Monthly State Let Construction Report For Austin District As Of Dec 10, 2014 Page 6 Of 8

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-322
Proj ID STP 2013(476)
Work Type FY 2013 NON - SITE SPECIFIC SIGNALS
 
0.100 865508.00 0.00 1627048.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-13
Work Began 06-24-13
Work Completed  
Time Computed 06-06-13
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 278
Percent Time Used 60
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-322
KRL CONSTRUCTION INC.(6.58%)
D. I. J. CONSTRUCTION, INC.(3.40%)
M.G. DRILLING(5.15%)
CHANDLER CONCRETE, INC.(2.13%)
Contract # 03133223
Totals 865508.00 0.00 1627048.40 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-323
Proj ID STP 2014(533)
Work Type FY 2014 NON - SITE SPECIFIC SIGNALS
 
0.100 991388.00 98135.90 445980.40 44.9
Work Order 04-25-14
Work Began 07-21-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 312
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 27
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-323
MG DRILLING(5.08%)
BAILEY H.D.D.(0.91%)
Contract # 03143015
Totals 991388.00 98135.90 445980.40 44.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-324
Proj ID STP 2013(554)
Work Type FY 2013 SITE - SPECIFIC SIGNALS
 
0.100 870431.70 67663.27 773817.83 88.9
Work Order 07-08-13
Work Began 12-02-13
Work Completed  
Time Computed 11-05-13
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 225
Percent Time Used 86
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-324
VACA UNDERGROUND UTILITIES INC (5.67%)
JND CONSTRUCTION CONSULTANTS, LLC( 18.39%)
YORK & YORK FOUNDATION DRILLING, INC.(5.29%)
UNITED PAVEMENT & MARKINGS, LLC(0.00%)
M & M STRIPING & POWER WASHING, LLC(4.60%)
Contract # 04133013
Totals 870431.70 67663.27 773817.83 88.9

CountyTRAVIS
Highway VA
From VARIOUS ON-SYS LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-345
Proj ID NH 2012(379)
Work Type SCHOOL ZONE UPGRADES
 
0.100 287731.00 0.00 278410.88 96.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-12
Work Began 12-03-12
Work Completed  
Time Computed 07-15-12
Contract Working Days 102
Addl Days Granted 4
Working Days Charged 75
Percent Time Used 70
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-345
CODY DRILLING(5.44%)
ESA ENGINEERING, LLC (5.05%)
Contract # 03123023
Totals 287731.00 0.00 278410.88 96.7

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN
To HAYS & TRAVIS COUNTIES
CSJ 0914-00-349
Proj ID STP 2013(793)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 1269800.80 20275.00 1340350.20 100.0
Work Order 08-12-13
Work Began 09-03-13
Work Completed 11-06-14
Time Computed 08-28-13
Contract Working Days 163
Addl Days Granted 15
Working Days Charged 178
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-349
CLASSIC TEJAS CONSTRUCTION, INC. (4.18%)
PAVEMENT MARKINGS INC. (2.10%)
Contract # 06133221
Totals 1269800.80 20275.00 1340350.20 100.0

CountyTRAVIS
Highway VA
From VARIOUS ON-SYSTEM LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-374
Proj ID STP 2013(929)
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 816189.28 3696.70 96392.40 11.8
Work Order 06-05-14
Work Began 00-00-00
Work Completed  
Time Computed 06-21-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 19
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-374
JCD CONSTRUCTION, LLC(0.00%)
Contract # 04143225
Totals 816189.28 3696.70 96392.40 11.8

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-379
Proj ID STP 2014(723)
Work Type SIGN IMPROVEMENT
 
0.001 266630.98 79445.16 146343.36 54.8
Work Order 07-18-14
Work Began 11-03-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 15
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-379
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143040
Totals 266630.98 79445.16 146343.36 54.8

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To ON IH 35 AND ON US 183
CSJ 0914-04-269
Proj ID STP 2012(551)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 775000.00 0.00 669177.84 86.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 08-13-12
Work Completed  
Time Computed 08-13-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 98
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123049
Totals 775000.00 0.00 669177.84 86.3

CountyWILLIAMSON
Highway CR
From ON CR 111 AT NORTH FORK MCNUTT CRK
To (STR AA0535001)
CSJ 0914-05-142
Proj ID BR 1102(561)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.087 609359.30 97188.96 286206.58 46.9
Work Order 05-21-14
Work Began 08-14-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 54
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-142
APAC-TEXAS, INC. ( 20.18%)
D. I. J. CONSTRUCTION, INC.(0.75%)
O & S TRAFFIC SUPPLIES (0.62%)
ROADWAY SPECIALTIES, INC.(5.09%)
CAPITOL CONCRETE CONTRACTORS, INC. (1.56%)
Contract # 03143229
Totals 609359.30 97188.96 286206.58 46.9

CountyGILLESPIE
Highway CR
From ON OLD SAN ANTONIO AT PEDERNALES
To STR AA0119002
CSJ 0914-19-022
Proj ID BR 2012(703)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.500 2659843.09 92347.39 1145138.16 43.0
Work Order 04-09-14
Work Began 05-05-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 623
Addl Days Granted 0
Working Days Charged 117
Percent Time Used 18
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-022
O & S TRAFFIC SUPPLIES (0.95%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.68%)
ALLEN KELLER COMPANY ( 24.37%)
J R RAMON, INC.(2.72%)
JUST GROOVING, LTD.(0.22%)
ROADWAY SPECIALTIES, INC.(4.79%)
FLASHER EQUIPMENT COMPANY(0.72%)
MESA ROD BUSTERS, INC. (0.25%)
Contract # 02143012
Totals 2659843.09 92347.39 1145138.16 43.0

CountyLEE
Highway CR
From ON CR 306 AT MIDDLE YEGUA CREEK
To STR AA01-24-001
CSJ 0914-21-029
Proj ID BR 2012(236)
Work Type REPLACE BRIDGE & APPROACHES
 
0.059 255411.33 0.00 181804.10 99.9
CountyLEE
Highway CR
From ON CR 113 AT ELM CREEK
To STR AA00-34-001
CSJ 0914-21-030
Proj ID BR 2012(235)
Work Type REPLACE BRIDGE & APPROACHES
 
0.072 314588.67 0.00 305693.15 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 08-19-13
Work Completed  
Time Computed 08-18-13
Contract Working Days 98
Addl Days Granted 23
Working Days Charged 181
Percent Time Used 149
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-029
ROADWAY SPECIALTIES, INC.(3.59%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.08%)
BATTEN DRILLING, INC.(7.56%)
JIM"S SAND & GRAVEL(2.05%)
LONE STAR PAVING CO. (5.98%)
Contract # 05133025
Totals 570000.00 0.00 487497.25 99.1

CountyCALDWELL
Highway CR
From ON OAK GROVE RD AT W FORK PLUM CRK
To (STR AA02-28-001)
CSJ 0914-22-056
Proj ID BR 2013(195)
Work Type REPLACE BRIDGE & APPROACHES
 
0.155 656797.82 103299.07 386249.53 58.8
CountyCALDWELL
Highway CR
From ON OAK GROVE ROAD (CR 127) @
To TRIBUTARY TO WEST FORK PLUM CREEK
CSJ 0914-22-062
Proj ID CC 914-22-62
Work Type REPLACE STRUCTURE & APPROACHES
 
0.051 160259.62 27439.00 79933.36 49.8
Work Order 07-10-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 109
Addl Days Granted 12
Working Days Charged 45
Percent Time Used 37
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-056
O & S TRAFFIC SUPPLIES (0.66%)
CL CONCRETE( 12.36%)
DOUBLE S PAVING, INC.( 12.00%)
VOGES DRILLING CO. (2.04%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.60%)
Contract # 05143036
Totals 817057.44 130738.07 466182.89 57.0

CountyBURNET
Highway CR
From ON CR 202 AT N FORK SAN GABRIEL RVR
To STR AA06-22-001
CSJ 0914-24-016
Proj ID BR 2014(460)
Work Type REPLACE BRIDGE & APPROACHES
 
0.036 285095.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0914-24-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143007
Totals 285095.75 0.00 0.00 0.0

CountyLLANO
Highway CR
From ON CR 216 AT BOARD BRANCH
To STR AA0552001
CSJ 0914-25-006
Proj ID BR 2011(981)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 226113.43 22906.36 216864.26 93.6
Work Order 07-18-14
Work Began 09-22-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 82
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-006
BXB GROUP INCORPORATION( 46.45%)
TRP CONSTRUCTION GROUP, LLC(2.17%)
Contract # 05143026
Totals 226113.43 22906.36 216864.26 93.6

CountyHAYS
Highway CR
From ON CR 266 AT SAN MARCOS RIVER
To STR AA02-24-001
CSJ 0914-33-035
Proj ID BR 2005(711)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 576253.11 110074.69 184310.89 31.9
Work Order 07-11-14
Work Began 10-13-14
Work Completed  
Time Computed 07-27-14
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 44
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-035
ALTUS TRAFFIC MANAGEMENT LLC (0.64%)
ENVIRONMENTAL SAFETY SERVICES, INC.( 11.82%)
FLASHER EQUIPMENT COMPANY(0.74%)
J.D. RAMMING PAVING CO./AUSTIN MATERIALS LLC (6.82%)
BAIRD DRILLING SERVICES, INC.(3.49%)
Contract # 05143214
Totals 576253.11 110074.69 184310.89 31.9

CountyHAYS
Highway VA
From VARIOUS LOCATIONS IN HAYS COUNTY
To ON IH 35 AND SH 80
CSJ 0914-33-063
Proj ID STP 2012(552)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 467144.80 4610.40 483996.41 99.9
Work Order 06-14-12
Work Began 07-09-12
Work Completed  
Time Computed 07-09-12
Contract Working Days 72
Addl Days Granted 6
Working Days Charged 78
Percent Time Used 100
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-063
LONE STAR TRAFFIC SERVICE, INC.(1.37%)
TERRY PRATHER( 16.78%)
Contract # 05123226
Totals 467144.80 4610.40 483996.41 99.9

CountyBLANCO
Highway RM 165
From SL 163
To HAYS C/L
CSJ 0954-02-016
Proj ID STP 2012(553)HRR
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
11.900 816534.84 0.00 878235.90 99.9
CountyBLANCO
Highway RM 165
From SL 163
To BLANCO/HAYS COUNTY LINE
CSJ 0954-02-017
Proj ID STP 2012(553)HRR
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
11.949 4792086.66 0.00 5635776.57 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 10-02-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 261
Addl Days Granted 57
Working Days Charged 471
Percent Time Used 148
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0954-02-017
HIGHWAY TECHNOLOGIES, INC. (1.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.76%)
ABC EROSION CONTROL, INC.(0.72%)
AUSTIN WOOD RECYCLING(1.45%)
JMHP, INC. (0.85%)
Contract # 05123212
Totals 5608621.50 0.00 6514012.47 99.9

CountyGILLESPIE
Highway RM 783
From US 290
To 8.977 MI S OF US 290
CSJ 1135-01-026
Proj ID STP 2013(028)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
8.977 5106864.29 10980.78 4672290.11 96.3
Work Order 04-03-13
Work Began 04-15-13
Work Completed  
Time Computed 04-15-13
Contract Working Days 229
Addl Days Granted 0
Working Days Charged 331
Percent Time Used 144
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026
ROADWAY SPECIALTIES, INC.(3.51%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%)
RELMCO, INC. ( 31.14%)
D. I. J. CONSTRUCTION, INC.(1.16%)
VOGES DRILLING CO. (1.08%)
LONE STAR PAVING COMPANY (2.40%)
Contract # 02133212
Totals 5106864.29 10980.78 4672290.11 96.3

CountyTRAVIS
Highway FM 969
From DECKER CREEK DRIVE
To BASTROP COUNTY LINE
CSJ 1186-01-087
Proj ID STP 2015(277)HES
Work Type PROVIDE ADD'L PAVED SURFACE WIDTH
 
7.101 5894316.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 398
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
M.A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143219
Totals 5894316.37 0.00 0.00 0.0

CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-028
Proj ID BR 2013(930)
Work Type REPLACE BRIDGE & APPROACHES
 
1.530 11659867.54 672175.90 4777814.69 40.9
CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-048
Proj ID STP 2012(591)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.530 2188836.25 285474.75 1019439.64 46.5
Work Order 02-13-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 37
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
C4 CONSTRUCTION SERVICES, LLC(0.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.67%)
LINDAMOOD DEMOLITION, INC. (0.95%)
MURRAY CONSTRUCTION(0.13%)
ROADWAY SPECIALTIES, INC.(1.54%)
M & M STRIPING & POWER WASHING, LLC(0.43%)
AARON CONCRETE CONTRACTORS, L.P. (0.81%)
AUSTIN WOOD RECYCLING(0.28%)
BRYANT & FREY CONSTRUCTION (1.50%)
TEX OP CONSTRUCTION, LP(0.14%)
APAC-TEXAS, INC. ( 11.02%)
CP REBAR AND PT INSTALLATION (0.46%)
PRIMATE CONSTRUCTION, INC. (0.12%)
MCKINNEY DRILLING COMPANY(2.77%)
TEXAS HIGHWAY WALLS(3.63%)
Contract # 12133203
Totals 13848703.79 957650.65 5797254.33 41.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8