Monthly State Let Construction Report For Fort Worth District As Of Sep 15, 2014 Page 3 Of 6

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPALO PINTO
Highway SH 16
From SH-337
To SH-254
CSJ 0362-04-040
Proj ID STP 2014(937)
Work Type PAVEMENT REPAIR AND SEAL COAT
 
6.717 4193583.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0362-04-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143248
Totals 4193583.00 0.00 0.00 0.0

CountyTARRANT
Highway SH 26
From BRUMLOW ROAD (GRAPEVINE SECTION)
To 0.5 MILES SOUTH OF SH 114
CSJ 0363-01-111
Proj ID STP 2011(208)ES
Work Type RECONST GR, ACP, CONC PVMT, BRDGS
 
1.482 11897196.21 0.00 11849134.63 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-10
Work Began 04-27-11
Work Completed  
Time Computed 10-01-10
Contract Working Days 491
Addl Days Granted 108
Working Days Charged 599
Percent Time Used 100
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0363-01-111
DALLAS LITE AND BARRICADE INC. (0.43%)
FORTSON CONTRACTING, INC.(0.36%)
HIGHWAY TECHNOLOGIES, INC. (1.59%)
INLET STRUCTURE SPECIALTIES LTD. (2.87%)
NORTH TEXAS BOMANITE, INC. (2.08%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 16.56%)
W.O.E. CONSTRUCTION(4.98%)
BREDA COMPANY, INC.(0.80%)
LIRA ELECTRIC(2.39%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.75%)
THELIN RECYCLING COMPANY, L.P. (0.06%)
DUSTROL, INC. (ROANOKE)(2.35%)
METRO CUTTING AND SEALING, INC.(0.03%)
P & C INLETS, INC. (0.24%)
RAMBO CONTRACTING, INC.(0.24%)
PRESERVATION...A TREE SERVICE, INC.(0.00%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.59%)
BIG DOG DRILLING, LLC(0.08%)
NORTHEAST SERVICE, INC.(0.11%)
C.T. AND S. METALWORKS, INC. (0.32%)
JAGOE-PUBLIC COMPANY (0.31%)
SCOTT DERR PAINTING CO (0.13%)
BENCHMARK GARDENS, LLC (3.40%)
IRRI-TECH CORPORATION(0.78%)
ILLUMINATIONS BY GREENLEE(0.29%)
URBANOVSKY ADVANCED CONSTRUCTION, LLC(0.08%)
AQUA BORE(0.04%)
DOWAGER CONSTRUCTION, INC. (0.12%)
ARLINGTON PAVERS, INC. (0.06%)
Contract # 07103228
Totals 11897196.21 0.00 11849134.63 99.9

CountyTARRANT
Highway SH 26
From BRUMLOW/POOL
To JOHN MCCAIN
CSJ 0363-01-136
Proj ID STP 1102(295)MM
Work Type GRADING, BASE, DRAINAGE AND PAVEMENT
 
0.909 11469297.64 136618.47 6551896.79 58.3
Work Order 10-21-11
Work Began 07-16-12
Work Completed  
Time Computed 04-19-12
Contract Working Days 394
Addl Days Granted 10
Working Days Charged 501
Percent Time Used 124
Contractor(s)
AUI CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0363-01-136
TOTAL HIGHWAY MAINTENANCE, LLC (1.04%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.28%)
DUSTIN ALLEN, INC. (0.20%)
THELIN RECYCLING COMPANY, L.P. (0.29%)
DUSTROL, INC.(0.87%)
DURABLE SPECIALTIES, INC.(3.81%)
TEXAS STAR SAWING & SEALING(0.02%)
LINDAMOOD DEMOLITION, INC. (0.75%)
USA SWPPP INSPECTIONS, INC.(0.52%)
J/M MATERIALS, INC.(0.37%)
TEXAS INLETS, INC. (1.87%)
NORTH TEXAS REBAR, LLC (0.00%)
HAYDEN CAPITAL CORPORATION (0.98%)
ATS DRILLING, INC. (2.63%)
FOUNDATION DRILLERS, INC.(0.08%)
HAYWARD BAKER, INC.(0.30%)
J.L. STEEL REINFORCING, LLC(0.12%)
MCL CONTRACTING, LLC (3.79%)
SCOTT DERR PAINTING CO, LLC(0.10%)
TEXAS BOMANITE (0.00%)
FORTSON CONTRACTING, INC.(0.00%)
Contract # 08113208
Totals 11469297.64 136618.47 6551896.79 58.3

CountyTARRANT
Highway SH 121
From WESTERN OAKS DRIVE
To APPROX.1.2 MI N OF STONE MYERS PKWY
CSJ 0364-01-140
Proj ID CC 364-1-140
Work Type GR, BS, DR AND PAVEMENT
 
0.123 366150.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0364-01-140
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143046
Totals 366150.05 0.00 0.00 0.0

CountyTARRANT
Highway SH 26
From GAYLORD TRAIL DRIVE
To GRAPEVINE MILLS BOULEVARD SOUTH
CSJ 0364-06-011
Proj ID STP 2011(227)TE
Work Type CROSSWALKS, ADA RAMPS & IMPROVEMENTS
 
1.360 1240195.30 0.00 215658.47 17.3
CountyTARRANT
Highway VA
From GAYLORD TEXAN; IN GRAPEVINE
To NORTH OF GRAPEVINE MILLS MALL
CSJ 0902-48-663
Proj ID HP 2013(083)
Work Type GR, DR, STRUCTURE AND PAVEMENT
 
1.000 308901.54 0.00 0.00 0.0
Work Order 01-17-14
Work Began 05-20-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 37
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0364-06-011
PORTER INTERNATIONAL CONSTRUCTION LLC( 35.37%)
Contract # 08133257
Totals 1549096.84 0.00 215658.47 13.9

CountyTARRANT
Highway SH 121
From SOUTH OF ARBORLAWN DRIVE
To SOUTH OF OVERTON RIDGE BLVD
CSJ 0504-02-022
Proj ID STP 2009(485)ES
Work Type GR, DR, STRUCTURES AND PAVEMENT
 
0.100 116646468.88 233505.51 111555726.33 96.6
Work Order 02-01-10
Work Began 03-15-10
Work Completed  
Time Computed 02-17-10
Contract Working Days 896
Addl Days Granted 0
Working Days Charged 1,332
Percent Time Used 148
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0504-02-022
COWTOWN TRAFFIC CONTROL, INC.(0.08%)
S & S BRIDGE PAINTING, INC.(0.04%)
INTERSTATE FOUNDATION, LLC (3.14%)
W.O.E. CONSTRUCTION(1.75%)
MARIO SINACOLA & SONS EXCAVATING, INC. ( 23.31%)
ODUM SERVICES, L.P.(0.67%)
ARLINGTON PAVERS, INC. (0.06%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.64%)
MICA CORPORATION (0.34%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(2.98%)
STRIPE-A-ZONE, INC.(0.23%)
MUSTANG TURF & LANDSCAPE, LLC(0.60%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.00%)
CRAIG OLDEN, INC.(5.50%)
RAMBO CONTRACTING, INC.(1.18%)
NORTH TEXAS CONTRACTING, INC.(5.20%)
INDUS CONSTRUCTION, L.P. (5.32%)
JONA CONTRACTING, INC. (0.00%)
SOUTHWEST CONSTRUCTION SERVICES(0.04%)
RMI WORLDWIDE, LLC (0.11%)
GUIDO'S TRUCKS (1.28%)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.21%)
STOMPER DEMOLITION COMPANY, INC. (0.00%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.02%)
SCOTT DERR PAINTING CO, LLC(0.14%)
BRENDA PRICE TRUCKING(0.08%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.08%)
SHEA SERVICES, INC (0.46%)
TEXAS CONSTRUCTION SUPPLY, INC.(1.01%)
NORTH TEXAS TRUCKING, INC. (0.17%)
WEBBER BARRIER SERVICES, INC.(0.43%)
BIG DOG DRILLING, LLC(0.01%)
TX DOWN UNDER CONSTRUCTION LLC (0.02%)
FOUNDATION DRILLERS, INC.(0.04%)
RIVER CITIES SAWING, LLC (0.10%)
FORTSON CONTRACTING, INC.(0.00%)
RELIABLE TRUCKING(0.04%)
TEXAS MANHOLES COMPANY, INC. (0.00%)
KD SERVICES(0.38%)
GAMCOR, INC. (0.07%)
EROSION PREVENTION PRODUCTS(0.00%)
J.A. MANNING CONSTRUCTION CO., INC.(1.24%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.01%)
Contract # 11093001
Totals 116646468.88 233505.51 111555726.33 96.6

CountyJOHNSON
Highway SH 174
From AT FM 916 WB & EB INTER
To IN RIO VISTA
CSJ 0519-01-023
Proj ID STP 2013(673)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.100 315236.00 33052.00 161935.80 51.3
Work Order 11-05-13
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 95
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0519-01-023
AAA DRILLING FOUNDATION CO., INC.(3.96%)
BUYERS BARRICADES, INC.(0.52%)
GJ SEEDING, LLC(2.31%)
ROAD MASTER STRIPING LLC (0.94%)
DOWN UNDER CONSTRUCTION(1.75%)
SOUTH TEXAS ILLUMINATION, LLC( 42.08%)
BICK"S CONSTRUCTION, INC.( 14.88%)
HAROS BROS. CO.(3.96%)
Contract # 05133022
Totals 315236.00 33052.00 161935.80 51.3

CountyPALO PINTO
Highway SH 254
From FM 4 IN GRAFORD
To US 281
CSJ 0539-04-035
Proj ID STP 2013(539)
Work Type HMAC OVERLAY AND BASE REPAIR
 
11.191 2066986.35 73202.28 2075387.41 99.9
Work Order 07-31-13
Work Began 09-23-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 100
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0539-04-035
W.S. CONSTRUCTION COMPANY(3.93%)
COTHRAN TRUCKING, LLC(2.87%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.51%)
LONE STAR BARRIER SERVICES, LLC(2.01%)
CHEROKEE SERVICES(0.23%)
RICE ENVIRONMENTAL SERVICES(1.07%)
TEX OP CONSTRUCTION, LP(2.37%)
Contract # 04133225
Totals 2066986.35 73202.28 2075387.41 99.9

CountyTARRANT
Highway FM 156
From 1000 FT NORTH OF AVONDALE-HASLETT
To 500 FT SOUTH OF AVONDALE-HASLETT RD
CSJ 0718-02-065
Proj ID STP 2013(954)
Work Type GR, BS, AND PAVEMENT
 
0.852 403357.75 0.00 412106.60 99.9
Work Order 09-17-13
Work Began 10-21-13
Work Completed  
Time Computed 10-03-13
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 154
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0718-02-065
CROSSROADS, L.P. (1.29%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.98%)
FORTSON CONTRACTING, INC.(2.48%)
PEACHTREE CONSTRUCTION, LTD. ( 21.40%)
STRIPING TECHNOLOGY, L.P.(1.84%)
BRENDA PRICE TRUCKING(0.00%)
Contract # 08133261
Totals 403357.75 0.00 412106.60 99.9

CountyTARRANT
Highway FM 157
From MITCHELL STREET; IN ARLINGTON
To IH 20
CSJ 0747-04-065
Proj ID STP 1402(034)HRR
Work Type GR, BS AND PAVEMENT
 
3.795 5294353.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 281
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE FAIN GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0747-04-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143213
Totals 5294353.95 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE FY 14
CSJ 0902-00-126
Proj ID STP 1302(027)
Work Type CONCRETE REPAIR
 
0.100 1413335.00 154406.98 1708723.74 99.9
Work Order 08-19-13
Work Began 10-21-13
Work Completed  
Time Computed 10-19-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 312
Percent Time Used 85
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-126
W.O.E. CONSTRUCTION(2.37%)
BRENDA PRICE TRUCKING(2.36%)
CROSSROADS, L.P. (0.23%)
Contract # 07133010
Totals 1413335.00 154406.98 1708723.74 99.9

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To CONCRETE PAVEMENT REPAIR
CSJ 0902-00-131
Proj ID STP 2015(071)
Work Type CONCRETE PAVT REPAIR
 
0.100 1587885.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-131
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143228
Totals 1587885.00 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-132
Proj ID STP 2015(072)
Work Type PAVEMENT MARKINGS
 
0.100 930000.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-132
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143015
Totals 930000.05 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-133
Proj ID STP 2013(552)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.100 815000.00 40978.25 890002.70 99.9
Work Order 04-23-13
Work Began 07-23-13
Work Completed  
Time Computed 07-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 399
Percent Time Used 109
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-133
ROADMASTER, INC. (1.45%)
DYNAMIC VISION CO., INC. (6.56%)
Contract # 03133030
Totals 815000.00 40978.25 890002.70 99.9

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICT WIDE FY 2013
CSJ 0902-00-134
Proj ID NH 2013(957)G
Work Type SIGN STUCTURES
 
41.900 476055.25 0.00 0.00 0.0
Work Order 07-08-14
Work Began 00-00-00
Work Completed  
Time Computed 07-24-14
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143241
Totals 476055.25 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-136
Proj ID STP 2014(353)G
Work Type TRAFFIC SIGNALS
 
0.100 1275000.00 1700.00 1700.00 0.1
Work Order 03-12-14
Work Began 08-25-14
Work Completed  
Time Computed 03-28-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 1
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-136
ROAD MASTER STRIPING LLC (0.85%)
Contract # 01143223
Totals 1275000.00 1700.00 1700.00 0.1

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To ON FM 1187 AND FM 731
CSJ 0902-00-139
Proj ID STP 2014(663)
Work Type LANDSCAPING
 
0.100 317349.10 66411.20 68911.20 21.7
Work Order 05-09-14
Work Began 07-16-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 27
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-139
TOTAL HIGHWAY MAINTENANCE, LLC (1.96%)
AQUA BORE(2.97%)
Contract # 04143237
Totals 317349.10 66411.20 68911.20 21.7

CountyWISE
Highway CR
From FOSTER RD AT TRIBUTARY OF DENTON CR
To .
CSJ 0902-20-100
Proj ID BR 2009(902)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.168 820802.59 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 209
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143050
Totals 820802.59 0.00 0.00 0.0

CountyWISE
Highway CR
From CR 2675 (PARKER DAIRY RD) AT DENTON
To .
CSJ 0902-20-108
Proj ID BR 2012(347)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 549711.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ASHLAR CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143247
Totals 549711.00 0.00 0.00 0.0

CountyPALO PINTO
Highway VA
From VARIOUS LOCATIONS
To ON US 180 AND US 281
CSJ 0902-39-032
Proj ID STP 2014(770)
Work Type LANDSCAPING
 
0.200 191130.12 80914.10 80914.10 42.3
Work Order 07-18-14
Work Began 08-25-14
Work Completed  
Time Computed 08-12-14
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 9
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-39-032
AQUA BORE( 28.15%)
Contract # 06143033
Totals 191130.12 80914.10 80914.10 42.3