Monthly State Let Construction Report For San Antonio District As Of Sep 18, 2019 Page 4 Of 8

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKENDALL
HighwayIH 10
FromNORTH CREEK RD.
ToUS 87
CSJ0142-15-026
Proj IDNH 2019(788)
Work TypeFOI
 
0.9927663986.450.000.0
CountyKENDALL
HighwayIH 10
FromKENDALL/KERR COUNTY LINE
To0.09 MILES NORTH OF FM 473
CSJ0142-15-028
Proj IDNH 2019(788)
Work TypeOVERLAY
 
1.9484938415.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days227
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0142-15-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193057
Totals12602401.700.000.000.0

CountyBEXAR
HighwayUS 87
FromIH 10
ToRIGSBY
CSJ0143-01-055
Proj IDNH 2019(036)
Work TypeGRAD, BSE, SURF, PAV'R MRKNGS
 
0.5872805913.66770706.2927.4
CountyBEXAR
HighwayUS 87
FromIH 10
ToRIGSBY
CSJ0143-01-057
Proj IDROW 143-1-57
Work TypeUTILITY ONLY
 
0.605645086.34371833.1057.6
Work Order10-22-18
Work Began02-04-19
Work Completed
Time Computed11-21-18
Contract Working Days203
Addl Days Granted18
Working Days Charged152
Percent Time Used68
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0143-01-055
CHEROKEE SERVICES (0.62)
FARR FOUNDATION, INC. (2.78)
THE LEVY COMPANY, INC. (3.07)
LONE STAR PAVING COMPANY (18.47)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.39)
RUCOBA & MAYA CONSTRUCTION, LLC (5.30)
BLACKTOP INDUSTRIES LLC (0.54)
A K FUQUAY CONSTRUCTION (0.44)
ZAMCO TRUCKING, LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (1.19)
BMP SPECIALIST, LLC (0.01)
TEXAS MATERIALS GROUP, INC. (0.01)
Contract #09183216
Totals3451000.00181482.471142539.3933.1

CountyWILSON
HighwayUS 87
FromFM 539
To0.5 MI EAST OF FM 538
CSJ0143-04-066
Proj IDSTP 1902(212)
Work TypeRER
 
9.75118988547.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days247
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0143-04-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193203
Totals18988547.950.000.000.0

CountyKENDALL
HighwaySH 46
FromUS 87
ToKENDALL / COMAL COUNTY LINE
CSJ0215-06-037
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
3.9055575747.696166433.3099.9
CountyCOMAL
HighwaySH 46
FromCOMAL / KENDALL COUNTY LINE
ToUS 281
CSJ0215-07-022
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
2.0503394595.793698313.7799.9
Work Order10-06-16
Work Began11-07-16
Work Completed
Time Computed11-05-16
Contract Working Days413
Addl Days Granted63
Working Days Charged530
Percent Time Used111
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-037
MPB, INC. (13.64)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (11.20)
FLASHER EQUIPMENT COMPANY (3.20)
ROADWAY SPECIALTIES, INC. (2.33)
THE LEVY COMPANY, L.P. (0.55)
EGGEMEYER LAND CLEARING, LLC (0.57)
AREA WIDE PROTECTIVE, INC. (0.02)
Contract #08163008
Totals8970343.48771.009864747.0799.9

CountyKENDALL
HighwaySH 46
FromHERFF ROAD
ToAMMANN ROAD
CSJ0215-06-039
Proj IDNH 1802(389)
Work TypeGRAD,STR,BASE & SURF
 
1.91311710627.967645079.7057.4
CountyKENDALL
HighwaySH 46
FromHERFF ROAD
ToAMMANN ROAD
CSJ0215-06-040
Proj IDNH 2017(418)
Work TypeROW ACQUISITION & UTILITIES ADJSTMT
 
1.777288693.69212620.0073.6
Work Order08-16-18
Work Began12-03-18
Work Completed
Time Computed09-15-18
Contract Working Days229
Addl Days Granted0
Working Days Charged219
Percent Time Used95
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-039
AREA WIDE PROTECTIVE, INC. (0.08)
CAPITAL EXCAVATION COMPANY (6.79)
DEPENDABLE FENCE & WELDING CO. INC. (0.55)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.76)
FUQUAY, INC. (1.22)
GEOSOURCE, INC. (0.34)
LONE STAR EROSION CONTROL (0.54)
FLASHER EQUIPMENT COMPANY (1.58)
VOGES DRILLING (2.90)
MURRAY CONSTRUCTION (0.58)
OSCAR ORDUNO, INC. (1.31)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (1.57)
IVY ROSALVA CRUZ DBA IVY"S TRUCKING (1.57)
PRESIDIO CONTRACTING, LLC (10.66)
SOUTH TEXAS PAINTING COMPANY (0.13)
SAECO ELECTRIC & UTILITY, LTD. (7.44)
DU-MOR ENTERPRISES INC. (0.39)
TEXAS ROAD BORING (0.39)
Contract #07183210
Totals11999321.652417374.437857699.7057.8

CountyKENDALL
HighwaySH 46
FromCORDILLERA TRCE
ToFM 3351
CSJ0215-06-043
Proj IDSTP 1902(345)HES
Work TypeSFT
 
0.811128748.850.000.0
CountyKERR
HighwaySH 16
From0.1 MI N OF MADRONA DR
To0.4 MI N OF SH 173
CSJ0291-03-071
Proj IDSTP 1902(214)
Work TypeOV
 
4.3703385032.290.000.0
CountyKERR
HighwaySL 534
FromIH 10
To0.2 MI SOUTH OF FM 1341
CSJ3362-01-016
Proj IDNH 1902(346)
Work TypeOV
 
1.9001414528.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193233
Totals4928309.140.000.000.0

CountyCOMAL
HighwaySL 337
FromSH 46, SOUTHERLY
ToIH 35
CSJ0216-01-036
Proj IDSTP 1702(434)
Work TypeGR, STRS, BASE & SURF
 
2.99718902660.0715661006.1182.8
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToHILLCREST DRIVE
CSJ0216-01-054
Proj IDSTP 1702(435)MM
Work TypeGR, BASE, SURF, PVMT MRK, SGNS, STR
 
1.43112457946.0310632420.6085.3
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToSH 46
CSJ0216-01-055
Proj IDNH 1702(436)
Work TypeGR,BASE,STRS, SURF
 
2.23010947785.377957454.3372.6
Work Order09-27-17
Work Began10-23-17
Work Completed
Time Computed10-27-17
Contract Working Days1,239
Addl Days Granted0
Working Days Charged554
Percent Time Used44
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0216-01-036
HOSS LAND SERVICE (0.23)
LONE STAR EROSION CONTROL (2.44)
INTERSTATE BARRICADES & MARKINGS, INC. (0.30)
VOGES DRILLING CO. (2.77)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.75)
CHEROKEE SERVICES (0.36)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.20)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (1.98)
HILL COUNTRY BRIDGE, INC (2.46)
GK CONSTRUCTION, LLC (0.41)
HOUSTON SAWING & DRILLING (0.03)
OSCAR ORDUNO, INC. (1.65)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.41)
THE LEVY COMPANY, INC. (4.91)
FLASHER EQUIPMENT COMPANY (1.01)
R K STEPHENS CONSTRUCTION, LLC (2.21)
ROADWAY SPECIALTIES, INC. (1.07)
SOUTH TEXAS PAINTING COMPANY (0.08)
PIPE WHOLESALERS OF TEXAS, INC. (1.19)
HARPER BROTHERS CONSTRUCTION LLC (0.16)
GK CONSTRUCTION, LLC (0.16)
FRANK JR REINFORCEMENT LLC (0.01)
GEOSOURCE, INC. (0.01)
Contract #07173003
Totals42308391.47896426.0434250881.0480.9

CountyCOMAL
HighwayUS 281
FromSB MAINLANE @ GUADALUPE RIVER
To.
CSJ0253-03-067
Proj IDBR 1702(038)
Work TypeGRAD,BSE,STRUCTURE,SURF,CLN & PAINT
 
0.1723271173.602603503.3079.5
Work Order06-14-17
Work Began08-07-17
Work Completed
Time Computed07-14-17
Contract Working Days304
Addl Days Granted96
Working Days Charged396
Percent Time Used99
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-067
S&S BRIDGE PAINTING (39.67)
FLASHER EQUIPMENT COMPANY (0.94)
AUSTIN MATERIALS, LLC (4.28)
Contract #05173036
Totals3271173.60155125.002603503.3079.5

CountyBEXAR
HighwayUS 281
From0.8 MI.NORTH OF STONE OAK
ToBEXAR / COMAL COUNTY LINE
CSJ0253-04-138
Proj IDNH 1802(390)
Work TypeGR, STRS, BASE, SIGN, DELIN & PAV
 
4.790168848816.1520045031.0811.8
CountyBEXAR
HighwayUS 281
From0.8 MI.NORTH OF STONE OAK
ToBEXAR / COMAL COUNTY LINE
CSJ0253-04-149
Proj IDROW 253-4-149
Work TypeROW ACQ., RELO. ASSIST. & UTIL. ADJ
 
4.8009534675.662974495.7831.1
Work Order08-15-18
Work Began02-07-19
Work Completed
Time Computed09-14-18
Contract Working Days1,286
Addl Days Granted0
Working Days Charged169
Percent Time Used13
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-138
BADECO, INC (1.00)
LONE STAR EROSION CONTROL (0.37)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.41)
PERFORMANCE EQUIPMENT SERVICE (0.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15)
GEOSOURCE, INC. (0.93)
HOSS LAND SERVICES LLC (0.00)
QUALITY TURF FARMS, L.C. (0.58)
SOUTH TEXAS PAINTING COMPANY (0.12)
ROYAL REBAR (4.71)
MICA CORPORATION (4.07)
DAKOTA UTILITY CONTRACTORS, INC. (0.14)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.23)
BEAIRD DRILLING (1.31)
PANTHER CREEK TRANSPORTATION, INC. (0.71)
MARIO SINACOLA & SONS EXCAVATING, INC. (9.47)
CJW CONSTRUCTION SERVICES, INC. (4.25)
OSCAR ORDUNO, INC. (3.05)
CORSAIR CONSULTING, LLC (0.04)
ANTIGO CONSTRUCTION, INC. (0.01)
ROADWAY SPECIALTIES, INC. (0.47)
PSI, INC. (0.00)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.99)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS (0.05)
GK CONSTRUCTION, LLC (0.14)
ELLIS AND ELLIS (0.68)
MCL CONTRACTING, LLC (0.12)
TEXAS ROAD BORING (0.09)
BREDA COMPANY, INC. (0.02)
PANTHER CREEK TRANSPORTATION, INC. (0.05)
ADCOCK 4 INVESTMENTS, LLC (3.19)
HOLES OF SAN ANTONIO (0.00)
Contract #07183001
Totals178383491.813251639.0523019526.8612.9

CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-146
Proj IDNH 2017(592)
Work TypeGR, STRS, BASE, SIGN, DELIN & PAV
 
3.778179542332.71111991882.4762.3
CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-151
Proj IDSTP 1602(378)
Work TypeROW ACQUISITION
 
3.57712759009.8811990608.3693.9
Work Order03-15-17
Work Began08-01-17
Work Completed
Time Computed04-14-17
Contract Working Days1,077
Addl Days Granted0
Working Days Charged574
Percent Time Used53
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-146
FLASHER EQUIPMENT COMPANY (0.58)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.60)
LONE STAR EROSION CONTROL (0.59)
ROYAL VISTA INC. (4.58)
W. W. FOUNDATION DRILLING, LTD. (1.75)
WEBBER BARRIER SERVICES, LLC. (1.70)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (1.99)
EARTH REINFORCEMENTS LLC (0.95)
LONE STAR PAVING COMPANY (7.22)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.17)
HOUSTON SAWING & DRILLING (0.03)
THE LEVY COMPANY, L.P. (5.61)
(USE 26300)BRADCO, LLC (2.06)
GEOSOURCE, INC. (0.05)
GK CONSTRUCTION, LLC (0.09)
HOSS LAND SERVICES LLC (0.01)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.01)
CP REBAR AND PT INSTALLATION (0.87)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (1.25)
DU MOR ENTERPRISES (0.50)
TEXAS HIGHWAY WALLS (0.75)
INDUS ROAD & BRIDGE, INC (2.29)
FUQUAY, INC. (1.18)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.17)
DAKOTA UTILITY CONTRACTORS, INC. (0.15)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.11)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.10)
SUPERIOR PUMP SOLUTIONS LLC (0.02)
HOWELL CRANE & RIGGING, INC. (0.00)
DAKOTA UTILITY CONTRACTORS, INC. (0.06)
JSS BORI GROUP, LLC (0.20)
FUQUAY, INC. (0.00)
CALAME CONTRACTING, LLC (0.39)
CHOCTAW ERECTORS, INC. (0.49)
BRYANT & FREY CONSTRUCTION (0.03)
OSCAR ORDUNO, INC. (0.02)
2 J RESOURCES COMPANY (0.11)
URBAN INFRACONSTRUCTION, LLC. (0.82)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06)
MCL CONTRACTING, LLC (0.02)
C2 CONCRETE, INC. (0.00)
FARR FOUNDATION, INC. (0.44)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.10)
DAKOTA UTILITY CONTRACTORS, INC. (0.05)
TPG PRESSURE, INC. (0.04)
MTAM CORPORATION (0.09)
ANCORTEX, INC. (0.27)
J & J REBAR & POST TENSION (0.32)
Contract #02173001
Totals192301342.594959930.97123982490.8364.4

CountyBEXAR
HighwayUS 281
FromLP 1604
ToNAKOMA
CSJ0253-04-158
Proj IDNH 1902(213)
Work TypeCTM
 
4.3011221392.730.000.0
CountyBEXAR
HighwaySL 1604
FromIH 10 W
ToUS 281
CSJ2452-02-123
Proj IDNH 1902(213)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
8.048190646.670.000.0
CountyBEXAR
HighwaySL 1604
FromUS 281
ToIH 35 N
CSJ2452-03-124
Proj IDNH 1902(213)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
9.546931308.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days338
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-158
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193234
Totals2343347.790.000.000.0

CountyBANDERA
HighwaySH 16
From1.813 MI W OF SH 46
To2.627 MI NW OF PR 37
CSJ0291-07-034
Proj IDSTP 1902(064)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.7894979183.600.000.0
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed08-16-19
Contract Working Days205
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0291-07-034
DEPENDABLE FENCE & WELDING CO. INC. (1.93)
LONE STAR EROSION CONTROL (2.02)
TRP CONSTRUCTION GROUP, LLC (4.74)
THE LEVY COMPANY, INC. (0.75)
FLASHER EQUIPMENT COMPANY (0.57)
BLACKTOP INDUSTRIES LLC (0.24)
GEOSOURCE, INC. (0.19)
Contract #06193225
Totals4979183.600.000.000.0

CountyBEXAR
HighwaySH 16
FromAT CEDAR TRAIL
To.
CSJ0291-10-110
Proj IDNH 2019(511)
Work TypeBSE, STR, SURF, PAV'T MRK
 
0.0601957752.501331344.0668.0
CountyBEXAR
HighwaySH 16
FromAT CEDAR TRAIL
To.
CSJ0291-10-111
Proj IDROW 291-10-111
Work TypeROW UTILITIES ADJUSTMENTS
 
0.060150209.25129609.2586.2
Work Order03-07-19
Work Began00-00-00
Work Completed
Time Computed04-06-19
Contract Working Days190
Addl Days Granted0
Working Days Charged81
Percent Time Used42
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0291-10-110
A BROTHERS MILLING, LLC (1.44)
LONE STAR PAVING COMPANY (13.52)
F & W ELECTRICAL CONTRACTORS, INC. (4.59)
FLASHER EQUIPMENT COMPANY (2.88)
BADECO, INC (1.70)
UNDERGROUND WATER SOLUTIONS, CO. (4.59)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.09)
Contract #02193217
Totals2107961.75187318.621460953.3169.3

CountyBEXAR
HighwaySS 421
From0.1 MI WEST OF GOODRICH
To0.1 MI EAST OF HAMILTON
CSJ0291-11-021
Proj IDSTP 2019(067)HES
Work TypeRAISED MEDIAN
 
0.602320840.00306877.7095.6
Work Order11-15-18
Work Began00-00-00
Work Completed
Time Computed12-15-18
Contract Working Days58
Addl Days Granted0
Working Days Charged40
Percent Time Used68
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0291-11-021
BUYERS BARRICADES, INC. (2.75)
FLASHER EQUIPMENT COMPANY (7.84)
WG ENGINEERING & CONSTRUCTION, LLC (4.39)
Contract #10183019
Totals320840.000.00306877.7095.6

CountyFRIO
HighwaySH 85
FromIH 35
ToBI 35D
CSJ0301-03-026
Proj IDC 301-3-26
Work TypeGRD, BSE, SURF, PAV'T MRK
 
0.7981754395.661549197.8688.3
Work Order03-25-19
Work Began06-21-19
Work Completed
Time Computed04-24-19
Contract Working Days105
Addl Days Granted0
Working Days Charged54
Percent Time Used51
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0301-03-026
BLACKTOP INDUSTRIES LLC (1.21)
EGGEMEYER LAND CLEARING, LLC (0.62)
BEAVER CONTRACTORS, LLC (6.02)
FLASHER EQUIPMENT COMPANY (3.63)
A K FUQUAY CONSTRUCTION (6.30)
Contract #01193219
Totals1754395.66115238.961549197.8688.3

CountyFRIO
HighwaySH 85
FromDIMMIT/FRIO COUNTY LINE
ToIH 35
CSJ0301-03-027
Proj IDSTP 1902(058)
Work TypeSUPER-2 HIGHWAY
 
14.05718027137.640.000.0
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed08-16-19
Contract Working Days421
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0301-03-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193207
Totals18027137.640.000.000.0

CountyFRIO
HighwaySH 85
FromBI 35D
ToFM 1582
CSJ0301-06-018
Proj IDSTP 1902(059)
Work TypeSUPER-2 HIGHWAY
 
14.11722794970.100.000.0
Work Order07-31-19
Work Began00-00-00
Work Completed
Time Computed08-30-19
Contract Working Days388
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0301-06-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193206
Totals22794970.100.000.000.0

CountyFRIO
HighwaySH 85
FromFM 1582
ToATASCOSA COUNTY LINE
CSJ0301-07-013
Proj IDSTP 1902(060)
Work TypeSUPER-2 HIGHWAY
 
12.62524665468.7510055.000.0
CountyATASCOSA
HighwaySH 85
FromFRIO COUNTY LINE
ToFM 140
CSJ0301-08-012
Proj IDSTP 1902(060)
Work TypeSUPER-2 HIGHWAY
 
0.9102139283.9026325.001.2
CountyATASCOSA
HighwaySH 85
FromFM 140
ToSH 97
CSJ0748-02-022
Proj IDSTP 1902(060)
Work TypeSUPER-2 HIGHWAY
 
7.5518626138.10103467.701.1
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed08-16-19
Contract Working Days463
Addl Days Granted0
Working Days Charged12
Percent Time Used2
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0301-07-013
GEOSOURCE, INC. (0.09)
LONE STAR EROSION CONTROL (1.62)
Contract #06193005
Totals35430890.75139847.70139847.700.3

CountyATASCOSA
HighwaySH 97
FromUS 281
To.
CSJ0328-04-041
Proj IDC 328-4-41
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
0.061304204.38108426.4235.6
CountyATASCOSA
HighwaySH 97
From0.8 MI S OF FM 476
ToUS 281
CSJ0328-04-044
Proj IDC 328-4-44
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
1.3643927267.153014924.2276.7
Work Order07-18-18
Work Began11-13-18
Work Completed
Time Computed08-17-18
Contract Working Days278
Addl Days Granted0
Working Days Charged175
Percent Time Used62
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-04-041
AREA WIDE PROTECTIVE, INC. (0.20)
FLASHER EQUIPMENT COMPANY (1.49)
THE LEVY COMPANY, INC. (3.47)
MURRAY CONSTRUCTION (0.58)
PRESIDIO CONTRACTING, LLC (15.04)
ROADWAY SPECIALTIES, INC. (4.44)
Contract #06183005
Totals4231471.53231475.273123350.6473.8

CountyATASCOSA
HighwaySH 97
FromFM 140
To0.6 MILES EAST OF BURNETT AVE
CSJ0328-05-044
Proj IDSTP 1502(612)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
0.9571760591.971521922.4899.9
CountyATASCOSA
HighwaySH 97
From9.0 MI NORTH OF MCMULLEN C/L
ToFM 140
CSJ0328-06-027
Proj IDSTP 1502(612)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
6.84810776872.6610640499.6398.7
Work Order10-30-15
Work Began01-14-16
Work Completed
Time Computed12-29-15
Contract Working Days417
Addl Days Granted8
Working Days Charged784
Percent Time Used184
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-05-044
B & B HIGHWAY SERVICES (0.18)
CHEROKEE SERVICES (0.34)
CUATRO T CONSTRUCTION, INC. (10.95)
D & S TEXAS ICON CONSTRUCTION, LLC. (0.07)
INTERSTATE BARRICADES & MARKINGS, INC. (0.39)
THE LEVY COMPANY, L.P. (0.18)
LONE STAR EROSION CONTROL (1.64)
RELMCO, INC. (2.54)
ROADWAY SPECIALTIES, INC. (1.92)
FLASHER EQUIPMENT COMPANY (2.07)
K-BAR SERVICES, INC. (0.02)
Contract #08153208
Totals12537464.630.0012162422.1199.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8