,028 |
District: | Lufkin | Let Date: | APR 2010 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2010(767) | CSJ: | 0109-04-026 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | 3.9 MI S OF BU 287-V | Fund Cat: | 1 |
Limits To: | LP 304 | Estimate: | $736,033 |
Length: | 6.3 Miles | Actual: | $714,620 |
District: | Lufkin | Let Date: | APR 2010 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2010(767) | CSJ: | 0341-01-025 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | VICKERY ST IN GROVETON | Fund Cat: | 1 |
Limits To: | POLK COUNTY LINE | Estimate: | $521,246 |
Length: | 8.9 Miles | Actual: | $504,348 |
Back... |
Totals for 0109-03-030 | ||
---|---|---|---|
Length: | 18.8 Miles | ||
Estimate: | $1,685,781 | ||
Actual: | $1,636,996 | ||
CCSJ: 0109-03-031 | |||
District: | Lufkin | Let Date: | JAN 2010 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2010(250) | CSJ: | 0109-03-031 |
Description: | RESURFACE WITH SEAL COAT | Handling Code: |
|
Limits From: | ANDERSON COUNTY LINE | Fund Cat: | 1 |
Limits To: | 0.26 MI S OF BU 287-V | Estimate: | $428,422 |
Length: | 6.4 Miles | Actual: | $395,583 |
District: | Lufkin | Let Date: | JAN 2010 |
Highway: | US 69 | Let Status: | Actual |
Project ID: | NH 2010(251) | CSJ: | 0200-01-078 |
Description: | RESURFACE WITH SEAL COAT | Handling Code: |
|
Limits From: | 0.18 MI W OF FM 841 | Fund Cat: | 1 |
Limits To: | 0.26 MI E OF FM 326 (N) | Estimate: | $189,294 |
Length: | 2.5 Miles | Actual: | $175,082 |
District: | Lufkin | Let Date: | JAN 2010 |
Highway: | FM 943 | Let Status: | Actual |
Project ID: | STP 2010(250) | CSJ: | 1194-01-019 |
Description: | RESURFACE WITH SEAL COAT | Handling Code: |
|
Limits From: | SH 146 | Fund Cat: | 1 |
Limits To: | HARDIN COUNTY LINE | Estimate: | $583,889 |
Length: | 19.1 Miles | Actual: | $530,075 |
District: | Lufkin | Let Date: | JAN 2010 |
Highway: | FM 3154 | Let Status: | Actual |
Project ID: | STP 2010(250) | CSJ: | 3222-02-008 |
Description: | RESURFACE WITH SEAL COAT | Handling Code: |
|
Limits From: | 4.7 MI N OF US 287 | Fund Cat: | 1 |
Limits To: | US 287 | Estimate: | $137,601 |
Length: | 4.7 Miles | Actual: | $125,012 |
Back... |
Totals for 0109-03-031 | ||
Length: | 32.7 Miles | ||
Estimate: | $1,339,206 | ||
Actual: | $1,225,752 | ||
CCSJ: 0118-02-026 | |||
District: | Lufkin | Let Date: | DEC 2009 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2010(444)SB | CSJ: | 0118-02-026 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | FM 1733 | Fund Cat: | 8 |
Limits To: | FM 227 (S) | Estimate: | $2,554,915 |
Length: | 7.2 Miles | Actual: | $2,110,564 |
Back... |
Totals for 0118-02-026 | ||
Length: | 7.2 Miles | ||
Estimate: | $2,554,915 | ||
Actual: | $2,110,564 | ||
CCSJ: 0635-03-021 | |||
District: | Lufkin | Let Date: | AUG 2010 |
Highway: | FM 228 | Let Status: | Actual |
Project ID: | STP 2011(176)HES | CSJ: | 0635-03-021 |
Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: |
|
Limits From: | BU 287-V | Fund Cat: | 8 |
Limits To: | ANDERSON COUNTY LINE | Estimate: | $284,714 |
Length: | 10.4 Miles | Actual: | $278,552 |
Bid Tabulations Back... |
Totals for 0635-03-021 | ||
Length: | 10.4 Miles | ||
Estimate: | $284,714 | ||
Actual: | $278,552 | ||
CCSJ: 1854-01-031 | |||
District: | Lufkin | Let Date: | MAY 2010 |
Highway: | LP 304 | Let Status: | Actual |
Project ID: | DMO 2004(820)ES | CSJ: | 1854-01-031 |
Description: | ADD CONTINUOUS TWO - WAY LEFT TURN LANE | Handling Code: |
|
Limits From: | SH 7 (E) | Fund Cat: | 1 |
Limits To: | US 287 (E) | Estimate: | $1,252,457 |
Length: | 0.7 Miles | Actual: | $1,080,525 |
District: | Lufkin | Let Date: | MAY 2010 |
Highway: | LP 304 | Let Status: | Actual |
Project ID: | STP 2010(757)ES | CSJ: | 1854-01-042 |
Description: | RECONSTRUCT PAVEMENT & ADD CONTINUOUS TWO - WAY LEFT TURN LANE | Handling Code: |
|
Limits From: | US 287 (E) | Fund Cat: | 1 |
Limits To: | SH 19 (S) | Estimate: | $3,263,104 |
Length: | 1.6 Miles | Actual: | $2,798,478 |
Back... |
Totals for 1854-01-031 | ||
Length: | 2.3 Miles | ||
Estimate: | $4,515,561 | ||
Actual: | $3,879,003 | ||
CCSJ: 1854-01-039 | |||
District: | Lufkin | Let Date: | SEP 2009 |
Highway: | LP 304 | Let Status: | Actual |
Project ID: | STP 2010(076) | CSJ: | 1854-01-039 |
Description: | INSTALLATION OF TRAFFIC SIGNALS | Handling Code: |
|
Limits From: | AT ENTRANCE/EXIT OF WAL-MART | Fund Cat: | 1 |
Limits To: | . | Estimate: | $386,190 |
Length: | 0.0 Miles | Actual: | $371,041 |
Back... |
Totals for 1854-01-039 | ||
Length: | 0.0 Miles | ||
Estimate: | $386,190 | ||
Actual: | $371,041 |
|
|