Monthly Local Let Maintenance Report For Bryan District As Of Sep 13, 2021 Page 6 Of 6

Last Update: Wednesday, September 15, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6385-22-001
Proj IDMMC - 638522001
Work TypeAGGREGATE
 
0.01047424.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6385-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08211705
Totals47424.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6385-23-001
Proj IDMMC - 638523001
Work TypeAGGREGATE
 
0.01061948.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6385-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08211706
Totals61948.000.000.000.0

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6385-24-001
Proj IDMMC - 638524001
Work TypeAGGREGATE
 
0.01076758.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6385-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08211707
Totals76758.750.000.000.0

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6385-71-001
Proj IDMMC - 638571001
Work TypeWINTER WEATHER MATERIAL
 
0.01017460.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE BARGAIN SOURCE
SUBCONTRACTOR(S) FOR CCSJ: 6385-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08211704
Totals17460.000.000.000.0

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6385-74-001
Proj IDSUP - 638574001
Work TypeJANITORIAL MAINTENANCE
 
0.01067227.341217.201.8
Work Order08-01-21
Work Began08-01-21
Work Completed
Time Computed08-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6385-74-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #06211730
Totals67227.341217.201217.201.8

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6385-76-001
Proj IDSUP - 638576001
Work TypePICNIC AREA MAINTENANCE
 
0.01079072.563179.374.0
Work Order08-01-21
Work Began08-01-21
Work Completed
Time Computed08-01-21
Contract Working Days180
Addl Days Granted0
Working Days Charged31
Percent Time Used17
Contractor(s)
WORKQUEST
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6385-76-001
LINDLEY CONSTRUCTION (0.00)
Contract #06211731
Totals79072.563179.373179.374.0

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6388-10-001
Proj IDMMC - 638810001
Work TypeWINTER WEATHER MATERIAL
 
0.01096480.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6388-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09211702
Totals96480.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6388-12-001
Proj IDMMC - 638812001
Work TypeWINTER WEATHER MATERIAL
 
0.01096480.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6388-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09211703
Totals96480.000.000.000.0

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6388-13-001
Proj IDMMC - 638813001
Work TypeWINTER WEATHER MATERIAL
 
0.010128640.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6388-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09211704
Totals128640.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6389-64-001
Proj IDSUP - 638964001
Work TypeJANITORIAL MAINTENANCE
 
0.010124293.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6389-64-001
JUNCTION FIVE-O-FIVE (0.00)
Contract #08211730
Totals124293.170.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6390-57-001
Proj IDSUP - 639057001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010288530.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6390-57-001
RUCON, INC. (0.00)
Contract #09211730
Totals288530.950.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6