Monthly State Let Construction Report For Austin District As Of Dec 10, 2014 Page 7 Of 8

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To 600 FT. SOUTH OF MURCHISON ST.
CSJ 1200-03-045
Proj ID CC 1200-3-45
Work Type ADD CONTINUOUS LEFT TURN LANE
 
0.312 85872.74 0.00 0.00 0.0
CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To DECKER CREEK
CSJ 1200-03-052
Proj ID STP 1402(058)
Work Type REHAB RDWY, ADD 6' SHOULDERS
 
4.911 3246677.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-14
Work Began 00-00-00
Work Completed  
Time Computed 11-28-14
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143236
Totals 3332550.36 0.00 0.00 0.0

CountyTRAVIS
Highway FM 973
From 3880 FT SOUTH OF SH 71
To FM 812
CSJ 1200-03-046
Proj ID STP 2014(621)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
3.418 4060301.69 115357.26 1353046.60 33.3
Work Order 05-29-14
Work Began 08-07-14
Work Completed  
Time Computed 07-28-14
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 22
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-046
AUSTIN WOOD RECYCLING(1.13%)
CHEROKEE SERVICES(0.13%)
FLASHER EQUIPMENT COMPANY(2.42%)
ROADWAY SPECIALTIES, INC.(7.52%)
TRP CONSTRUCTION GROUP, LLC(0.43%)
RELMCO, INC. ( 13.01%)
HAYWOOD BAKER(4.07%)
THE LEVY COMPANY, L.P. (0.10%)
MURRAY CONSTRUCTION(0.53%)
VOGES DRILLING CO. (1.38%)
Contract # 04143030
Totals 4060301.69 115357.26 1353046.60 33.3

CountyTRAVIS
Highway FM 973
From FM 812
To US 183
CSJ 1200-05-016
Proj ID STP 2014(559)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
2.466 3060816.52 373441.71 1574090.12 51.4
Work Order 06-16-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 46
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-016
AUSTIN WOOD RECYCLING(1.13%)
D. I. J. CONSTRUCTION, INC.(1.12%)
THE LEVY COMPANY, L.P. (0.14%)
MURRAY CONSTRUCTION(0.88%)
RELMCO, INC. ( 30.62%)
ROADWAY SPECIALTIES, INC.(4.85%)
TRP CONSTRUCTION GROUP, LLC(0.28%)
Contract # 04143018
Totals 3060816.52 373441.71 1574090.12 51.4

CountyTRAVIS
Highway SH 45
From LOOP 1
To RM 1826
CSJ 1200-06-010
Proj ID STP 2014(724)
Work Type MILL, SEAL & THIN OVERLAY
 
2.599 1283793.90 13582.87 1041803.96 81.6
Work Order 08-04-14
Work Began 09-03-14
Work Completed  
Time Computed 08-20-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 121
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-010
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
D. I. J. CONSTRUCTION, INC.(3.74%)
ROADWAY SPECIALTIES, INC.(4.80%)
Contract # 06143028
Totals 1283793.90 13582.87 1041803.96 81.6

CountyWILLIAMSON
Highway FM 487
From SH 195
To 1500 FEET WEST OF CR 233
CSJ 1201-02-019
Proj ID STP 2014(420)
Work Type REHAB RDWY
 
5.303 6128687.87 141278.49 1802569.41 29.4
Work Order 04-16-14
Work Began 06-25-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 287
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 30
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019
AARON CONCRETE CONTRACTORS, L.P. (1.40%)
AUSTIN WOOD RECYCLING(1.19%)
TEXAS HIGHWAY WALLS(5.57%)
R K STEPHENS CONSTRUCTION, LLC (3.21%)
D. I. J. CONSTRUCTION, INC.(0.77%)
J & M CONTRACTING, COMPANY (7.41%)
ROADWAY SPECIALTIES, INC.(2.24%)
SAN-ANN-CO., INC.(0.55%)
LONE STAR PAVING CO. ( 10.66%)
Contract # 02143227
Totals 6128687.87 141278.49 1802569.41 29.4

CountyWILLIAMSON
Highway FM 487
From 1500 FEET WEST OF CR 233
To IH 35
CSJ 1201-02-021
Proj ID STP 2015(190)
Work Type REHAB RDWY
 
7.186 9058441.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143016
Totals 9058441.29 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 487
From BELL C/L
To BELL C/L IN BARTLETT
CSJ 1201-03-021
Proj ID STP 2012(417)
Work Type PAVMNT RESTORATION AND ADD SHLDRS
 
7.520 6421595.35 491211.87 6401358.89 99.6
CountyBELL
Highway FM 487
From WILLIAMSON CO LINE W OF FM 2115
To WILLIAMSON CO LINE E OF FM 2115
CSJ 1201-05-010
Proj ID STP 2012(423)
Work Type PAV RESTORATION AND ADD SHOULDERS
 
0.395 285832.17 0.00 288962.04 99.9
Work Order 05-04-12
Work Began 05-20-13
Work Completed  
Time Computed 05-20-12
Contract Working Days 391
Addl Days Granted 0
Working Days Charged 308
Percent Time Used 78
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1201-03-021
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
SILVA CONTRACTING COMPANY, INC.( 11.18%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%)
MURRAY CONSTRUCTION(0.48%)
D. I. J. CONSTRUCTION, INC.(1.28%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.04%)
JAG TRUCKING INC (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
THE LEVY COMPANY, L.P. (0.25%)
R K STEPHENS CONSTRUCTION, LLC (6.66%)
Contract # 03123002
Totals 6707427.52 491211.87 6690320.93 99.7

CountyWILLIAMSON
Highway FM 972
From 0.652 MI E OF FM 1105
To 0.841 MI E OF FM 1105
CSJ 1202-01-016
Proj ID BR 2013(932)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.189 535693.01 0.00 566239.64 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-13
Work Began 01-16-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 91
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1202-01-016
GK CONSTRUCTION, LLC (1.06%)
BEAIRD DRILLING(4.90%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.46%)
ROADWAY SPECIALTIES, INC.(2.84%)
RAMMING PAVING COMPANY (8.93%)
D. I. J. CONSTRUCTION, INC.(1.12%)
Contract # 08133270
Totals 535693.01 0.00 566239.64 99.9

CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK
To (STR 1202-3-12)
CSJ 1202-03-010
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.115 643228.90 142694.22 475151.34 73.8
CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK RELIEF
To (STR 1202-3-11)
CSJ 1202-03-011
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.064 286828.45 30231.85 176904.59 61.6
CountyWILLIAMSON
Highway FM 1063
From AT DRAW
To (STR 1202-3-10)
CSJ 1202-03-012
Proj ID BR 2014(673)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.131 609386.85 0.00 592431.18 97.2
Work Order 04-25-14
Work Began 05-19-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 83
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1202-03-010
FLASHER EQUIPMENT COMPANY(1.52%)
GK CONSTRUCTION, LLC (0.78%)
HOUSTON SAWING & DRILLING(0.23%)
ROADWAY SPECIALTIES, INC.(0.62%)
APAC-TEXAS, INC. (9.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.81%)
SAN-ANN-CO., INC.(0.42%)
Contract # 03143222
Totals 1539444.20 172926.07 1244487.11 80.8

CountyTRAVIS
Highway FM 1325
From LP 1
To US 183
CSJ 1376-02-039
Proj ID STP 2013(478)
Work Type MILL, SEAL & THIN OVERLAY
 
2.500 2027036.96 0.00 1734155.12 86.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-13
Work Began 09-30-13
Work Completed  
Time Computed 08-02-13
Contract Working Days 50
Addl Days Granted 26
Working Days Charged 92
Percent Time Used 121
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1376-02-039
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.98%)
D. I. J. CONSTRUCTION, INC.(3.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C. (2.98%)
ROADWAY SPECIALTIES, INC.(0.42%)
NEWMAN & KENG PAVING COMPANY, INC. ( 19.25%)
TEX OP CONSTRUCTION, LP(0.43%)
TEXAS TRUCKING COMPANY, INC. (3.37%)
Contract # 03133230
Totals 2027036.96 0.00 1734155.12 86.1

CountyWILLIAMSON
Highway RM 1431
From 0.2 MI E OF CR 185
To IH 35
CSJ 1378-02-033
Proj ID STP 2012(251)
Work Type FULL DEPTH REPAIR, SEAL & THIN OV
 
6.888 2895175.70 0.00 2383441.75 83.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-22-12
Work Began 06-03-13
Work Completed  
Time Computed 03-09-12
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 162
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-033
D. I. J. CONSTRUCTION, INC.(4.01%)
CPAVE, INC.(2.17%)
RPV CONSTRUCTION ( 15.51%)
Contract # 01123226
Totals 2895175.70 0.00 2383441.75 83.4

CountyWILLIAMSON
Highway RM 1431
From FM 734
To CR 175
CSJ 1378-02-036
Proj ID PTF 2014(560)
Work Type WIDEN TO 6 - LANE URBAN ROADWAY
 
1.491 17353255.75 1010912.07 3353890.70 19.3
Work Order 06-05-14
Work Began 08-17-14
Work Completed  
Time Computed 06-21-14
Contract Working Days 269
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 22
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-036
AARON CONCRETE CONTRACTORS, L.P. (4.48%)
ABC EROSION CONTROL, INC.(0.65%)
AUSTIN WOOD RECYCLING(0.11%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.30%)
FLASHER EQUIPMENT COMPANY(1.47%)
G. CARTER CONSTRUCTION COMPANY, INC. (7.06%)
GK CONSTRUCTION, LLC (0.07%)
KELLYSTONE, INC(0.94%)
ROADWAY SPECIALTIES, INC.(2.95%)
ROYAL VISTA INC. ( 16.40%)
VOGES DRILLING CO. (0.14%)
Contract # 04143201
Totals 17353255.75 1010912.07 3353890.70 19.3

CountyWILLIAMSON
Highway RM 1431
From US 183
To 183-A
CSJ 1378-02-037
Proj ID STP 1102(351)
Work Type LANDSCAPING, IRRIGATION & PAVERS
 
0.904 357255.50 0.00 347858.62 97.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-11
Work Began 03-05-12
Work Completed  
Time Computed 12-12-11
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 95
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-037
N-LINE TRAFFIC MAINTENANCE, L.P. (1.04%)
Contract # 08113010
Totals 357255.50 0.00 347858.62 97.3

CountyWILLIAMSON
Highway RM 1431
From ANDERSON MILL RD
To 600 FT WEST OF 183A
CSJ 1378-02-039
Proj ID C 1378-2-39
Work Type INNOVATIVE INTERSECTION IMPROVEMNTS
 
1.417 3965954.63 0.00 2722704.63 68.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-13
Work Began 03-05-14
Work Completed  
Time Computed 01-12-14
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 100
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-039
PERFORMANCE EQUIPMENT(0.15%)
RAMMING PAVING COMPANY ( 40.83%)
ROADWAY SPECIALTIES, INC.(0.58%)
FLASHER EQUIPMENT COMPANY(4.37%)
G. CARTER CONSTRUCTION COMPANY, INC. (7.73%)
Contract # 08133073
Totals 3965954.63 0.00 2722704.63 68.6

CountyWILLIAMSON
Highway RM 1431
From 1000 WEST OF CHANDLER CREEK
To 200 EAST OF UNIVERSITY OAKS BLVD.
CSJ 1378-02-040
Proj ID STP 2013(297)
Work Type CONST DIVERGING DIAMOND INTRSCTN
 
0.392 6684011.97 490792.57 521665.87 7.8
Work Order 08-13-14
Work Began 10-20-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 15
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-040
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37%)
ROADWAY SPECIALTIES, INC.(5.23%)
CHEROKEE SERVICES(0.32%)
SPEEDY PAVING(1.10%)
Contract # 06143242
Totals 6684011.97 490792.57 521665.87 7.8

CountyWILLIAMSON
Highway RM 1431
From 183A (TOLL) NBFR
To 0.20 MI. EAST OF CR 185
CSJ 1378-02-045
Proj ID STP 2014(938)
Work Type MILL, SEAL, OVRLAY & RESTRP TO 6 - LN
 
0.821 430708.20 4127.90 507494.63 99.9
Work Order 08-15-14
Work Began 09-23-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 88
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-045
D. I. J. CONSTRUCTION, INC.(8.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.81%)
Contract # 07143241
Totals 430708.20 4127.90 507494.63 99.9

CountyCALDWELL
Highway FM 1977
From SAN MARCOS RIVER
To (STR 1434-03-002)
CSJ 1434-03-010
Proj ID BR 2013(250)
Work Type REPLACE BRIDGE & APPROACHES
 
0.104 1254724.88 411.88 984357.09 91.2
Work Order 01-15-13
Work Began 06-10-13
Work Completed  
Time Computed 01-31-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 314
Percent Time Used 392
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1434-03-010
O & S TRAFFIC SUPPLIES (0.51%)
RICE ENVIRONMENTAL SERVICES(3.26%)
FLASHER EQUIPMENT COMPANY(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 16.88%)
Contract # 12123209
Totals 1254724.88 411.88 984357.09 91.2

CountyHAYS
Highway RM 1826
From AT DARDEN HILL RD
To .
CSJ 1754-02-019
Proj ID CC 1754-2-19
Work Type ADD TURN LANES & SHOULDERS
 
0.365 746842.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
M.A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143210
Totals 746842.80 0.00 0.00 0.0

CountyHAYS
Highway RM 1826
From TRAVIS C/L
To RM 150
CSJ 1754-02-024
Proj ID STP 2015(193)HESG
Work Type C.L & SHOULDERS RAISED PROF MARKS
 
26.276 605145.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 11-30-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143009
Totals 605145.34 0.00 0.00 0.0

CountyHAYS
Highway RM 967
From COLE SPRING ROAD
To FM 1626
CSJ 1776-01-032
Proj ID STP 2013(655)
Work Type ADD TWLTL AND SHOULDERS
 
2.618 4408237.86 124509.90 607101.45 13.7
Work Order 07-11-14
Work Began 09-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 19
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1776-01-032
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
AUSTIN WOOD RECYCLING(1.86%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.21%)
FLASHER EQUIPMENT COMPANY(0.45%)
FUQUAY, INC. (1.42%)
RAMMING PAVING COMPANY ( 32.68%)
ROADWAY SPECIALTIES, INC.(1.40%)
Contract # 05143014
Totals 4408237.86 124509.90 607101.45 13.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8