Detail Letting Schedule for Hidalgo County (FY 2006)
Detail Letting Schedule for Hidalgo County (FY 2006) | ||||
Last Update: Monday, August 28, 2006 |
Hidalgo County (FY 2006) |
CCSJ: 0039-17-159 | |||
District: | Pharr | Let Date: | JUL 2006 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | C 39-17-159 | CSJ: | 0039-17-159 |
Description: | GOVERNOR'S COMMUNITY ACHIEVEMENT AWARD | Handling Code: |
|
Limits From: | AT THE INTRSCTN OF US 83 & FM 2220 | Fund Cat: | 10 |
Limits To: | . | Estimate: | $285,544 |
Length: | 0.5 Miles | Actual: | $354,066 |
District: | Pharr | Let Date: | JUL 2006 |
Highway: | FM 2220 | Let Status: | Actual |
Project ID: | C 2094-1-41 | CSJ: | 2094-01-041 |
Description: | SIDEWALK AND PEDESTRIAN IMPROVEMENTS | Handling Code: |
|
Limits From: | BUS 83 | Fund Cat: | 11 |
Limits To: | EXPRESSWAY 83 IN MCALLEN | Estimate: | $140,049 |
Length: | 1.0 Miles | Actual: | $193,180 |
Bid Tabulations Back... |
Totals for 0039-17-159 | ||
---|---|---|---|
Length: | 1.5 Miles | ||
Estimate: | $425,593 | ||
Actual: | $547,246 | ||
CCSJ: 0255-07-110 | |||
District: | Pharr | Let Date: | MAR 2006 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | MG 2005(523) | CSJ: | 0255-07-110 |
Description: | WIDEN TO 6 LANES | Handling Code: |
|
Limits From: | BUSINESS 281 SOUTH | Fund Cat: | 2 |
Limits To: | SH 107 SOUTH | Estimate: | $38,661,535 |
Length: | 3.1 Miles | Actual: | $45,941,811 |
Back... |
Totals for 0255-07-110 | ||
Length: | 3.1 Miles | ||
Estimate: | $38,661,535 | ||
Actual: | $45,941,811 | ||
CCSJ: 0669-03-012 | |||
District: | Pharr | Let Date: | SEP 2005 |
Highway: | FM 2221 | Let Status: | Actual |
Project ID: | STP 2004(622) | CSJ: | 0669-03-012 |
Description: | REHABILITATE PAVEMENT AND ADD SHOULDERS | Handling Code: |
|
Limits From: | (CITRUS CITY) 0.80 MI W OF FM 492 | Fund Cat: | 1 |
Limits To: | INTERSECTION @ JARA CHINAS RD. | Estimate: | $3,945,640 |
Length: | 5.4 Miles | Actual: | $4,387,802 |
District: | Pharr | Let Date: | SEP 2005 |
Highway: | FM 2221 | Let Status: | Actual |
Project ID: | STP 2004(622) | CSJ: | 2416-02-004 |
Description: | REHABILITATE PAVEMENT AND ADD SHOULDERS | Handling Code: |
|
Limits From: | INTERSECTION OF SEVEN MILE RD., S | Fund Cat: | 1 |
Limits To: | INTERSECTION OF US 83 IN LA JOYA | Estimate: | $3,957,581 |
Length: | 6.3 Miles | Actual: | $4,229,691 |
Back... |
Totals for 0669-03-012 | ||
Length: | 11.7 Miles | ||
Estimate: | $7,903,221 | ||
Actual: | $8,617,493 | ||
CCSJ: 0921-00-061 | |||
District: | Pharr | Let Date: | OCT 2005 |
Highway: | VA | Let Status: | Actual |
Project ID: | C 921-00-61 | CSJ: | 0921-00-061 |
Description: | NON - SITE SPECIFIC TRAFFIC SIGNALS | Handling Code: |
|
Limits From: | DISTRICTWIDE AT VARIOUS LOCATIONS | Fund Cat: | 1 |
Limits To: | . | Estimate: | $887,602 |
Length: | 0.1 Miles | Actual: | $939,283 |
Back... |
Totals for 0921-00-061 | ||
Length: | 0.1 Miles | ||
Estimate: | $887,602 | ||
Actual: | $939,283 | ||
CCSJ: 0921-00-063 | |||
District: | Pharr | Let Date: | JUL 2006 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2006(665) | CSJ: | 0921-00-063 |
Description: | FY 2006 REHABILITATION OF TRAFFIC SIGNALS_NON - SITE SPECIFIC | Handling Code: |
|
Limits From: | DISTRICT WIDE | Fund Cat: | 1 |
Limits To: | . | Estimate: | $1,072,747 |
Length: | 0.0 Miles | Actual: | $904,015 |
Bid Tabulations Back... |
Totals for 0921-00-063 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,072,747 | ||
Actual: | $904,015 | ||
CCSJ: 0921-02-102 | |||
District: | Pharr | Let Date: | MAR 2006 |
Highway: | CR | Let Status: | Actual |
Project ID: | DMO 2005(235) | CSJ: | 0921-02-102 |
Description: | WIDEN TO 4 LANES | Handling Code: |
|
Limits From: | SH 495 | Fund Cat: | 7 |
Limits To: | OWASSA ROAD | Estimate: | $7,062,096 |
Length: | 2.5 Miles | Actual: | $6,029,975 |
Back... |
Totals for 0921-02-102 | ||
Length: | 2.5 Miles | ||
Estimate: | $7,062,096 | ||
Actual: | $6,029,975 | ||
CCSJ: 0921-02-109 | |||
District: | Pharr | Let Date: | JUN 2006 |
Highway: | CR | Let Status: | Actual |
Project ID: | STP 2006(584)SRS | CSJ: | 0921-02-109 |
Description: | SIDEWALK IMPROVEMENTS | Handling Code: |
|
Limits From: | SCHUERBACH ROAD S OF BUS 83 | Fund Cat: | 9 |
Limits To: | . | Estimate: | $51,158 |
Length: | 0.2 Miles | Actual: | $55,075 |
District: | Pharr | Let Date: | JUN 2006 |
Highway: | CR | Let Status: | Actual |
Project ID: | STP 2006(584)SRS | CSJ: | 0921-02-110 |
Description: | SIDEWALK AND CROSSWALK IMPROVEMENTS | Handling Code: |
|
Limits From: | ON LA HOMA ROAD CITY OF PALMVIEW | Fund Cat: | 9 |
Limits To: | . | Estimate: | $51,913 |
Length: | 0.3 Miles | Actual: | $58,181 |
Bid Tabulations Back... |
Totals for 0921-02-109 | ||
Length: | 0.5 Miles | ||
Estimate: | $103,071 | ||
Actual: | $113,256 | ||
CCSJ: 0921-02-174 | |||
District: | Pharr | Let Date: | MAR 2006 |
Highway: | CR | Let Status: | Actual |
Project ID: | HP 2006(622) | CSJ: | 0921-02-174 |
Description: | WIDEN TO 4 LANES | Handling Code: |
|
Limits From: | SH 495 | Fund Cat: | 10 |
Limits To: | OWASSA ROAD | Estimate: | $1,900,000 |
Length: | 2.5 Miles | Actual: | $1,900,000 |
Back... |
Totals for 0921-02-174 | ||
Length: | 2.5 Miles | ||
Estimate: | $1,900,000 | ||
Actual: | $1,900,000 | ||
CCSJ: 1228-03-027 | |||
District: | Pharr | Let Date: | AUG 2006 |
Highway: | FM 1015 | Let Status: | Actual |
Project ID: | SFT 1228-3-27 | CSJ: | 1228-03-027 |
Description: | INSTALL TRAFFIC SIGNAL, ADD THROUGH LANES & CONTINOUS LEFT | Handling Code: |
|
Limits From: | MILE 12 N ROAD (1.6 MI N OF US 83) | Fund Cat: | 7 |
Limits To: | MILE 9 N ROAD (4.6 MI N OF US 83) | Estimate: | $9,546,159 |
Length: | 3.1 Miles | Actual: | $11,277,854 |
Bid Tabulations Award Status Back... |
Totals for 1228-03-027 | ||
Length: | 3.1 Miles | ||
Estimate: | $9,546,159 | ||
Actual: | $11,277,854 | ||
CCSJ: 1802-01-029 | |||
District: | Pharr | Let Date: | MAR 2006 |
Highway: | FM 1924 | Let Status: | Actual |
Project ID: | STP 2006(374)SFT | CSJ: | 1802-01-029 |
Description: | IMPROVE TRAFFIC SIGNAL, ADD THROUGH LANES AND CONTINUOUS | Handling Code: |
|
Limits From: | SH 107, EAST | Fund Cat: | 7 |
Limits To: | 0.03 MILE WEST OF FM 494 | Estimate: | $9,865,304 |
Length: | 2.5 Miles | Actual: | $9,868,293 |
Back... |
Totals for 1802-01-029 | ||
Length: | 2.5 Miles | ||
Estimate: | $9,865,304 | ||
Actual: | $9,868,293 | ||
CCSJ: 1803-02-019 | |||
District: | Pharr | Let Date: | OCT 2005 |
Highway: | FM 1925 | Let Status: | Actual |
Project ID: | STP 99(376)MM | CSJ: | 1803-02-019 |
Description: | WIDEN TO 4 LANE DIVIDED | Handling Code: |
|
Limits From: | BUS 281 | Fund Cat: | 7 |
Limits To: | US 281 | Estimate: | $2,550,680 |
Length: | 0.5 Miles | Actual: | $2,640,714 |
District: | Pharr | Let Date: | OCT 2005 |
Highway: | FM 1925 | Let Status: | Actual |
Project ID: | STP 2005(966)SFT | CSJ: | 1803-02-022 |
Description: | CONSTRUCT PAVED SHOULDERS, ADD THROUGH LANE AND INSTALL | Handling Code: |
|
Limits From: | US 281 | Fund Cat: | 7 |
Limits To: | KENYON RD. | Estimate: | $6,739,342 |
Length: | 1.9 Miles | Actual: | $5,918,789 |
Back... |
Totals for 1803-02-019 | ||
Length: | 2.4 Miles | ||
Estimate: | $9,290,022 | ||
Actual: | $8,559,503 | ||
CCSJ: 1804-01-058 | |||
District: | Pharr | Let Date: | FEB 2006 |
Highway: | SP 115 | Let Status: | Actual |
Project ID: | CL 1804-1-58 | CSJ: | 1804-01-058 |
Description: | LANDSCAPE AND IRRIGATION IMPROVEMENTS | Handling Code: |
|
Limits From: | ON SP 115,1.2 MILES NORTH OF BU 281 | Fund Cat: | 10 |
Limits To: | (COMA STREET) IN HIDALGO, TEXAS | Estimate: | $41,168 |
Length: | 0.3 Miles | Actual: | $54,521 |
Back... |
Totals for 1804-01-058 | ||
Length: | 0.3 Miles | ||
Estimate: | $41,168 | ||
Actual: | $54,521 | ||
CCSJ: 1939-01-046 | |||
District: | Pharr | Let Date: | JAN 2006 |
Highway: | FM 2061 | Let Status: | Actual |
Project ID: | C 1939-1-46 | CSJ: | 1939-01-046 |
Description: | WIDEN TO 4 LANE | Handling Code: |
|
Limits From: | SH 107 N | Fund Cat: | 11 |
Limits To: | FM 1925 (MONTE CRISTO RD) | Estimate: | $5,590,970 |
Length: | 2.5 Miles | Actual: | $5,307,361 |
Back... |
Totals for 1939-01-046 | ||
Length: | 2.5 Miles | ||
Estimate: | $5,590,970 | ||
Actual: | $5,307,361 | ||
CCSJ: 3343-04-010 | |||
District: | Pharr | Let Date: | DEC 2005 |
Highway: | FM 1425 | Let Status: | Actual |
Project ID: | STP 2006(078) | CSJ: | 3343-02-014 |
Description: | REHABILITATING PAVEMENT & ADDING SHOULDERS | Handling Code: |
|
Limits From: | WILLACY/CAM COUNTY LINE (FM 2629) | Fund Cat: | 1 |
Limits To: | SH 186 | Estimate: | $913,134 |
Length: | 9.0 Miles | Actual: | $888,253 |
District: | Pharr | Let Date: | DEC 2005 |
Highway: | FM 1425 | Let Status: | Actual |
Project ID: | STP 2006(078) | CSJ: | 3343-03-001 |
Description: | REHABILITATION PAVEMENT & ADDING | Handling Code: |
|
Limits From: | HIDALGO/CAM COUNTY LINE | Fund Cat: | 1 |
Limits To: | 0.2 MI. N. TO WILLACY/CAM CTY LINE | Estimate: | $21,697 |
Length: | 0.2 Miles | Actual: | $21,777 |
District: | Pharr | Let Date: | DEC 2005 |
Highway: | FM 1425 | Let Status: | Actual |
Project ID: | STP 2006(078) | CSJ: | 3343-04-010 |
Description: | REHABILITATION PAVEMENT & ADD SHOULDERS | Handling Code: |
|
Limits From: | SH 107 | Fund Cat: | 1 |
Limits To: | 5.9 MILES NORTH | Estimate: | $750,680 |
Length: | 5.9 Miles | Actual: | $717,981 |
Back... |
Totals for 3343-04-010 | ||
Length: | 15.1 Miles | ||
Estimate: | $1,685,511 | ||
Actual: | $1,628,011 |
|
|