Monthly State Let Construction Report For Tyler District As Of Nov 10, 2024 Page 6 Of 6

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwaySL 323
From.3 MI N OF SH31, ELM ST IN WEST TYLER, N
To0.25 MI E OF US 69
CSJ2075-01-058
Proj IDC 2075-1-58
Work TypeOVERLAY
 
4548986.944766379.5699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-23
Work Began09-11-23
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged89
Percent Time Used61
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2075-01-058
MORRIS COUNTY CONTRACTORS, L.L.C. (0.30)
PANOLA SIGN & BARRICADE, INC. (0.69)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03)
STRIPING TECHNOLOGY, L.P. (4.79)
TRUE ROADS CONSTRUCTION, LLC (4.06)
Contract #02233020
Totals4548986.941205833.484766379.5699.9

CountyGREGG
HighwaySL 281
From0.2 MI W OF FM 2208
ToHARRISON CL
CSJ2642-01-049
Proj IDSTP 2B23(070)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
225254.70238234.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-23
Work Began09-20-23
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged23
Percent Time Used51
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2642-01-049
FLEX SUPPLY, LLC (2.42)
MORRIS COUNTY CONTRACTORS, L.L.C. (12.93)
Contract #08233267
Totals225254.700.00238234.4099.9

CountyRUSK
HighwayFM 2658
FromFM 2658
ToBRIDGE REPLACEMENT
CSJ2653-01-016
Proj IDBR 2B23(067)
Work TypeBRIDGE REPLACEMENT
 
3094483.612172704.0470.5
CountyRUSK
HighwayFM 2658
From1.571 MI S OF SH 43
To0.427 MILES N OF FM 1251
CSJ2653-01-017
Proj IDF 2B23(068)
Work TypeREHABILITATION OF EXISTING ROAD
 
6517754.743472787.1653.2
Work Order09-07-23
Work Began03-19-24
Work Completed
Time Computed10-09-23
Contract Working Days220
Addl Days Granted0
Working Days Charged122
Percent Time Used55
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2653-01-016
TEX OP CONSTRUCTION, LP (0.13)
FLEX SUPPLY, LLC (0.13)
STRIPING TECHNOLOGY, L.P. (1.64)
SCOTT DERR PAINTING CO, LLC (0.28)
PENHALL COMPANY (0.04)
A. E. MOORE CONSTRUCTION, INC. (2.92)
JE CASEY, LLC (2.93)
REYNOLDS & KAY, LTD. (5.81)
Contract #08233009
Totals9612238.35828702.565645491.2058.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6