Monthly State Let Construction Report For Austin District As Of Jul 13, 2015 Page 7 Of 11

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBASTROP
Highway FM 535
From 0.052 MI E OF TRAVIS C/L
To 1.252 MI E OF TRAVIS C/L
CSJ 0807-05-020
Proj ID STP 2015(736)
Work Type FULL DEPTH REPAIR & SEAL COAT
 
1.200 301991.50 224867.16 298056.78 98.6
Work Order 04-20-15
Work Began 05-28-15
Work Completed  
Time Computed 05-21-15
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 30
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0807-05-020
FLASHER EQUIPMENT COMPANY(3.68%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.80%)
AARON CONCRETE CONTRACTORS, L.P. (6.62%)
Contract # 03153204
Totals 301991.50 224867.16 298056.78 98.6

CountyTRAVIS
Highway VA
From VARIOUS
To .
CSJ 0914-00-301
Proj ID NH 2012(007)
Work Type FY 2012 NON - SITE SPECIFIC ITS MAINT
 
0.100 4204759.50 10522.50 3568422.75 84.8
Work Order 10-25-11
Work Began 02-21-12
Work Completed  
Time Computed 11-10-11
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 411
Percent Time Used 80
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-301
ROADWAY SPECIALTIES, INC.(2.80%)
AUSTIN UNDERGROUND INCORPORATED(2.05%)
M.G. DRILLING(0.62%)
Contract # 09113230
Totals 4204759.50 10522.50 3568422.75 84.8

CountyTRAVIS
Highway VA
From VARIOUS
To (ON-SYSTEM)
CSJ 0914-00-314
Proj ID NH 2013(027)
Work Type FY 2013 NON - SITE SPECIFIC ITS MAINT
 
0.100 2958819.25 0.00 10000.00 0.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-12-12
Work Began 00-00-00
Work Completed  
Time Computed 10-28-12
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-314
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123244
Totals 2958819.25 0.00 10000.00 0.3

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-319
Proj ID NH 1402(057)
Work Type FY 2014 SITE - SPECIFIC SIGNALS
 
0.100 1113486.77 31154.58 256574.06 23.0
Work Order 11-04-14
Work Began 00-00-00
Work Completed  
Time Computed 11-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 21
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-319
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(2.63%)
Contract # 08143029
Totals 1113486.77 31154.58 256574.06 23.0

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-320
Proj ID NH 2014(015)
Work Type FY 2013 SIGNING
 
0.100 452778.70 0.00 439387.51 97.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-13
Work Began 06-17-14
Work Completed  
Time Computed 10-23-13
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-320
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133233
Totals 452778.70 0.00 439387.51 97.0

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-321
Proj ID NH 2015(018)
Work Type FY 2014 SIGNING
 
0.003 495077.78 116155.59 534725.84 99.9
Work Order 10-09-14
Work Began 01-23-15
Work Completed  
Time Computed 01-23-15
Contract Working Days 147
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 72
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-321
ROADWAY SPECIALTIES, INC.( 31.56%)
JCD CONSTRUCTION, LLC(1.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. ( 11.81%)
Contract # 09143036
Totals 495077.78 116155.59 534725.84 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-322
Proj ID STP 2013(476)
Work Type FY 2013 NON - SITE SPECIFIC SIGNALS
 
0.100 865508.00 0.00 1627048.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-13
Work Began 06-24-13
Work Completed  
Time Computed 06-06-13
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 278
Percent Time Used 60
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-322
KRL CONSTRUCTION INC.(6.58%)
D. I. J. CONSTRUCTION, INC.(3.40%)
M.G. DRILLING(5.15%)
CHANDLER CONCRETE, INC.(2.13%)
Contract # 03133223
Totals 865508.00 0.00 1627048.40 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-323
Proj ID STP 2014(533)
Work Type FY 2014 NON - SITE SPECIFIC SIGNALS
 
0.100 991388.00 28133.40 1019021.86 99.9
Work Order 04-25-14
Work Began 07-21-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 312
Addl Days Granted 0
Working Days Charged 210
Percent Time Used 67
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-323
MG DRILLING(5.08%)
BAILEY H.D.D.(0.91%)
KRL CONSTRUCTION INC.(1.33%)
D. I. J. CONSTRUCTION, INC.(2.81%)
Contract # 03143015
Totals 991388.00 28133.40 1019021.86 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-324
Proj ID STP 2013(554)
Work Type FY 2013 SITE - SPECIFIC SIGNALS
 
0.100 870431.70 0.00 900145.83 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 12-02-13
Work Completed  
Time Computed 11-05-13
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 296
Percent Time Used 113
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-324
VACA UNDERGROUND UTILITIES INC (5.67%)
JND CONSTRUCTION CONSULTANTS, LLC( 18.39%)
YORK & YORK FOUNDATION DRILLING, INC.(5.29%)
UNITED PAVEMENT & MARKINGS, LLC(0.00%)
M & M STRIPING & POWER WASHING, LLC(4.60%)
Contract # 04133013
Totals 870431.70 0.00 900145.83 99.9

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-343
Proj ID STP 1502(147)
Work Type FY 2015 SITE - SPECIFIC SIGNALS
 
0.003 614705.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-15
Work Began 00-00-00
Work Completed  
Time Computed 08-01-15
Contract Working Days 132
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-343
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153246
Totals 614705.10 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-344
Proj ID NH 2015(575)
Work Type FY 2015 NON - SITE SPECIFIC SIGNALS
 
0.003 1083323.50 0.00 7560.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-344
D. I. J. CONSTRUCTION, INC.(4.07%)
MG DRILLING(3.18%)
KRL CONSTRUCTION INC.( 13.11%)
Contract # 02153027
Totals 1083323.50 0.00 7560.00 0.6

CountyTRAVIS
Highway VA
From VARIOUS ON-SYS LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-345
Proj ID NH 2012(379)
Work Type SCHOOL ZONE UPGRADES
 
0.100 287731.00 0.00 281104.46 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-12
Work Began 12-03-12
Work Completed 01-05-15
Time Computed 07-15-12
Contract Working Days 102
Addl Days Granted 4
Working Days Charged 76
Percent Time Used 71
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-345
CODY DRILLING(5.44%)
ESA ENGINEERING, LLC (5.05%)
Contract # 03123023
Totals 287731.00 0.00 281104.46 100.0

CountyTRAVIS
Highway VA
From VARIOUS ON-SYSTEM LOCATIONS
To DISTRICTWIDE
CSJ 0914-00-374
Proj ID STP 2013(929)
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 816189.28 13235.63 596667.25 73.1
Work Order 06-05-14
Work Began 12-15-14
Work Completed  
Time Computed 06-21-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 59
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-374
JCD CONSTRUCTION, LLC(0.00%)
TRP CONSTRUCTION GROUP, LLC(2.31%)
Contract # 04143225
Totals 816189.28 13235.63 596667.25 73.1

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-379
Proj ID STP 2014(723)
Work Type SIGN IMPROVEMENT
 
0.001 266630.98 46850.18 193193.54 72.4
Work Order 07-18-14
Work Began 11-03-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 37
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-379
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143040
Totals 266630.98 46850.18 193193.54 72.4

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN
To BASTROP, LEE & CALDWELL COUNTIES
CSJ 0914-00-381
Proj ID STP 1502(148)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.100 994912.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-381
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153046
Totals 994912.00 0.00 0.00 0.0

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To ON IH 35 AND ON US 183
CSJ 0914-04-269
Proj ID STP 2012(551)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 775000.00 0.00 669177.84 86.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 08-13-12
Work Completed  
Time Computed 08-13-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 98
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123049
Totals 775000.00 0.00 669177.84 86.3

CountyTRAVIS
Highway CS
From 1.2 MI. EAST OF OLD HWY 20
To 0.2 MI. WEST OF BITTING SCHOOL RD.
CSJ 0914-04-292
Proj ID STP 2015(604)HES
Work Type HIGH FRICTION SURFACE TREATMENT
 
3.210 311425.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 12
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-292
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153027
Totals 311425.79 0.00 0.00 0.0

CountyWILLIAMSON
Highway CR
From ON CR 111 AT NORTH FORK MCNUTT CRK
To (STR AA0535001)
CSJ 0914-05-142
Proj ID BR 1102(561)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.087 609359.30 0.00 614193.52 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-14
Work Began 08-14-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 97
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-142
APAC-TEXAS, INC. ( 20.18%)
D. I. J. CONSTRUCTION, INC.(0.75%)
O & S TRAFFIC SUPPLIES (0.62%)
ROADWAY SPECIALTIES, INC.(5.09%)
CAPITOL CONCRETE CONTRACTORS, INC. (1.56%)
Contract # 03143229
Totals 609359.30 0.00 614193.52 99.9

CountyWILLIAMSON
Highway CS
From COLORADO ST @ WILLIS CREEK BRANCH
To STR# 246-J001-15-001
CSJ 0914-05-173
Proj ID BR 2014(427)
Work Type REPLACE BRIDGE & APPROACHES
 
0.068 627714.08 120726.34 120726.34 19.2
Work Order 05-14-15
Work Began 06-15-15
Work Completed  
Time Computed 06-14-15
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 15
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-173
FLASHER EQUIPMENT COMPANY(1.35%)
APAC-TEXAS, INC. (FORT WORTH)( 11.12%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.46%)
Contract # 03153038
Totals 627714.08 120726.34 120726.34 19.2

CountyBASTROP
Highway CR
From ON PAINT CRK RD AT PAINT CRK
To AA01-62-001
CSJ 0914-18-092
Proj ID BR 2014(690)
Work Type REPLACE BRIDGE & APPROACHES
 
0.072 542982.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153204
Totals 542982.86 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11