Monthly State Let Construction Report For Austin District As Of Aug 10, 2015 Page 5 Of 11

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHAYS
Highway SH 80
From AT IH 35
To .
CSJ 0286-01-055
Proj ID NH 2015(492)
Work Type LANDSCAPING AND IRRIGATION
 
0.078 295843.00 24611.60 69521.60 23.4
Work Order 02-10-15
Work Began 04-27-15
Work Completed  
Time Computed 02-26-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 70
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0286-01-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153014
Totals 295843.00 24611.60 69521.60 23.4

CountyCALDWELL
Highway SH 80
From 0.235 MI WEST OF FM 20
To FM 20
CSJ 0286-02-030
Proj ID STP 2014(714)HES
Work Type INSTALL CONTINUOUS TURN LANE
 
8.541 499490.10 0.00 517848.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-27-14
Work Began 09-29-14
Work Completed 05-04-15
Time Computed 09-29-14
Contract Working Days 71
Addl Days Granted 1
Working Days Charged 67
Percent Time Used 93
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0286-02-030
N-LINE TRAFFIC MAINTENANCE, L.P. (1.87%)
M.V. HENKE ENTERPRISES, INC. (0.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) ( 14.16%)
MURRAY CONSTRUCTION(1.50%)
ROADWAY SPECIALTIES, INC.(1.02%)
FLASHER EQUIPMENT COMPANY(4.86%)
WEST TEXAS RUMBLE STRIP(0.84%)
Contract # 06143018
Totals 499490.10 0.00 517848.57 100.0

CountyCALDWELL
Highway SH 80
From 0.336 MI W OF FM 1984
To 0.246 MI E OF FM 1979
CSJ 0286-02-031
Proj ID STP 1502(308)HES
Work Type INSTALL CONTINUOUS TURN LANE
 
3.006 832763.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-15
Work Began 00-00-00
Work Completed  
Time Computed 08-10-15
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0286-02-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153230
Totals 832763.37 0.00 0.00 0.0

CountyGILLESPIE
Highway SH 16
From RIDGEWOOD DR IN FREDERICKSBURG
To US 87 (MAIN STREET)
CSJ 0290-03-027
Proj ID STP 2015(735)
Work Type MILL, SEAL & THIN OVERLAY
 
1.734 493928.85 588333.09 588333.09 99.9
Work Order 04-20-15
Work Began 06-28-15
Work Completed  
Time Computed 05-21-15
Contract Working Days 13
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 115
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0290-03-027
ALTUS TRAFFIC MANAGEMENT LLC (0.72%)
D.I.J. CONSTRUCTION, INC (3.00%)
FLASHER EQUIPMENT COMPANY(0.61%)
Contract # 03153014
Totals 493928.85 588333.09 588333.09 99.9

CountyGILLESPIE
Highway SH 16
From BOOS LANE
To 0.5 MI SOUTH MORRIS RANCH ROAD
CSJ 0291-01-048
Proj ID STP 2015(276)
Work Type UPGRADE TO SUPER 2 AND ADD LTLS
 
6.670 6732998.40 123792.17 1275343.00 18.9
CountyGILLESPIE
Highway SH 16
From 0.5 MI SOUTH OF MORRIS RANCH ROAD
To KERR/GILLESPIE COUNTY LINE
CSJ 0291-01-049
Proj ID STP 2015(493)
Work Type UPGRADE TO SUPER 2 AND ADD LTLS
 
6.714 5676561.76 -15005.71 791385.54 13.9
CountyKERR
Highway SH 16
From GILLESPIE/KERR COUNTY LINE
To WOLF CREEK
CSJ 0291-02-035
Proj ID STP 2015(493)
Work Type UPGRADE TO SUPER 2 AND ADD LTLS
 
0.466 584945.99 0.00 65885.76 11.2
Work Order 03-13-15
Work Began 04-06-15
Work Completed  
Time Computed 03-29-15
Contract Working Days 333
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 16
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0291-01-049
EGGEMEYER LAND CLEARING, LLC (0.35%)
BMP SPECIALIST, LLC(2.18%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.19%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57%)
MPB, INC.( 11.12%)
DUSTROL, INC.(0.47%)
CLARK CONSTRUCTION OF TEXAS, INC.(4.83%)
ROADWAY SPECIALTIES, INC.(0.62%)
RPV CONSTRUCTION (2.74%)
WEST TEXAS RUMBLE STRIP(0.08%)
Contract # 01153201
Totals 12994506.15 108786.46 2132614.30 16.4

CountyWILLIAMSON
Highway SH 95
From AT WILLIS CREEK
To (STR 0320-03-032)
CSJ 0320-03-083
Proj ID BR 1502(592)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.105 2497365.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 0320-03-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153253
Totals 2497365.80 0.00 0.00 0.0

CountyWILLIAMSON
Highway SH 95
From BELL COUNTY LINE
To FM 971 WEST
CSJ 0320-03-091
Proj ID STP 2012(307)
Work Type UPGRADE TO SUPER 2
 
5.590 3350557.08 0.00 3652490.24 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-26-12
Work Began 06-11-12
Work Completed  
Time Computed 06-15-12
Contract Working Days 281
Addl Days Granted 0
Working Days Charged 281
Percent Time Used 100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0320-03-091
ENVIRONMENTAL SAFETY SERVICES, INC.(0.18%)
J.D. RAMMING PAVING CO., LTD.( 50.21%)
D. I. J. CONSTRUCTION, INC.(1.99%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.39%)
JCS LOGISTICS, LLC (3.17%)
J.E.D. TRUCKING, INC.(0.00%)
FRANK PRASIFKA & SONS, INC.(0.41%)
EDGAR GALAVAN DBA TRISA TRUCKING (0.39%)
TIM ARMSTRONG TRUCKING, INC. (0.14%)
JUAN MALDONADO DBA KRUNC TRANSPORTATION(0.29%)
CTBX, INC. (1.35%)
TEXAS TRUCKING COMPANY, INC. (0.00%)
PENNTEX MILLING, LLC (0.25%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
BLACKTOPPER TECHNOLOGY, INC. (4.18%)
Contract # 03123226
Totals 3350557.08 0.00 3652490.24 99.9

CountyWILLIAMSON
Highway FM 397
From SH 95
To US 79
CSJ 0320-04-025
Proj ID STP 2014(716)
Work Type PAVEMENT REPAIR & OVERLAY
 
3.417 1152734.41 1282334.32 1282334.32 99.9
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 09-05-14
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 50
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0320-04-025
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37%)
D. I. J. CONSTRUCTION, INC.(4.80%)
Contract # 06143243
Totals 1152734.41 1282334.32 1282334.32 99.9

CountyWILLIAMSON
Highway SH 95
From US 79
To TRAVIS C/L
CSJ 0321-01-053
Proj ID STP 2014(617)HESG
Work Type IMPROVE GUARDRAIL & SAFETY TREAT
 
9.498 342863.78 2403.24 328276.38 100.0
CountyTRAVIS
Highway SH 95
From WILLIAMSON COUNTY LINE
To BASTROP COUNTY LINE
CSJ 0321-02-015
Proj ID STP 2014(618)HESG
Work Type IMPROVE GUARDRAIL & SAFETY TREAT
 
1.050 4080.82 0.00 435.00 100.0
CountyBASTROP
Highway SH 95
From TRAVIS COUNTY LINE
To US 290 IN ELGIN
CSJ 0321-03-019
Proj ID STP 2014(619)HESG
Work Type IMPROVE GUARDRAIL & SAFETY TREAT
 
3.379 89634.00 0.00 74958.20 100.0
CountyTRAVIS
Highway FM 1100
From US 290
To BASTROP COUNTY LINE
CSJ 1234-01-011
Proj ID STP 2014(620)HESG
Work Type IMPROVE GUARDRAIL & SFTY TRT FIXED OB
 
6.534 379746.65 0.00 310952.79 100.0
Work Order 06-10-14
Work Began 08-11-14
Work Completed 06-24-15
Time Computed 06-26-14
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 80
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0321-01-053
TRP CONSTRUCTION GROUP, LLC(1.14%)
Contract # 05143035
Totals 816325.25 2403.24 714622.37 100.0

CountyWILLIAMSON
Highway SH 95
From OLD COUPLAND ROAD
To TRAVIS C/L
CSJ 0321-01-054
Proj ID STP 1502(593)
Work Type CONVERT SUPER 2
 
14.826 13427785.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0321-01-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153009
Totals 13427785.21 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 112
From AT BRUSHY CREEK WEST RELIEF
To (STR 14-246-0334-01-026)
CSJ 0334-01-030
Proj ID BR 2013(842)
Work Type REPLACE BRIDGE & APPROACHES
 
0.122 682347.00 0.00 753743.49 100.0
CountyWILLIAMSON
Highway FM 112
From AT BRUSHY CREEK EAST RELIEF
To (STR 14-246-0334-01-027)
CSJ 0334-01-031
Proj ID BR 2013(842)
Work Type REPLACE BRIDGE & APPROACHES
 
0.152 727144.40 0.00 739323.97 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-13
Work Began 02-17-14
Work Completed 01-29-15
Time Computed 01-15-14
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 78
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 0334-01-030
LHOIST NORTH AMERICA (0.33%)
FLASHER EQUIPMENT COMPANY(0.33%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.85%)
ABC EROSION CONTROL, INC.(2.78%)
MCKINNEY DRILLING COMPANY( 12.49%)
APAC-TEXAS, INC. (7.07%)
ROADWAY SPECIALTIES, INC.(2.21%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.42%)
Contract # 07133037
Totals 1409491.40 0.00 1493067.46 100.0

CountyWILLIAMSON
Highway FM 112
From SH 95
To MILAM C/L
CSJ 0334-01-042
Proj ID STP 1402(056)
Work Type DEPTH REPAIR, UNDERSEAL & THIN OV
 
18.059 1682489.00 103186.73 196815.43 11.6
Work Order 01-05-15
Work Began 06-15-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 45
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0334-01-042
CANTU CONSTRUCTION, INC. (1.60%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 31.31%)
D. I. J. CONSTRUCTION, INC.(7.96%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54%)
Contract # 08143026
Totals 1682489.00 103186.73 196815.43 11.6

CountyWILLIAMSON
Highway FM 112
From AT DRAW 1.0 MI E OF US 79
To STR 0334-01-003
CSJ 0334-01-043
Proj ID BR 1502(594)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.317 1052935.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0334-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153245
Totals 1052935.48 0.00 0.00 0.0

CountyLEE
Highway FM 448
From US 77
To FM 2239
CSJ 0334-06-026
Proj ID STP 1502(595)
Work Type LEVEL - UP, OVERLAY, WIDEN & SEAL
 
4.850 3138496.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0334-06-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153040
Totals 3138496.55 0.00 0.00 0.0

CountyWILLIAMSON
Highway SH 29
From US 183
To CEDAR HOLLOW ROAD
CSJ 0337-01-035
Proj ID STP 2014(519)
Work Type PAVEMENT REPAIR & OVERLAY
 
6.924 3556401.05 0.00 3128238.16 87.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-22-14
Work Began 08-25-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0337-01-035
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
D. I. J. CONSTRUCTION, INC.(2.45%)
ROADWAY SPECIALTIES, INC.( 10.09%)
TEX OP CONSTRUCTION, LP(4.47%)
BRYDL CONTRACTING, INC.(0.25%)
Contract # 03143033
Totals 3556401.05 0.00 3128238.16 87.9

CountyWILLIAMSON
Highway SH 29
From WEST OF MAPLE ST
To .
CSJ 0337-02-042
Proj ID STP 1302(089)FRS
Work Type REPLACE RR SIGNALS AND XING SURF
 
0.001 335143.25 18461.16 312363.86 93.2
Work Order 12-05-14
Work Began 05-06-15
Work Completed  
Time Computed 12-21-14
Contract Working Days 23
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 69
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0337-02-042
DIAMOND K CORPORATION( 17.73%)
FLASHER EQUIPMENT COMPANY(2.50%)
N-LINE TRAFFIC MAINTENANCE, L.P. (4.74%)
RAILROAD SIGNAL INTERNATIONAL LLC( 30.16%)
Contract # 11143221
Totals 335143.25 18461.16 312363.86 93.2

CountyHAYS
Highway SH 123
From 3500 FT NORTH OF RM 12
To 3500 FT SOUTH OF RM 12
CSJ 0366-01-066
Proj ID C 366-1-66
Work Type CONST GRADE SEPARATION
 
1.326 11596550.48 424498.46 1935779.46 16.6
Work Order 08-27-14
Work Began 03-31-15
Work Completed  
Time Computed 02-23-15
Contract Working Days 465
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 13
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-01-066
BMP SPECIALIST, LLC(1.56%)
FLASHER EQUIPMENT COMPANY(1.80%)
HOUSTON SAWING & DRILLING(0.04%)
THE LEVY COMPANY, L.P. (3.95%)
MCL CONTRACTING, LLC (0.24%)
MURRAY CONSTRUCTION(0.22%)
R K STEPHENS CONSTRUCTION, LLC (1.77%)
VEGETATION MANAGEMENT SPECIALIST, INC. (0.06%)
VOGES DRILLING CO. (0.73%)
Contract # 06143202
Totals 11596550.48 424498.46 1935779.46 16.6

CountyHAYS
Highway SH 123
From OLD BASTROP HIGHWAY
To GUADALUPE COUNTY LINE
CSJ 0366-01-072
Proj ID STP 2014(718)
Work Type MILL, LEVEL - UP, SEAL & THIN OVERLAY
 
1.180 618977.41 0.00 693189.34 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-07-14
Work Began 10-13-14
Work Completed 04-20-15
Time Computed 08-23-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 89
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-01-072
FLASHER EQUIPMENT COMPANY(6.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
ROADWAY SPECIALTIES, INC.(2.47%)
Contract # 06143021
Totals 618977.41 0.00 693189.34 100.0

CountyWILLIAMSON
Highway SH 195
From SH 138
To 3.4 MI S OF SH 138
CSJ 0440-01-035
Proj ID STP 2011(738)
Work Type WIDEN GR, STRS & SURF
 
7.026 39167328.18 384.00 38374921.78 97.9
Work Order 03-04-11
Work Began 03-28-11
Work Completed  
Time Computed 03-20-11
Contract Working Days 765
Addl Days Granted 106
Working Days Charged 869
Percent Time Used 99
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0440-01-035
TEXAS ALTERNATIVE GRASSER, INC.(1.51%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.46%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
RICE ENVIRONMENTAL SERVICES(0.21%)
STAR OPERATIONS, INC.(1.84%)
INDUS CONSTRUCTION, L.P. (0.82%)
ROADWAY SPECIALTIES, INC.(0.56%)
SOUTH TEXAS PAINTING COMPANY (0.05%)
RANGER EXCAVATING, L.P.( 22.22%)
HOUSTON SAWING & DRILLING(0.06%)
BEAIRD DRILLING(0.87%)
COWBELL TRAFFIC SERVICES, INC. (0.02%)
D. I. J. CONSTRUCTION, INC.(0.64%)
WOLFF CONSTRUCTION (1.05%)
J.D. RAMMING PAVING CO., LTD.( 29.54%)
AUSTIN WOOD RECYCLING(0.11%)
GK CONSTRUCTION, LLC (0.05%)
JAG TRUCKING INC (0.00%)
AUSTIN POWDER COMPANY(0.09%)
BLACKTOPPER TECHNOLOGY, INC. (0.06%)
Contract # 01113020
Totals 39167328.18 384.00 38374921.78 97.9

CountyWILLIAMSON
Highway SH 195
From 4.987 MI SOUTH OF SH 138
To 8.486 MI SOUTH OF SH 138
CSJ 0440-01-039
Proj ID NH 2013(792)
Work Type WIDEN GR, STRS & SURF
 
3.499 17429949.35 1464855.16 14501377.99 83.1
CountyWILLIAMSON
Highway SH 195
From 8.486 MI SOUTH OF SH 138
To 9.793 MI SOUTH OF SH 138
CSJ 0440-02-014
Proj ID C 440-2-14
Work Type GR, STRS, SURF / WIDEN TO FOUR LANE DIV
 
3.310 15881161.65 329813.14 13410185.79 84.4
Work Order 07-16-13
Work Began 12-18-13
Work Completed  
Time Computed 11-14-13
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 398
Percent Time Used 78
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0440-01-039
RAMMING PAVING COMPANY ( 13.10%)
ROYAL VISTA INC. (2.10%)
TEXAS HIGHWAY WALLS(4.51%)
WEBBER BARRIER SERVICES, LLC.(0.73%)
D. I. J. CONSTRUCTION, INC.(0.27%)
AUSTIN WOOD RECYCLING(0.59%)
BEAIRD DRILLING(0.39%)
ROADWAY SPECIALTIES, INC.(0.10%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.29%)
TEXAS OPERATIONS (0.16%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.16%)
PERFORMANCE EQUIPMENT(0.00%)
GK CONSTRUCTION, LLC (0.06%)
COWBELL TRAFFIC SERVICES, INC. (0.02%)
HOUSTON SAWING & DRILLING(0.01%)
TOM ARNOLD DRILLING CONTRACTOR II, LLC (0.00%)
BMP SPECIALIST, LLC(0.73%)
INDUS CONSTRUCTION, L.P. (0.55%)
Contract # 06133201
Totals 33311111.00 1794668.30 27911563.78 83.7