Monthly State Let Construction Report For Austin District As Of Mar 10, 2015 Page 5 Of 9

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWILLIAMSON
Highway SH 29
From WEST OF MAPLE ST
To .
CSJ 0337-02-042
Proj ID STP 1302(089)FRS
Work Type REPLACE RR SIGNALS AND XING SURF
 
0.001 335143.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-14
Work Began 00-00-00
Work Completed  
Time Computed 12-21-14
Contract Working Days 23
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0337-02-042
DIAMOND K CORPORATION( 17.73%)
FLASHER EQUIPMENT COMPANY(2.50%)
N-LINE TRAFFIC MAINTENANCE, L.P. (4.74%)
RAILROAD SIGNAL INTERNATIONAL LLC( 30.16%)
Contract # 11143221
Totals 335143.25 0.00 0.00 0.0

CountyHAYS
Highway SH 123
From 3500 FT NORTH OF RM 12
To 3500 FT SOUTH OF RM 12
CSJ 0366-01-066
Proj ID C 366-1-66
Work Type CONST GRADE SEPARATION
 
1.326 11596550.48 0.00 126503.51 1.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-27-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 465
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-01-066
BMP SPECIALIST, LLC(1.56%)
FLASHER EQUIPMENT COMPANY(1.80%)
Contract # 06143202
Totals 11596550.48 0.00 126503.51 1.0

CountyHAYS
Highway SH 123
From OLD BASTROP HIGHWAY
To GUADALUPE COUNTY LINE
CSJ 0366-01-072
Proj ID STP 2014(718)
Work Type MILL, LEVEL - UP, SEAL & THIN OVERLAY
 
1.180 618977.41 0.00 688534.84 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-07-14
Work Began 10-13-14
Work Completed  
Time Computed 08-23-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 89
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-01-072
FLASHER EQUIPMENT COMPANY(6.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
ROADWAY SPECIALTIES, INC.(2.47%)
Contract # 06143021
Totals 618977.41 0.00 688534.84 99.9

CountyWILLIAMSON
Highway SH 195
From SH 138
To 3.4 MI S OF SH 138
CSJ 0440-01-035
Proj ID STP 2011(738)
Work Type WIDEN GR, STRS & SURF
 
7.026 39167328.18 6396.58 37765265.75 97.0
Work Order 03-04-11
Work Began 03-28-11
Work Completed  
Time Computed 03-20-11
Contract Working Days 765
Addl Days Granted 18
Working Days Charged 869
Percent Time Used 110
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0440-01-035
TEXAS ALTERNATIVE GRASSER, INC.(1.51%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.46%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
RICE ENVIRONMENTAL SERVICES(0.21%)
STAR OPERATIONS, INC.(1.84%)
INDUS CONSTRUCTION, L.P. (0.82%)
ROADWAY SPECIALTIES, INC.(0.56%)
SOUTH TEXAS PAINTING COMPANY (0.05%)
RANGER EXCAVATING, L.P.( 22.22%)
HOUSTON SAWING & DRILLING(0.06%)
BEAIRD DRILLING(0.87%)
COWBELL TRAFFIC SERVICES, INC. (0.02%)
D. I. J. CONSTRUCTION, INC.(0.64%)
WOLFF CONSTRUCTION (1.05%)
J.D. RAMMING PAVING CO., LTD.( 29.54%)
AUSTIN WOOD RECYCLING(0.11%)
GK CONSTRUCTION, LLC (0.05%)
JAG TRUCKING INC (0.00%)
AUSTIN POWDER COMPANY(0.09%)
BLACKTOPPER TECHNOLOGY, INC. (0.06%)
Contract # 01113020
Totals 39167328.18 6396.58 37765265.75 97.0

CountyWILLIAMSON
Highway SH 195
From 4.987 MI SOUTH OF SH 138
To 8.486 MI SOUTH OF SH 138
CSJ 0440-01-039
Proj ID NH 2013(792)
Work Type WIDEN GR, STRS & SURF
 
3.499 17429949.35 -11988.54 10022913.44 57.5
CountyWILLIAMSON
Highway SH 195
From 8.486 MI SOUTH OF SH 138
To 9.793 MI SOUTH OF SH 138
CSJ 0440-02-014
Proj ID C 440-2-14
Work Type GR, STRS, SURF / WIDEN TO FOUR LANE DIV
 
3.310 15881161.65 2599291.71 9203084.59 57.9
Work Order 07-16-13
Work Began 12-18-13
Work Completed  
Time Computed 11-14-13
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 291
Percent Time Used 57
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0440-01-039
RAMMING PAVING COMPANY ( 13.10%)
ROYAL VISTA INC. (2.10%)
TEXAS HIGHWAY WALLS(4.51%)
WEBBER BARRIER SERVICES, LLC.(0.73%)
D. I. J. CONSTRUCTION, INC.(0.27%)
AUSTIN WOOD RECYCLING(0.59%)
BEAIRD DRILLING(0.39%)
ROADWAY SPECIALTIES, INC.(0.10%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.29%)
TEXAS OPERATIONS (0.16%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.16%)
PERFORMANCE EQUIPMENT(0.00%)
GK CONSTRUCTION, LLC (0.06%)
COWBELL TRAFFIC SERVICES, INC. (0.02%)
HOUSTON SAWING & DRILLING(0.01%)
TOM ARNOLD DRILLING CONTRACTOR II, LLC (0.00%)
BMP SPECIALIST, LLC(0.73%)
INDUS CONSTRUCTION, L.P. (0.55%)
Contract # 06133201
Totals 33311111.00 2587303.17 19225998.03 57.7

CountyWILLIAMSON
Highway SH 195
From 9.271 MI S OF SH 138
To IH 35
CSJ 0440-02-010
Proj ID HP 2013(023)
Work Type WIDEN GR, STRS & SURF
 
5.179 18778887.62 4978.64 17188575.38 91.5
Work Order 11-16-12
Work Began 01-10-13
Work Completed  
Time Computed 12-02-12
Contract Working Days 368
Addl Days Granted 145
Working Days Charged 479
Percent Time Used 93
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0440-02-010
G. CARTER CONSTRUCTION COMPANY, INC. (2.15%)
PERFORMANCE EQUIPMENT(0.46%)
AUSTIN WOOD RECYCLING(0.62%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33%)
ROYAL VISTA INC. (5.40%)
AARON CONCRETE CONTRACTORS, L.P. (0.25%)
BMP SPECIALIST, LLC(1.37%)
D. I. J. CONSTRUCTION, INC.(1.02%)
RAMMING PAVING COMPANY ( 42.87%)
ROADWAY SPECIALTIES, INC.(0.69%)
TOM ARNOLD DRILLING CONTRACTOR II, LLC (0.02%)
TEXAS TRUCKING COMPANY, INC. (2.43%)
DOWN UNDER CONSTRUCTION(0.09%)
Contract # 09123203
Totals 18778887.62 4978.64 17188575.38 91.5

CountyBURNET
Highway RM 243
From SH 29
To WILLIAMSON C/L
CSJ 0440-04-013
Proj ID STP 2014(719)HES
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
12.534 622587.90 20140.00 318786.60 51.2
CountyBURNET
Highway RM 243
From 0.609 MI N OF SH 29
To 7.923 MI N OF SH 29
CSJ 0440-04-014
Proj ID STP 2014(720)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
7.314 3173322.49 287771.00 1166713.35 36.7
Work Order 08-04-14
Work Began 09-02-14
Work Completed  
Time Computed 08-20-14
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 37
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0440-04-013
N-LINE TRAFFIC MAINTENANCE, L.P. (0.94%)
ROADWAY SPECIALTIES, INC.(6.58%)
LONE STAR PAVING, INC. ( 13.34%)
D. I. J. CONSTRUCTION, INC.(3.36%)
MPB, INC.( 15.66%)
Contract # 06143207
Totals 3795910.39 307911.00 1485499.95 39.1

CountyWILLIAMSON
Highway SH 130
From 252 FT NORTH OF US 79 CENTERLINE
To 2748 FT SOUTH OF US 79 CENTERLINE
CSJ 0440-05-008
Proj ID NH 2012(481)
Work Type LANDSCAPING
 
0.568 155600.10 400.00 163275.63 99.9
Work Order 05-15-12
Work Began 06-18-12
Work Completed  
Time Computed 06-18-12
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 82
Contractor(s)
NALLE LANDSCAPE LLC
SUBCONTRACTOR(S) FOR CCSJ: 0440-05-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123233
Totals 155600.10 400.00 163275.63 99.9

CountyHAYS
Highway SH 21
From AT INTERSECTION OF RM 150
To .
CSJ 0471-02-067
Proj ID STP 2013(286)MM
Work Type CONSTR LEFT TURN LANE ON SH 21 NB
 
0.100 862311.69 70.79 896081.95 99.9
Work Order 04-11-14
Work Began 04-28-14
Work Completed  
Time Computed 04-27-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 93
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0471-02-067
ROADWAY SPECIALTIES, INC.(3.56%)
THE LEVY COMPANY, L.P. (1.55%)
FUQUAY, INC. (1.13%)
FLASHER EQUIPMENT COMPANY(4.77%)
RAMMING PAVING COMPANY ( 29.55%)
AARON CONCRETE CONTRACTORS, L.P. (0.57%)
Contract # 02143219
Totals 862311.69 70.79 896081.95 99.9

CountyBASTROP
Highway SH 304
From 0.043 MI. SOUTH OF SH 71
To 2.677 MI. SOUTH OF SH 71
CSJ 0573-01-029
Proj ID STP 2013(703)
Work Type UPGRD TO 3 LN SEC WITH SHOULDERS
 
2.634 6181473.52 0.00 6177593.11 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-13
Work Began 08-05-13
Work Completed  
Time Computed 07-27-13
Contract Working Days 144
Addl Days Granted 75
Working Days Charged 228
Percent Time Used 104
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0573-01-029
FLASHER EQUIPMENT COMPANY(0.16%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.86%)
D. I. J. CONSTRUCTION, INC.(0.41%)
THE LEVY COMPANY, L.P. (0.14%)
APAC-TEXAS, INC. ( 33.04%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(1.27%)
Contract # 05133207
Totals 6181473.52 0.00 6177593.11 99.9

CountyBASTROP
Highway SH 304
From FM 2571
To CALDWELL COUNTY LINE
CSJ 0573-01-031
Proj ID STP 2014(721)HES
Work Type IMPRV GUARDRAIL & SFTY TRT FXD OBJS
 
22.194 1160129.99 209985.06 1011971.64 87.2
Work Order 08-08-14
Work Began 10-07-14
Work Completed  
Time Computed 10-07-14
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 48
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0573-01-031
R K STEPHENS CONSTRUCTION, LLC (8.02%)
TRP CONSTRUCTION GROUP, LLC(2.02%)
Contract # 06143050
Totals 1160129.99 209985.06 1011971.64 87.2

CountyLLANO
Highway SH 71 ETC
From MASON COUNTY LINE
To SH 29
CSJ 0577-04-021
Proj ID STP 2014(531)HESG
Work Type TEXTURIZE SHOULDERS - PROFILE MARKERS
 
101.943 566990.25 0.00 526606.85 92.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 04-23-14
Work Completed  
Time Computed 04-23-14
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 47
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0577-04-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143219
Totals 566990.25 0.00 526606.85 92.8

CountyTRAVIS
Highway RM 620
From RM 2222
To RM 2769
CSJ 0683-02-057
Proj ID STP 2014(532)
Work Type UNDERSEAL & OVERLAY
 
3.872 1640913.50 0.00 1740817.49 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-17-14
Work Began 07-14-14
Work Completed  
Time Computed 06-16-14
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0683-02-057
ENVIRONMENTAL SAFETY SERVICES, INC.(0.06%)
TEX OP CONSTRUCTION, LP(6.89%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.03%)
TRP CONSTRUCTION GROUP, LLC(6.25%)
Contract # 03143027
Totals 1640913.50 0.00 1740817.49 99.9

CountyTRAVIS
Highway RM 620
From SH 71
To COLORADO RIVER(MANSFIELD DAM)
CSJ 0683-02-058
Proj ID STP 2014(304)
Work Type SEAL & OVERLAY
 
8.589 2734590.56 3780.00 2765486.88 99.9
Work Order 01-17-14
Work Began 06-25-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 111
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0683-02-058
R K STEPHENS CONSTRUCTION, LLC (0.69%)
TEX OP CONSTRUCTION, LP(1.81%)
D. I. J. CONSTRUCTION, INC.(6.00%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.04%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.25%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.24%)
Contract # 12133222
Totals 2734590.56 3780.00 2765486.88 99.9

CountyTRAVIS
Highway RM 3238
From 0.31 MI W OF SH 71
To RM 12
CSJ 0683-04-018
Proj ID STP 2015(574)
Work Type ADD SHOULDERS AND LEFT TURN LANE
 
6.337 1504303.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0683-04-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153022
Totals 1504303.45 0.00 0.00 0.0

CountyWILLIAMSON
Highway SH 45
From WEST OF RATTAN CRK
To MCNEIL ROAD
CSJ 0683-06-027
Proj ID C 683-6-27
Work Type GR, BASE, STRUC, ACP, SGN & PVMT MK
 
1.256 24729960.53 213156.26 27219169.78 99.9
Work Order 09-27-11
Work Began 11-08-11
Work Completed  
Time Computed 11-08-11
Contract Working Days 495
Addl Days Granted 142
Working Days Charged 676
Percent Time Used 106
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0683-06-027
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (3.26%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.30%)
AUSTIN WOOD RECYCLING(0.04%)
BEAIRD DRILLING(2.06%)
CARTEL PLACERS, LLC(0.00%)
FLASHER EQUIPMENT COMPANY(0.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.27%)
PRIMATE CONSTRUCTION, INC. (0.16%)
SITE-SAFE PRODUCTS OF TEXAS, L.P.(0.80%)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC.(0.49%)
VALLEY PLACERS, LLC(0.10%)
ROADWAY SPECIALTIES, INC.(0.76%)
TEXAS HIGHWAY WALLS(3.26%)
ZACHRY CONSTRUCTION CORPORATION( 89.37%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
APAC-TEXAS, INC. (0.62%)
AARON CONCRETE CONTRACTORS, L.P. (1.04%)
KELLYSTONE, INC(0.12%)
NORTH TEXAS REBAR, LLC (2.79%)
Contract # 07113013
Totals 24729960.53 213156.26 27219169.78 99.9

CountyTRAVIS
Highway SH 71
From 0.55 MILES W OF SOUTHWEST PKWY
To 0.14 MILES E OF SOUTHWEST PKWY
CSJ 0700-03-114
Proj ID STP 2011(949)HES
Work Type INSTALL CTL, ACCEL LN & SHLDRS
 
0.697 5035450.53 0.00 5814345.07 100.0
CountyTRAVIS
Highway SH 71
From 0.55 MILES W OF SOUTHWEST PKWY
To 0.14 MILES E OF SOUTHWEST PKWY
CSJ 0700-03-120
Proj ID RW 700-3-120
Work Type UTILITY ADJUSTMENTS
 
0.697 322251.00 0.00 250715.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-27-11
Work Began 01-23-12
Work Completed 11-04-14
Time Computed 08-12-11
Contract Working Days 244
Addl Days Granted 108
Working Days Charged 513
Percent Time Used 145
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-114
AUSTIN WOOD RECYCLING(0.54%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.87%)
FLASHER EQUIPMENT COMPANY(2.03%)
J & M CONTRACTING, COMPANY ( 13.54%)
MENADE, INC. ( 22.85%)
ROADWAY SPECIALTIES, INC.(2.04%)
WEBBER BARRIER SERVICES, INC.(1.35%)
J.A. ROAD BORING, INC. (2.03%)
FARR FOUNDATION, INC.(2.78%)
KEN-WAY, INCORPORATED(4.19%)
VOGES DRILLING CO. (0.25%)
DRILL TECH DRILLING & SHORING, INC.(3.15%)
CHLOR-SERV, INC. (0.06%)
DESERT STEEL CO., INC. (0.17%)
Contract # 05113226
Totals 5357701.53 0.00 6065060.07 100.0

CountyTRAVIS
Highway SH 71
From 1.49 MI. EAST OF BEE CREEK ROAD
To 0.2 MI. WEST OF VAIL DIVIDE
CSJ 0700-03-122
Proj ID C 700-3-122
Work Type ADD LEFT TURN LANE & SHOULDERS
 
0.449 1633474.93 50364.93 797914.74 48.8
CountyTRAVIS
Highway SH 71
From 0.15 MI. EAST OF VAIL DIVIDE
To 0.2 MI. WEST OF RM 3238
CSJ 0700-03-123
Proj ID C 700-3-123
Work Type ADD LEFT TURN LANE & SHOULDERS
 
1.533 6535849.48 208370.89 4702086.08 72.3
CountyTRAVIS
Highway SH 71
From 0.15 MI. EAST OF VAIL DIVIDE
To 0.2 MI. WEST OF RM 3238
CSJ 0700-03-132
Proj ID RW 700-3-132
Work Type ROW UTL. ADJ.
 
1.536 76681.00 0.00 76681.00 99.9
Work Order 12-05-13
Work Began 02-17-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 161
Addl Days Granted 65
Working Days Charged 250
Percent Time Used 110
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-123
ROADWAY SPECIALTIES, INC.(3.25%)
AUSTIN WOOD RECYCLING(0.27%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.12%)
TEX OP CONSTRUCTION, LP(0.21%)
PANTHER CREEK TRANSPORTATION, INC. (2.15%)
BRYANT & FREY CONSTRUCTION (0.26%)
TEXAS HIGHWAY WALLS(5.50%)
RAMMING PAVING COMPANY ( 35.78%)
FLASHER EQUIPMENT COMPANY(1.98%)
JAG TRUCKING INC (0.77%)
Contract # 08133049
Totals 8246005.41 258735.82 5576681.82 67.9

CountyTRAVIS
Highway SH 71
From WEST OF THOMAS SPRINGS ROAD
To WEST OF COVERED BRIDGE ROAD
CSJ 0700-03-125
Proj ID C 700-3-125
Work Type ADD LEFT TURN LANE & SHOULDERS
 
5.702 15965613.32 914107.72 5073308.56 31.7
Work Order 03-18-14
Work Began 06-16-14
Work Completed  
Time Computed 05-17-14
Contract Working Days 289
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 42
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-125
PANTHER CREEK TRANSPORTATION, INC. (4.57%)
BRYANT & FREY CONSTRUCTION (2.07%)
ROADWAY SPECIALTIES, INC.(1.42%)
FLASHER EQUIPMENT COMPANY(1.12%)
SCOTT DERR PAINTING CO, LLC(0.00%)
TEXAS HIGHWAY WALLS(0.63%)
THE LEVY COMPANY, L.P. (2.36%)
HAEGELIN CONSTRUCTION CO., LTD.(8.02%)
SCOTT DERR PAINTING CO, LLC(0.08%)
AUSTIN WOOD RECYCLING(0.45%)
RAMI MATERIALS TRANSPORT, LLC(1.25%)
BREDA COMPANY, INC.(0.00%)
CANTU CONSTRUCTION, INC. (0.15%)
MCKINNEY DRILLING COMPANY(0.09%)
ROSCH COMPANY(0.85%)
CHLOR-SERV, INC. (0.03%)
Contract # 11133027
Totals 15965613.32 914107.72 5073308.56 31.7

CountyLLANO
Highway SH 71
From 0.1 MILES EAST OF CR 308
To 1.8 MILES EAST OF CR 309
CSJ 0700-04-045
Proj ID STP 2013(928)
Work Type UPGRADE TO SUPER 2 & ADD LTL'S
 
4.784 4402628.35 4348.23 4559973.12 99.9
Work Order 11-19-13
Work Began 12-05-13
Work Completed  
Time Computed 12-05-13
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 101
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0700-04-045
D. I. J. CONSTRUCTION, INC.(2.75%)
AUSTIN WOOD RECYCLING(1.24%)
ROADWAY SPECIALTIES, INC.(8.10%)
LONE STAR PAVING CO. (9.63%)
ERFURT BLASTING COMPANY, INC.(0.90%)
Contract # 09133225
Totals 4402628.35 4348.23 4559973.12 99.9