Detail Letting Schedule for Collin County (FY 2022)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Collin County (FY 2022) |
CCSJ: 0047-04-036 |
|||
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0047-04-036 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | PENNSYLVANIA AVE | Fund Cat: | 1 |
Limits To: | FM 455 | ESTIMATE: | $1,258,871 |
Length: | 3.5 | Actual | $1,710,092 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0047-04-037 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | ROSAMOND PKWY | Fund Cat: | 1 |
Limits To: | COLLIN COUNTY LINE | ESTIMATE: | $174,033 |
Length: | 2.6 | Actual | $144,203 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | SH 342 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0048-03-096 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | FM 664 | ESTIMATE: | $291,009 |
Length: | 3.5 | Actual | $246,046 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | BU 377E | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0081-14-008 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 377S | Fund Cat: | 1 |
Limits To: | US 377N | ESTIMATE: | $174,538 |
Length: | 2.9 | Actual | $158,106 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | F 2022(042) | CSJ: | 0092-03-056 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SOUTH OF RISINGER RD | Fund Cat: | 1 |
Limits To: | DALLAS CL | ESTIMATE: | $356,717 |
Length: | 4.7 | Actual | $327,094 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | F 2022(042) | CSJ: | 0092-04-079 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SOUTH OF HAMPER RD | Fund Cat: | 1 |
Limits To: | SOUTH OF RISINGER RD | ESTIMATE: | $158,138 |
Length: | 2.3 | Actual | $148,336 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 688 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0095-11-010 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 80 | Fund Cat: | 1 |
Limits To: | FM 548 | ESTIMATE: | $160,541 |
Length: | 2.3 | Actual | $131,350 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | SH 22 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0121-04-028 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 667 | Fund Cat: | 1 |
Limits To: | NW CR 1190 | ESTIMATE: | $887,064 |
Length: | 12.5 | Actual | $807,676 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | SS 263 | Let Status: | Actual |
Project ID: | C 162-10-2 | CSJ: | 0162-10-002 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | AT SH 31 | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $4,425 |
Length: | 0.1 | Actual | $4,097 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | SH 34 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0173-04-061 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | IH 20 | Fund Cat: | 1 |
Limits To: | SH 243 | ESTIMATE: | $495,514 |
Length: | 8.6 | Actual | $479,898 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | F 2022(042) | CSJ: | 0195-02-082 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | COOKE COUNTY LINE | ESTIMATE: | $861,739 |
Length: | 11.2 | Actual | $792,801 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 878 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0596-04-044 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | WAXAHACHIE / WYATT ST | Fund Cat: | 1 |
Limits To: | US 287 | ESTIMATE: | $34,735 |
Length: | 0.7 | Actual | $28,864 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 633 | Let Status: | Actual |
Project ID: | C 719-1-19 | CSJ: | 0719-01-019 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 31 | Fund Cat: | 1 |
Limits To: | FM 1393 | ESTIMATE: | $230,752 |
Length: | 4.8 | Actual | $208,538 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 667 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0747-01-019 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | NAVARRO CL | Fund Cat: | 1 |
Limits To: | SH 34 | ESTIMATE: | $289,622 |
Length: | 6.2 | Actual | $259,401 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 148 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0751-02-030 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | CREEKVIEW LN | Fund Cat: | 1 |
Limits To: | FM 1390 S | ESTIMATE: | $495,418 |
Length: | 5.9 | Actual | $498,555 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 875 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0815-08-038 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 157 | Fund Cat: | 1 |
Limits To: | FM 663 | ESTIMATE: | $269,240 |
Length: | 5.2 | Actual | $241,748 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 455 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0816-04-107 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | DENTON CL | Fund Cat: | 1 |
Limits To: | EAST OF FM 428 | ESTIMATE: | $237,005 |
Length: | 4.8 | Actual | $219,145 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | VA | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0918-00-355 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | VARIOUS HIGHWAYS | Fund Cat: | 1 |
Limits To: | IN DALLAS DISTRICT | ESTIMATE: | $1,676,800 |
Length: | 0.0 | Actual | $1,770,707 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 1394 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 0999-01-047 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 641 | Fund Cat: | 1 |
Limits To: | IH 45 | ESTIMATE: | $432,821 |
Length: | 9.0 | Actual | $405,671 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 543 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1012-01-019 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | COWAN RD | Fund Cat: | 1 |
Limits To: | 770 W OF TRINITY FALLS PKWY | ESTIMATE: | $438,763 |
Length: | 6.8 | Actual | $410,565 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 981 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1012-03-025 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1562 | Fund Cat: | 1 |
Limits To: | COLLIN CL | ESTIMATE: | $209,898 |
Length: | 3.6 | Actual | $199,290 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 547 | Let Status: | Actual |
Project ID: | C 1014-1-18 | CSJ: | 1014-01-018 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 380 | Fund Cat: | 1 |
Limits To: | SH 6 | ESTIMATE: | $334,140 |
Length: | 7.9 | Actual | $311,266 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 548 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1014-02-047 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 276 | Fund Cat: | 1 |
Limits To: | IH 30 E FRONTAGE | ESTIMATE: | $214,777 |
Length: | 4.9 | Actual | $180,098 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 35 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1017-02-013 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | IH 30 | Fund Cat: | 1 |
Limits To: | ROCKWALL CL | ESTIMATE: | $97,670 |
Length: | 1.6 | Actual | $79,765 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 983 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1048-01-032 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 813 | Fund Cat: | 1 |
Limits To: | FM 664 | ESTIMATE: | $514,135 |
Length: | 7.6 | Actual | $495,497 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 660 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1048-02-036 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 813 | Fund Cat: | 1 |
Limits To: | BI 45J | ESTIMATE: | $495,922 |
Length: | 9.7 | Actual | $470,015 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 664 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1051-01-058 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | BU 287R | Fund Cat: | 1 |
Limits To: | US 287 | ESTIMATE: | $74,051 |
Length: | 1.6 | Actual | $66,987 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 987 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1217-02-018 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 148 | Fund Cat: | 1 |
Limits To: | N. JEFFERSON ST. | ESTIMATE: | $304,525 |
Length: | 7.3 | Actual | $255,803 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 1388 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1217-03-025 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 34 BYPASS | Fund Cat: | 1 |
Limits To: | FM 148 | ESTIMATE: | $275,946 |
Length: | 6.0 | Actual | $230,804 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 1182 | Let Status: | Actual |
Project ID: | C 1317-2-12 | CSJ: | 1317-02-012 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | IH 45 | Fund Cat: | 1 |
Limits To: | FM 85 | ESTIMATE: | $214,825 |
Length: | 4.2 | Actual | $211,954 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 308 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 1393-01-019 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 66 | Fund Cat: | 1 |
Limits To: | US 77 | ESTIMATE: | $395,790 |
Length: | 10.7 | Actual | $361,619 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 3486 | Let Status: | Actual |
Project ID: | C 1494-3-3 | CSJ: | 1494-03-003 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 986 | Fund Cat: | 1 |
Limits To: | SH 34 | ESTIMATE: | $131,434 |
Length: | 2.5 | Actual | $122,632 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 1126 | Let Status: | Actual |
Project ID: | C 1724-1-19 | CSJ: | 1724-01-019 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 31 | Fund Cat: | 1 |
Limits To: | SH 22 | ESTIMATE: | $365,546 |
Length: | 7.4 | Actual | $332,208 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 2452 | Let Status: | Actual |
Project ID: | C 1724-2-15 | CSJ: | 1724-02-015 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 709 | Fund Cat: | 1 |
Limits To: | SH 31 | ESTIMATE: | $258,859 |
Length: | 5.2 | Actual | $234,570 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 2930 | Let Status: | Actual |
Project ID: | C 1724-3-10 | CSJ: | 1724-03-010 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 55 | Fund Cat: | 1 |
Limits To: | FM 1126 | ESTIMATE: | $282,298 |
Length: | 6.3 | Actual | $268,827 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 1827 | Let Status: | Actual |
Project ID: | C 1746-1-28 | CSJ: | 1746-01-028 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 75 | Fund Cat: | 1 |
Limits To: | FM 545 | ESTIMATE: | $254,298 |
Length: | 5.2 | Actual | $234,441 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 2478 | Let Status: | Actual |
Project ID: | C 2351-2-16 | CSJ: | 2351-02-016 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | N OF FM 1461 | Fund Cat: | 1 |
Limits To: | FM 455 | ESTIMATE: | $272,323 |
Length: | 5.9 | Actual | $243,600 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 2450 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 2353-02-027 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | GREGORY RD | Fund Cat: | 1 |
Limits To: | FM 156 | ESTIMATE: | $477,008 |
Length: | 11.5 | Actual | $432,685 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 1394 | Let Status: | Actual |
Project ID: | C 2462-1-11 | CSJ: | 2462-01-011 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FREESTONE CL | Fund Cat: | 1 |
Limits To: | FM 641 | ESTIMATE: | $143,251 |
Length: | 3.2 | Actual | $129,480 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 2728 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 2512-02-011 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 80 | Fund Cat: | 1 |
Limits To: | FM 429 | ESTIMATE: | $140,061 |
Length: | 2.9 | Actual | $132,425 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 455 | Let Status: | Actual |
Project ID: | C 2845-1-23 | CSJ: | 2845-01-023 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 121 | Fund Cat: | 1 |
Limits To: | FM 2862 | ESTIMATE: | $68,083 |
Length: | 1.5 | Actual | $61,513 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 2860 | Let Status: | Actual |
Project ID: | C 2846-1-7 | CSJ: | 2846-01-007 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 175 | Fund Cat: | 1 |
Limits To: | FM 1895 | ESTIMATE: | $145,384 |
Length: | 2.8 | Actual | $131,767 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 2932 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 2981-01-008 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 741 | Fund Cat: | 1 |
Limits To: | FM 148 | ESTIMATE: | $166,491 |
Length: | 3.6 | Actual | $154,287 |
District: | DALLAS | Let Date: | Oct 2021 |
Highway: | FM 3163 | Let Status: | Actual |
Project ID: | F 2022(041) | CSJ: | 3226-01-009 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | IH 35 | Fund Cat: | 1 |
Limits To: | FM 2164 | ESTIMATE: | $163,304 |
Length: | 2.7 | Actual | $153,837 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 0047-04-036 | ||
---|---|---|---|
Length: | 223.4 | ||
Estimate: | $14,927,765 | ||
Actual: | $14,488,264 | ||
CCSJ: 0047-05-059 |
|||
District: | DALLAS | Let Date: | Aug 2022 |
Highway: | SH 5 | Let Status: | Tentative |
Project ID: | CSJ: | 0047-05-059 | |
Description: | TRANSPORTATION NON-ROADWAY | Handling Code: | XX |
Limits From: | LOUISIANA STREET | Fund Cat: | 7 |
Limits To: | VIRGINIA STREET | ESTIMATE: | $2,000,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0047-05-059 | ||
Length: | 0 | ||
Estimate: | $2,000,000 | ||
Actual: | |||
CCSJ: 0047-06-164 |
|||
District: | DALLAS | Let Date: | Jan 2022 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | CC 47-6-164 | CSJ: | 0047-06-164 |
Description: | INTERSECTION IMPROVEMENT | Handling Code: | LC |
Limits From: | AT ALLEN DRIVE | Fund Cat: | 3 |
Limits To: | . | ESTIMATE: | $3,327,650 |
Length: | 0.6 | Actual | $3,672,466 |
Back... | Totals for 0047-06-164 | ||
Length: | 0.6 | ||
Estimate: | $3,327,650 | ||
Actual: | $3,672,466 | ||
CCSJ: 0619-03-061 |
|||
District: | DALLAS | Let Date: | May 2022 |
Highway: | FM 544 | Let Status: | Actual |
Project ID: | CM 2022(513) | CSJ: | 0619-03-061 |
Description: | INTERSECTION IMPROVEMENT | Handling Code: | |
Limits From: | AT FM 1378 (COUNTRY CLUB ROAD) | Fund Cat: | 5 |
Limits To: | . | ESTIMATE: | $3,560,439 |
Length: | 0.4 | Actual | $4,293,544 |
District: | DALLAS | Let Date: | May 2022 |
Highway: | FM 544 | Let Status: | Actual |
Project ID: | STP 2021(368) | CSJ: | 0619-03-063 |
Description: | RIGHT OF WAY | Handling Code: | |
Limits From: | AT FM 1378 (COUNTRY CLUB ROAD) | Fund Cat: | ROW |
Limits To: | . | ESTIMATE: | $558,200 |
Length: | 0.4 | Actual | $277,041 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0619-03-061 | ||
Length: | 0.8 | ||
Estimate: | $4,118,639 | ||
Actual: | $4,570,585 | ||
CCSJ: 0918-24-263 |
|||
District: | DALLAS | Let Date: | Jan 2022 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2021(959)TP | CSJ: | 0918-24-263 |
Description: | TRANSPORTATION NON-ROADWAY | Handling Code: | TR |
Limits From: | SILVER LINE TRAIL BRG N OF E PLANO PKWY | Fund Cat: | 9 |
Limits To: | S OF E PLANO PKWY | ESTIMATE: | $3,639,740 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0918-24-263 | ||
Length: | 0 | ||
Estimate: | $3,639,740 | ||
Actual: | |||
CCSJ: 0918-24-265 |
|||
District: | DALLAS | Let Date: | Aug 2022 |
Highway: | CS | Let Status: | Approved |
Project ID: | F 2022(915) | CSJ: | 0918-24-265 |
Description: | CONSTRUCT NEW ROAD | Handling Code: | LC |
Limits From: | SH 289 (PRESTON ROAD) | Fund Cat: | 3 |
Limits To: | DALLAS NORTH TOLLWAY | ESTIMATE: | $30,000,000 |
Length: | 2.1 | Actual | $0 |
Back... | Totals for 0918-24-265 | ||
Length: | 2.1 | ||
Estimate: | $30,000,000 | ||
Actual: | |||
CCSJ: 0918-24-270 |
|||
District: | DALLAS | Let Date: | Aug 2022 |
Highway: | VA | Let Status: | Tentative |
Project ID: | CSJ: | 0918-24-270 | |
Description: | TRANSPORTATION NON-ROADWAY | Handling Code: | TR |
Limits From: | SILVER LINE FROM DFW AIRPORT | Fund Cat: | 7 |
Limits To: | SHILOH ROAD | ESTIMATE: | $800,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0918-24-270 | ||
Length: | 0 | ||
Estimate: | $800,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |