Detail Letting Schedule for Collin County (FY 2010)
Detail Letting Schedule for Collin County (FY 2010) | ||||
Last Update: Tuesday, November 2, 2010 |
Collin County (FY 2010) |
CCSJ: 0047-04-021 | |||
District: | Dallas | Let Date: | NOV 2009 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | STP 2010(332)SB | CSJ: | 0047-04-021 |
Description: | ADD NB AND SB LEFT TURN LANES | Handling Code: |
|
Limits From: | AT FM 455 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $157,341 |
Length: | 0.2 Miles | Actual: | $180,942 |
Back... |
Totals for 0047-04-021 | ||
---|---|---|---|
Length: | 0.2 Miles | ||
Estimate: | $157,341 | ||
Actual: | $180,942 | ||
CCSJ: 0047-05-043 | |||
District: | Dallas | Let Date: | AUG 2010 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | BR 2011(145) | CSJ: | 0047-05-041 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT EAST FORK OF TRINITY RIVER RELIE | Fund Cat: | 6 |
Limits To: | . | Estimate: | $1,152,069 |
Length: | 0.1 Miles | Actual: | $1,064,249 |
District: | Dallas | Let Date: | AUG 2010 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | BR 2011(145) | CSJ: | 0047-05-043 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT EAST FORK OF TRINITY RIVER RELIE | Fund Cat: | 6 |
Limits To: | . | Estimate: | $3,986,600 |
Length: | 0.3 Miles | Actual: | $3,646,805 |
District: | Dallas | Let Date: | AUG 2010 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | STP 2011(146) | CSJ: | 0047-05-047 |
Description: | RECONSTRUCT AND WIDEN SHOULDERS OF EXISTING ROADWAY | Handling Code: |
|
Limits From: | AT EAST FORK TRINITY RIVER | Fund Cat: | 1 |
Limits To: | . | Estimate: | $1,583,371 |
Length: | 0.4 Miles | Actual: | $1,498,474 |
Bid Tabulations Back... |
Totals for 0047-05-043 | ||
Length: | 0.8 Miles | ||
Estimate: | $6,722,040 | ||
Actual: | $6,209,528 | ||
CCSJ: 0047-06-144 | |||
District: | Dallas | Let Date: | JUL 2010 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | C 47-6-144 | CSJ: | 0047-06-144 |
Description: | EXTEND EXISTING ITS NETWORK | Handling Code: |
|
Limits From: | EXCHANGE PARKWAY IN ALLEN | Fund Cat: | 10 |
Limits To: | WILSON CREEK IN MCKINNEY | Estimate: | $642,309 |
Length: | 5.1 Miles | Actual: | $353,896 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | C 47-14-66 | CSJ: | 0047-14-066 |
Description: | EXTEND EXISTING ITS NETWORK | Handling Code: |
|
Limits From: | WILSON CREEK IN MCKINNEY | Fund Cat: | 10 |
Limits To: | US 380 | Estimate: | $216,382 |
Length: | 2.2 Miles | Actual: | $154,710 |
Back... |
Totals for 0047-06-144 | ||
Length: | 7.3 Miles | ||
Estimate: | $858,691 | ||
Actual: | $508,606 | ||
CCSJ: 0047-14-065 | |||
District: | Dallas | Let Date: | MAY 2010 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | C 47-14-65 | CSJ: | 0047-14-065 |
Description: | RECONSTRUCT AND WIDEN FROM 4 TO 8 LANES WITH 3 LANE | Handling Code: |
|
Limits From: | NORTH OF US 380 | Fund Cat: | 10 |
Limits To: | SOUTH OF BLOOMDALE IN MCKINNEY | Estimate: | $30,498,475 |
Length: | 1.3 Miles | Actual: | $24,888,311 |
Back... |
Totals for 0047-14-065 | ||
Length: | 1.3 Miles | ||
Estimate: | $30,498,475 | ||
Actual: | $24,888,311 | ||
CCSJ: 0091-05-058 | |||
District: | Dallas | Let Date: | APR 2010 |
Highway: | SH 289 | Let Status: | Actual |
Project ID: | NH 2010(735) | CSJ: | 0091-05-058 |
Description: | LANDSCAPE DEVELOPMENT TO INCLUDE TREE PLANTING | Handling Code: |
|
Limits From: | MCCALLUM BLVD (COLLIN C/L) | Fund Cat: | 10 |
Limits To: | DALLAS CITY LIMITS (NORTH) | Estimate: | $91,517 |
Length: | 1.9 Miles | Actual: | $79,363 |
District: | Dallas | Let Date: | APR 2010 |
Highway: | SH 289 | Let Status: | Actual |
Project ID: | NH 2010(735) | CSJ: | 0091-06-056 |
Description: | LANDSCAPE DEVELOPMENT TO INCLUDE TREE PLANTING | Handling Code: |
|
Limits From: | MCCALLUM BLVD (COLLIN C/L) | Fund Cat: | 10 |
Limits To: | ARAPAHO RD | Estimate: | $61,530 |
Length: | 1.7 Miles | Actual: | $55,040 |
Back... |
Totals for 0091-05-058 | ||
Length: | 3.6 Miles | ||
Estimate: | $153,047 | ||
Actual: | $134,403 | ||
CCSJ: 0135-04-028 | |||
District: | Dallas | Let Date: | SEP 2009 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | C 135-4-28 | CSJ: | 0135-04-028 |
Description: | WIDEN EXISTING RURAL 2 LANE HIGHWAY TO 4 LANE DIVIDED | Handling Code: |
|
Limits From: | 0.929 MI W OF CR 557 (LAKE LAVON) | Fund Cat: | 10 |
Limits To: | WEST OF CR 608 (IN FARMERSVILLE) | Estimate: | $24,633,664 |
Length: | 3.0 Miles | Actual: | $19,981,329 |
Back... |
Totals for 0135-04-028 | ||
Length: | 3.0 Miles | ||
Estimate: | $24,633,664 | ||
Actual: | $19,981,329 | ||
CCSJ: 0135-05-023 | |||
District: | Dallas | Let Date: | JUL 2010 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | C 135-5-23 | CSJ: | 0135-05-023 |
Description: | RECONSTRUCT EXISTING 2 LANES TO 4 LANES DIVIDED | Handling Code: |
|
Limits From: | EAST OF FLOYD RD | Fund Cat: | 10 |
Limits To: | CR 698 (HUNT COUNTY LINE) | Estimate: | $17,575,880 |
Length: | 3.2 Miles | Actual: | $16,564,930 |
Back... |
Totals for 0135-05-023 | ||
Length: | 3.2 Miles | ||
Estimate: | $17,575,880 | ||
Actual: | $16,564,930 | ||
CCSJ: 0387-05-019 | |||
District: | Dallas | Let Date: | SEP 2009 |
Highway: | FM 982 | Let Status: | Actual |
Project ID: | STP 2010(037)ES | CSJ: | 0387-05-019 |
Description: | RECONSTRUCT RURAL 2 LANE HIGHWAY TO 2 LANE URBAN WITH | Handling Code: |
|
Limits From: | US 380 | Fund Cat: | 1 |
Limits To: | 0.1 MI SOUTH OF CR 400 | Estimate: | $5,762,212 |
Length: | 1.1 Miles | Actual: | $4,887,963 |
Back... |
Totals for 0387-05-019 | ||
Length: | 1.1 Miles | ||
Estimate: | $5,762,212 | ||
Actual: | $4,887,963 | ||
CCSJ: 0619-03-048 | |||
District: | Dallas | Let Date: | APR 2010 |
Highway: | FM 544 | Let Status: | Actual |
Project ID: | STP 2010(836) | CSJ: | 0619-03-048 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | AT FM 1378 INTERSECTION | Fund Cat: | 11 |
Limits To: | . | Estimate: | $1,068,990 |
Length: | 0.0 Miles | Actual: | $858,870 |
Back... |
Totals for 0619-03-048 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,068,990 | ||
Actual: | $858,870 | ||
CCSJ: 0918-24-040 | |||
District: | Dallas | Let Date: | NOV 2009 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 94(179)ESTE | CSJ: | 0918-24-040 |
Description: | CONSTRUCT 10 FOOT WIDE CONCRETE WALKWAY | Handling Code: |
LC |
Limits From: | ALMA ROAD | Fund Cat: | 9 |
Limits To: | 0.24 MILES SOUTH OF RENNER ROAD | Estimate: | $2,370,000 |
Length: | 2.2 Miles | Actual: | $2,099,994 |
Back... |
Totals for 0918-24-040 | ||
Length: | 2.2 Miles | ||
Estimate: | $2,370,000 | ||
Actual: | $2,099,994 | ||
CCSJ: 0918-24-119 | |||
District: | Dallas | Let Date: | DEC 2009 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2005(145)MM | CSJ: | 0918-24-119 |
Description: | OHIO TO RASOR PKWY: WIDEN 2 TO 4 LN DIVIDED URBAN; | Handling Code: |
LC |
Limits From: | MCDERMOTT RD FROM COIT RD | Fund Cat: | 7 |
Limits To: | OHIO DR IN CITY OF PLANO | Estimate: | $3,052,265 |
Length: | 1.5 Miles | Actual: | $2,038,822 |
District: | Dallas | Let Date: | DEC 2009 |
Highway: | VA | Let Status: | Actual |
Project ID: | RW 918-24-165 | CSJ: | 0918-24-165 |
Description: | RIGHT OF WAY ACQUISITION, UTILITY ADJUSTMENTS AND RELOCATION | Handling Code: |
LC |
Limits From: | MCDERMOTT RD FROM COIT RD | Fund Cat: | 7 |
Limits To: | OHIO DR IN CITY OF PLANO | Estimate: | |
Length: | 1.5 Miles | Actual: | $93,447 |
Back... |
Totals for 0918-24-119 | ||
Length: | 3.0 Miles | ||
Estimate: | $3,052,265 | ||
Actual: | $2,132,269 | ||
CCSJ: 0918-24-151 | |||
District: | Dallas | Let Date: | SEP 2009 |
Highway: | VA | Let Status: | Actual |
Project ID: | CM 2009(956) | CSJ: | 0918-24-151 |
Description: | CONSTRUCT 709 SPACE PARK - AND - RIDE STATION IN THE RICHARDSON / | Handling Code: |
TR |
Limits From: | RICHARDSON/DALLAS COUNTY AREA | Fund Cat: | 5 |
Limits To: | PARK-AND-RIDE | Estimate: | $1,481,250 |
Length: | 0.0 Miles | Actual: | $1,481,250 |
Back... |
Totals for 0918-24-151 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,481,250 | ||
Actual: | $1,481,250 | ||
CCSJ: 0918-24-163 | |||
District: | Dallas | Let Date: | AUG 2010 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2011(477)MM | CSJ: | 0918-24-163 |
Description: | CITYWIDE SIGNAL DATA COLLECTION FOR SIGNAL RETIMING | Handling Code: |
XX |
Limits From: | VARIOUS LOCATIONS IN CITY OF PLANO | Fund Cat: | 7 |
Limits To: | . | Estimate: | $196,000 |
Length: | 0.0 Miles | Actual: | $196,000 |
Back... |
Totals for 0918-24-163 | ||
Length: | 0.0 Miles | ||
Estimate: | $196,000 | ||
Actual: | $196,000 | ||
CCSJ: 0918-24-164 | |||
District: | Dallas | Let Date: | MAR 2010 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2010(621) | CSJ: | 0918-24-164 |
Description: | FULL DEPTH REPAIR OF CONCRETE PAVEMENT | Handling Code: |
|
Limits From: | ON VARIOUS ROADWAYS | Fund Cat: | 1 |
Limits To: | IN COLLIN COUNTY | Estimate: | $634,194 |
Length: | 0.0 Miles | Actual: | $515,276 |
Back... |
Totals for 0918-24-164 | ||
Length: | 0.0 Miles | ||
Estimate: | $634,194 | ||
Actual: | $515,276 | ||
CCSJ: 1012-02-023 | |||
District: | Dallas | Let Date: | AUG 2010 |
Highway: | FM 545 | Let Status: | Actual |
Project ID: | BR 2011(086) | CSJ: | 1012-02-022 |
Description: | REPLACE BRIDGE | Handling Code: |
|
Limits From: | AT CLEMMONS CREEK RELIEF | Fund Cat: | 6 |
Limits To: | . | Estimate: | $414,636 |
Length: | 0.1 Miles | Actual: | $354,807 |
District: | Dallas | Let Date: | AUG 2010 |
Highway: | FM 545 | Let Status: | Actual |
Project ID: | BR 2011(086) | CSJ: | 1012-02-023 |
Description: | REPLACE BRIDGE | Handling Code: |
|
Limits From: | AT CLEMMONS CREEK | Fund Cat: | 6 |
Limits To: | . | Estimate: | $464,518 |
Length: | 0.1 Miles | Actual: | $411,476 |
District: | Dallas | Let Date: | AUG 2010 |
Highway: | FM 545 | Let Status: | Actual |
Project ID: | C 1012-2-27 | CSJ: | 1012-02-027 |
Description: | RECONSTRUCT AND WIDEN EXISTING ROADWAY | Handling Code: |
|
Limits From: | SH 121 | Fund Cat: | 1 |
Limits To: | FM 2933 | Estimate: | $1,204,935 |
Length: | 0.7 Miles | Actual: | $1,107,717 |
Bid Tabulations Back... |
Totals for 1012-02-023 | ||
Length: | 0.9 Miles | ||
Estimate: | $2,084,089 | ||
Actual: | $1,874,000 | ||
CCSJ: 1013-01-024 | |||
District: | Dallas | Let Date: | MAY 2010 |
Highway: | FM 546 | Let Status: | Actual |
Project ID: | C 1013-1-24 | CSJ: | 1013-01-024 |
Description: | CONSTRUCT 2 LANE ROADWAY ON NEW ALIGNMENT | Handling Code: |
NC |
Limits From: | 0.758 MI WEST OF CR 317 | Fund Cat: | 10 |
Limits To: | 0.192 MI EAST OF CR 317 | Estimate: | $3,292,821 |
Length: | 1.4 Miles | Actual: | $2,609,837 |
Back... |
Totals for 1013-01-024 | ||
Length: | 1.4 Miles | ||
Estimate: | $3,292,821 | ||
Actual: | $2,609,837 | ||
CCSJ: 1013-01-025 | |||
District: | Dallas | Let Date: | AUG 2010 |
Highway: | FM 546 | Let Status: | Actual |
Project ID: | C 1013-1-25 | CSJ: | 1013-01-025 |
Description: | RECONSTRUCT EXISTING 6 LANE UNDIVIDED URBAN TO 4 LANE | Handling Code: |
|
Limits From: | SH 5 IN MCKINNEY | Fund Cat: | 1 |
Limits To: | AIRPORT RD | Estimate: | $3,859,730 |
Length: | 1.1 Miles | Actual: | $3,276,548 |
Bid Tabulations Back... |
Totals for 1013-01-025 | ||
Length: | 1.1 Miles | ||
Estimate: | $3,859,730 | ||
Actual: | $3,276,548 | ||
CCSJ: 1013-01-029 | |||
District: | Dallas | Let Date: | JUL 2010 |
Highway: | US 377 | Let Status: | Actual |
Project ID: | STP 2011(022)HES | CSJ: | 0081-03-050 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | SH 114 | Fund Cat: | 8 |
Limits To: | 0.27 MILE NORTH OF JOHNSON LN | Estimate: | $67,693 |
Length: | 9.5 Miles | Actual: | $65,212 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | STP 2011(022)HES | CSJ: | 0134-09-064 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | WISE COUNTY LINE | Fund Cat: | 8 |
Limits To: | 0.25 MILE EAST OF FM 156 | Estimate: | $68,845 |
Length: | 8.5 Miles | Actual: | $66,802 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | STP 2011(022)HES | CSJ: | 0135-10-049 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | US 377 | Fund Cat: | 1 |
Limits To: | COLLIN COUNTY LINE | Estimate: | $228,771 |
Length: | 10.2 Miles | Actual: | $172,135 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | FM 51 | Let Status: | Actual |
Project ID: | STP 2011(022)HES | CSJ: | 0312-02-015 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | WISE COUNTY LINE | Fund Cat: | 8 |
Limits To: | COOKE COUNTY LINE | Estimate: | $26,762 |
Length: | 3.7 Miles | Actual: | $25,341 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | FM 455 | Let Status: | Actual |
Project ID: | STP 2011(022)HES | CSJ: | 0816-02-071 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | 1ST ST IN SANGER (NEAR BNSF RR) | Fund Cat: | 8 |
Limits To: | US 377 | Estimate: | $91,266 |
Length: | 13.1 Miles | Actual: | $87,527 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | FM 546 | Let Status: | Actual |
Project ID: | STP 2010(981)HES | CSJ: | 1013-01-029 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | WEST OF CR 317 | Fund Cat: | 8 |
Limits To: | WEST OF THE CROSSINGS | Estimate: | $72,577 |
Length: | 3.3 Miles | Actual: | $39,527 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | FM 407 | Let Status: | Actual |
Project ID: | STP 2011(022)HES | CSJ: | 1310-01-039 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | FM 156 | Fund Cat: | 8 |
Limits To: | FM 1830 | Estimate: | $75,468 |
Length: | 9.8 Miles | Actual: | $71,596 |
District: | Dallas | Let Date: | JUL 2010 |
Highway: | FM 1378 | Let Status: | Actual |
Project ID: | STP 2010(981)HES | CSJ: | 1392-01-033 |
Description: | INSTALL CENTERLINE RUMBLE STRIPS | Handling Code: |
|
Limits From: | SOUTH OF FM 2514 | Fund Cat: | 8 |
Limits To: | SH 5 | Estimate: | $102,850 |
Length: | 10.1 Miles | Actual: | $95,415 |
Back... |
Totals for 1013-01-029 | ||
Length: | 68.2 Miles | ||
Estimate: | $734,232 | ||
Actual: | $623,555 |
|
|