Monthly State Let Construction Report For Fort Worth District As Of Apr 11, 2016 Page 1 Of 5

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway US 180 ETC
From SP 312
To PALO PINTO C/L
CSJ 0008-02-072
Proj ID STP 2015(068)
Work Type MICROSURFACING
 
28.155 2644391.29 0.00 3240679.63 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-14
Work Began 11-07-14
Work Completed  
Time Computed 11-07-14
Contract Working Days 59
Addl Days Granted 3
Working Days Charged 84
Percent Time Used 135
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-072
STRIPE-A-ZONE, INC.( 12.65%)
ALTUS TRAFFIC MANAGEMENT LLC (0.53%)
FLEX SUPPLY, LLC (0.17%)
TEX OP CONSTRUCTION, LP(0.23%)
Contract # 09143219
Totals 2644391.29 0.00 3240679.63 99.9

CountyPARKER
Highway IH 20
From AT FM 1187
To .
CSJ 0008-03-103
Proj ID IMD 1102(447)
Work Type GR, HMAC, CRCP, STR, SGN, PVT MK, & SGNLS
 
0.016 4795524.90 0.00 2133163.39 44.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-14
Work Began 08-22-15
Work Completed  
Time Computed 11-12-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 56
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-103
W. W. FOUNDATION DRILLING, LTD.(1.02%)
DALLAS LITE AND BARRICADE INC. (0.33%)
WOLFE CONSTRUCTION GROUP, INC. (0.45%)
FORTSON CONTRACTING, INC.(0.39%)
STRIPING TECHNOLOGY, L.P.(0.76%)
EROSION CONTROL MANAGEMENT SERVICES(0.27%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(5.45%)
TEX OP CONSTRUCTION, LP(1.36%)
NORTHEASTERN PAVERS, INC.( 11.37%)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (1.27%)
Contract # 08143237
Totals 4795524.90 0.00 2133163.39 44.4

CountyTARRANT
Highway SS 580
From IH 820
To WELLINGTON ROAD
CSJ 0008-04-046
Proj ID NH 2016(585)
Work Type PAVT REPAIR AND OVERLAY
 
2.808 3743231.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-04-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163238
Totals 3743231.89 0.00 0.00 0.0

CountyTARRANT
Highway SH 180
From LOUISE ST.
To WEST OF VILLAGE CREEK BRIDGE
CSJ 0008-06-050
Proj ID NH 2016(818)
Work Type MILL AND OVERLAY
 
5.449 4321303.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0008-06-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163227
Totals 4321303.01 0.00 0.00 0.0

CountyTARRANT
Highway IH 820
From US 287/IH 820 SPLIT
To NORTH OF SUN VALLEY DRIVE
CSJ 0008-13-229
Proj ID STP 2015(850)HES
Work Type TRAFFIC PROTECTION DEVICES
 
0.558 675364.70 0.00 195441.92 28.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-15
Work Began 09-15-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 5
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-229
BROCK ENVIRONMENTAL SERVICES, LLC(0.39%)
BRENDA PRICE TRUCKING(0.00%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED( 10.87%)
Contract # 04153238
Totals 675364.70 0.00 195441.92 28.9

CountyTARRANT
Highway IH 820
From IH 30
To LAKE WORTH BRIDGE
CSJ 0008-15-049
Proj ID CM 1502(534)
Work Type INSTALL ITS FIBER, DETECTION, & DMS
 
12.900 3652534.53 113688.61 217694.61 5.9
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 03-21-16
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 2
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0008-15-049
LAYFIELD CONSTRUCTION, INC (0.06%)
THE ANCHOR GROUP, INC. (0.15%)
Contract # 11153223
Totals 3652534.53 113688.61 217694.61 5.9

CountyTARRANT
Highway IH 20
From AT IH 20
To ON BRYANT IRVIN ROAD
CSJ 0008-16-036
Proj ID STP 1502(095)MM
Work Type GR, LIM TRT, HMA, PCCP, BRG, PAV MK
 
0.220 3864789.85 0.00 81662.71 2.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-24-15
Work Began 00-00-00
Work Completed  
Time Computed 08-24-15
Contract Working Days 363
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 2
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-16-036
FORTSON CONTRACTING, INC.(0.38%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(0.20%)
FOUNDATION DRILLERS, INC.(3.47%)
DALLAS LIGHT & BARRICADES(1.52%)
Contract # 05153244
Totals 3864789.85 0.00 81662.71 2.1

CountyWISE
Highway US 81
From MONTAGUE COUNTY LINE
To FM1655
CSJ 0013-06-042
Proj ID NH 2015(467)
Work Type HMAC OVERLAY
 
11.685 3343656.91 0.00 19920.00 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-15
Work Began 00-00-00
Work Completed  
Time Computed 04-01-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0013-06-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153220
Totals 3343656.91 0.00 19920.00 0.5

CountyWISE
Highway US 81
From 2000' SOUTH OF SH 114
To TARRANT COUNTY LINE
CSJ 0013-08-126
Proj ID STP 2013(388)
Work Type HMAC OVERLAY
 
3.844 940340.80 0.00 1259131.45 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 09-22-14
Work Completed  
Time Computed 07-03-13
Contract Working Days 25
Addl Days Granted 20
Working Days Charged 36
Percent Time Used 80
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-126
O. TREVINO CONSTRUCTION, LLC (6.21%)
STRIPING TECHNOLOGY, L.P.(3.41%)
CROSSROADS, L.P. (0.41%)
DUSTROL, INC.(0.72%)
BRENDA PRICE TRUCKING(0.74%)
W.O.E. CONSTRUCTION(0.18%)
Contract # 02133229
Totals 940340.80 0.00 1259131.45 99.9

CountyWISE
Highway US 81
From US 81/@BU 81-SOUTH SIDE DECATUR
To US 81/@BU 81-SOUTH SIDE DECATUR
CSJ 0013-08-127
Proj ID NH 2013(802)
Work Type CONSTRUCT 4 LANE GRADE SEPARATION
 
2.105 12119453.03 16849.17 14071988.00 99.9
Work Order 01-06-14
Work Began 01-20-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 543
Addl Days Granted 0
Working Days Charged 536
Percent Time Used 98
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-127
ALTUS TRAFFIC MANAGEMENT LLC (0.45%)
NORTH TEXAS CONTRACTING, INC.(4.12%)
PEACHTREE CONSTRUCTION, LTD. (3.02%)
STORM WATER MANAGEMENT, INC. (0.25%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(9.51%)
FORTSON CONTRACTING, INC.(0.77%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(2.34%)
O. TREVINO CONSTRUCTION, LLC (0.19%)
MCL CONTRACTING, LLC (0.17%)
SCOTT DERR PAINTING CO (0.16%)
STRIPING TECHNOLOGY, L.P.(1.21%)
TEXAS SHAFTS, INC. (0.48%)
W.O.E. CONSTRUCTION(1.86%)
J. E. GUZMAN CONSTRUCTION, INC.(0.33%)
BORE TECH CONSTRUCTION, LLC(0.16%)
INLET STRUCTURE SPECIALTIES LTD. (0.13%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.11%)
PENHALL COMPANY(0.12%)
Contract # 08133007
Totals 12119453.03 16849.17 14071988.00 99.9

CountyTARRANT
Highway BU 287P
From AT FM 718 (AVONDALE HASLET ROAD)
To IN NORTH TARRANT COUNTY
CSJ 0013-10-070
Proj ID STP 2015(851)
Work Type INTERSEC.IMPRVMNT INCLD TRAF.SIGNAL
 
0.100 823422.86 170898.31 448381.19 54.4
Work Order 08-27-15
Work Began 02-06-16
Work Completed  
Time Computed 09-28-15
Contract Working Days 69
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 81
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-070
PEACHTREE CONSTRUCTION, LTD. ( 30.79%)
ACU CONSTRUCTION LLC (0.73%)
TRP CONSTRUCTION GROUP, LLC(2.38%)
DALLAS LITE AND BARRICADE INC. (1.21%)
Contract # 07153056
Totals 823422.86 170898.31 448381.19 54.4

CountyTARRANT
Highway BU 287P ETC
From BAILEY BOSWELL
To IH 820
CSJ 0013-10-081
Proj ID STP 1502(535)HES
Work Type PROFILE PAVEMENT MARKERS
 
16.737 123477.25 10450.00 109203.47 88.4
Work Order 10-22-15
Work Began 02-22-16
Work Completed  
Time Computed 11-23-15
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 9
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-081
RED SIXTEEN CONSTRUCTION, INC(0.00%)
COWBELL TRAFFIC SERVICES, INC. ( 14.13%)
Contract # 08153230
Totals 123477.25 10450.00 109203.47 88.4

CountyTARRANT
Highway US 81
From AT FM 156 (BLUE MOUND RD)
To IN FORT WORTH
CSJ 0014-15-039
Proj ID STP 2015(852)HES
Work Type INSTALL TRAFFIC SIGNAL
 
0.544 177985.19 11000.00 167945.00 94.3
Work Order 05-15-15
Work Began 08-17-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-15-039
ROADMASTER, INC. (2.01%)
Contract # 04153040
Totals 177985.19 11000.00 167945.00 94.3

CountyTARRANT
Highway IH 35W
From IH 820
To US 81/287 SPLIT
CSJ 0014-16-255
Proj ID IM 0355(151)
Work Type GR, BSE, DR, SURF & SIGN
 
3.580 120205602.75 1715453.71 85714511.19 71.3
CountyTARRANT
Highway IH 35W
From IH 820
To US 81/287_SPLIT
CSJ 0014-16-267
Proj ID NH 2012(657)
Work Type ROW ACQ, RELOC ASSIT, UTILITY ADJ
 
2.735 3080289.85 0.00 2621511.25 85.1
Work Order 11-01-12
Work Began 04-29-13
Work Completed  
Time Computed 04-29-13
Contract Working Days 847
Addl Days Granted 0
Working Days Charged 867
Percent Time Used 102
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0014-16-255
JACKSON CONSTRUCTION, LTD. (2.32%)
STRIPING TECHNOLOGY, L.P.(0.53%)
USA SWPPP INSPECTIONS, INC.(0.39%)
C.B. SERVICES, INC.(0.94%)
MAVERICK PUMP SERVICES, LLC(0.04%)
W.O.E. CONSTRUCTION(0.04%)
MICA CORPORATION (5.31%)
COWBELL TRAFFIC SERVICES, INC. (0.01%)
CROSSROADS, L.P. (0.09%)
FORTSON CONTRACTING, INC.(0.38%)
HOUSTON SAWING & DRILLING(0.02%)
FOUNDATION DRILLERS, INC.(1.60%)
GREAT WESTERN ERECTORS (0.04%)
LINDAMOOD DEMOLITION, INC. (0.23%)
FARR FOUNDATION, INC.(1.86%)
DURABLE SPECIALTIES, INC.(0.36%)
NORTH TEXAS BOMANITE, INC. (0.17%)
ANTIGO CONSTRUCTION, INC.(0.15%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(0.54%)
THELIN RECYCLING COMPANY, L.P. (0.02%)
TEX OP CONSTRUCTION, LP(0.33%)
BREDA COMPANY, INC.(0.39%)
BRENDA PRICE TRUCKING(0.00%)
CHOCTAW ERECTORS, INC. (4.52%)
CLEANSERVE, INC. (0.07%)
DANRIDGE CONSTRUCTION, LLC.(0.01%)
SCOTT DERR PAINTING CO, LLC(0.28%)
MASTERPIECE GRINDING & GROOVING, LLC (0.00%)
INDUS CONSTRUCTION, L.P. (0.02%)
MENDEZ EXCAVATION(0.03%)
WEBBER BARRIER SERVICES, LLC.(4.34%)
DCCS, LLC(2.62%)
RAMBO CONTRACTING, INC.(0.06%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.06%)
ACTION CONSTRUCTORS(0.39%)
CENTRAL NORTH CONSTRUCTION, LLC(0.07%)
O. TREVINO CONSTRUCTION, LLC (0.12%)
Contract # 09123201
Totals 123285892.60 1715453.71 88336022.44 71.6

CountyJOHNSON
Highway IH 35W
From NB & SB IH 35 @ CR 391 & FM 916
To .
CSJ 0014-22-031
Proj ID BR 1502(330)
Work Type UPGRADE BRIDGE & APPROACH RAILING
 
0.400 1323249.06 47808.66 891018.76 70.2
Work Order 07-31-15
Work Began 09-14-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 211
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-22-031
AARON CONCRETE CONTRACTORS, L.P. ( 15.74%)
CROSS ROADS, L.P.(0.47%)
DIAMOND SURFACE, INC.(0.57%)
FORTSON CONTRACTING, INC.( 15.43%)
PRIMATE CONSTRUCTION, INC. (2.39%)
STRIPING TECHNOLOGY, L.P.(2.02%)
TEX OP CONSTRUCTION, LP(4.01%)
J&M CONTRACTING COMPANY( 11.40%)
SOUTHERN DEMOLITION, LLC.(0.96%)
W.O.E. CONSTRUCTION(0.00%)
Contract # 06153234
Totals 1323249.06 47808.66 891018.76 70.2

CountyJOHNSON
Highway SH 174
From SOUTH OF FM 731
To PHILLIPS DRIVE SOUTH OF JOSHUA
CSJ 0019-01-144
Proj ID NH 2016(741)
Work Type MILL AND OVERLAY
 
6.100 3929910.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-144
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163219
Totals 3929910.03 0.00 0.00 0.0

CountyERATH
Highway US 67
From 1.75 MI N OF COMANCHE COUNTY LINE
To SH 6
CSJ 0079-08-003
Proj ID NH 2013(949)
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
2.790 12608803.68 19142.54 12897240.89 99.9
Work Order 10-24-13
Work Began 01-06-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 380
Addl Days Granted 78
Working Days Charged 452
Percent Time Used 98
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-08-003
J & M CONTRACTING, COMPANY (4.38%)
COPPELL CONSTRUCTION CO., INC. ( 24.86%)
(USE 05534)TEXAS ENVIRONMENTAL MANAGEMENT, INC.(2.87%)
SAN-ANN-CO., INC.(0.61%)
D. I. J. CONSTRUCTION, INC.(0.45%)
WEST TEXAS RUMBLE STRIP(0.03%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
RICE ENVIRONMENTAL SERVICES(0.53%)
GARY A. CRAIN, INC.(0.09%)
WILLIS ELECTRIC CO., LP(0.14%)
Contract # 08133211
Totals 12608803.68 19142.54 12897240.89 99.9

CountyHOOD
Highway US 377
From PIRATE DRIVE
To FM 56 IN TOLAR
CSJ 0080-03-054
Proj ID STP 2016(826)
Work Type BS REPAIR, SEAL COAT AND HMAC
 
15.541 4079052.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0080-03-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163013
Totals 4079052.20 0.00 0.00 0.0

CountyTARRANT
Highway US 377
From IH 20
To WINSCOTT/LAKEWAY
CSJ 0080-07-094
Proj ID C 80-7-94
Work Type GR, DR, STR AND PAVEMENT
 
1.350 19065202.71 404803.52 9418172.44 49.3
Work Order 06-23-14
Work Began 10-01-14
Work Completed  
Time Computed 07-09-14
Contract Working Days 684
Addl Days Granted 0
Working Days Charged 359
Percent Time Used 52
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0080-07-094
DALLAS LITE AND BARRICADE INC. (0.32%)
C.B. SERVICES, INC.(0.80%)
DUSTROL, INC.(1.52%)
MELS ELECTRIC, L.P.(7.57%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 11.27%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.09%)
INDUS CONSTRUCTION, L.P. (0.72%)
CLLA GROUP, LLC(7.47%)
INLET STRUCTURE SPECIALTIES LTD. (2.64%)
STRAIGHT LINE SAWING & SEALING (0.21%)
SCOTT DERR PAINTING CO (0.00%)
WYLIE DRILLING & DRAINAGE, INC.(0.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.12%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(0.09%)
RAMBO CONTRACTING, INC.(0.29%)
HAYWARD BAKER, INC.(0.35%)
RICE TUNNELING & BORING, INC.(0.08%)
ALLIED DRILLING COMPANY(0.20%)
HIGH QUALITY ELECTRIC(1.49%)
C & S UTILITY CONTRACTORS, INC.(0.07%)
GSI HIGHWAY PRODUCTS (0.04%)
STEEL EFFECTS(0.46%)
BRADCO, LLC(1.68%)
Contract # 05143004
Totals 19065202.71 404803.52 9418172.44 49.3

CountyTARRANT
Highway US 377
From AT EAST BELKNAP STREET
To IN HALTOM CITY
CSJ 0081-01-046
Proj ID CM 1102(122)
Work Type GR, DR, SIGNAL AND PAVEMENT
 
0.451 4198919.20 21779.57 2391551.81 57.4
Work Order 07-25-14
Work Began 11-06-14
Work Completed  
Time Computed 11-06-14
Contract Working Days 236
Addl Days Granted 62
Working Days Charged 321
Percent Time Used 107
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-01-046
PLACIDO CONSTRUCTION COMPANY (1.88%)
PEACHTREE CONSTRUCTION, LTD. (8.68%)
EROSION CONTROL MANAGEMENT SERVICES(0.53%)
A BROTHERS MILLING, LLC(2.09%)
BUYERS BARRICADES, INC.(0.72%)
BRADCO, LLC(2.07%)
ABC EROSION CONTROL, INC.(0.79%)
MCL CONTRACTING, LLC (0.98%)
VENUS CONSTRUCTION (6.92%)
W.O.E. CONSTRUCTION(0.20%)
A & A CONSTRUCTION (0.08%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.29%)
COWBOY TRUCKING(3.28%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(8.56%)
DFW SERVICES, LLC(2.12%)
UNION ELECTRICAL CONTRACTOR, INC.(0.08%)
LINDAMOOD DEMOLITION, INC. (0.08%)
Contract # 04143224
Totals 4198919.20 21779.57 2391551.81 57.4

page 1 | page 2 | page 3 | page 4 | page 5