Monthly State Let Construction Report For Fort Worth District As Of Feb 09, 2018 Page 3 Of 5

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyERATH ETC
HighwayFM 8 ETC
FromFM 988
ToEASTLAND COUNTY LINE
CSJ0550-02-038
Proj IDSTP 2017(350)
Work TypeSEAL COAT
 
188.1556225724.974852769.0378.4
Work Order02-13-17
Work Began05-31-17
Work Completed
Time Computed03-16-17
Contract Working Days74
Addl Days Granted0
Working Days Charged100
Percent Time Used135
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0550-02-038
INNOVATIVE ROADWAY SOLUTIONS LLC (24.30)
TRP CONSTRUCTION GROUP, LLC (15.49)
BRYDL CONTRACTING, INC. (0.74)
Contract #01173035
Totals6225724.970.004852769.0378.4

CountyTARRANT
HighwayVA
FromIN TARRANT COUNTY
To.
CSJ0902-00-135
Proj IDSTP 2016(591)
Work TypeCONSTRUCT CURB RAMPS
 
0.1001617402.201587014.1898.1
Work Order02-22-17
Work Began05-01-17
Work Completed
Time Computed03-25-17
Contract Working Days120
Addl Days Granted47
Working Days Charged155
Percent Time Used92
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-135
CLASSIC TEJAS CONSTRUCTION, INC. (6.54)
LONE STAR HIGHWAY PRODUCTS, INC. (2.00)
AMERICAN STRIPING COMPANY, INC. (3.94)
Contract #01173248
Totals1617402.207341.001587014.1898.1

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ0902-00-142
Proj IDSTP 2016(592)
Work TypeTRAFFIC SIGNAL INSTALLATION
 
0.1001179390.47952402.6980.7
Work Order03-28-16
Work Began06-13-16
Work Completed
Time Computed04-28-16
Contract Working Days300
Addl Days Granted10
Working Days Charged274
Percent Time Used88
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-142
BUYERS BARRICADES, INC. (0.99)
GJ SEEDING, LLC (0.21)
M & M STRIPING & POWER WASHING, LLC (2.17)
TX DOWN UNDER CONSTRUCTION, LLC (0.64)
AAA DRILLING FOUNDATION CO., INC. (2.10)
SIX STAR CONCRETE (0.83)
BADGER DAYLIGHTING CORP. (0.73)
J&M TELCOM (0.51)
TCB FOUNDATION DRILLERS, INC. (0.29)
Contract #01163218
Totals1179390.4726011.69952402.6980.7

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToDISTRICTWIDE FY 17
CSJ0902-00-143
Proj IDC 902-00-143
Work TypeCONCRETE PAVEMENT REPAIR
 
0.1001734750.001187413.4468.4
Work Order11-29-16
Work Began04-03-17
Work Completed
Time Computed12-30-16
Contract Working Days256
Addl Days Granted109
Working Days Charged298
Percent Time Used81
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-143
W.O.E. CONSTRUCTION (3.53)
BRENDA PRICE TRUCKING (2.97)
Contract #10163214
Totals1734750.0034535.311187413.4468.4

CountyTARRANT
HighwayVA
FromDISTRICTWIDE
ToVARIOUS LOCATIONS
CSJ0902-00-147
Proj IDSTP 2018(454)
Work TypeTRAFFIC SIGNALS
 
0.1001292000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-147
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183030
Totals1292000.000.000.000.0

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToDISTRICTWIDE PLACEHOLDER FY 17
CSJ0902-00-148
Proj IDSTP 2017(513)
Work TypeTRAFFIC SIGNALS
 
0.1001240000.00401145.0932.3
Work Order03-08-17
Work Began04-24-17
Work Completed
Time Computed04-17-17
Contract Working Days300
Addl Days Granted0
Working Days Charged141
Percent Time Used47
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-148
ROAD MASTER STRIPING LLC (2.71)
DYNAMIC VISION CO., INC. (0.00)
Contract #01173216
Totals1240000.0020790.00401145.0932.3

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToIN JOHNSON COUNTY
CSJ0902-00-155
Proj IDSTP 1702(735)
Work TypeCONSTRUCT CURB RAMPS
 
0.1002091441.7748959.672.3
Work Order09-20-17
Work Began01-11-18
Work Completed
Time Computed10-21-17
Contract Working Days315
Addl Days Granted0
Working Days Charged12
Percent Time Used3
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-155
W.A. ROBBINS CONSTRUCTION CO., INC. (6.50)
Contract #08173011
Totals2091441.7748959.6748959.672.3

CountyWISE
HighwayCR
FromFOSTER RD AT TRIBUTARY OF DENTON CR
To.
CSJ0902-20-100
Proj IDBR 2009(902)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.168820802.5988000.0010.7
Work Order10-07-14
Work Began02-04-15
Work Completed
Time Computed10-23-14
Contract Working Days209
Addl Days Granted0
Working Days Charged28
Percent Time Used13
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-100
OMEGA CONSTRUCTION, LLC (65.14)
MCKINNEY DRILLING COMPANY (18.33)
Contract #08143050
Totals820802.590.0088000.0010.7

CountyPARKER
HighwayCS
FromAT US 180/IH20; ON LAKESHORE DRIVE
ToIN HUDSON OAKS
CSJ0902-38-075
Proj IDSTP 2015(679)
Work TypeGR,DR,STR, PAVEMENT & STRIPING
 
0.1007269140.697346307.8999.9
Work Order09-11-15
Work Began05-23-16
Work Completed
Time Computed01-10-16
Contract Working Days299
Addl Days Granted73
Working Days Charged423
Percent Time Used113
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0902-38-075
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.67)
BREDA COMPANY, INC. (0.65)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (5.62)
CROSSROADS, L.P. (0.54)
SOUTHEAST GRINDING & GROOVING, LLC (0.08)
SYNERGY SIGNS & SERVICES (0.45)
DUSTROL, INC. (1.94)
NORTHEASTERN PAVERS, INC. (11.96)
HAYWARD BAKER, INC. (0.53)
TEXAS SHAFTS, INC. (1.80)
SCOTT DERR PAINTING CO (0.05)
W.O.E. CONSTRUCTION (0.10)
STRIPING TECHNOLOGY, L.P. (0.99)
WILLOW CREEK SIGNS (0.66)
DURABLE SPECIALTIES, INC. (0.06)
Contract #07153251
Totals7269140.6995793.277346307.8999.9

CountyTARRANT
HighwayCS
FromWEST OF MILLER
ToSTALCUP WEST OF IH 820, IN FT WORTH
CSJ0902-48-453
Proj IDSTP 2013(725)MM
Work TypeGR, BS, PAVEMENT AND STRIPING
 
4.27424298000.009297204.3938.2
Work Order08-08-16
Work Began07-05-17
Work Completed
Time Computed11-07-16
Contract Working Days427
Addl Days Granted0
Working Days Charged137
Percent Time Used32
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-453
FARR FOUNDATION, INC. (0.23)
JSS BORI GROUP, LLC (4.45)
MELS ELECTRIC, L.P. (6.24)
NORTH TEXAS CONTRACTING, INC. (27.50)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.27)
STRIPING TECHNOLOGY, L.P. (1.06)
SYNERGY SIGNS & SERVICES, LLC (0.20)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.56)
W.O.E. CONSTRUCTION (0.18)
ALTUS TRAFFIC MANAGEMENT LLC (0.24)
NORTH TEXAS BOMANITE, INC. (1.63)
BREDA COMPANY, INC. (2.91)
TEXOP CONSTRUCTION (0.83)
Q. ROBERTS TRUCKING INCORPORATED (2.45)
ALLIED DRILLING COMPANY (0.12)
C & S UTILITY CONTRACTORS, INC. (0.06)
HIGH QUALITY ELECTRIC (0.07)
PANTHER CREEK TRANSPORTATION, INC. (0.57)
BUYERS BARRICADES, INC. (0.30)
URBAN INFRACONSTRUCTION, LLC. (2.03)
GMNW,LLC DBA TRINITY UTILITIES & BORING (0.63)
Contract #01163243
Totals24298000.00575168.499297204.3938.2

CountyTARRANT
HighwayCS
FromEAST FIRST ST AT W FORK OF TRINITY
ToFORT WORTH
CSJ0902-48-502
Proj IDBR 2003(355)
Work TypeREPLACE BRIDGE
 
1.31213943404.4514385722.9399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began03-23-15
Work Completed
Time Computed01-21-15
Contract Working Days533
Addl Days Granted0
Working Days Charged532
Percent Time Used99
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-502
DALLAS LITE AND BARRICADE INC. (0.46)
USA SWPPP INSPECTIONS, INC. (1.95)
FOWLER UNLIMITED, LLC (0.59)
NORTH TEXAS CONTRACTING, INC. (4.35)
HOUSTON SAWING & DRILLING (0.06)
PERFORMANCE EQUIPMENT SERVICE (0.54)
STRIPING TECHNOLOGY, L.P. (0.48)
TEX OP CONSTRUCTION, LP (0.34)
WYLIE DRILLING & DRAINAGE, INC. (3.63)
STAR OPERATIONS, INC. (3.22)
PEACHTREE CONSTRUCTION, LTD. (12.44)
INDUS CONSTRUCTION, L.P. (4.72)
DCCS, LLC (3.80)
FORTSON CONTRACTING, INC. (0.38)
A & A CONSTRUCTION (0.21)
RAMBO CONTRACTING, INC. (0.81)
RG PAINTING (0.17)
BRENDA PRICE TRUCKING (0.14)
TEXAS MANHOLES COMPANY, INC. (0.06)
J. E. GUZMAN CONSTRUCTION, INC. (0.06)
WG ENGINEERING & CONSTRUCTION, LLC (0.03)
Contract #11143201
Totals13943404.450.0014385722.9399.9

CountyTARRANT
HighwayCS
FromSOUTH STEWART STREET AT ASH CREEK
ToIN AZLE
CSJ0902-48-506
Proj IDBR 2003(356)
Work TypeREPLACE BR & APPRS
 
0.135799000.00103370.9112.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-12
Work Began00-00-00
Work Completed
Time Computed06-05-12
Contract Working Days84
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EMPIRE CIVIL CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-506
ACTION SERVICES (0.35)
FORTSON CONTRACTING, INC. (1.63)
GJ SEEDING, LLC (2.58)
PEACHTREE CONSTRUCTION, LTD. (5.65)
TEXAS SHAFTS, INC. (6.70)
TOTAL HIGHWAY MAINTENANCE, LLC (0.35)
Contract #01123025
Totals799000.000.00103370.9112.9

CountyTARRANT
HighwayCS
From0.152 MI S OF MID CITIES BLVD
To0.114 MI N OF MID CITIES BLVD
CSJ0902-48-576
Proj IDCM 2007(227)
Work TypeINTERSECTION IMPROVEMENTS
 
0.2664658453.88270906.365.8
Work Order09-21-17
Work Began11-27-17
Work Completed
Time Computed10-22-17
Contract Working Days165
Addl Days Granted0
Working Days Charged10
Percent Time Used6
Contractor(s)
MCMAHON CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-576
BROCK ENVIRONMENTAL SERVICES, LLC (0.18)
GJ SEEDING, LLC (2.22)
INLET STRUCTURE SPECIALTIES LTD. (2.44)
TEXAS BOMANITE (2.93)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (10.00)
URBAN INFRACONSTRUCTION, LLC. (6.07)
BEAN ELECTRICAL, INC. (7.06)
STRIPING TECHNOLOGY, L.P. (2.14)
BUYERS BARRICADES, INC. (0.33)
TEXAS STAR SAWING & SEALING (0.30)
ALLIANCE GEOTECHNICAL GROUP (0.90)
JESUS MORALES TRUCKING (0.43)
TRINITY CONCRETE SAWING, LLC (0.30)
Contract #08173243
Totals4658453.8811414.59270906.365.8

CountyTARRANT
HighwayCS
FromFOREST HILL DR. AT TRIB. OF VILLAGE
ToCREEK IN FOREST HILL.
CSJ0902-48-659
Proj IDBR 2006(543)
Work TypeREPLACE BRIDGES AND APPROACHES
 
0.1002252080.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-659
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08153244
Totals2252080.580.000.000.0

CountyTARRANT
HighwayCS
FromAT IH 30; ON CHAPEL CREEK BLVD
ToIN FORT WORTH
CSJ0902-48-722
Proj IDSTP 2012(777)MM
Work TypeGR, BS, STR & STRIPING
 
0.1009048794.522820368.8031.1
Work Order01-17-17
Work Began07-13-17
Work Completed
Time Computed02-17-17
Contract Working Days363
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-722
ALTUS TRAFFIC MANAGEMENT LLC (0.41)
BREDA COMPANY, INC. (2.99)
BRENDA PRICE TRUCKING (1.88)
DIIBS SPECIALISTS (0.39)
DUSTROL, INC. (0.43)
HOUSTON SAWING & DRILLING (0.05)
LINDAMOOD DEMOLITION, INC. (0.57)
MICA CORPORATION (4.78)
PRIMATE CONSTRUCTION, INC. (0.09)
RAMBO CONTRACTING, INC. (1.21)
RG PAINTING, INC. (0.14)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (5.84)
SOUTHERN CROSS CONTRACTORS, LLC (0.80)
STRIPING TECHNOLOGY, L.P. (0.56)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.38)
TEXAS SHAFTS, INC. (0.97)
DURABLE SPECIALTIES, INC. (2.53)
FARR FOUNDATION, INC. (1.10)
ACADIA SERVICES (0.30)
Contract #11163008
Totals9048794.52485919.492820368.8031.1

CountyERATH
HighwayVA
FromTARLETON ST
ToNEAR FM 8
CSJ0902-49-068
Proj IDSTP 2014(119)TE
Work TypeGR, BS, DR, STRUCTURE AND PAVEMENT
 
0.9272150084.20746695.6134.7
Work Order06-14-17
Work Began08-14-17
Work Completed
Time Computed07-15-17
Contract Working Days180
Addl Days Granted0
Working Days Charged94
Percent Time Used52
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-068
STORM WATER MANAGEMENT, INC. (0.76)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (19.06)
STRIPE-A-ZONE, INC. (0.51)
TEXAS ALTERNATIVE GRASSER, INC. (0.22)
LUZ LERMA CONSTRUCTION, INC. (9.53)
Contract #08163051
Totals2150084.204000.00746695.6134.7

CountyTARRANT
HighwayCS
FromFOREST HILL DR. AT TRIB. OF VILLAGE
ToCREEK IN FOREST HILL
CSJ0902-90-067
Proj IDBR 2006(543)
Work TypeREPLACE BRIDGES AND APPROACHES
 
0.1002474990.241358278.9654.8
Work Order01-10-17
Work Began02-27-17
Work Completed
Time Computed02-10-17
Contract Working Days192
Addl Days Granted0
Working Days Charged183
Percent Time Used95
Contractor(s)
MCMAHON CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-067
ACTION COMMERCIAL SERVICES, L.L.C. (0.66)
FORTSON CONTRACTING, INC. (0.24)
INLET STRUCTURE SPECIALTIES LTD. (2.67)
JESUS MORALES TRUCKING (0.00)
KLP COMMERCIAL, LLC (0.00)
LUZ TRUCKING, INC. (0.00)
STOIC CIVIL CONSTRUCTION, INC. (6.78)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.08)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.87)
FOUNDATION DRILLERS, INC. (1.78)
AAA DRILLING FOUNDATION CO., INC. (0.26)
EL CALA CONSTRUCTION LLC (0.64)
Contract #11163010
Totals2474990.24112085.281358278.9654.8

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToON DFW CONNECTOR
CSJ0902-90-071
Proj IDC 902-90-71
Work TypeILLUMINATION REFURBISHMENT
 
0.1002906756.940.000.0
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed10-22-17
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173209
Totals2906756.940.000.000.0

CountyTARRANT
HighwayIH 30
FromWB IH30 COL DIST FROM UNIVERISTY DR
ToOVER WB IH30 EXIT RAMP TO MONTGOMER
CSJ1068-01-216
Proj IDBR 1702(737)
Work TypeGR, BS, DR, PAV
 
0.130997337.740.000.0
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed10-15-17
Contract Working Days128
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 1068-01-216
T & R EXCAVATION, INC. (5.47)
CROSS ROADS, L.P. (1.38)
PENHALL COMPANY (0.30)
S & S BRIDGE PAINTING, INC. (20.10)
TOTAL HIGHWAY MAINTENANCE, LLC (1.19)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.81)
DFW SERVICES, LLC (3.06)
FORTSON CONTRACTING, INC. (2.88)
TEXOP CONSTRUCTION (0.56)
PEACHTREE CONSTRUCTION, LTD. (2.38)
Contract #08173018
Totals997337.740.000.000.0

CountyTARRANT
HighwayIH 30
From1.0 MI W OF SH 360
ToGREAT SOUTHWEST PKWY
CSJ1068-02-076
Proj IDNH 2016(183)
Work TypeGR STRS & SURF
 
2.933228440784.53109761015.2148.0
CountyTARRANT
HighwayIH 30
From1.0 MI W OF SH 360
ToGREAT SOUTHWEST PKWY
CSJ1068-02-123
Proj IDNH 2007(893)
Work TypeROW ACQ, RELOC & UTILITIES
 
0.0014741104.002920231.6061.5
Work Order12-09-15
Work Began01-19-16
Work Completed
Time Computed01-19-16
Contract Working Days1,150
Addl Days Granted249
Working Days Charged620
Percent Time Used44
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-076
USA SWPPP INSPECTIONS, INC. (0.99)
THELIN RECYCLING COMPANY, L.P. (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06)
SCOTT DERR PAINTING CO, LLC (0.21)
BROOKLYN SWEEPS (0.35)
F A BROWN"S CONSTRUCTION, LLC (0.67)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (5.72)
W.O.E. CONSTRUCTION (3.34)
BUYERS BARRICADES, INC. (0.00)
ROYAL REBAR (5.43)
ARK CONTRACTING SERVICES, LLC (2.29)
INTEGRATED ROADWAY SERVICES, INC. (4.41)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59)
NORTH TEXAS CONTRACTING, INC. (7.30)
MIKE ALBERT, INC. (0.13)
1 PRIORITY ENVIRONMENTAL SERVICES, INC. (0.40)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.07)
BORE COMPANY, LLC (0.29)
EXCEL 4 CONSTRUCTION, LLC (0.09)
JAGOE-PUBLIC COMPANY (0.13)
UNDER CONSTRUCTION INC. (0.07)
FOUNDATION DRILLERS, INC. (0.03)
MORNING STAR TREE SERVICE (0.00)
Contract #11153231
Totals233181888.531685711.12112681246.8148.3

page 1 | page 2 | page 3 | page 4 | page 5