Monthly State Let Construction Report For Fort Worth District As Of Oct 14, 2014 Page 4 Of 6

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWISE
Highway CR
From CR 2675 (PARKER DAIRY RD) AT DENTON
To .
CSJ 0902-20-108
Proj ID BR 2012(347)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 549711.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ASHLAR CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143247
Totals 549711.00 0.00 0.00 0.0

CountyPALO PINTO
Highway VA
From VARIOUS LOCATIONS
To ON US 180 AND US 281
CSJ 0902-39-032
Proj ID STP 2014(770)
Work Type LANDSCAPING
 
0.200 191130.12 86329.16 167243.26 87.5
Work Order 07-18-14
Work Began 08-25-14
Work Completed  
Time Computed 08-12-14
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 35
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-39-032
AQUA BORE( 28.15%)
Contract # 06143033
Totals 191130.12 86329.16 167243.26 87.5

CountyJACK
Highway CR
From BURWICK RD AT BIG CLEVELAND CREEK
To .
CSJ 0902-40-025
Proj ID BR 2009(926)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 419877.10 0.00 0.00 0.0
Work Order 09-11-14
Work Began 00-00-00
Work Completed  
Time Computed 09-27-14
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-40-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143034
Totals 419877.10 0.00 0.00 0.0

CountyTARRANT
Highway CS
From AT HARRISON LANE
To ON PIPELINE RD IN HURST
CSJ 0902-48-186
Proj ID STP 94(82)MM
Work Type INTERSECTION IMPROVEMENTS
 
0.010 801805.98 0.00 145395.00 18.1
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 11-09-13
Contract Working Days 111
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 4
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-186
BRENDA PRICE TRUCKING(0.00%)
ROAD MASTER STRIPING LLC (0.41%)
GJ SEEDING, LLC(2.31%)
ALTUS TRAFFIC MANAGEMENT LLC (0.49%)
DURABLE SPECIALTIES, INC.( 12.07%)
DUSTROL, INC.(1.01%)
EROSION CONTROL MANAGEMENT SERVICES(0.50%)
MIKE ALBERT, INC.( 15.82%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(4.62%)
W.O.E. CONSTRUCTION(0.17%)
Contract # 08133062
Totals 801805.98 0.00 145395.00 18.1

CountyTARRANT
Highway CS
From W 7TH ST OVER THE TRINITY
To .
CSJ 0902-48-505
Proj ID BR 2006(767)
Work Type REPL BR & APPRS
 
0.559 24150158.45 89209.62 25023753.94 99.9
Work Order 08-10-11
Work Began 05-07-12
Work Completed  
Time Computed 08-26-11
Contract Working Days 327
Addl Days Granted 0
Working Days Charged 327
Percent Time Used 100
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-505
COWTOWN TRAFFIC CONTROL, INC.(0.06%)
C.T. AND S. METALWORKS, INC. (1.16%)
CAIN FENCE (0.07%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
INDUS CONSTRUCTION, L.P. (1.83%)
MICA CORPORATION (2.46%)
NORTH TEXAS CONTRACTING, INC.(1.06%)
SCOTT DERR PAINTING CO, LLC(1.62%)
TEX OP CONSTRUCTION, LP(0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.29%)
VSTRUCTURAL LLC(3.46%)
BURKHALTER RIGGING, INC. (7.22%)
PEACHTREE CONSTRUCTION, LTD. (0.30%)
ATS DRILLING, INC. (4.50%)
GREAT WESTERN ERECTORS (0.23%)
LINDAMOOD DEMOLITION, INC. (3.04%)
PENHALL COMPANY(0.04%)
CROSSROADS, L.P. (0.10%)
BRENDA PRICE TRUCKING(0.03%)
SKAGGS ROAD BORING INC.(0.00%)
STRIPING TECHNOLOGY, L.P.(0.10%)
INLET STRUCTURE SPECIALTIES LTD. (0.21%)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.22%)
GREEN SCAPING(1.46%)
EROSION PREVENTION PRODUCTS(1.35%)
Contract # 06113245
Totals 24150158.45 89209.62 25023753.94 99.9

CountyTARRANT
Highway CS
From SOUTH STEWART STREET AT ASH CREEK
To IN AZLE
CSJ 0902-48-506
Proj ID BR 2003(356)
Work Type REPLACE BR & APPRS
 
0.135 799000.00 0.00 65370.91 8.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-12
Work Began 00-00-00
Work Completed  
Time Computed 06-05-12
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EMPIRE CIVIL CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-506
ACTION SERVICES(0.35%)
FORTSON CONTRACTING, INC.(1.63%)
GJ SEEDING, LLC(2.58%)
PEACHTREE CONSTRUCTION, LTD. (5.65%)
TEXAS SHAFTS, INC. (6.70%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.35%)
Contract # 01123025
Totals 799000.00 0.00 65370.91 8.1

CountyTARRANT
Highway CS
From PRECINCT LINE RD. AT WALKER BRANCH
To FORT WORTH
CSJ 0902-48-539
Proj ID BR 2006(132)
Work Type REPLACE BRIDGE
 
0.138 2287447.40 0.00 419672.26 18.3
CountyTARRANT
Highway CS
From SH 10; ON PRECINCT LINE ROAD
To N OF TRAMMEL DAVIS; IN FT. WORTH
CSJ 0902-48-680
Proj ID HP 2007(860)
Work Type GR, DR, STR & PAVING
 
0.642 4245929.63 268097.99 477444.04 11.2
CountyTARRANT
Highway CS
From TRINITY BLVD; IN FORT WORTH
To AT PRECINCT LINE ROAD
CSJ 0902-48-793
Proj ID CM 2013(785)
Work Type GR, DR, PAVEMENT
 
0.420 3954288.21 454516.10 620716.10 15.6
Work Order 11-08-13
Work Began 08-11-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 10
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-539
TOTAL HIGHWAY MAINTENANCE, LLC (0.77%)
SCOTT DERR PAINTING CO, LLC(0.13%)
TEX OP CONSTRUCTION, LP(0.62%)
STAR OPERATIONS, INC.(2.74%)
PREMIER PAVING, LTD. (8.52%)
BREDA COMPANY, INC.(0.76%)
SUNDANCE FENCE & IRON, LLC (0.19%)
GJ SEEDING, LLC(1.25%)
BUYERS BARRICADES, INC.(0.26%)
HANSON PRESSURE PIPE, INC. (0.03%)
A & A CONSTRUCTION (1.15%)
DISPLAYS UNLIMITED, INC. (0.08%)
THELIN RECYCLING COMPANY, L.P. (0.34%)
FOUNDATION DRILLERS, INC.(1.28%)
MCL CONTRACTING, LLC (0.05%)
COWBOY TRUCKING(0.00%)
Contract # 08133013
Totals 10487665.24 722614.09 1517832.40 14.4

CountyTARRANT
Highway CS
From SILVER CREEK RD @ SILVER CREEK,FT W
To .
CSJ 0902-48-742
Proj ID BR 2009(953)
Work Type REPLACE BRIDGE
 
0.087 1031130.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-742
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143052
Totals 1031130.80 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To IN TARRANT COUNTY
CSJ 0902-48-822
Proj ID NH 2012(353)
Work Type CONSTRUCT CURB RAMPS
 
0.001 3378473.70 0.00 3313831.06 98.1
Work Order 06-08-12
Work Began 07-16-12
Work Completed  
Time Computed 06-24-12
Contract Working Days 283
Addl Days Granted 143
Working Days Charged 429
Percent Time Used 100
Contractor(s)
KEN-DO CONTRACTING, LP
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-822
ROAD MASTER STRIPING LLC (7.83%)
MEL"S ELECTRIC SERVICE, INC. ( 21.22%)
TEX OP CONSTRUCTION, LP(0.11%)
ALLIANCE TRUCKING(0.18%)
APAC-TEXAS, INC. (0.07%)
CHAPAS TRUCKING(0.11%)
ROJO TRUCKING(0.00%)
Contract # 03123020
Totals 3378473.70 0.00 3313831.06 98.1

CountyTARRANT
Highway CS
From ARBROOK BLVD
To BARDIN ROAD, IN ARLINGTON
CSJ 0902-48-838
Proj ID CC 902-48-838
Work Type GRADING, STRUCTURES AND PAVEMENT
 
0.740 10457967.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-14
Work Began 00-00-00
Work Completed  
Time Computed 09-27-14
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-838
ACTION SERVICES(0.21%)
EROSION CONTROL MANAGEMENT SERVICES(0.23%)
HARDSCAPE SPECIALTIES, INC.(0.09%)
PLACIDO CONSTRUCTION COMPANY (1.02%)
S & S BRIDGE PAINTING, INC.(0.14%)
VENUS CONSTRUCTION (1.19%)
W.O.E. CONSTRUCTION(0.09%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.27%)
Contract # 04143005
Totals 10457967.33 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To IN TARRANT COUNTY
CSJ 0902-48-844
Proj ID STP 2014(071)
Work Type CURB RAMPS
 
0.001 1813396.74 0.00 456592.06 25.1
Work Order 01-17-14
Work Began 02-10-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 216
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 68
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-844
ALTUS TRAFFIC MANAGEMENT LLC (0.66%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(7.68%)
Contract # 10133220
Totals 1813396.74 0.00 456592.06 25.1

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To TARRANT COUNTY ONLY FY 2013
CSJ 0902-48-849
Proj ID STP 2013(836)
Work Type BRIDGE REPAIR
 
0.100 2687139.38 83757.48 2224990.29 82.8
Work Order 11-05-13
Work Began 04-13-14
Work Completed  
Time Computed 11-21-13
Contract Working Days 175
Addl Days Granted 22
Working Days Charged 107
Percent Time Used 54
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-849
PEACHTREE CONSTRUCTION, LTD. ( 45.90%)
VIKING CONSTRUCTION, INC.(1.14%)
TEX OP CONSTRUCTION, LP(2.68%)
M & M STRIPING & POWER WASHING, LLC(1.78%)
COWBOY TRUCKING(0.00%)
GLORIA VALENZUELA ENTERPRISE, INC(0.00%)
Contract # 07133234
Totals 2687139.38 83757.48 2224990.29 82.8

CountyTARRANT
Highway VA
From IH 20, IH 30, IH 820, IH 35W_AT
To VARIOUS LOCATIONS IN TARRANT COUNTY
CSJ 0902-48-895
Proj ID NH 1402(035)
Work Type GR, STR
 
0.100 1299947.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-22-14
Work Began 00-00-00
Work Completed  
Time Computed 10-08-14
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-895
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143242
Totals 1299947.50 0.00 0.00 0.0

CountyERATH
Highway CR
From CR 266 AT GREEN CREEK
To .
CSJ 0902-49-063
Proj ID BR 2009(105)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 457947.66 0.00 451326.83 98.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 05-07-14
Work Completed  
Time Computed 05-07-14
Contract Working Days 51
Addl Days Granted 10
Working Days Charged 59
Percent Time Used 96
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-063
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.33%)
RICE ENVIRONMENTAL SERVICES(3.46%)
LONE OAK LANDSCAPE LLC (0.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.50%)
MCL CONTRACTING, LLC (0.46%)
KLP COMMERCIAL, LLC(0.00%)
Contract # 02143229
Totals 457947.66 0.00 451326.83 98.5

CountyERATH
Highway VA
From VARIOUS LOCATIONS
To AROUND STEPHENVILLE
CSJ 0902-49-066
Proj ID STP 2012(569)
Work Type LANDSCAPE ENHANCEMENT
 
0.282 379628.18 0.00 336988.91 88.7
Work Order 06-18-12
Work Began 10-01-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 95
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-066
MEMCO(6.42%)
LONE OAK LANDSCAPE LLC ( 50.03%)
Contract # 05123017
Totals 379628.18 0.00 336988.91 88.7

CountyERATH
Highway VA
From US 377/SH 108 INTERSECTION
To BU377J/LILLIAN ST; IN STEPHENVILLE
CSJ 0902-49-067
Proj ID STP 2013(193)
Work Type LANDSCAPE ENHANCEMENT
 
0.100 137204.63 431.04 133815.94 97.5
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 66
Contractor(s)
ALL AROUND LAWN CARE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-067
MEMCO( 14.55%)
Contract # 06133010
Totals 137204.63 431.04 133815.94 97.5

CountyJOHNSON
Highway CR
From AT KING BRANCH
To ON CR 519
CSJ 0902-50-108
Proj ID BR 2012(761)
Work Type GR, BS, STRUCTURE
 
0.083 392475.80 0.00 415820.38 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-13
Work Began 12-03-13
Work Completed  
Time Computed 10-02-13
Contract Working Days 57
Addl Days Granted 16
Working Days Charged 73
Percent Time Used 100
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-50-108
STRIPING TECHNOLOGY, L.P.(0.80%)
GJ SEEDING, LLC(3.76%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
PEACHTREE CONSTRUCTION, LTD. (6.35%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (3.66%)
FORTSON CONTRACTING, INC.(2.34%)
Contract # 08133046
Totals 392475.80 0.00 415820.38 99.9

CountyTARRANT
Highway IH 30
From AT UPRR
To IN GRAND PRAIRIE
CSJ 1068-02-129
Proj ID IM 0304(100)
Work Type BRIDGE REPAIRS
 
0.100 98730.00 0.00 0.00 0.0
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 09-05-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-129
TOTAL HIGHWAY MAINTENANCE, LLC (3.31%)
Contract # 07143036
Totals 98730.00 0.00 0.00 0.0

CountyTARRANT
Highway IH 30
From COOPER_STREET
To FIELDER_ROAD
CSJ 1068-02-140
Proj ID IM 0304(097)
Work Type GR, BS AND SURFACE
 
0.999 639953.15 0.00 632534.52 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-19-13
Work Began 09-30-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 64
Addl Days Granted 1
Working Days Charged 100
Percent Time Used 153
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-140
BRENDA PRICE TRUCKING(0.00%)
CROSSROADS, L.P. (0.75%)
DUSTROL, INC.(2.47%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(9.29%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.98%)
STRIPING TECHNOLOGY, L.P.(3.07%)
PEACHTREE CONSTRUCTION, LTD. (9.72%)
W.O.E. CONSTRUCTION(0.16%)
Contract # 06133215
Totals 639953.15 0.00 632534.52 99.9

CountyTARRANT
Highway IH 30
From IH 820
To W OF COOPER STREET
CSJ 1068-02-141
Proj ID IM 0304(099)
Work Type HMAC OVERLAY
 
5.681 5418484.81 864295.44 2613294.40 48.4
Work Order 04-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 114
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-141
DUSTROL, INC.( 10.85%)
PRIMATE CONSTRUCTION, INC. (3.47%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.09%)
BRENDA PRICE TRUCKING(0.90%)
COWBOY TRUCKING(2.10%)
Contract # 02143222
Totals 5418484.81 864295.44 2613294.40 48.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6