Monthly State Let Construction Report For San Antonio District As Of Aug 23, 2019 Page 1 Of 9

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOMAL
HighwayIH 35
FromGUADALUPE RIVER
ToFM 306
CSJ0016-04-115
Proj IDNH 2019(775)
Work TypeOVERLAY
 
3.3214185078.960.000.0
CountyCOMAL
HighwayIH 35
From1.2 MILES SOUTH OF FM 306
ToFM 306
CSJ0016-04-116
Proj IDNH 2019(775)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
14245900.530.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days476
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-115
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193001
Totals18430979.490.000.000.0

CountyCOMAL
HighwayIH 35
FromFM 306
ToHAYS/COMAL COUNTY LINE
CSJ0016-04-117
Proj IDNH 1902(057)
Work TypeFOI
 
3.83863795147.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days659
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-117
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193010
Totals63795147.300.000.000.0

CountyCOMAL
HighwayIH 35
FromAT FM 1103
To.
CSJ0016-05-115
Proj IDNH 2017(797)
Work TypeGRAD,BSE, STR, SURF, PAVT MRK, SIGN
 
0.2277256065.098693932.5599.9
Work Order04-26-17
Work Began09-18-17
Work Completed
Time Computed04-07-17
Contract Working Days408
Addl Days Granted124
Working Days Charged536
Percent Time Used100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-115
AUSTIN MATERIALS, LLC (17.11)
AARON CONCRETE CONTRACTORS, L.P. (1.40)
F & W ELECTRICAL CONTRACTORS, INC. (7.39)
S&S BRIDGE PAINTING (0.14)
PRIMATE CONSTRUCTION, INC. (0.24)
TEXAS HIGHWAY WALLS (11.65)
WEST TEXAS RUMBLE STRIP (0.05)
VOGES DRILLING CO. (2.21)
FLASHER EQUIPMENT COMPANY (1.04)
ROADWAY SPECIALTIES, INC. (2.00)
RELMCO, INC. (1.46)
R K STEPHENS CONSTRUCTION, LLC (2.06)
CND CONTRACTING (0.82)
JAG PUBLIC SAFETY, LLC (0.11)
FRANK JR REINFORCEMENT LLC (0.17)
FRANK JR REINFORCEMENT LLC (0.49)
LONE STAR SITEWORK, LLC (0.45)
BUYERS BARRICADES SAN ANTONIO, LLC (0.08)
Contract #03173017
Totals7256065.09426931.368693932.5599.9

CountyCOMAL ETC
HighwayIH 35 ETC
FromGUADALUPE COUNTY LINE
To1.2 MILES SOUTH OF LP 337
CSJ0016-05-118
Proj IDNH 2018(178)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
271.72810109086.0211658720.9399.9
Work Order11-10-17
Work Began04-28-18
Work Completed
Time Computed12-10-17
Contract Working Days100
Addl Days Granted0
Working Days Charged97
Percent Time Used97
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-118
INTERSTATE BARRICADES & MARKINGS, INC. (20.54)
COX PAVING COMPANY OF TEXAS, INC. (6.37)
Contract #10173002
Totals10109086.02512128.0611658720.9399.9

CountyCOMAL
HighwayIH 35
FromFM 2252
ToSCHWAB RD
CSJ0016-05-119
Proj IDNH 2019(507)
Work TypeGRAD, STR, BASE & SURF
 
3.09824566550.721717883.086.9
Work Order03-18-19
Work Began07-09-19
Work Completed
Time Computed04-17-19
Contract Working Days441
Addl Days Granted0
Working Days Charged20
Percent Time Used4
Contractor(s)
BRIDGES AND ROADS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-119
TRP CONSTRUCTION GROUP, LLC (1.06)
ADCOCK 4 INVESTMENTS, LLC (2.71)
FLASHER EQUIPMENT COMPANY (1.14)
JB PINNACLE GROUP, LLC (5.24)
AUSTIN MATERIALS, LLC (40.35)
Contract #02193201
Totals24566550.721717883.081717883.086.9

CountyBEXAR
HighwayIH 35
From0.2 MI N OF TOEPPERWEIN RD
To0.2 MI S OF LOOP 1604
CSJ0016-07-132
Proj IDIM 0352(341)
Work TypeLANDSCAPE DEVELOPMENT
 
0.800287874.50285932.0799.3
Work Order05-13-13
Work Began10-20-14
Work Completed
Time Computed07-22-13
Contract Working Days57
Addl Days Granted0
Working Days Charged49
Percent Time Used85
Contractor(s)
ALTEX LANDSCAPE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-07-132
N-LINE TRAFFIC MAINTENANCE, L.P. (1.72)
Contract #02133206
Totals287874.500.00285932.0799.3

CountyBEXAR
HighwaySL 368
FromAT N. NEW BRAUNFELS INTERSECTION
To.
CSJ0016-08-036
Proj IDNH 1802(611)
Work TypeBASE, SURF, STRUC, PVMT MARKINGS
 
0.1621081603.251088953.4799.9
CountyBEXAR
HighwaySL 368
FromAT N. NEW BRAUNFELS INTERSECTION
To.
CSJ0016-08-040
Proj IDROW 16-8-40
Work TypeROW UTILITY ADJUSTMENTS
 
0.162264076.75253669.9196.0
Work Order09-19-18
Work Began11-09-18
Work Completed
Time Computed10-19-18
Contract Working Days165
Addl Days Granted0
Working Days Charged144
Percent Time Used87
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-036
D&S TEXAS ICON CONSTRUCTION (2.16)
FLASHER EQUIPMENT COMPANY (3.18)
BADECO, INC (7.53)
LONE STAR PAVING COMPANY (15.52)
FUQUAY, INC. (0.23)
HEARN CO. (0.66)
Contract #08183022
Totals1345680.0090276.501342623.3899.7

CountyBEXAR ETC
HighwaySL 368 ETC
FromAT CASA BLANCA
To.
CSJ0016-08-037
Proj IDSTP 2019(037)HES
Work TypeTRAFFIC SIGNALS & ILLUMINATION
 
4.0633513969.162140036.8460.9
Work Order10-16-18
Work Began00-00-00
Work Completed
Time Computed11-15-18
Contract Working Days527
Addl Days Granted0
Working Days Charged55
Percent Time Used10
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-037
FIBERTEL, LLC (8.18)
CATO ELECTRIC COMPANY (1.22)
FLASHER EQUIPMENT COMPANY (1.44)
ALAMO CRANE SERVICE, INC. (0.69)
Contract #09183213
Totals3513969.16353843.142140036.8460.9

CountyCOMAL ETC
HighwayFM 482 ETC
From0.4 MILES SW OF KRUEGER CANYON
ToIH 35
CSJ0016-19-024
Proj IDSTP 2019(091)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
335.52115797806.8411525468.4872.9
Work Order11-07-18
Work Began04-29-19
Work Completed
Time Computed12-07-18
Contract Working Days135
Addl Days Granted0
Working Days Charged59
Percent Time Used43
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0016-19-024
STRIPE-A-ZONE, INC. (23.54)
FLASHER EQUIPMENT COMPANY (1.07)
BRYDL CONTRACTING, INC. (0.61)
COX PAVING OF TEXAS, INC. (26.24)
BARRICADES PLUS, LLC (0.17)
Contract #10183005
Totals15797806.843060919.1511525468.4872.9

CountyBEXAR ETC
HighwaySL 353 ETC
FromPITLUK RD
ToCASSIN RD
CSJ0017-01-024
Proj IDSTP 1802(612)HES
Work TypeRUMBLE STRIPS
 
117.2971022882.27460640.4345.0
Work Order09-18-18
Work Began03-29-19
Work Completed
Time Computed10-18-18
Contract Working Days210
Addl Days Granted0
Working Days Charged85
Percent Time Used40
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-01-024
WEST TEXAS ROCK RESOURCES, LLC (0.48)
Contract #08183225
Totals1022882.270.00460640.4345.0

CountyATASCOSA
HighwayIH 35
FromATASCOSA/BEXAR COUNTY LINE
ToATASCOSA/MEDINA COUNTY LINE
CSJ0017-04-042
Proj IDNH 2019(646)
Work TypeBSE, SURF, PAV'T MRKINGS
 
2.5063383807.081456049.7743.0
CountyMEDINA
HighwayIH 35
FromFRIO/MEDINA COUNTY LINE
ToMEDINA/ATASCOSA COUNTY LINE
CSJ0017-05-094
Proj IDNH 2019(646)
Work TypeBSE, SURF, PAV'T MRKINGS
 
12.6849526910.400.000.0
Work Order04-25-19
Work Began00-00-00
Work Completed
Time Computed05-25-19
Contract Working Days345
Addl Days Granted0
Working Days Charged15
Percent Time Used4
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-042
DEPENDABLE FENCE & WELDING CO. INC. (5.02)
RELMCO, INC. (8.01)
FLASHER EQUIPMENT COMPANY (5.81)
PERFORMANCE EQUIPMENT SERVICE (3.99)
ALL AMERICAN TRUCKING, INC. (1.47)
Contract #03193204
Totals12910717.481456049.771456049.7711.2

CountyMEDINA ETC
HighwayIH 35 ETC
FromAT FM 471
To.
CSJ0017-05-095
Proj IDSTP 1802(614)HES
Work TypeINTERSECTION FLASHING BEACON
 
3.8002442867.71887535.2136.3
Work Order09-24-18
Work Began00-00-00
Work Completed
Time Computed10-24-18
Contract Working Days466
Addl Days Granted0
Working Days Charged35
Percent Time Used7
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-095
FLASHER EQUIPMENT COMPANY (1.50)
Contract #08183051
Totals2442867.71115201.47887535.2136.3

CountyFRIO
HighwayIH 35
FromFM 3352
ToFM 462
CSJ0017-06-084
Proj IDNH 2018(910)
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
6.42813995985.028099823.9557.8
Work Order06-14-18
Work Began07-14-18
Work Completed
Time Computed07-14-18
Contract Working Days358
Addl Days Granted0
Working Days Charged167
Percent Time Used46
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-06-084
EGGEMEYER LAND CLEARING, LLC (0.58)
FLASHER EQUIPMENT COMPANY (2.12)
WEST TEXAS RUMBLE STRIP (0.03)
GEOSOURCE, INC. (1.30)
SAECO ELECTRIC & UTILITY, LTD. (0.10)
DELGADO"S CONTRACTORS, LLC (6.67)
ALL AMERICAN TRUCKING, INC. (3.57)
K. L. DURHAM CONSTRUCTION, L.L.C. (2.02)
J & P PAVING CO. (0.00)
DEPENDABLE FENCE & WELDING CO. INC. (0.67)
Contract #05183056
Totals13995985.02522292.018099823.9557.8

CountyFRIO
HighwayIH 35
FromFM 140
ToUS 57
CSJ0017-06-085
Proj IDNH 2019(900)
Work TypeOVERLAY
 
9.7827715069.150.000.0
CountyFRIO
HighwayIH 35
FromLA SALLE/FRIO COUNTY LINE
ToFM 140
CSJ0017-07-135
Proj IDNH 2019(900)
Work TypeOVERLAY
 
18.78715405952.990.000.0
CountyATASCOSA
HighwayIH 37
From1.1 MILES SOUTH OF US 281
To0.5 MI SOUTH OF FM 541
CSJ0073-05-072
Proj IDNH 2019(900)
Work TypeOVERLAY
 
4.7392195399.310.000.0
CountyATASCOSA
HighwayIH 37
From0.7 MI SOUTH OF US 281
To1.1 MILES SOUTH OF US 281
CSJ0073-10-052
Proj IDNH 2019(900)
Work TypeOVERLAY
 
0.390215684.620.000.0
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed07-17-19
Contract Working Days303
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-06-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193204
Totals25532106.070.000.000.0

CountyFRIO ETC
HighwayIH 35 ETC
FromAT FM 1581
To.
CSJ0017-07-136
Proj IDSTP 1902(204)HES
Work TypeSFT
 
13.884952818.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days185
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-136
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193045
Totals952818.040.000.000.0

CountyBEXAR
HighwayIH 35
From0.25 MILES S OF S ZARZAMORA ST
To0.25 MILES N OF S ZARZAMORA ST
CSJ0017-09-104
Proj IDNH 2018(801)
Work TypeLANDSCAPE DEVELOPMENT
 
0.500482084.04453779.0494.1
Work Order06-14-18
Work Began08-06-18
Work Completed
Time Computed07-14-18
Contract Working Days56
Addl Days Granted0
Working Days Charged39
Percent Time Used69
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-104
FLASHER LIMITED (1.38)
Contract #05183211
Totals482084.043500.00453779.0494.1

CountyBEXAR
HighwayIH 35
From0.9 MILES N OF IH 410
To0.3 MILES N OF IH 410
CSJ0017-09-105
Proj IDNH 1902(205)
Work TypeLSE
 
0.583641593.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193032
Totals641593.000.000.000.0

CountyBEXAR
HighwayIH 35
FromAT NEW BRAUNFELS AVENUE
To.
CSJ0017-10-273
Proj IDBR 2016(406)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0014992612.146205519.4599.9
CountyZERO COUNTIES
Highway
From
To
CSJ0017-10-276
Proj ID
Work Type
 
0.005229.000.0
Work Order06-30-16
Work Began10-17-16
Work Completed
Time Computed09-28-16
Contract Working Days289
Addl Days Granted174
Working Days Charged625
Percent Time Used134
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-273
ROADWAY SPECIALTIES, INC. (0.49)
FLASHER EQUIPMENT COMPANY (0.87)
F & W ELECTRICAL CONTRACTORS, INC. (15.44)
SCOTT DERR PAINTING CO, LLC (0.08)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.30)
HUNTER DEMOLITION & WRECKING CORPORATION (2.64)
W. W. FOUNDATION DRILLING, LTD. (3.35)
CERTIFIED PLACERS LLC (0.35)
WEBB & BEXAR CONSTRUCTION, LLC. (5.63)
CP REBAR AND PT INSTALLATION (0.25)
LIGHT IT UP ELECTRIC (2.26)
LONE STAR PAVING COMPANY (7.65)
AR EXCAVATIONS, LLC (0.51)
BLUETEX IRRIGATION & CONSTRUCTION (0.21)
PENHALL COMPANY (AUSTIN) (0.11)
SHORT-LINE CORPORATION (0.50)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (0.50)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.06)
L&E PIPELINE CONSTRUCTION LLC (0.13)
Contract #04163023
Totals4992612.145575.076210748.4599.9

CountyBEXAR
HighwayIH 35
FromAUSTIN ST.
ToCRESTWAY/RANDOLPH
CSJ0017-10-275
Proj IDC 17-10-275
Work TypeGRAD, BASE, SURF, PVMT MRKINGS
 
9.1317362618.043631746.6549.3
Work Order09-24-18
Work Began03-25-19
Work Completed
Time Computed10-24-18
Contract Working Days240
Addl Days Granted0
Working Days Charged77
Percent Time Used32
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-275
SAN ANTONIO CONCEPTS CONSTRUCTION, LLC (18.84)
INTERSTATE BARRICADES & MARKINGS, INC. (4.38)
THE LEVY COMPANY, INC. (0.23)
MPB, INC. (0.27)
Contract #06183215
Totals7362618.041319647.063631746.6549.3

CountyBEXAR
HighwayIH 35
FromSL 353 (NOGALITOS)
ToMCCULLOUGH AVE
CSJ0017-10-277
Proj IDSTP 2019(040)HES
Work TypeWRONG WAY DRIVER ADVANCED TECH
 
3.01483094.7357551.4069.2
Work Order10-16-18
Work Began00-00-00
Work Completed
Time Computed11-15-18
Contract Working Days60
Addl Days Granted0
Working Days Charged28
Percent Time Used46
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-277
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (23.64)
LIGHT IT UP ELECTRIC (51.15)
Contract #09183004
Totals83094.730.0057551.4069.2