Monthly State Let Construction Report For Tyler District As Of Oct 12, 2021 Page 1 Of 3

Last Update: Tuesday, October 12, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVAN ZANDT ETC
HighwayUS 80 ETC
FromKAUFMAN C/L
ToEDGEWOOD WEST C/L
CSJ0095-06-074
Proj IDSTP 2021(169)
Work TypeSEAL COAT
 
11795597.9211243789.4995.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-21
Work Began05-04-21
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged107
Percent Time Used100
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0095-06-074
STRIPE-A-ZONE, INC. (8.21)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (5.08)
INNOVATIVE ROADWAY SOLUTIONS, LLC (2.24)
BARRICADES PLUS, LLC (1.35)
BRYDL CONTRACTING, INC. (1.22)
Contract #12203203
Totals11795597.92153089.3311243789.4995.3

CountyGREGG
HighwayUS 80
FromUS 259, E
ToGREGG C/L
CSJ0096-06-074
Proj IDC 96-6-74
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.2061094462.311216629.1499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-21
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged52
Percent Time Used78
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-06-074
FLEX SUPPLY, LLC (0.72)
ISAACS CONSTRUCTION SERVICES LLC (0.31)
STRIPE-A-ZONE, INC. (1.85)
STRIPING TECHNOLOGY, L.P. (0.66)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.58)
Contract #03213021
Totals1094462.311994.951216629.1499.9

CountyVAN ZANDT
HighwaySH 19
From0.3 MI S OF SH 234(DEBBIE)IN CANTON,S
To0.3 MI S OF FM 1861 (HENDERSON C/L)
CSJ0108-02-033
Proj IDF 2021(821)
Work TypeSUPER-2 HIGHWAY
 
12.71812108565.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days434
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213211
Totals12108565.850.000.000.0

CountyCHEROKEE
HighwaySH 21
FromHOUSTON C/L, E
ToUS 69 IN ALTO
CSJ0118-04-032
Proj IDF 2021(822)
Work TypeOVERLAY
 
7.4425923688.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0118-04-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213222
Totals5923688.840.000.000.0

CountyCHEROKEE
HighwayUS 84
From0.5 MI E OF SH 110, IN RUSK, NE
ToRUSK C/L IN REKLAW
CSJ0123-03-022
Proj IDSTP 2021(216)
Work TypeREHABILITATION OF EXISTING ROAD
 
9.3307859265.16507544.156.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-05-21
Work Began04-05-21
Work Completed
Time Computed00-00-00
Contract Working Days295
Addl Days Granted0
Working Days Charged83
Percent Time Used28
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0123-03-022
A R BROTHERS CONSTRUCTION SERVICES, INC. (14.63)
ASE CONTRACTORS LLC (2.91)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (2.40)
J. H. ODEN CONTRACTING COMPANY (5.41)
PANOLA SIGN & BARRICADE, INC. (0.42)
R & G CONSTRUCTION, LLC (6.42)
STRIPE-A-ZONE, INC. (1.43)
FREDONIA CONSTRUCTION SERVICES (0.57)
DREWERY BROS TREE SERVICE, INC. (1.92)
ROWC ENERGY SERVICES, LLC (0.29)
Contract #01213204
Totals7859265.16136882.35507544.156.4

CountyGREGG ETC
HighwayUS 259 ETC
FromSH 31 (HENDERSON EXIT)
ToRUSK C/L
CSJ0138-16-006
Proj IDF 2021(712)
Work TypeSEAL COAT
 
1966926.460.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days41
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-16-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213032
Totals1966926.460.000.000.0

CountyHENDERSON ETC
HighwaySH 31 ETC
From@ FM 315 (BROAD ST.)
ToIN CHANDLER
CSJ0164-03-054
Proj IDSTP 2020(095)HES
Work TypeTRAFFIC CONTROL DEVICES
 
1.1001043571.001032142.3198.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-19
Work Began11-19-20
Work Completed
Time Computed00-00-00
Contract Working Days171
Addl Days Granted4
Working Days Charged120
Percent Time Used68
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0164-03-054
STRIPE-A-ZONE, INC. (1.91)
SOUTH TEXAS ILLUMINATION, LLC (3.91)
Contract #10193214
Totals1043571.0095861.161032142.3198.9

CountySMITH
HighwaySH 31
From@ TOLL 49
To.
CSJ0164-04-159
Proj IDSTP 2020(100)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200185057.00178511.0096.4
CountySMITH
HighwayUS 69
From@ ANN CAMPBELL/CR492
To0.45 MI N OF FM 3271
CSJ0190-05-067
Proj IDSTP 2020(101)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.20089985.2588618.2598.4
CountySMITH
HighwayIH 20
From@ US 69
ToIN LINDALE
CSJ0495-04-074
Proj IDSTP 2020(102)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.20063040.2562068.5098.4
CountyGREGG
HighwaySH 42
FromAT FM 1252
ToIN KILGORE
CSJ0545-04-050
Proj IDSTP 2020(103)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200119398.00123087.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-19
Work Began08-24-20
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged64
Percent Time Used64
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0164-04-159
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10193025
Totals457480.500.00452284.7598.8

CountySMITH
HighwayUS 271
FromFM 16, SW
ToIH 20
CSJ0165-02-065
Proj IDF 2021(509)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.30010173182.3693068.000.9
CountySMITH
HighwayUS 271
FromGREGG C/L, SW
ToFM 757
CSJ0165-02-066
Proj IDSTP 2021(510)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.1332204218.853150.000.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-21
Work Began08-03-21
Work Completed
Time Computed00-00-00
Contract Working Days323
Addl Days Granted0
Working Days Charged41
Percent Time Used12
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0165-02-065
R & G CONSTRUCTION, LLC (11.55)
REYNOLDS & KAY, LTD. (5.32)
PANOLA SIGN & BARRICADE, INC. (0.49)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.38)
STRIPE-A-ZONE, INC. (1.15)
COLD CREEK CONSTRUCTION, LTD (0.50)
ISAACS CONSTRUCTION SERVICES LLC (2.52)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.48)
Contract #05213006
Totals12377401.2127468.0096218.000.7

CountyWOOD
HighwaySH 37
From1.683 MI N OF FM 779 (QUITMAN CL), S
To1.455 MI N OF SL 546 (CR 2460)
CSJ0190-03-087
Proj IDF 2021(820)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4577457.440.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days83
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0190-03-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213024
Totals4577457.440.000.000.0

CountySMITH
HighwayUS 69
FromSS 147 IN TYLER, S
ToSH 64 (ERWIN ST.)
CSJ0190-06-012
Proj IDNH 2021(033)
Work TypeOVERLAY
 
1.2001333003.691334289.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-20
Work Began05-23-21
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged21
Percent Time Used60
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0190-06-012
DUSTROL, INC. (11.90)
PANOLA SIGN & BARRICADE, INC. (0.79)
STRIPING TECHNOLOGY, L.P. (3.89)
Contract #09203036
Totals1333003.6919856.771334289.6299.9

CountySMITH
HighwayUS 69
FromAT FM 346, E OF FLINT
To.
CSJ0191-01-063
Proj IDNH 2013(216)
Work TypeGR, STRS, ACP SURF, PVMT MRKG, MBGF
 
0.94816738120.3316661661.4699.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-18
Work Began10-12-18
Work Completed
Time Computed00-00-00
Contract Working Days430
Addl Days Granted0
Working Days Charged429
Percent Time Used99
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0191-01-063
TOTAL HIGHWAY MAINTENANCE, LLC (0.18)
ISAACS CONSTRUCTION SERVICES, LLC. (2.32)
WOLFE CONSTRUCTION GROUP, INC. (0.95)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.33)
TEXOP CONSTRUCTION (0.45)
MORRIS COUNTY CONTRACTORS, LLC (1.40)
STRIPING TECHNOLOGY, L.P. (2.48)
BOWMAN ENGINEERING & CONSULTING, INC. (0.06)
LS HIGHWAY PRODUCTS, INC. (2.80)
SOUTH TEXAS PAINTING COMPANY (0.04)
TORO BRAVO CONSTRUCTION, LLC (0.16)
AARON CONCRETE CONTRACTORS, L.P. (1.28)
ROYAL REBAR (0.19)
SOUTHEAST GRINDING & GROOVING, LLC (0.04)
Contract #08183210
Totals16738120.3377343.6216661661.4699.5

CountyCHEROKEE
HighwayUS 69
FromUS 175
ToLINCOLN ST.
CSJ0191-02-068
Proj IDF 2021(511)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
131127.09185256.8599.9
CountyCHEROKEE
HighwayUS 69
FromLINCOLN ST
ToCANADA ST
CSJ0199-01-085
Proj IDF 2021(511)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
670932.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0191-02-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213226
Totals802060.0456877.00185256.8523.0

CountySMITH
HighwayFM 2493
FromFM 2813 IN GRESHAM, S
ToFM 346 IN FLINT
CSJ0191-03-081
Proj IDSTP 2013(215)
Work TypeGR,FLX BS,ACP,CULV EXT&RPLCMT,SIGNS
 
2.24114458790.4813971549.5595.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-17-18
Work Began04-12-19
Work Completed
Time Computed00-00-00
Contract Working Days506
Addl Days Granted0
Working Days Charged458
Percent Time Used90
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0191-03-081
AREA WIDE PROTECTIVE, INC. (0.36)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.43)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (22.60)
STRIPING TECHNOLOGY, L.P. (1.95)
TEXAS ORGANIC ENTERPRISES, LTD (3.45)
DUSTROL, INC. (0.68)
MARCOM"S MOWING SERVICE, LLC (0.24)
RELIABLE CONCRETE CUTTING LLC (0.03)
TEX OP CONSTRUCTION, LP (0.05)
Contract #07183036
Totals14458790.488892.4013971549.5595.9

CountyHENDERSON
HighwayUS 175
FromSH 19/SL 7 IN ATHENS, SE
ToFM 804
CSJ0198-01-031
Proj IDNH 2020(009)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.30112138162.7712631342.0999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-19
Work Began12-19-19
Work Completed
Time Computed00-00-00
Contract Working Days262
Addl Days Granted19
Working Days Charged272
Percent Time Used96
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-031
AREA WIDE PROTECTIVE, INC. (0.18)
A BROTHERS MILLING, LLC (1.55)
MASSEY CONTRACTORS, LLC (3.08)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.42)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.73)
STRIPING TECHNOLOGY, L.P. (2.04)
TOTAL HIGHWAY MAINTENANCE, LLC (0.05)
L.L. TRUCKING (0.14)
PATTERSON"S COMPLETE TREE SERVICE LLC (0.06)
DUSTROL, INC. (0.12)
Contract #09193207
Totals12138162.77126229.0612631342.0999.9

CountyCHEROKEE
HighwaySH 204
FromUS 79 IN JACKSONVILLE, SE
ToSH 110
CSJ0198-07-014
Proj IDSTP 1902(166)
Work TypeSP2
 
10.70413705298.2812182377.8289.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-19
Work Began11-20-19
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged227
Percent Time Used110
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-07-014
PANOLA SIGN & BARRICADE, INC. (0.35)
LONGVIEW BRIDGE AND ROAD, LTD. (12.58)
ISAACS CONSTRUCTION SERVICES LLC (4.37)
SOUTHWEST ENVIRONMENT SERIVES, LLC (3.30)
A R BROTHERS CONSTRUCTION SERVICES, INC. (4.31)
STRIPING TECHNOLOGY, L.P. (1.05)
STRIPE-A-ZONE, INC. (0.15)
COLLIER-MANPOWER, INC. (0.00)
DUSTIN ALLEN, INC. (1.13)
REYNOLDS & KAY, LTD. (4.57)
R & G CONSTRUCTION, LLC (0.25)
B & E CONSTRUCTION INC (0.00)
Contract #07193205
Totals13705298.2816221.5612182377.8289.0

CountyCHEROKEE
HighwayUS 69
FromNACOGDOCHES ST (0.1 MI S OF US79),S
ToTENA(.1 MI S OF FM768)IN JACK'VILLE
CSJ0199-01-084
Proj IDNH 1902(286)
Work TypePED
 
0.916502100.00510037.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-19
Work Began02-24-20
Work Completed
Time Computed00-00-00
Contract Working Days231
Addl Days Granted0
Working Days Charged231
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0199-01-084
TOTAL HIGHWAY MAINTENANCE, LLC (2.61)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.41)
STRIPING TECHNOLOGY, L.P. (0.94)
Contract #08193034
Totals502100.005700.00510037.0299.9

CountyANDERSON
HighwayUS 79
FromUS 79 AT SOUTH LP 256
To.
CSJ0205-07-078
Proj IDSTP 2020(878)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200320892.25331419.5099.9
CountyANDERSON
HighwaySL 256
FromAT FM 322
ToIN PALESTINE
CSJ0520-09-052
Proj IDSTP 2020(878)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20085525.0067028.0078.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-21-20
Work Began11-02-20
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged72
Percent Time Used83
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-078
CARTHAGE DRILLING, INC. (5.27)
PANOLA SIGN & BARRICADE, INC. (1.88)
Contract #06203234
Totals406417.255900.00398447.5098.0

CountyANDERSON
HighwayUS 79
From0.5 MI NE OF SL 256 IN PALESTINE, NE
To2.8 MI NE OF FM 2574(S)
CSJ0206-01-050
Proj IDNH 1902(161)
Work TypeSP2
 
19.71114425842.227519126.9352.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began01-06-20
Work Completed
Time Computed00-00-00
Contract Working Days405
Addl Days Granted0
Working Days Charged347
Percent Time Used85
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0206-01-050
CHEROKEE SERVICES (0.20)
ISAACS CONSTRUCTION SERVICES LLC (1.76)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.22)
PANOLA SIGN & BARRICADE, INC. (0.52)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (20.05)
SOUTHWEST ENVIRONMENT SERIVES, LLC (2.08)
STRIPE-A-ZONE, INC. (0.21)
STRIPING TECHNOLOGY, L.P. (1.21)
R & G CONSTRUCTION, LLC (10.13)
REYNOLDS & KAY, LTD. (6.10)
Contract #07193006
Totals14425842.22582952.107519126.9352.1

CountyCHEROKEE
HighwayUS 79
From2.8 MI W OF SH110 (C-S BREAK), W
To3.5 MI E OF SH204,MUD CRK RELIEF BR
CSJ0206-04-042
Proj IDNH 2019(733)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.4138163209.188015775.5998.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-21-19
Work Began06-26-19
Work Completed
Time Computed00-00-00
Contract Working Days367
Addl Days Granted0
Working Days Charged352
Percent Time Used95
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0206-04-042
CHEROKEE SERVICES (1.31)
ISAACS CONSTRUCTION SERVICES LLC (1.60)
R & G CONSTRUCTION, LLC (22.44)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.23)
PANOLA SIGN & BARRICADE, INC. (0.36)
STRIPE-A-ZONE, INC. (0.14)
STRIPING TECHNOLOGY, L.P. (1.59)
SOUTHWEST ENVIRONMENT SERIVES, LLC (2.13)
REYNOLDS & KAY, LTD. (7.57)
Contract #04193011
Totals8163209.185909.908015775.5998.1

page 1 | page 2 | page 3