Monthly State Let Construction Report For Austin District As Of May 10, 2016 Page 7 Of 10

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-323
Proj ID STP 2014(533)
Work Type FY 2014 NON - SITE SPECIFIC SIGNALS
 
0.100 991388.00 0.00 1101989.91 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-25-14
Work Began 07-21-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 312
Addl Days Granted 0
Working Days Charged 239
Percent Time Used 76
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-323
MG DRILLING(5.08%)
BAILEY H.D.D.(0.91%)
KRL CONSTRUCTION INC.(1.33%)
D. I. J. CONSTRUCTION, INC.(2.81%)
Contract # 03143015
Totals 991388.00 0.00 1101989.91 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-324
Proj ID STP 2013(554)
Work Type FY 2013 SITE - SPECIFIC SIGNALS
 
0.100 870431.70 847.21 900993.04 100.0
Work Order 07-08-13
Work Began 12-02-13
Work Completed 04-12-16
Time Computed 11-05-13
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 296
Percent Time Used 113
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-324
VACA UNDERGROUND UTILITIES INC (5.67%)
JND CONSTRUCTION CONSULTANTS, LLC( 18.39%)
YORK & YORK FOUNDATION DRILLING, INC.(5.29%)
UNITED PAVEMENT & MARKINGS, LLC(0.00%)
M & M STRIPING & POWER WASHING, LLC(4.60%)
Contract # 04133013
Totals 870431.70 847.21 900993.04 100.0

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-343
Proj ID STP 1502(147)
Work Type FY 2015 SITE - SPECIFIC SIGNALS
 
0.003 614705.10 143317.40 196074.88 31.8
Work Order 07-01-15
Work Began 01-15-16
Work Completed  
Time Computed 08-01-15
Contract Working Days 132
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 48
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-343
M & M STRIPING & POWER WASHING, LLC(4.38%)
UNION ELECTRICAL CONTRACTOR, INC.(8.97%)
Contract # 05153246
Totals 614705.10 143317.40 196074.88 31.8

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-344
Proj ID NH 2015(575)
Work Type FY 2015 NON - SITE SPECIFIC SIGNALS
 
0.003 1083323.50 33029.00 1034700.00 95.5
Work Order 03-20-15
Work Began 08-31-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 47
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-344
D. I. J. CONSTRUCTION, INC.(4.07%)
MG DRILLING(3.18%)
KRL CONSTRUCTION INC.( 13.11%)
G. CARTER CONSTRUCTION COMPANY, INC. (5.57%)
Contract # 02153027
Totals 1083323.50 33029.00 1034700.00 95.5

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To INCLUDE IH 35, SH 71, SL 360, ETC
CSJ 0914-00-367
Proj ID NH 2016(104)
Work Type FY 2016 SIGNING
 
0.003 278620.64 34910.77 99400.98 35.6
Work Order 10-22-15
Work Began 00-00-00
Work Completed  
Time Computed 02-16-19
Contract Working Days 133
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 4
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-367
ROADWAY SPECIALTIES, INC.(9.10%)
JCD CONSTRUCTION, LLC(3.58%)
BREDA COMPANY, INC.(0.00%)
Contract # 09153020
Totals 278620.64 34910.77 99400.98 35.6

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-369
Proj ID NH 1602(020)
Work Type FY 2016 NON - SITE SPECIFIC SIGNALS
 
0.003 1104881.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-369
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163231
Totals 1104881.00 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From VARIOUS ON-SYSTEM LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-374
Proj ID STP 2013(929)
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 816189.28 0.00 820570.39 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-14
Work Began 12-15-14
Work Completed  
Time Computed 06-21-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 288
Percent Time Used 96
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-374
JCD CONSTRUCTION, LLC(0.00%)
TRP CONSTRUCTION GROUP, LLC(2.31%)
Contract # 04143225
Totals 816189.28 0.00 820570.39 99.9

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN
To BASTROP, LEE & CALDWELL COUNTIES
CSJ 0914-00-381
Proj ID STP 1502(148)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.100 994912.00 316775.16 913489.89 91.8
Work Order 07-22-15
Work Began 01-04-16
Work Completed  
Time Computed 08-22-15
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 42
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-381
FLASHER EQUIPMENT COMPANY(2.41%)
W.A. ROBBINS CONSTRUCTION CO., INC.(7.14%)
Contract # 05153046
Totals 994912.00 316775.16 913489.89 91.8

CountyTRAVIS
Highway CS
From 1.2 MI. EAST OF OLD HWY 20
To 0.2 MI. WEST OF BITTING SCHOOL RD.
CSJ 0914-04-292
Proj ID STP 2015(604)HES
Work Type HIGH FRICTION SURFACE TREATMENT
 
3.210 311425.79 0.00 336867.37 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-15
Work Began 01-05-16
Work Completed  
Time Computed 09-20-15
Contract Working Days 12
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-292
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153027
Totals 311425.79 0.00 336867.37 99.9

CountyTRAVIS
Highway VA
From WITHIN TPWD HEADQUARTERS
To .
CSJ 0914-04-297
Proj ID C 914-4-297
Work Type MILL AND OVERLAY
 
0.003 172877.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 12
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-297
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163011
Totals 172877.64 0.00 0.00 0.0

CountyBASTROP
Highway VA
From AT BUESCHER STATE PARK
To .
CSJ 0914-18-102
Proj ID C 914-18-102
Work Type OVERLAY
 
2.968 1227537.85 0.00 1242433.71 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 07-27-15
Work Completed 05-03-16
Time Computed 07-21-15
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 127
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-102
ENVIRONMENTAL SAFETY SERVICES, INC.(0.15%)
TRP CONSTRUCTION GROUP, LLC(2.07%)
PEDRO CARLOS CONSTRUCTION CO.(2.24%)
Contract # 04153005
Totals 1227537.85 0.00 1242433.71 100.0

CountyGILLESPIE
Highway CR
From ON OLD SAN ANTONIO AT PEDERNALES
To STR AA0119002
CSJ 0914-19-022
Proj ID BR 2012(703)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.500 2659843.09 59843.39 2227677.89 83.7
Work Order 04-09-14
Work Began 05-05-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 623
Addl Days Granted 0
Working Days Charged 400
Percent Time Used 64
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-022
O & S TRAFFIC SUPPLIES (0.95%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.68%)
ALLEN KELLER COMPANY ( 24.37%)
J R RAMON, INC.(2.72%)
JUST GROOVING, LTD.(0.22%)
ROADWAY SPECIALTIES, INC.(4.79%)
FLASHER EQUIPMENT COMPANY(0.72%)
MESA ROD BUSTERS, INC. (0.25%)
METALINK CORPORATION (0.29%)
Contract # 02143012
Totals 2659843.09 59843.39 2227677.89 83.7

CountyLLANO
Highway CR
From ON CR 202 AT LITTLE LLANO
To STR AA0630001
CSJ 0914-25-007
Proj ID BR 2011(982)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 299364.78 19984.41 234304.60 97.2
Work Order 03-26-15
Work Began 06-22-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 52
Addl Days Granted 5
Working Days Charged 72
Percent Time Used 126
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-007
N LINE TRAFFIC CONTROL (3.62%)
RICE ENVIRONMENTAL SERVICES(7.82%)
DAVID MEIER CONSTRUCTION (5.67%)
MATOKA, INC. (4.80%)
LONE STAR PAVING (5.25%)
ROADWAY SPECIALTIES, INC.(0.40%)
ROAD MASTER STRIPING LLC (2.33%)
Contract # 02153214
Totals 299364.78 19984.41 234304.60 97.2

CountyMASON
Highway CS
From ON BROAD ST AT COMANCHE CREEK
To STR. B00300001
CSJ 0914-26-006
Proj ID BR 2007(154)
Work Type CONST NEW BRDG & REPAIR EXSTG BRDG
 
0.100 1239821.20 111726.88 111726.88 9.0
Work Order 02-16-16
Work Began 04-06-16
Work Completed  
Time Computed 03-17-16
Contract Working Days 116
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 6
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0914-26-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153236
Totals 1239821.20 111726.88 111726.88 9.0

CountyHAYS
Highway CR
From FISCHER STORE ROAD AT BLANCO RIVER
To .(STR NO. AA01-80-001)
CSJ 0914-33-071
Proj ID BR 2016(249)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.114 1532523.36 0.00 1730410.90 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-15
Work Began 11-23-15
Work Completed  
Time Computed 11-23-15
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-071
AARON CONCRETE CONTRACTORS, L.P. (3.25%)
ENVIRONMENTAL SAFETY SERVICES, INC.(3.34%)
FLASHER EQUIPMENT COMPANY(0.61%)
HOUSTON SAWING & DRILLING(0.20%)
VOGES DRILLING CO. (2.51%)
LONE STAR PAVING COMPANY (2.01%)
FRANK JR REINFORCEMENT LLC (0.38%)
GK CONSTRUCTION, LLC (0.12%)
INDUS CONSTRUCTION, L.P. (0.16%)
Contract # 09153232
Totals 1532523.36 0.00 1730410.90 99.9

CountyWILLIAMSON
Highway FM 619
From 0.089 MI. NORTH OF BRUSHY CREEK
To 0.100 MI. SOUTH OF BRUSHY CREEK
CSJ 0986-01-042
Proj ID BR 1502(149)
Work Type REPLACE BRIDGE
 
0.189 1143838.60 0.00 1185587.03 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-14-15
Work Began 11-19-15
Work Completed  
Time Computed 11-12-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 97
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 0986-01-042
APAC-TEXAS, INC. (4.98%)
BEAIRD DRILLING(7.74%)
FLASHER EQUIPMENT COMPANY(0.52%)
ROADWAY SPECIALTIES, INC.(2.43%)
Contract # 05153051
Totals 1143838.60 0.00 1185587.03 99.9

CountyBASTROP
Highway FM 696
From 1.165 MI N OF US 290
To 1.296 MI N OF US 290
CSJ 1073-01-020
Proj ID BR 1502(072)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.131 2191679.00 114436.84 992600.80 45.2
Work Order 08-26-15
Work Began 01-05-16
Work Completed  
Time Computed 10-25-15
Contract Working Days 202
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 41
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1073-01-020
ROADWAY SPECIALTIES, INC.(1.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.35%)
MESA ROD BUSTERS, INC. (0.82%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.95%)
AUSTIN WOOD RECYCLING(0.71%)
MURRAY CONSTRUCTION(0.14%)
TEXAS CUTTING & CORING, INC. (0.20%)
Contract # 06153008
Totals 2191679.00 114436.84 992600.80 45.2

CountyTRAVIS
Highway FM 969
From DECKER CREEK DRIVE
To BASTROP COUNTY LINE
CSJ 1186-01-087
Proj ID STP 2015(277)HES
Work Type PROVIDE ADD'L PAVED SURFACE WIDTH
 
7.101 5894316.37 3000.00 2904907.30 49.2
Work Order 01-05-15
Work Began 03-17-15
Work Completed  
Time Computed 03-17-15
Contract Working Days 398
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 54
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087
ENVIRONMENTAL SAFETY SERVICES, INC.(7.14%)
TRP CONSTRUCTION GROUP, LLC(2.30%)
LONE STAR PAVING, INC. ( 47.54%)
Contract # 11143219
Totals 5894316.37 3000.00 2904907.30 49.2

CountyTRAVIS
Highway FM 969
From TANNEHILL LANE
To FM 3177
CSJ 1186-01-089
Proj ID STP 2016(636)
Work Type MILL, SEAL & TY D OVERLAY
 
2.051 1000145.83 0.00 0.00 0.0
CountyTRAVIS
Highway FM 969
From AIRPORT BLVD
To TANNEHILL LN
CSJ 1186-01-093
Proj ID STP 2016(853)
Work Type MILL, SEAL & OVERLAY
 
2.083 1067405.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163028
Totals 2067551.68 0.00 0.00 0.0

CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-028
Proj ID BR 2013(930)
Work Type REPLACE BRIDGE & APPROACHES
 
1.530 11659867.54 649182.17 9976710.78 85.5
CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-048
Proj ID STP 2012(591)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.530 2188836.25 215.00 2216990.04 99.9
Work Order 02-13-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 296
Addl Days Granted 8
Working Days Charged 301
Percent Time Used 99
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
C4 CONSTRUCTION SERVICES, LLC(0.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.67%)
LINDAMOOD DEMOLITION, INC. (0.95%)
MURRAY CONSTRUCTION(0.13%)
ROADWAY SPECIALTIES, INC.(1.54%)
M & M STRIPING & POWER WASHING, LLC(0.43%)
AARON CONCRETE CONTRACTORS, L.P. (0.81%)
AUSTIN WOOD RECYCLING(0.28%)
BRYANT & FREY CONSTRUCTION (1.50%)
TEX OP CONSTRUCTION, LP(0.14%)
APAC-TEXAS, INC. ( 11.02%)
CP REBAR AND PT INSTALLATION (0.46%)
PRIMATE CONSTRUCTION, INC. (0.12%)
MCKINNEY DRILLING COMPANY(2.77%)
TEXAS HIGHWAY WALLS(3.63%)
PANTHER CREEK TRANSPORTATION, INC. (0.89%)
Contract # 12133203
Totals 13848703.79 649397.17 12193700.82 88.0