Monthly State Let Construction Report For Austin District As Of Jun 10, 2015 Page 7 Of 10

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-323
Proj ID STP 2014(533)
Work Type FY 2014 NON - SITE SPECIFIC SIGNALS
 
0.100 991388.00 74654.62 990888.46 99.9
Work Order 04-25-14
Work Began 07-21-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 312
Addl Days Granted 0
Working Days Charged 191
Percent Time Used 61
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-323
MG DRILLING(5.08%)
BAILEY H.D.D.(0.91%)
KRL CONSTRUCTION INC.(1.33%)
D. I. J. CONSTRUCTION, INC.(2.81%)
Contract # 03143015
Totals 991388.00 74654.62 990888.46 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-324
Proj ID STP 2013(554)
Work Type FY 2013 SITE - SPECIFIC SIGNALS
 
0.100 870431.70 0.00 900145.83 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 12-02-13
Work Completed  
Time Computed 11-05-13
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 296
Percent Time Used 113
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-324
VACA UNDERGROUND UTILITIES INC (5.67%)
JND CONSTRUCTION CONSULTANTS, LLC( 18.39%)
YORK & YORK FOUNDATION DRILLING, INC.(5.29%)
UNITED PAVEMENT & MARKINGS, LLC(0.00%)
M & M STRIPING & POWER WASHING, LLC(4.60%)
Contract # 04133013
Totals 870431.70 0.00 900145.83 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-343
Proj ID STP 1502(147)
Work Type FY 2015 SITE - SPECIFIC SIGNALS
 
0.003 614705.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 132
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-343
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153246
Totals 614705.10 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-344
Proj ID NH 2015(575)
Work Type FY 2015 NON - SITE SPECIFIC SIGNALS
 
0.003 1083323.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-344
D. I. J. CONSTRUCTION, INC.(4.07%)
MG DRILLING(3.18%)
KRL CONSTRUCTION INC.( 13.11%)
Contract # 02153027
Totals 1083323.50 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From VARIOUS ON-SYS LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-345
Proj ID NH 2012(379)
Work Type SCHOOL ZONE UPGRADES
 
0.100 287731.00 0.00 281104.46 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-12
Work Began 12-03-12
Work Completed 01-05-15
Time Computed 07-15-12
Contract Working Days 102
Addl Days Granted 4
Working Days Charged 76
Percent Time Used 71
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-345
CODY DRILLING(5.44%)
ESA ENGINEERING, LLC (5.05%)
Contract # 03123023
Totals 287731.00 0.00 281104.46 100.0

CountyTRAVIS
Highway VA
From VARIOUS ON-SYSTEM LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-374
Proj ID STP 2013(929)
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 816189.28 43248.57 583431.62 71.4
Work Order 06-05-14
Work Began 12-15-14
Work Completed  
Time Computed 06-21-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 156
Percent Time Used 52
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-374
JCD CONSTRUCTION, LLC(0.00%)
Contract # 04143225
Totals 816189.28 43248.57 583431.62 71.4

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-379
Proj ID STP 2014(723)
Work Type SIGN IMPROVEMENT
 
0.001 266630.98 0.00 146343.36 54.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-18-14
Work Began 11-03-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 15
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-379
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143040
Totals 266630.98 0.00 146343.36 54.8

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN
To BASTROP, LEE & CALDWELL COUNTIES
CSJ 0914-00-381
Proj ID STP 1502(148)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.100 994912.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-381
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153046
Totals 994912.00 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To ON IH 35 AND ON US 183
CSJ 0914-04-269
Proj ID STP 2012(551)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 775000.00 0.00 669177.84 86.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 08-13-12
Work Completed  
Time Computed 08-13-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 98
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123049
Totals 775000.00 0.00 669177.84 86.3

CountyTRAVIS
Highway CS
From 1.2 MI. EAST OF OLD HWY 20
To 0.2 MI. WEST OF BITTING SCHOOL RD.
CSJ 0914-04-292
Proj ID STP 2015(604)HES
Work Type HIGH FRICTION SURFACE TREATMENT
 
3.210 311425.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 12
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-292
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153027
Totals 311425.79 0.00 0.00 0.0

CountyWILLIAMSON
Highway CR
From ON CR 111 AT NORTH FORK MCNUTT CRK
To (STR AA0535001)
CSJ 0914-05-142
Proj ID BR 1102(561)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.087 609359.30 0.00 614193.52 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-14
Work Began 08-14-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 97
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-142
APAC-TEXAS, INC. ( 20.18%)
D. I. J. CONSTRUCTION, INC.(0.75%)
O & S TRAFFIC SUPPLIES (0.62%)
ROADWAY SPECIALTIES, INC.(5.09%)
CAPITOL CONCRETE CONTRACTORS, INC. (1.56%)
Contract # 03143229
Totals 609359.30 0.00 614193.52 99.9

CountyWILLIAMSON
Highway CS
From COLORADO ST @ WILLIS CREEK BRANCH
To STR# 246-J001-15-001
CSJ 0914-05-173
Proj ID BR 2014(427)
Work Type REPLACE BRIDGE & APPROACHES
 
0.068 627714.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-14-15
Work Began 00-00-00
Work Completed  
Time Computed 06-14-15
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-173
FLASHER EQUIPMENT COMPANY(1.35%)
APAC-TEXAS, INC. (FORT WORTH)( 11.12%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.46%)
Contract # 03153038
Totals 627714.08 0.00 0.00 0.0

CountyBASTROP
Highway CR
From ON PAINT CRK RD AT PAINT CRK
To AA01-62-001
CSJ 0914-18-092
Proj ID BR 2014(690)
Work Type REPLACE BRIDGE & APPROACHES
 
0.072 542982.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153204
Totals 542982.86 0.00 0.00 0.0

CountyBASTROP
Highway VA
From AT BUESCHER STATE PARK
To .
CSJ 0914-18-102
Proj ID C 914-18-102
Work Type OVERLAY
 
2.968 1227537.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 07-21-15
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153005
Totals 1227537.85 0.00 0.00 0.0

CountyGILLESPIE
Highway CR
From ON OLD SAN ANTONIO AT PEDERNALES
To STR AA0119002
CSJ 0914-19-022
Proj ID BR 2012(703)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.500 2659843.09 11224.83 1510266.41 56.7
Work Order 04-09-14
Work Began 05-05-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 623
Addl Days Granted 0
Working Days Charged 192
Percent Time Used 30
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-022
O & S TRAFFIC SUPPLIES (0.95%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.68%)
ALLEN KELLER COMPANY ( 24.37%)
J R RAMON, INC.(2.72%)
JUST GROOVING, LTD.(0.22%)
ROADWAY SPECIALTIES, INC.(4.79%)
FLASHER EQUIPMENT COMPANY(0.72%)
MESA ROD BUSTERS, INC. (0.25%)
Contract # 02143012
Totals 2659843.09 11224.83 1510266.41 56.7

CountyLEE
Highway CR
From ON CR 306 AT MIDDLE YEGUA CREEK
To STR AA01-24-001
CSJ 0914-21-029
Proj ID BR 2012(236)
Work Type REPLACE BRIDGE & APPROACHES
 
0.059 255411.33 0.00 181804.10 99.9
CountyLEE
Highway CR
From ON CR 113 AT ELM CREEK
To STR AA00-34-001
CSJ 0914-21-030
Proj ID BR 2012(235)
Work Type REPLACE BRIDGE & APPROACHES
 
0.072 314588.67 0.00 305693.15 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 08-19-13
Work Completed  
Time Computed 08-18-13
Contract Working Days 98
Addl Days Granted 23
Working Days Charged 181
Percent Time Used 149
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-029
ROADWAY SPECIALTIES, INC.(3.59%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.08%)
BATTEN DRILLING, INC.(7.56%)
JIM"S SAND & GRAVEL(2.05%)
LONE STAR PAVING CO. (5.98%)
Contract # 05133025
Totals 570000.00 0.00 487497.25 99.1

CountyCALDWELL
Highway CR
From ON OAK GROVE RD AT W FORK PLUM CRK
To (STR AA02-28-001)
CSJ 0914-22-056
Proj ID BR 2013(195)
Work Type REPLACE BRIDGE & APPROACHES
 
0.155 656797.82 35545.04 688583.23 99.9
CountyCALDWELL
Highway CR
From ON OAK GROVE ROAD (CR 127) @
To TRIBUTARY TO WEST FORK PLUM CREEK
CSJ 0914-22-062
Proj ID CC 914-22-62
Work Type REPLACE STRUCTURE & APPROACHES
 
0.051 160259.62 400.20 151932.18 94.8
Work Order 07-10-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 109
Addl Days Granted 12
Working Days Charged 116
Percent Time Used 95
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-056
O & S TRAFFIC SUPPLIES (0.66%)
CL CONCRETE( 12.36%)
DOUBLE S PAVING, INC.( 12.00%)
VOGES DRILLING CO. (2.04%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.60%)
FUQUAY, INC. (0.25%)
LONE STAR PAVING (0.00%)
Contract # 05143036
Totals 817057.44 35945.24 840515.41 99.9

CountyCALDWELL
Highway CS
From ON N WALNUT AVE AT SALT BRANCH CRK
To (STR C004-71-001)
CSJ 0914-22-057
Proj ID BR 2014(691)
Work Type REPLACE BRIDGE & APPROACHES
 
0.045 291669.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153060
Totals 291669.35 0.00 0.00 0.0

CountyCALDWELL
Highway VA
From WITHIN LOCKHART STATE PARK
To .
CSJ 0914-22-065
Proj ID C 914-22-65
Work Type REPAIR & RESURFACE ROADWAY
 
1.850 405128.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-15
Work Began 00-00-00
Work Completed  
Time Computed 07-02-15
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153208
Totals 405128.50 0.00 0.00 0.0

CountyBURNET
Highway CR
From ON CR 202 AT N FORK SAN GABRIEL RVR
To STR AA06-22-001
CSJ 0914-24-016
Proj ID BR 2014(460)
Work Type REPLACE BRIDGE & APPROACHES
 
0.036 285095.75 16671.40 270633.95 94.9
Work Order 01-05-15
Work Began 02-04-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 83
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0914-24-016
SAN-ANN-CO., INC.(2.21%)
ROADWAY SPECIALTIES, INC.(7.37%)
D. I. J. CONSTRUCTION, INC.(0.56%)
JUST GROOVING, LTD.(0.43%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.92%)
Contract # 11143007
Totals 285095.75 16671.40 270633.95 94.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10