Item No Description Units August 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
1003 2001 LANDSCAPE BOULDERS EA     594.000 130.00000 1
1016 2001 LOOSE AGGREGATE FOR GROUNDCOVER (TY I) CY     1,025.000 40.00000 1
1016 2002 LOOSE AGGREGATE FOR GROUNDCOVER (TY II CY     289.000 42.00000 1
1018 2001 TREE PROTECTION EA 160.000 225.00000 241.000 222.44813 4
1018 2003 TREE PROTECTION LF 587.000 2.00000 3,128.000 1.87815 2
1018 2004 TREE PLANKING EA 9.000 200.00000 49.000 138.77551 2
1068 2002 LOOSE AGR FOR GRNCVR (DECOMP GRAN) (4IN) SY 65.000 27.00000 65.000 27.00000 1
1122 2001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 455.000 11.53297 2,334.000 23.15617 5
1122 2002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 1,677.000 21.62194 16,449.000 19.95739 32
1122 2003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 280.000 32.00000 1,786.000 26.12904 6
1122 2004 ROCK FILTER DAMS (INSTALL) (TY 4) LF     40.000 18.00000 1
1122 2009 ROCK FILTER DAMS (REMOVE) LF 2,287.000 7.52121 20,037.000 6.19131 38
1122 2016 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 4,153.000 10.20607 14,408.000 10.74478 23
1122 2019 CONSTRUCTION EXITS (REMOVE) SY 4,153.000 4.72666 14,408.000 5.03806 23
1122 2024 BACKHOE WORK (EROSION & SEDM CONT) HR     430.000 108.69070 3
1122 2030 CONSTRUCTION PERIMETER FENCE LF     8,600.000 2.00000 2
1122 2031 SANDBAGS FOR EROSION CONTROL EA 100.000 1.00000 100.000 1.00000 1
1122 2032 SANDBAGS FOR EROSION CONTROL (6") LF     1,854.000 4.15000 1
1122 2035 SANDBAGS FOR EROSION CONTROL (2') LF     435.000 6.15000 1
1122 2037 TEMPORARY SEDIMENT CONTROL FENCE INSTL LF 19,635.000 1.87777 204,858.000 2.00524 71
1122 2038 TEMP SDMT CONT FENCE (INLET PROTECTION LF 1,363.000 2.12553 6,358.000 2.86039 9
1122 2039 ROCK FILTER DAMS (REMOVE & REPLACE) LF     430.000 22.50000 1
1122 2047 BIOGRD EROSN CONT LOGS (8" DIA) INSTAL LF 9,128.000 5.00000 9,128.000 5.00000 1
1122 2048 BIOGRD EROSN CONT LOGS (12" DIA) INSTAL LF     3,041.000 4.00000 1
1122 2049 BIOGRD EROSN CONT LOGS (18" DIA) INSTAL LF 2,689.000 5.00000 9,559.000 4.93023 3
1122 2056 BIODEGRADBLE EROSION CONTROL LOGS REMO LF 2,689.000 1.00000 12,600.000 .75514 4
1122 2057 TEMPORARY SEDIMENT CONTROL FENCE REMOV LF 14,274.000 .35362 204,226.000 .25565 72