Monthly State Let Construction Report For Austin District As Of Apr 10, 2018 Page 4 Of 5

Last Update: Tuesday, April 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-320
Proj IDNH 2014(015)
Work TypeFY 2013 SIGNING
 
0.100452778.70502275.2499.9
Work Order10-07-13
Work Began06-17-14
Work Completed
Time Computed10-23-13
Contract Working Days77
Addl Days Granted0
Working Days Charged29
Percent Time Used37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-320
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09133233
Totals452778.7020467.73502275.2499.9

CountyTRAVIS
HighwayVA
FromVARIOUS_ON SYSTEM LOCATIONS
To.
CSJ0914-00-366
Proj IDSTP 1702(553)
Work TypeNON-SITE SPECIFIC ITS MAINT
 
0.003988888.503000.000.3
Work Order08-08-17
Work Began01-15-18
Work Completed
Time Computed10-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged45
Percent Time Used12
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-366
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173039
Totals988888.503000.003000.000.3

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-368
Proj IDNH 1602(280)
Work TypeFY 2016 SITE-SPECIFIC SIGNALS
 
0.0031041312.891027915.7299.9
Work Order09-20-16
Work Began01-19-17
Work Completed
Time Computed10-20-16
Contract Working Days150
Addl Days Granted10
Working Days Charged181
Percent Time Used113
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-368
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.20)
M & M STRIPING & POWER WASHING, LLC (14.13)
WG ENGINEERING & CONSTRUCTION, LLC (12.08)
UNION ELECTRICAL CONTRACTOR, INC. (5.89)
H6 BORING, LLC (1.24)
4D UTILITY CONSTRUCTION, LLC (0.61)
AMERICAN LIGHTING AND SIGNALIZATION, LLC (1.11)
Contract #07163030
Totals1041312.8912604.871027915.7299.9

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-369
Proj IDNH 1602(020)
Work TypeFY 2016 NON-SITE SPECIFIC SIGNALS
 
0.0031104881.001067284.9596.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-12-16
Work Began08-23-16
Work Completed
Time Computed06-11-16
Contract Working Days300
Addl Days Granted0
Working Days Charged230
Percent Time Used76
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-369
D. I. J. CONSTRUCTION, INC. (1.16)
G. CARTER CONSTRUCTION COMPANY, INC. (5.37)
Contract #03163231
Totals1104881.000.001067284.9596.5

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN BURNET, LLANO,
ToGILLESPIE & BLANCO COUNTIES
CSJ0914-00-382
Proj IDSTP 2018(406)
Work TypeCONSTRUCT CURB RAMPS
 
0.100626160.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days137
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-382
PAVEMENT MARKINGS INC. (1.99)
Contract #01183033
Totals626160.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATION IN AUSTIN
ToDISTRICT
CSJ0914-00-391
Proj IDNH 1602(493)
Work TypeTRAFFIC MANAGEMENT SYSTEM
 
0.00311464497.255541573.8748.3
Work Order12-28-16
Work Began05-02-17
Work Completed
Time Computed01-27-17
Contract Working Days360
Addl Days Granted0
Working Days Charged170
Percent Time Used47
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-391
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163208
Totals11464497.25248175.715541573.8748.3

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN THE CITY OF
ToELGIN IN TRAVIS & BASTROP COUNTIES
CSJ0914-00-393
Proj IDSTP 2017(768)TP
Work TypeINSTALL SIDEWALKS
 
0.003496481.33220697.8544.4
Work Order11-13-17
Work Began01-12-18
Work Completed
Time Computed01-12-18
Contract Working Days180
Addl Days Granted0
Working Days Charged21
Percent Time Used11
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-393
LONESTAR TRAFFIC SAFETY, LLC (1.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (10.28)
D. I. J. CONSTRUCTION, INC. (0.75)
Contract #10173024
Totals496481.33141910.00220697.8544.4

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-395
Proj IDSTP 2017(791)
Work TypeFY 17 NON-SITE SPECIFIC SIGNALS
 
0.0031439774.001141223.6879.2
Work Order04-12-17
Work Began06-21-17
Work Completed
Time Computed06-11-17
Contract Working Days300
Addl Days Granted0
Working Days Charged162
Percent Time Used54
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-395
KRL CONSTRUCTION INC. (8.59)
D. I. J. CONSTRUCTION, INC. (1.82)
G. CARTER CONSTRUCTION COMPANY, INC. (1.37)
Contract #03173204
Totals1439774.0029869.001141223.6879.2

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-396
Proj IDSTP 1702(554)
Work TypeFY 2017 SITE SPECIFIC SIGNALS
 
0.0031663381.12344880.3520.7
Work Order08-22-17
Work Began03-02-18
Work Completed
Time Computed11-20-17
Contract Working Days300
Addl Days Granted0
Working Days Charged16
Percent Time Used5
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-396
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.23)
M & M STRIPING & POWER WASHING, LLC (14.80)
TCB FOUNDATION DRILLERS, INC. (1.48)
J&M TELCOM (3.00)
Contract #07173219
Totals1663381.12344880.35344880.3520.7

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-397
Proj IDSTP 2018(597)
Work TypeFY 2018 NON-SITE SPECIFIC SIGNALS
 
0.0031469946.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-06-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-397
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183006
Totals1469946.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON IH35, LP1,SH71
ToUS183 & US290
CSJ0914-00-406
Proj IDNH 1702(582)
Work TypeCONCRETE PAVEMENT REPAIRS
 
0.1001116909.00178121.5715.9
Work Order08-11-17
Work Began10-16-17
Work Completed
Time Computed10-10-17
Contract Working Days730
Addl Days Granted0
Working Days Charged95
Percent Time Used13
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-406
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173246
Totals1116909.007250.00178121.5715.9

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON IH35, LP1,SH71
ToUS183 & US 290
CSJ0914-00-407
Proj IDNH 1702(583)
Work TypeASPHALTIC PAVEMENT REPAIRS
 
0.1002168168.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-407
TEX OP CONSTRUCTION, LP (0.73)
FLASHER EQUIPMENT COMPANY (0.78)
Contract #07173247
Totals2168168.000.000.000.0

CountyTRAVIS
HighwayCR
FromON LUND CARLSON RD AT WILLOW CREEK
ToSTR AA1531002
CSJ0914-04-227
Proj IDBR 2008(234)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.066377671.08374005.8499.0
Work Order08-16-17
Work Began10-23-17
Work Completed
Time Computed09-15-17
Contract Working Days109
Addl Days Granted0
Working Days Charged84
Percent Time Used77
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-227
VOGES DRILLING CO. (3.44)
FLASHER EQUIPMENT COMPANY (2.72)
ENVIRONMENTAL SAFETY SERVICES, INC. (11.40)
LONE STAR PAVING (11.33)
PENHALL COMPANY (AUSTIN) (0.98)
Contract #07173228
Totals377671.086806.00374005.8499.0

CountyTRAVIS
HighwayCR
FromHAYS C/L (ON FITZHUGH RD)
ToUS 290
CSJ0914-04-289
Proj IDSTP 1602(245)HES
Work TypeINSTALL WARN/GUIDE SIGN/DELINEATOR
 
0.00116803.0015107.0089.9
CountyHAYS
HighwayCR
FromBLANCO C/L ON W FITZHUGH RD
ToTRAVIS C/L
CSJ0914-33-070
Proj IDSTP 2017(895)HES
Work TypeINSTALL WARN/GUIDE SIGN/DELINEATOR
 
0.001132962.00133410.0099.9
Work Order09-28-17
Work Began11-01-17
Work Completed
Time Computed10-28-17
Contract Working Days38
Addl Days Granted0
Working Days Charged38
Percent Time Used100
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-289
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173019
Totals149765.001622.00148517.0099.1

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN TRAVIS COUNTY
To.
CSJ0914-04-298
Proj IDSTP 1602(290)
Work TypeLANDSCAPING AND IRRIGATION
 
0.0011177598.301033114.0587.7
Work Order08-24-16
Work Began12-19-16
Work Completed
Time Computed09-23-16
Contract Working Days160
Addl Days Granted0
Working Days Charged100
Percent Time Used62
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-298
FLASHER EQUIPMENT COMPANY (0.85)
J & V UTILTIY (1.06)
Contract #07163209
Totals1177598.305900.001033114.0587.7

CountyTRAVIS
HighwayCR
FromON TURNERSVILLE RD @ MAHA CRK TRIB
To.
CSJ0914-04-305
Proj IDBR 2018(328)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.055329780.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-305
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183230
Totals329780.760.000.000.0

CountyLEE
HighwayCR
FromON CR 418 AT ALLEN CREEK
ToSTR AA01-81-001
CSJ0914-21-031
Proj IDBR 2016(252)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.064313217.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-031
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.32)
FUQUAY, INC. (1.69)
D. I. J. CONSTRUCTION, INC. (0.80)
LONESTAR TRAFFIC SAFETY, LLC (1.14)
Contract #01183011
Totals313217.770.000.000.0

CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-090
Proj IDPTF 2017(143)
Work TypeREHAB ROADWAY; ADD TWLTL & SHLDRS
 
2.1944540893.021711725.2437.6
CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-096
Proj IDROW 1186-1-96
Work TypeUTILITY ADJUSTMENTS
 
2.1942107410.60518619.4024.6
Work Order02-27-17
Work Began06-05-17
Work Completed
Time Computed03-29-17
Contract Working Days321
Addl Days Granted0
Working Days Charged124
Percent Time Used38
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-090
LONE STAR PAVING (15.32)
ESSL,LLC (6.81)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33)
BRYANT & FREY CONSTRUCTION (0.96)
TRP CONSTRUCTION GROUP, LLC (0.48)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.92)
AUSTIN WOOD RECYCLING (0.71)
OSCAR ORDUNO, INC. (0.67)
Contract #01173041
Totals6648303.62214654.402230344.6433.5

CountyWILLIAMSON
HighwayFM 1660
FromFM 973
ToSH 95
CSJ1200-01-023
Proj IDSTP 2017(949)
Work TypeREHAB RDWY
 
3.3434076992.453379737.0682.8
Work Order05-18-17
Work Began07-17-17
Work Completed
Time Computed07-17-17
Contract Working Days145
Addl Days Granted0
Working Days Charged133
Percent Time Used91
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-01-023
AWP, INC. (0.14)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.86)
FLASHER EQUIPMENT COMPANY (1.68)
MURRAY CONSTRUCTION (0.63)
ROADWAY SPECIALTIES, INC. (6.22)
RUCOBA & MAYA CONSTRUCTION (23.18)
AUSTIN WOOD RECYCLING (0.65)
THE DAVEY TREE EXPERT COMPANY (0.07)
TEXAS CUTTING & CORING, INC. (0.09)
Contract #04173229
Totals4076992.45385333.083379737.0682.8

CountyWILLIAMSON
HighwayFM 973
FromFM 1660
ToTRAVIS C/L
CSJ1200-01-027
Proj IDSTP 2018(599)
Work TypeONE COURSE SURFACE TREATMENT
 
16.3921408397.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days28
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183239
Totals1408397.940.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5