Monthly State Let Construction Report For Austin District As Of Sep 15, 2014 Page 6 Of 8

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway VA
From VARIOUS ON-SYS LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-345
Proj ID NH 2012(379)
Work Type SCHOOL ZONE UPGRADES
 
0.100 287731.00 0.00 278410.88 96.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-12
Work Began 12-03-12
Work Completed  
Time Computed 07-15-12
Contract Working Days 102
Addl Days Granted 4
Working Days Charged 75
Percent Time Used 70
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-345
CODY DRILLING(5.44%)
ESA ENGINEERING, LLC (5.05%)
Contract # 03123023
Totals 287731.00 0.00 278410.88 96.7

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN
To HAYS & TRAVIS COUNTIES
CSJ 0914-00-349
Proj ID STP 2013(793)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 1269800.80 245.15 1318808.10 99.9
Work Order 08-12-13
Work Began 09-03-13
Work Completed  
Time Computed 08-28-13
Contract Working Days 163
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 109
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-349
CLASSIC TEJAS CONSTRUCTION, INC. (4.18%)
PAVEMENT MARKINGS INC. (2.10%)
Contract # 06133221
Totals 1269800.80 245.15 1318808.10 99.9

CountyTRAVIS
Highway VA
From VARIOUS ON-SYSTEM LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-374
Proj ID STP 2013(929)
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 816189.28 34903.00 86213.00 10.5
Work Order 06-05-14
Work Began 00-00-00
Work Completed  
Time Computed 06-21-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-374
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143225
Totals 816189.28 34903.00 86213.00 10.5

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-379
Proj ID STP 2014(723)
Work Type SIGN IMPROVEMENT
 
0.001 266630.98 0.00 0.00 0.0
Work Order 07-18-14
Work Began 00-00-00
Work Completed  
Time Computed 08-03-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-379
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143040
Totals 266630.98 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To ON IH 35 AND ON US 183
CSJ 0914-04-269
Proj ID STP 2012(551)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 775000.00 0.00 669177.84 86.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 08-13-12
Work Completed  
Time Computed 08-13-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 98
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123049
Totals 775000.00 0.00 669177.84 86.3

CountyWILLIAMSON
Highway CR
From ON CR 111 AT NORTH FORK MCNUTT CRK
To (STR AA0535001)
CSJ 0914-05-142
Proj ID BR 1102(561)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.087 609359.30 36301.00 36301.00 5.9
Work Order 05-21-14
Work Began 08-14-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 7
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-142
APAC-TEXAS, INC. ( 20.18%)
D. I. J. CONSTRUCTION, INC.(0.75%)
O & S TRAFFIC SUPPLIES (0.62%)
ROADWAY SPECIALTIES, INC.(5.09%)
Contract # 03143229
Totals 609359.30 36301.00 36301.00 5.9

CountyGILLESPIE
Highway CR
From ON OLD SAN ANTONIO AT PEDERNALES
To STR AA0119002
CSJ 0914-19-022
Proj ID BR 2012(703)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.500 2659843.09 113334.45 910321.49 34.2
Work Order 04-09-14
Work Began 05-05-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 623
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 10
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-022
O & S TRAFFIC SUPPLIES (0.95%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.68%)
ALLEN KELLER COMPANY ( 24.37%)
J R RAMON, INC.(2.72%)
JUST GROOVING, LTD.(0.22%)
ROADWAY SPECIALTIES, INC.(4.79%)
FLASHER EQUIPMENT COMPANY(0.72%)
MESA ROD BUSTERS, INC. (0.25%)
Contract # 02143012
Totals 2659843.09 113334.45 910321.49 34.2

CountyLEE
Highway CR
From ON CR 306 AT MIDDLE YEGUA CREEK
To STR AA01-24-001
CSJ 0914-21-029
Proj ID BR 2012(236)
Work Type REPLACE BRIDGE & APPROACHES
 
0.059 255411.33 0.00 181804.10 99.9
CountyLEE
Highway CR
From ON CR 113 AT ELM CREEK
To STR AA00-34-001
CSJ 0914-21-030
Proj ID BR 2012(235)
Work Type REPLACE BRIDGE & APPROACHES
 
0.072 314588.67 0.00 305693.15 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 08-19-13
Work Completed  
Time Computed 08-18-13
Contract Working Days 98
Addl Days Granted 23
Working Days Charged 181
Percent Time Used 149
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-029
ROADWAY SPECIALTIES, INC.(3.59%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.08%)
BATTEN DRILLING, INC.(7.56%)
JIM"S SAND & GRAVEL(2.05%)
LONE STAR PAVING CO. (5.98%)
Contract # 05133025
Totals 570000.00 0.00 487497.25 99.1

CountyCALDWELL
Highway CR
From ON OAK GROVE RD AT W FORK PLUM CRK
To (STR AA02-28-001)
CSJ 0914-22-056
Proj ID BR 2013(195)
Work Type REPLACE BRIDGE & APPROACHES
 
0.155 656797.82 0.00 84577.74 12.8
CountyCALDWELL
Highway CR
From ON OAK GROVE ROAD (CR 127) @
To TRIBUTARY TO WEST FORK PLUM CREEK
CSJ 0914-22-062
Proj ID CC 914-22-62
Work Type REPLACE STRUCTURE & APPROACHES
 
0.051 160259.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-14
Work Began 09-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-056
O & S TRAFFIC SUPPLIES (0.66%)
CL CONCRETE( 12.36%)
Contract # 05143036
Totals 817057.44 0.00 84577.74 10.3

CountyLLANO
Highway CR
From ON CR 216 AT BOARD BRANCH
To STR AA0552001
CSJ 0914-25-006
Proj ID BR 2011(981)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 226113.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-18-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143026
Totals 226113.43 0.00 0.00 0.0

CountyHAYS
Highway CR
From ON CR 266 AT SAN MARCOS RIVER
To STR AA02-24-001
CSJ 0914-33-035
Proj ID BR 2005(711)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 576253.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-14
Work Began 00-00-00
Work Completed  
Time Computed 07-27-14
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143214
Totals 576253.11 0.00 0.00 0.0

CountyHAYS
Highway VA
From VARIOUS LOCATIONS IN HAYS COUNTY
To ON IH 35 AND SH 80
CSJ 0914-33-063
Proj ID STP 2012(552)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 467144.80 4655.20 469994.41 99.9
Work Order 06-14-12
Work Began 07-09-12
Work Completed  
Time Computed 07-09-12
Contract Working Days 72
Addl Days Granted 6
Working Days Charged 78
Percent Time Used 100
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-063
LONE STAR TRAFFIC SERVICE, INC.(1.37%)
TERRY PRATHER( 16.78%)
Contract # 05123226
Totals 467144.80 4655.20 469994.41 99.9

CountyBLANCO
Highway RM 165
From SL 163
To HAYS C/L
CSJ 0954-02-016
Proj ID STP 2012(553)HRR
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
11.900 816534.84 2718.06 863663.32 99.9
CountyBLANCO
Highway RM 165
From SL 163
To BLANCO/HAYS COUNTY LINE
CSJ 0954-02-017
Proj ID STP 2012(553)HRR
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
11.949 4792086.66 560656.66 5118974.32 99.9
Work Order 07-12-12
Work Began 10-02-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 261
Addl Days Granted 57
Working Days Charged 459
Percent Time Used 144
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0954-02-017
HIGHWAY TECHNOLOGIES, INC. (1.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.76%)
ABC EROSION CONTROL, INC.(0.72%)
AUSTIN WOOD RECYCLING(1.45%)
JMHP, INC. (0.85%)
Contract # 05123212
Totals 5608621.50 563374.72 5982637.64 99.9

CountyGILLESPIE
Highway RM 783
From US 290
To 8.977 MI S OF US 290
CSJ 1135-01-026
Proj ID STP 2013(028)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
8.977 5106864.29 449691.74 4594171.22 94.8
Work Order 04-03-13
Work Began 04-15-13
Work Completed  
Time Computed 04-15-13
Contract Working Days 229
Addl Days Granted 0
Working Days Charged 331
Percent Time Used 144
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026
ROADWAY SPECIALTIES, INC.(3.51%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%)
RELMCO, INC. ( 31.14%)
D. I. J. CONSTRUCTION, INC.(1.16%)
VOGES DRILLING CO. (1.08%)
LONE STAR PAVING COMPANY (2.40%)
Contract # 02133212
Totals 5106864.29 449691.74 4594171.22 94.8

CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-028
Proj ID BR 2013(930)
Work Type REPLACE BRIDGE & APPROACHES
 
1.530 11659867.54 697317.79 2577214.10 22.1
CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-048
Proj ID STP 2012(591)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.530 2188836.25 67223.65 345603.88 15.7
Work Order 02-13-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 19
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
C4 CONSTRUCTION SERVICES, LLC(0.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.67%)
LINDAMOOD DEMOLITION, INC. (0.95%)
MURRAY CONSTRUCTION(0.13%)
ROADWAY SPECIALTIES, INC.(1.54%)
M & M STRIPING & POWER WASHING, LLC(0.43%)
AARON CONCRETE CONTRACTORS, L.P. (0.81%)
AUSTIN WOOD RECYCLING(0.28%)
BRYANT & FREY CONSTRUCTION (1.50%)
TEX OP CONSTRUCTION, LP(0.14%)
APAC-TEXAS, INC. ( 11.02%)
CP REBAR AND PT INSTALLATION (0.46%)
PRIMATE CONSTRUCTION, INC. (0.12%)
MCKINNEY DRILLING COMPANY(2.77%)
TEXAS HIGHWAY WALLS(3.63%)
Contract # 12133203
Totals 13848703.79 764541.44 2922817.98 21.1

CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To 600 FT. SOUTH OF MURCHISON ST.
CSJ 1200-03-045
Proj ID CC 1200-3-45
Work Type ADD CONTINUOUS LEFT TURN LANE
 
0.312 85872.74 0.00 0.00 0.0
CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To DECKER CREEK
CSJ 1200-03-052
Proj ID STP 1402(058)
Work Type REHAB RDWY, ADD 6' SHOULDERS
 
4.911 3246677.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143236
Totals 3332550.36 0.00 0.00 0.0

CountyTRAVIS
Highway FM 973
From 3880 FT SOUTH OF SH 71
To FM 812
CSJ 1200-03-046
Proj ID STP 2014(621)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
3.418 4060301.69 455743.25 455743.25 11.2
Work Order 05-29-14
Work Began 08-07-14
Work Completed  
Time Computed 07-28-14
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 4
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-046
AUSTIN WOOD RECYCLING(1.13%)
CHEROKEE SERVICES(0.13%)
FLASHER EQUIPMENT COMPANY(2.42%)
ROADWAY SPECIALTIES, INC.(7.52%)
TRP CONSTRUCTION GROUP, LLC(0.43%)
RELMCO, INC. ( 13.01%)
HAYWOOD BAKER(4.07%)
THE LEVY COMPANY, L.P. (0.10%)
MURRAY CONSTRUCTION(0.53%)
VOGES DRILLING CO. (1.38%)
Contract # 04143030
Totals 4060301.69 455743.25 455743.25 11.2

CountyTRAVIS
Highway FM 973
From FM 812
To US 183
CSJ 1200-05-016
Proj ID STP 2014(559)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
2.466 3060816.52 284402.52 559098.43 18.2
Work Order 06-16-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 15
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-016
AUSTIN WOOD RECYCLING(1.13%)
D. I. J. CONSTRUCTION, INC.(1.12%)
THE LEVY COMPANY, L.P. (0.14%)
MURRAY CONSTRUCTION(0.88%)
RELMCO, INC. ( 30.62%)
ROADWAY SPECIALTIES, INC.(4.85%)
TRP CONSTRUCTION GROUP, LLC(0.28%)
Contract # 04143018
Totals 3060816.52 284402.52 559098.43 18.2

CountyTRAVIS
Highway SH 45
From LOOP 1
To RM 1826
CSJ 1200-06-010
Proj ID STP 2014(724)
Work Type MILL, SEAL & THIN OVERLAY
 
2.599 1283793.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-14
Work Began 00-00-00
Work Completed  
Time Computed 08-20-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-010
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
D. I. J. CONSTRUCTION, INC.(3.74%)
ROADWAY SPECIALTIES, INC.(4.80%)
Contract # 06143028
Totals 1283793.90 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 487
From SH 195
To 1500 FEET WEST OF CR 233
CSJ 1201-02-019
Proj ID STP 2014(420)
Work Type REHAB RDWY
 
5.303 6128687.87 488048.67 1081536.25 17.6
Work Order 04-16-14
Work Began 06-25-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 287
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 10
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019
AARON CONCRETE CONTRACTORS, L.P. (1.40%)
AUSTIN WOOD RECYCLING(1.19%)
TEXAS HIGHWAY WALLS(5.57%)
R K STEPHENS CONSTRUCTION, LLC (3.21%)
D. I. J. CONSTRUCTION, INC.(0.77%)
J & M CONTRACTING, COMPANY (7.41%)
ROADWAY SPECIALTIES, INC.(2.24%)
Contract # 02143227
Totals 6128687.87 488048.67 1081536.25 17.6