Monthly State Let Construction Report For Fort Worth District As Of Jul 13, 2015 Page 4 Of 7

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway FM 1885
From PARKER/PALO PINTO COUNTY LINE
To FM 52
CSJ 0539-05-015
Proj ID STP 1502(332)
Work Type GR, BS, DR, STRUC. AND PAVEMENT
 
5.943 5556310.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 299
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0539-05-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153244
Totals 5556310.37 0.00 0.00 0.0

CountyTARRANT
Highway FM 156
From 1000 FT NORTH OF AVONDALE-HASLETT
To 500 FT SOUTH OF AVONDALE-HASLETT RD
CSJ 0718-02-065
Proj ID STP 2013(954)
Work Type GR, BS, AND PAVEMENT
 
0.852 403357.75 0.00 428244.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-17-13
Work Began 10-21-13
Work Completed 01-28-15
Time Computed 10-03-13
Contract Working Days 35
Addl Days Granted 19
Working Days Charged 54
Percent Time Used 100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0718-02-065
CROSSROADS, L.P. (1.29%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.98%)
FORTSON CONTRACTING, INC.(2.48%)
PEACHTREE CONSTRUCTION, LTD. ( 21.40%)
STRIPING TECHNOLOGY, L.P.(1.84%)
BRENDA PRICE TRUCKING(0.00%)
Contract # 08133261
Totals 403357.75 0.00 428244.60 100.0

CountyTARRANT
Highway FM 157
From MITCHELL STREET; IN ARLINGTON
To IH 20
CSJ 0747-04-065
Proj ID STP 1402(034)HRR
Work Type GR, BS AND PAVEMENT
 
3.795 5294353.95 253885.59 1283770.47 24.2
Work Order 12-05-14
Work Began 02-11-15
Work Completed  
Time Computed 02-11-15
Contract Working Days 281
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 27
Contractor(s)
THE FAIN GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0747-04-065
BEAN ELECTRICAL, INC.(1.29%)
BUYERS BARRICADES, INC.(0.91%)
DUSTROL, INC.(1.88%)
O. TREVINO CONSTRUCTION, LLC ( 16.17%)
PEACHTREE CONSTRUCTION, LTD. ( 27.01%)
STRIPING TECHNOLOGY, L.P.(2.49%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.80%)
SUPER SURFACE, INC.(7.24%)
ORNELAS & SON"S TRUCKING (1.39%)
W.O.E. CONSTRUCTION(0.18%)
BRENDA PRICE TRUCKING(0.00%)
STRAIGHT LINE SAWING & SEALING (0.22%)
COWBOY TRUCKING(0.94%)
CLASSIC STEEL, LLC (0.50%)
Contract # 08143213
Totals 5294353.95 253885.59 1283770.47 24.2

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE FY 14
CSJ 0902-00-126
Proj ID STP 1302(027)
Work Type CONCRETE REPAIR
 
0.100 1413335.00 0.00 1891218.20 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-19-13
Work Began 10-21-13
Work Completed 10-20-14
Time Computed 10-19-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 364
Percent Time Used 99
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-126
W.O.E. CONSTRUCTION(2.37%)
BRENDA PRICE TRUCKING(2.36%)
CROSSROADS, L.P. (0.23%)
Contract # 07133010
Totals 1413335.00 0.00 1891218.20 100.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To CONCRETE PAVEMENT REPAIR
CSJ 0902-00-131
Proj ID STP 2015(071)
Work Type CONCRETE PAVT REPAIR
 
0.100 1587885.00 163081.24 1183606.95 74.5
Work Order 10-09-14
Work Began 10-13-14
Work Completed  
Time Computed 10-13-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 256
Percent Time Used 70
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-131
W.O.E. CONSTRUCTION(2.68%)
BRENDA PRICE TRUCKING(1.85%)
Contract # 09143228
Totals 1587885.00 163081.24 1183606.95 74.5

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-132
Proj ID STP 2015(072)
Work Type PAVEMENT MARKINGS
 
0.100 930000.05 0.00 1145739.07 100.0
Work Order 10-02-14
Work Began 10-20-14
Work Completed 06-08-15
Time Computed 10-20-14
Contract Working Days 35
Addl Days Granted 11
Working Days Charged 46
Percent Time Used 100
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-132
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143015
Totals 930000.05 0.00 1145739.07 100.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-133
Proj ID STP 2013(552)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.100 815000.00 0.00 966548.31 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-13
Work Began 07-23-13
Work Completed  
Time Computed 07-23-13
Contract Working Days 365
Addl Days Granted 51
Working Days Charged 416
Percent Time Used 100
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-133
ROADMASTER, INC. (1.45%)
DYNAMIC VISION CO., INC. (6.56%)
Contract # 03133030
Totals 815000.00 0.00 966548.31 99.9

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICT WIDE FY 2013
CSJ 0902-00-134
Proj ID NH 2013(957)G
Work Type SIGN STUCTURES
 
41.900 476055.25 37361.01 250168.02 52.5
Work Order 07-08-14
Work Began 01-05-15
Work Completed  
Time Computed 07-24-14
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 71
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-134
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.97%)
ODUM SERVICES, L.P.(1.73%)
DYNAMIC VISION CO., INC. (5.67%)
Contract # 04143241
Totals 476055.25 37361.01 250168.02 52.5

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-136
Proj ID STP 2014(353)G
Work Type TRAFFIC SIGNALS
 
0.100 1275000.00 80137.36 578131.51 45.3
Work Order 03-12-14
Work Began 08-25-14
Work Completed  
Time Computed 03-28-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 310
Percent Time Used 84
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-136
ROAD MASTER STRIPING LLC (0.85%)
Contract # 01143223
Totals 1275000.00 80137.36 578131.51 45.3

CountyTARRANT
Highway VA
From DISTRICTWIDE
To VARIOUS LOCATIONS
CSJ 0902-00-137
Proj ID STP 2015(226)
Work Type TRAFFIC SIGNALS
 
0.100 979264.66 6799.09 6799.09 0.6
Work Order 01-05-15
Work Began 06-18-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 3
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143217
Totals 979264.66 6799.09 6799.09 0.6

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To ON FM 1187 AND FM 731
CSJ 0902-00-139
Proj ID STP 2014(663)
Work Type LANDSCAPING
 
0.100 317349.10 3130.00 303434.14 95.6
Work Order 05-09-14
Work Began 07-16-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 87
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-139
TOTAL HIGHWAY MAINTENANCE, LLC (1.96%)
AQUA BORE(2.97%)
Contract # 04143237
Totals 317349.10 3130.00 303434.14 95.6

CountyWISE
Highway CR
From CR 2372 AT BRANCH OF BLACK CREEK
To .
CSJ 0902-20-098
Proj ID BR 2009(899)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 489840.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153261
Totals 489840.50 0.00 0.00 0.0

CountyWISE
Highway CR
From FOSTER RD AT TRIBUTARY OF DENTON CR
To .
CSJ 0902-20-100
Proj ID BR 2009(902)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.168 820802.59 0.00 88000.00 10.7
Work Order 10-07-14
Work Began 02-04-15
Work Completed  
Time Computed 10-23-14
Contract Working Days 209
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 13
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-100
OMEGA CONSTRUCTION, LLC( 65.14%)
MCKINNEY DRILLING COMPANY( 18.33%)
Contract # 08143050
Totals 820802.59 0.00 88000.00 10.7

CountyWISE
Highway CR
From CR 2675 (PARKER DAIRY RD) AT DENTON
To .
CSJ 0902-20-108
Proj ID BR 2012(347)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 549711.00 48469.40 454932.50 82.7
Work Order 10-02-14
Work Began 01-28-15
Work Completed  
Time Computed 01-01-15
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 96
Contractor(s)
ASHLAR CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-108
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.59%)
TEXAS SHAFTS, INC. ( 16.29%)
WOLFE CONSTRUCTION GROUP, INC. (0.84%)
MCL CONTRACTING, LLC (0.42%)
FORTSON CONTRACTING, INC.(2.75%)
PREMIER PAVING, LTD. (3.01%)
JUST GROOVING, LTD.(0.29%)
Contract # 08143247
Totals 549711.00 48469.40 454932.50 82.7

CountyWISE
Highway VA
From VARIOUS LOCATIONS
To ON US81/287 IN WISE COUNTY
CSJ 0902-20-109
Proj ID NH 2015(488)
Work Type GR, DR, PAVEMENT AND STRIPING
 
0.795 5019768.13 0.00 0.00 0.0
Work Order 03-03-15
Work Began 00-00-00
Work Completed  
Time Computed 03-19-15
Contract Working Days 196
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-109
BRENDA PRICE TRUCKING(0.65%)
BUYERS BARRICADES, INC.(0.65%)
DUSTROL, INC.(0.71%)
GJ SEEDING, LLC(2.21%)
HJC FARMS, INC.(0.73%)
JAGOE-PUBLIC COMPANY ( 21.98%)
MCL CONTRACTING, LLC (1.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.18%)
W.O.E. CONSTRUCTION(0.51%)
Contract # 01153022
Totals 5019768.13 0.00 0.00 0.0

CountyPARKER
Highway CS
From AT US 180/IH20; ON LAKESHORE DRIVE
To IN HUDSON OAKS
CSJ 0902-38-075
Proj ID STP 2015(679)
Work Type GR, DR, STR, PAVEMENT & STRIPING
 
0.100 7269140.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 299
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0902-38-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153251
Totals 7269140.69 0.00 0.00 0.0

CountyPARKER
Highway CR
From EARP RD AT TRIB TO WALNUT CREEK
To .
CSJ 0902-38-076
Proj ID BR 2009(423)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.300 1379496.35 61721.62 61721.62 4.4
Work Order 04-01-15
Work Began 00-00-00
Work Completed  
Time Computed 04-17-15
Contract Working Days 191
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-38-076
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.74%)
PEACHTREE CONSTRUCTION, LTD. (5.75%)
STRIPING TECHNOLOGY, L.P.(0.72%)
ALTUS TRAFFIC MANAGEMENT LLC (0.84%)
GJ SEEDING, LLC(3.07%)
FORTSON CONTRACTING, INC.(1.82%)
Contract # 02153014
Totals 1379496.35 61721.62 61721.62 4.4

CountyPALO PINTO
Highway VA
From VARIOUS LOCATIONS
To ON US 180 AND US 281
CSJ 0902-39-032
Proj ID STP 2014(770)
Work Type LANDSCAPING
 
0.200 191130.12 820.00 192053.76 99.9
Work Order 07-18-14
Work Began 08-25-14
Work Completed  
Time Computed 08-12-14
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 35
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-39-032
AQUA BORE( 28.15%)
Contract # 06143033
Totals 191130.12 820.00 192053.76 99.9

CountyJACK
Highway CR
From BURWICK RD AT BIG CLEVELAND CREEK
To .
CSJ 0902-40-025
Proj ID BR 2009(926)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 419877.10 4045.00 385265.28 100.0
Work Order 09-11-14
Work Began 11-10-14
Work Completed 06-17-15
Time Computed 09-27-14
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 86
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-40-025
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.83%)
ALTUS TRAFFIC MANAGEMENT LLC (1.21%)
DUSTIN ALLEN, INC. (2.65%)
WOLFE CONSTRUCTION GROUP, INC. (3.29%)
Contract # 08143034
Totals 419877.10 4045.00 385265.28 100.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To IN TARRANT COUNTY
CSJ 0902-48-058
Proj ID STP 1502(333)
Work Type CONSTRUCT CURB RAMPS
 
0.100 1966433.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153057
Totals 1966433.16 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7