Monthly State Let Construction Report For Tyler District As Of Nov 10, 2024 Page 5 Of 6

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwayCR
FromRATTLESNAKE CR
To.
CSJ0910-16-154
Proj IDBR 2022(769)
Work TypeBRIDGE REPLACEMENT
 
468056.50395348.9784.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-23
Work Began01-29-24
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged59
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-154
AWP SAFETY (0.90)
TEXANA LAND & ASPHALT, INC. (9.57)
Contract #05233050
Totals468056.500.00395348.9784.4

CountySMITH
HighwayCR
FromSTR NO 104, CR 35, HITTS CREEK TRIB
To.
CSJ0910-16-156
Proj IDBR 2022(748)
Work TypeBRIDGE REPLACEMENT
 
4280740.253493092.8381.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-23
Work Began09-05-23
Work Completed
Time Computed00-00-00
Contract Working Days523
Addl Days Granted0
Working Days Charged200
Percent Time Used38
Contractor(s)
BAKER & COMPANY CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-156
A. L. HELMCAMP, INC. (0.49)
FLEX SUPPLY, LLC (0.70)
NEED GRASS NOW LLC (0.47)
TEXANA LAND & ASPHALT, INC. (7.45)
FORTSON CONTRACTING, INC. (7.00)
JM YANEZ CONSTRUCTION, INC. (26.83)
COLD CREEK CONSTRUCTION, LTD (2.12)
CARTHAGE DRILLING, LLC (4.59)
STRIPING TECHNOLOGY, L.P. (0.13)
Contract #06233420
Totals4280740.253149.003493092.8381.6

CountySMITH
HighwayVA
FromSTEWART PARK
ToPEETE ELEMENTARY
CSJ0910-16-162
Proj IDSTP 2023(201)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
2988318.622384516.8479.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-13-23
Work Began10-03-23
Work Completed
Time Computed00-00-00
Contract Working Days209
Addl Days Granted0
Working Days Charged192
Percent Time Used91
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-162
PATTERSON"S COMPLETE TREE SERVICE LLC (4.14)
CAP RIVER LLC (2.50)
ISAACS CONSTRUCTION SERVICES LLC (2.48)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.78)
PANOLA SIGN & BARRICADE, INC. (0.88)
STRIPING TECHNOLOGY, L.P. (2.62)
J. H. ODEN CONTRACTING COMPANY (1.54)
Contract #08233233
Totals2988318.6236614.802384516.8479.7

CountySMITH
HighwayCS
FromN BROADWAY
ToAT W 26TH ST
CSJ0910-16-163
Proj IDSTP 2023(726)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
95960.0092558.7596.4
CountySMITH
HighwayCS
FromSHILOH RD
ToGRANDE BLVD
CSJ0910-16-164
Proj IDSTP 2023(726)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
643977.00626114.8397.2
Work Order06-14-23
Work Began07-21-23
Work Completed
Time Computed07-21-23
Contract Working Days64
Addl Days Granted0
Working Days Charged63
Percent Time Used98
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-163
STRIPING TECHNOLOGY, L.P. (58.60)
FLEX SUPPLY, LLC (1.31)
Contract #05233047
Totals739937.000.00718673.5897.1

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN SMITH COUNTY
To.
CSJ0910-16-166
Proj IDSTP 2023(729)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
551528.50560610.5099.9
CountyWOOD
HighwayVA
FromVARIOUS LOCATIONS IN
ToWOOD CO
CSJ0910-35-040
Proj IDSTP 2023(729)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
374185.50368585.5098.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-23
Work Began09-12-23
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged53
Percent Time Used84
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-166
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05233240
Totals925714.000.00929196.0099.9

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN
ToTYLER STATE PARK
CSJ0910-16-168
Proj IDC 910-16-168
Work TypeTEXAS PARK AND WILDLIFE
 
921722.85985545.5999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-12-23
Work Began03-08-23
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged123
Percent Time Used100
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-168
STRIPING TECHNOLOGY, L.P. (0.52)
PANOLA SIGN & BARRICADE, INC. (0.92)
ISAACS CONSTRUCTION SERVICES LLC (0.62)
INNOVATIVE ROADWAY SOLUTIONS, LLC (17.28)
Contract #12223024
Totals921722.850.00985545.5999.9

CountySMITH
HighwayCR ETC
From@ SAMUEL DR
To.
CSJ0910-16-171
Proj IDSTP 2023(830)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
203413.500.000.0
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed09-21-24
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-171
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243230
Totals203413.500.000.000.0

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE CITY OF TYLER
CSJ0910-16-178
Proj IDSTP 2024(808)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1451085.001215464.0083.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-25-24
Work Began07-15-24
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged53
Percent Time Used72
Contractor(s)
SYNERGY SIGNS & SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-178
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243034
Totals1451085.0025624.001215464.0083.7

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN SMITH COUNTY
To.
CSJ0910-16-180
Proj IDSTP 2025(155)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
299532.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-180
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243225
Totals299532.500.000.000.0

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN THE TYLER DISTRICT
To.
CSJ0910-16-181
Proj IDSTP 2B23(178)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
143045.00142425.0099.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-23
Work Began01-02-24
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged10
Percent Time Used66
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-181
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08233065
Totals143045.000.00142425.0099.5

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN SMITH COUNTY
To.
CSJ0910-16-182
Proj IDSTP 2024(336)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
232606.44210471.9590.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-23
Work Began02-20-24
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged20
Percent Time Used60
Contractor(s)
SNOWHILL CONTRACTING LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-182
FLEX SUPPLY, LLC (2.36)
Contract #11233221
Totals232606.440.00210471.9590.4

CountySMITH
HighwayCS
FromGLENEAGLES DR.
ToSHADY OAKS DR
CSJ0910-16-183
Proj IDSTP 2B23(179)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
108505.50109123.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began12-05-23
Work Completed
Time Computed00-00-00
Contract Working Days13
Addl Days Granted0
Working Days Charged12
Percent Time Used92
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-183
AWP SAFETY (4.60)
STRIPING TECHNOLOGY, L.P. (18.25)
Contract #08233064
Totals108505.500.00109123.5099.9

CountySMITH
HighwayVA
FromAT VARIOUS LOCATIONS
ToIN TYLER
CSJ0910-16-187
Proj IDF 2B24(310)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
865454.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-187
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243027
Totals865454.000.000.000.0

CountyCHEROKEE
HighwayVA
FromVARIOUS LOCATIONS IN
ToCHEROKEE CO
CSJ0910-36-134
Proj IDSTP 2B23(066)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
532752.50401423.2277.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-23
Work Began08-26-24
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged58
Percent Time Used145
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0910-36-134
BEST LAND CLEARING LLC (11.88)
Contract #08233260
Totals532752.5037985.46401423.2277.4

CountyCHEROKEE
HighwayVA
FromVARIOUS ROADS
ToIN CITY OF JACKSONVILLE
CSJ0910-36-137
Proj IDSTP 2025(022)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
159987.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RISE UP CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-36-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243238
Totals159987.100.000.000.0

CountyVAN ZANDT
HighwayFM 859
FromSH 19
ToUS 80
CSJ1171-01-022
Proj IDSTP 2022(813)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3629409.253947739.9799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-22
Work Began10-17-22
Work Completed
Time Computed00-00-00
Contract Working Days166
Addl Days Granted13
Working Days Charged179
Percent Time Used100
Contractor(s)
BAKER & COMPANY CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1171-01-022
TEXANA LAND & ASPHALT, INC. (12.92)
LINEAR TRAFFIC MARKINGS LLC (0.29)
J. H. ODEN CONTRACTING COMPANY (1.48)
FORTSON CONTRACTING, INC. (2.83)
JM YANEZ CONSTRUCTION, INC. (20.17)
FLEX SUPPLY, LLC (0.44)
DUSTROL, INC. (0.38)
COLD CREEK CONSTRUCTION, LTD (10.48)
NEED GRASS NOW LLC (0.96)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (0.55)
Contract #08223219
Totals3629409.250.003947739.9799.9

CountyVAN ZANDT
HighwayFM 1255
FromIH 20
ToSH 110
CSJ1322-02-017
Proj IDF 2024(023)
Work TypeREHABILITATION OF EXISTING ROAD
 
17084796.247900589.2846.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-12-23
Work Began11-15-23
Work Completed
Time Computed00-00-00
Contract Working Days363
Addl Days Granted0
Working Days Charged165
Percent Time Used45
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1322-02-017
DUSTIN ALLEN, INC. (0.56)
TRUE ROADS CONSTRUCTION, LLC (10.52)
STRIPING TECHNOLOGY, L.P. (2.35)
TEX OP CONSTRUCTION, LP (0.36)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.81)
FLEX SUPPLY, LLC (0.18)
PATTERSON"S COMPLETE TREE SERVICE LLC (0.98)
ISAACS CONSTRUCTION SERVICES LLC (0.45)
Contract #09233206
Totals17084796.241051866.317900589.2846.2

CountyVAN ZANDT
HighwayFM 1651
FromSH 198 E.
ToSH 19
CSJ1671-02-012
Proj IDC 1671-2-12
Work TypeREHABILITATION OF EXISTING ROAD
 
10542338.89712506.416.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-12-24
Work Began08-19-24
Work Completed
Time Computed00-00-00
Contract Working Days279
Addl Days Granted0
Working Days Charged45
Percent Time Used16
Contractor(s)
BAKER & COMPANY CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1671-02-012
TEXANA LAND & ASPHALT, INC. (43.95)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.74)
JM YANEZ CONSTRUCTION, INC. (10.49)
FLEX SUPPLY, LLC (0.17)
DUSTROL, INC. (0.20)
PROFESSIONAL TRAFFIC CONTROL LLC (0.13)
CATOCON, INC. (1.73)
STRIPING TECHNOLOGY, L.P. (1.29)
NEED GRASS NOW LLC (2.48)
Contract #05243207
Totals10542338.89191542.16712506.416.7

CountyGREGG
HighwayFM 2206
From2.05 MI E OF SH 42 (FISHER RD), E
ToSL 281 IN LONGVIEW
CSJ2073-01-009
Proj IDSTP 2013(212)
Work TypeWIDEN NON-FREEWAY
 
15164540.8914298333.4396.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-09-20
Work Began07-06-20
Work Completed
Time Computed00-00-00
Contract Working Days302
Addl Days Granted89
Working Days Charged679
Percent Time Used173
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2073-01-009
ISAACS CONSTRUCTION SERVICES LLC (0.73)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.25)
PANOLA SIGN & BARRICADE, INC. (0.34)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.43)
STRIPING TECHNOLOGY, L.P. (2.10)
WITHERS CONSTRUCTION, LLC (0.74)
CARTHAGE DRILLING, INC. (0.08)
REYNOLDS & KAY, LTD. (0.16)
Contract #04203004
Totals15164540.89884580.0714298333.4396.7

CountyGREGG
HighwayFM 2206
FromSH 42, E
To1.6 MI W OF SL281(FISHER RD)IN LGVW
CSJ2073-01-010
Proj IDSTP 2020(788)
Work TypeWIDEN NON-FREEWAY
 
13220500.1312884736.6099.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-20
Work Began11-09-20
Work Completed
Time Computed00-00-00
Contract Working Days396
Addl Days Granted25
Working Days Charged650
Percent Time Used154
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2073-01-010
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.58)
STRIPING TECHNOLOGY, L.P. (2.11)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.23)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.05)
PANOLA SIGN & BARRICADE, INC. (0.28)
ISAACS CONSTRUCTION SERVICES LLC (0.81)
TORO BRAVO CONSTRUCTION, LLC (0.00)
REYNOLDS & KAY, LTD. (0.12)
PENHALL COMPANY (0.10)
TEX OP CONSTRUCTION, LP (0.13)
Contract #08203005
Totals13220500.13944.2012884736.6099.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6