Monthly State Let Construction Report For Austin District As Of Aug 10, 2015 Page 7 Of 11

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLLANO
Highway SH 71
From 0.1 MILES EAST OF CR 308
To 1.8 MILES EAST OF CR 309
CSJ 0700-04-045
Proj ID STP 2013(928)
Work Type UPGRADE TO SUPER 2 & ADD LTL'S
 
4.784 4402628.35 0.00 5008906.89 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-19-13
Work Began 12-05-13
Work Completed  
Time Computed 12-05-13
Contract Working Days 200
Addl Days Granted 6
Working Days Charged 203
Percent Time Used 98
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0700-04-045
D. I. J. CONSTRUCTION, INC.(2.75%)
AUSTIN WOOD RECYCLING(1.24%)
ROADWAY SPECIALTIES, INC.(8.10%)
LONE STAR PAVING CO. (9.63%)
ERFURT BLASTING COMPANY, INC.(0.90%)
Contract # 09133225
Totals 4402628.35 0.00 5008906.89 99.9

CountyLLANO
Highway SH 71
From 0.2 MILES WEST OF CR 303
To 0.1 MILES WEST OF CR 307
CSJ 0700-04-046
Proj ID STP 2013(704)
Work Type UPGRADE TO SUPER 2 & ADD LTL'S
 
7.350 6036480.35 0.00 6487317.70 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-06-13
Work Began 08-26-13
Work Completed  
Time Computed 08-22-13
Contract Working Days 227
Addl Days Granted 14
Working Days Charged 241
Percent Time Used 100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0700-04-046
AUSTIN WOOD RECYCLING(0.78%)
D. I. J. CONSTRUCTION, INC.(2.15%)
FLASHER EQUIPMENT COMPANY(0.39%)
ROADWAY SPECIALTIES, INC.(4.41%)
Contract # 05133229
Totals 6036480.35 0.00 6487317.70 99.9

CountyBURNET
Highway SS 191
From AT CYPRESS CREEK
To STR 0700-05-030
CSJ 0700-05-007
Proj ID BR 1502(389)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.077 785219.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 93
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0700-05-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153260
Totals 785219.90 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 685
From US 79
To SH 130
CSJ 0757-01-020
Proj ID C 757-1-20
Work Type RECONSTRUCT TO 4 - LANE DIVIDED RDWY
 
1.820 10553004.78 134053.07 3842108.10 36.4
CountyWILLIAMSON
Highway FM 685
From US 79
To SH 130
CSJ 0757-01-021
Proj ID RW 757-1-21
Work Type ROW ACQ, RELOC ASSIST. & UTL. ADJ.
 
1.820 464544.39 0.00 392746.76 84.5
Work Order 08-27-14
Work Began 10-20-14
Work Completed  
Time Computed 10-20-14
Contract Working Days 441
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 34
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0757-01-020
ABC EROSION CONTROL, INC.(0.61%)
AUSTIN WOOD RECYCLING(0.49%)
TRP CONSTRUCTION GROUP, LLC( 50.52%)
GUERRA UNDERGROUND, LLC(2.61%)
BEAIRD DRILLING(1.78%)
MENDEZ EXCAVATION(0.32%)
TEXAS ROAD BORING(0.32%)
ROADWAY SPECIALTIES, INC.(0.64%)
EVT CONSTRUCTION (1.00%)
Contract # 02143003
Totals 11017549.17 134053.07 4234854.86 38.4

CountyCALDWELL
Highway FM 713
From 0.569 MI. EAST OF FM 86
To 0.698 MI. EAST OF FM 86
CSJ 0805-03-020
Proj ID BR 2014(893)
Work Type REPLACE BRIDGE & APPROACHES
 
0.129 562719.11 13319.94 377302.46 70.1
Work Order 09-09-14
Work Began 01-06-15
Work Completed  
Time Computed 11-08-14
Contract Working Days 130
Addl Days Granted 20
Working Days Charged 139
Percent Time Used 126
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0805-03-020
O & S TRAFFIC SUPPLIES (2.11%)
VOGES DRILLING (4.25%)
FLASHER EQUIPMENT COMPANY(2.21%)
Contract # 07143013
Totals 562719.11 13319.94 377302.46 70.1

CountyHAYS
Highway RM 150
From CENTER STREET
To HAWTHORN DRIVE
CSJ 0805-04-025
Proj ID STP 2013(285)MM
Work Type CONSTRUCT SIDEWALK & BIKE LANES
 
0.758 0.00 0.00 0.00 0.0
CountyHAYS
Highway FM 2770
From FAIRWAY DRIVE
To BOB SHELTON STADIUM
CSJ 3210-01-012
Proj ID STP 2013(285)MM
Work Type CONSTRUCT SIDEWALKS & BIKE LANES
 
0.998 0.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0805-04-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153262
Totals 0.00 0.00 0.00 0.0

CountyBASTROP
Highway FM 535
From FM 20
To MAIN ST
CSJ 0807-01-027
Proj ID STP 2014(014)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
10.546 3806543.90 0.00 3611084.52 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-13
Work Began 01-15-14
Work Completed 01-09-15
Time Computed 01-15-14
Contract Working Days 115
Addl Days Granted 17
Working Days Charged 129
Percent Time Used 97
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0807-01-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.58%)
ROADWAY SPECIALTIES, INC.(1.77%)
RAMI MATERIALS TRANSPORT, LLC(4.55%)
ADAM MEUTH CONSTRUCTION CO.(3.97%)
RAMMING PAVING COMPANY ( 27.30%)
D. I. J. CONSTRUCTION, INC.(3.10%)
NEWMAN & KENG PAVING COMPANY, INC. (6.65%)
Contract # 09133007
Totals 3806543.90 0.00 3611084.52 100.0

CountyBASTROP
Highway FM 535
From SH 21
To FM 20
CSJ 0807-05-019
Proj ID STP 2013(025)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
7.286 4348946.83 0.00 4270251.67 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-28-12
Work Began 02-25-13
Work Completed 08-22-14
Time Computed 01-27-13
Contract Working Days 121
Addl Days Granted 1
Working Days Charged 213
Percent Time Used 174
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0807-05-019
AUSTIN WOOD RECYCLING(1.75%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.63%)
RELMCO, INC. ( 13.62%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.75%)
MURRAY CONSTRUCTION(0.50%)
D. I. J. CONSTRUCTION, INC.(2.23%)
HIGHWAY TECHNOLOGIES, INC. (0.41%)
RICE ENVIRONMENTAL SERVICES(0.11%)
G. CARTER CONSTRUCTION COMPANY, INC. (0.29%)
FLASHER EQUIPMENT COMPANY(0.45%)
Contract # 09123007
Totals 4348946.83 0.00 4270251.67 100.0

CountyBASTROP
Highway FM 535
From 0.052 MI E OF TRAVIS C/L
To 1.252 MI E OF TRAVIS C/L
CSJ 0807-05-020
Proj ID STP 2015(736)
Work Type FULL DEPTH REPAIR & SEAL COAT
 
1.200 301991.50 0.00 298056.78 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-20-15
Work Began 05-28-15
Work Completed 08-06-15
Time Computed 05-21-15
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 30
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0807-05-020
FLASHER EQUIPMENT COMPANY(3.68%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.80%)
AARON CONCRETE CONTRACTORS, L.P. (6.62%)
Contract # 03153204
Totals 301991.50 0.00 298056.78 100.0

CountyTRAVIS
Highway VA
From VARIOUS
To .
CSJ 0914-00-301
Proj ID NH 2012(007)
Work Type FY 2012 NON - SITE SPECIFIC ITS MAINT
 
0.100 4204759.50 63460.45 3631883.20 86.3
Work Order 10-25-11
Work Began 02-21-12
Work Completed  
Time Computed 11-10-11
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 411
Percent Time Used 80
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-301
ROADWAY SPECIALTIES, INC.(2.80%)
AUSTIN UNDERGROUND INCORPORATED(2.05%)
M.G. DRILLING(0.62%)
Contract # 09113230
Totals 4204759.50 63460.45 3631883.20 86.3

CountyTRAVIS
Highway VA
From VARIOUS
To (ON-SYSTEM)
CSJ 0914-00-314
Proj ID NH 2013(027)
Work Type FY 2013 NON - SITE SPECIFIC ITS MAINT
 
0.100 2958819.25 0.00 10000.00 0.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-12-12
Work Began 00-00-00
Work Completed  
Time Computed 10-28-12
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-314
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123244
Totals 2958819.25 0.00 10000.00 0.3

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-319
Proj ID NH 1402(057)
Work Type FY 2014 SITE - SPECIFIC SIGNALS
 
0.100 1113486.77 25630.68 282204.74 25.3
Work Order 11-04-14
Work Began 00-00-00
Work Completed  
Time Computed 11-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 26
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-319
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(2.63%)
HIGHWAY 19 CONSTRUCTION, LLC (9.08%)
TX DOWN UNDER CONSTRUCTION LLC (4.00%)
Contract # 08143029
Totals 1113486.77 25630.68 282204.74 25.3

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-320
Proj ID NH 2014(015)
Work Type FY 2013 SIGNING
 
0.100 452778.70 0.00 439387.51 97.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-13
Work Began 06-17-14
Work Completed  
Time Computed 10-23-13
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-320
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133233
Totals 452778.70 0.00 439387.51 97.0

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-321
Proj ID NH 2015(018)
Work Type FY 2014 SIGNING
 
0.003 495077.78 15071.10 549796.94 99.9
Work Order 10-09-14
Work Began 01-23-15
Work Completed  
Time Computed 01-23-15
Contract Working Days 147
Addl Days Granted 0
Working Days Charged 128
Percent Time Used 87
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-321
ROADWAY SPECIALTIES, INC.( 31.56%)
JCD CONSTRUCTION, LLC(1.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. ( 11.81%)
Contract # 09143036
Totals 495077.78 15071.10 549796.94 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-322
Proj ID STP 2013(476)
Work Type FY 2013 NON - SITE SPECIFIC SIGNALS
 
0.100 865508.00 0.00 1627048.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-13
Work Began 06-24-13
Work Completed  
Time Computed 06-06-13
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 278
Percent Time Used 60
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-322
KRL CONSTRUCTION INC.(6.58%)
D. I. J. CONSTRUCTION, INC.(3.40%)
M.G. DRILLING(5.15%)
CHANDLER CONCRETE, INC.(2.13%)
Contract # 03133223
Totals 865508.00 0.00 1627048.40 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-323
Proj ID STP 2014(533)
Work Type FY 2014 NON - SITE SPECIFIC SIGNALS
 
0.100 991388.00 68194.45 1087216.31 99.9
Work Order 04-25-14
Work Began 07-21-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 312
Addl Days Granted 0
Working Days Charged 229
Percent Time Used 73
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-323
MG DRILLING(5.08%)
BAILEY H.D.D.(0.91%)
KRL CONSTRUCTION INC.(1.33%)
D. I. J. CONSTRUCTION, INC.(2.81%)
Contract # 03143015
Totals 991388.00 68194.45 1087216.31 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-324
Proj ID STP 2013(554)
Work Type FY 2013 SITE - SPECIFIC SIGNALS
 
0.100 870431.70 0.00 900145.83 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 12-02-13
Work Completed  
Time Computed 11-05-13
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 296
Percent Time Used 113
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-324
VACA UNDERGROUND UTILITIES INC (5.67%)
JND CONSTRUCTION CONSULTANTS, LLC( 18.39%)
YORK & YORK FOUNDATION DRILLING, INC.(5.29%)
UNITED PAVEMENT & MARKINGS, LLC(0.00%)
M & M STRIPING & POWER WASHING, LLC(4.60%)
Contract # 04133013
Totals 870431.70 0.00 900145.83 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-343
Proj ID STP 1502(147)
Work Type FY 2015 SITE - SPECIFIC SIGNALS
 
0.003 614705.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-15
Work Began 00-00-00
Work Completed  
Time Computed 08-01-15
Contract Working Days 132
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-343
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153246
Totals 614705.10 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-344
Proj ID NH 2015(575)
Work Type FY 2015 NON - SITE SPECIFIC SIGNALS
 
0.003 1083323.50 0.00 7560.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-344
D. I. J. CONSTRUCTION, INC.(4.07%)
MG DRILLING(3.18%)
KRL CONSTRUCTION INC.( 13.11%)
Contract # 02153027
Totals 1083323.50 0.00 7560.00 0.6

CountyTRAVIS
Highway VA
From VARIOUS ON-SYS LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-345
Proj ID NH 2012(379)
Work Type SCHOOL ZONE UPGRADES
 
0.100 287731.00 0.00 281104.46 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-12
Work Began 12-03-12
Work Completed 01-05-15
Time Computed 07-15-12
Contract Working Days 102
Addl Days Granted 4
Working Days Charged 76
Percent Time Used 71
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-345
CODY DRILLING(5.44%)
ESA ENGINEERING, LLC (5.05%)
Contract # 03123023
Totals 287731.00 0.00 281104.46 100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11