Monthly State Let Construction Report For Austin District As Of Feb 09, 2018 Page 4 Of 5

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWILLIAMSON
HighwayRM 620
FromRM 2769
ToSH 45
CSJ0683-01-095
Proj IDSTP 2018(405)
Work TypeMILL,SEAL & INLAY
 
5.3801482655.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0683-01-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183235
Totals1482655.750.000.000.0

CountyTRAVIS
HighwayRM 620
From200 FT WEST OF COMANCHE TRAIL
To600 FT EAST OF STEINER RANCH BLVD
CSJ0683-02-068
Proj IDCC 683-2-68
Work TypeINSTALL TRAFFIC SIGNAL
 
0.297181556.90172383.0594.9
Work Order07-11-17
Work Began11-13-17
Work Completed
Time Computed10-09-17
Contract Working Days49
Addl Days Granted0
Working Days Charged35
Percent Time Used71
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0683-02-068
KRL CONSTRUCTION INC. (11.01)
D. I. J. CONSTRUCTION, INC. (4.17)
G. CARTER CONSTRUCTION COMPANY, INC. (21.29)
Contract #06173231
Totals181556.9051542.69172383.0594.9

CountyHAYS
HighwayRM 150
FromCENTER STREET
ToSILVERADO DR.
CSJ0805-04-025
Proj IDSTP 2013(285)MM
Work TypeCONSTRUCT SIDEWALK & BIKE LANES
 
0.612364407.34265364.8587.5
CountyHAYS
HighwayFM 2770
FromFAIRWAY DRIVE
ToBOB SHELTON STADIUM
CSJ3210-01-012
Proj IDSTP 2013(285)MM
Work TypeCONSTRUCT SIDEWALKS & BIKE LANES
 
0.998484671.17442873.1791.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-14-16
Work Began09-06-16
Work Completed
Time Computed08-13-16
Contract Working Days84
Addl Days Granted0
Working Days Charged172
Percent Time Used204
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0805-04-025
F & W ELECTRICAL CONTRACTORS, INC. (6.20)
FLASHER EQUIPMENT COMPANY (2.51)
RICE ENVIRONMENTAL SERVICES (4.91)
Contract #05163235
Totals849078.510.00708238.0289.7

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-319
Proj IDNH 1402(057)
Work TypeFY 2014 SITE-SPECIFIC SIGNALS
 
0.1001113486.771095709.5498.4
Work Order11-04-14
Work Began02-02-15
Work Completed
Time Computed11-20-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-319
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.63)
HIGHWAY 19 CONSTRUCTION, LLC (9.08)
TX DOWN UNDER CONSTRUCTION LLC (4.00)
UNION ELECTRICAL CONTRACTOR, INC. (1.24)
FLASHER EQUIPMENT COMPANY (1.57)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (1.24)
MORGAN UTILITY CONSTRUCTION (1.04)
WG ENGINEERING & CONSTRUCTION, LLC (3.06)
Contract #08143029
Totals1113486.7752148.621095709.5498.4

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-320
Proj IDNH 2014(015)
Work TypeFY 2013 SIGNING
 
0.100452778.70481807.5199.9
Work Order10-07-13
Work Began06-17-14
Work Completed
Time Computed10-23-13
Contract Working Days77
Addl Days Granted0
Working Days Charged29
Percent Time Used37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-320
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09133233
Totals452778.701060.50481807.5199.9

CountyTRAVIS
HighwayVA
FromVARIOUS_ON SYSTEM LOCATIONS
To.
CSJ0914-00-366
Proj IDSTP 1702(553)
Work TypeNON-SITE SPECIFIC ITS MAINT
 
0.003988888.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-366
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173039
Totals988888.500.000.000.0

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-368
Proj IDNH 1602(280)
Work TypeFY 2016 SITE-SPECIFIC SIGNALS
 
0.0031041312.891015310.8598.8
Work Order09-20-16
Work Began01-19-17
Work Completed
Time Computed10-20-16
Contract Working Days150
Addl Days Granted10
Working Days Charged181
Percent Time Used113
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-368
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.20)
M & M STRIPING & POWER WASHING, LLC (14.13)
WG ENGINEERING & CONSTRUCTION, LLC (12.08)
UNION ELECTRICAL CONTRACTOR, INC. (5.89)
H6 BORING, LLC (1.24)
4D UTILITY CONSTRUCTION, LLC (0.61)
AMERICAN LIGHTING AND SIGNALIZATION, LLC (1.11)
Contract #07163030
Totals1041312.8941274.701015310.8598.8

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-369
Proj IDNH 1602(020)
Work TypeFY 2016 NON-SITE SPECIFIC SIGNALS
 
0.0031104881.001067284.9596.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-12-16
Work Began08-23-16
Work Completed
Time Computed06-11-16
Contract Working Days300
Addl Days Granted0
Working Days Charged230
Percent Time Used76
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-369
D. I. J. CONSTRUCTION, INC. (1.16)
G. CARTER CONSTRUCTION COMPANY, INC. (5.37)
Contract #03163231
Totals1104881.000.001067284.9596.5

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN BURNET, LLANO,
ToGILLESPIE & BLANCO COUNTIES
CSJ0914-00-382
Proj IDSTP 2018(406)
Work TypeCONSTRUCT CURB RAMPS
 
0.100626160.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days137
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-382
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183033
Totals626160.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATION IN AUSTIN
ToDISTRICT
CSJ0914-00-391
Proj IDNH 1602(493)
Work TypeTRAFFIC MANAGEMENT SYSTEM
 
0.00311464497.254836649.8342.1
Work Order12-28-16
Work Began05-02-17
Work Completed
Time Computed01-27-17
Contract Working Days360
Addl Days Granted0
Working Days Charged139
Percent Time Used38
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-391
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163208
Totals11464497.25181849.014836649.8342.1

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN THE CITY OF
ToELGIN IN TRAVIS & BASTROP COUNTIES
CSJ0914-00-393
Proj IDSTP 2017(768)TP
Work TypeINSTALL SIDEWALKS
 
0.003496481.3336761.007.4
Work Order11-13-17
Work Began01-12-18
Work Completed
Time Computed01-12-18
Contract Working Days180
Addl Days Granted0
Working Days Charged1
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-393
LONESTAR TRAFFIC SAFETY, LLC (1.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (10.28)
D. I. J. CONSTRUCTION, INC. (0.75)
Contract #10173024
Totals496481.3336761.0036761.007.4

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-395
Proj IDSTP 2017(791)
Work TypeFY 17 NON-SITE SPECIFIC SIGNALS
 
0.0031439774.00955507.1866.3
Work Order04-12-17
Work Began06-21-17
Work Completed
Time Computed06-11-17
Contract Working Days300
Addl Days Granted0
Working Days Charged129
Percent Time Used43
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-395
KRL CONSTRUCTION INC. (8.59)
D. I. J. CONSTRUCTION, INC. (1.82)
G. CARTER CONSTRUCTION COMPANY, INC. (1.37)
Contract #03173204
Totals1439774.00108885.53955507.1866.3

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-396
Proj IDSTP 1702(554)
Work TypeFY 2017 SITE SPECIFIC SIGNALS
 
0.0031663381.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-396
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173219
Totals1663381.120.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON IH35, LP1,SH71
ToUS183 & US290
CSJ0914-00-406
Proj IDNH 1702(582)
Work TypeCONCRETE PAVEMENT REPAIRS
 
0.1001116909.00163621.5714.6
Work Order08-11-17
Work Began10-16-17
Work Completed
Time Computed10-10-17
Contract Working Days730
Addl Days Granted0
Working Days Charged55
Percent Time Used7
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-406
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173246
Totals1116909.008510.00163621.5714.6

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON IH35, LP1,SH71
ToUS183 & US 290
CSJ0914-00-407
Proj IDNH 1702(583)
Work TypeASPHALTIC PAVEMENT REPAIRS
 
0.1002168168.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-407
TEX OP CONSTRUCTION, LP (0.73)
FLASHER EQUIPMENT COMPANY (0.78)
Contract #07173247
Totals2168168.000.000.000.0

CountyTRAVIS
HighwayCR
FromON LUND CARLSON RD AT WILLOW CREEK
ToSTR AA1531002
CSJ0914-04-227
Proj IDBR 2008(234)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.066377671.08316418.6883.7
Work Order08-16-17
Work Began10-23-17
Work Completed
Time Computed09-15-17
Contract Working Days109
Addl Days Granted0
Working Days Charged60
Percent Time Used55
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-227
VOGES DRILLING CO. (3.44)
FLASHER EQUIPMENT COMPANY (2.72)
ENVIRONMENTAL SAFETY SERVICES, INC. (11.40)
LONE STAR PAVING (11.33)
PENHALL COMPANY (AUSTIN) (0.98)
Contract #07173228
Totals377671.0884621.48316418.6883.7

CountyTRAVIS
HighwayCR
FromHAYS C/L (ON FITZHUGH RD)
ToUS 290
CSJ0914-04-289
Proj IDSTP 1602(245)HES
Work TypeINSTALL WARN/GUIDE SIGN/DELINEATOR
 
0.00116803.0014889.0088.6
CountyHAYS
HighwayCR
FromBLANCO C/L ON W FITZHUGH RD
ToTRAVIS C/L
CSJ0914-33-070
Proj IDSTP 2017(895)HES
Work TypeINSTALL WARN/GUIDE SIGN/DELINEATOR
 
0.001132962.00123594.0092.9
Work Order09-28-17
Work Began11-01-17
Work Completed
Time Computed10-28-17
Contract Working Days38
Addl Days Granted0
Working Days Charged36
Percent Time Used94
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-289
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173019
Totals149765.0068836.00138483.0092.4

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN TRAVIS COUNTY
To.
CSJ0914-04-298
Proj IDSTP 1602(290)
Work TypeLANDSCAPING AND IRRIGATION
 
0.0011177598.301021314.0586.7
Work Order08-24-16
Work Began12-19-16
Work Completed
Time Computed09-23-16
Contract Working Days160
Addl Days Granted0
Working Days Charged100
Percent Time Used62
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-298
FLASHER EQUIPMENT COMPANY (0.85)
J & V UTILTIY (1.06)
Contract #07163209
Totals1177598.305900.001021314.0586.7

CountyLEE
HighwayCR
FromON CR 418 AT ALLEN CREEK
ToSTR AA01-81-001
CSJ0914-21-031
Proj IDBR 2016(252)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.064313217.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183011
Totals313217.770.000.000.0

CountyMASON
HighwayCR
FromKATEMCY RD @ DRY PRONG KATEMCY CRK
ToSTR AA0180001
CSJ0914-26-007
Proj IDBR 1402(184)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.064264228.00237415.9289.8
Work Order08-16-17
Work Began11-13-17
Work Completed
Time Computed10-15-17
Contract Working Days63
Addl Days Granted0
Working Days Charged48
Percent Time Used76
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-26-007
D. I. J. CONSTRUCTION, INC. (0.40)
FLASHER EQUIPMENT COMPANY (1.04)
ROADWAY SPECIALTIES, INC. (2.84)
INCE ENTERPRISES, INC. (3.68)
FOUR-B PAVING, INC. (23.25)
Contract #07173011
Totals264228.0044350.12237415.9289.8