Monthly State Let Construction Report For Fort Worth District As Of Jul 12, 2016 Page 4 Of 4

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway FM 1189
From YOUNG BEND ROAD
To HOOD COUNTY LINE
CSJ 1468-01-024
Proj ID STP 1402(036)
Work Type GR, STR, FLX BS, SC, MBGF, SIGN, PVT MK
 
9.058 6481549.55 147109.29 1449364.55 22.3
Work Order 10-07-14
Work Began 01-25-16
Work Completed  
Time Computed 10-23-14
Contract Working Days 253
Addl Days Granted 6
Working Days Charged 65
Percent Time Used 25
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1468-01-024
RAMBO CONTRACTING, INC.(4.87%)
TEXAS ALTERNATIVE GRASSER, INC.(0.76%)
PEACHTREE CONSTRUCTION, LTD. ( 19.95%)
CHEROKEE SERVICES(0.03%)
FOUNDATION DRILLERS, INC.(0.65%)
WEST TEXAS RUMBLE STRIP(0.05%)
MARCOM"S MOWING SERVICE, LLC (0.87%)
D. I. J. CONSTRUCTION, INC.(1.69%)
Contract # 08143043
Totals 6481549.55 147109.29 1449364.55 22.3

CountyJOHNSON
Highway FM 916
From SH 171
To FM 4
CSJ 1599-02-014
Proj ID STP 1402(037)HES
Work Type GRADING, BASE AND PAVEMENT
 
12.842 6925133.46 25092.10 835081.12 12.0
Work Order 09-30-14
Work Began 09-02-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 201
Addl Days Granted 18
Working Days Charged 106
Percent Time Used 48
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1599-02-014
STRIPING TECHNOLOGY, L.P.(0.77%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67%)
RAMBO CONTRACTING, INC.(7.05%)
FARR FOUNDATION, INC.(2.15%)
PEACHTREE CONSTRUCTION, LTD. ( 21.42%)
FORTSON CONTRACTING, INC.(1.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.23%)
Contract # 08143036
Totals 6925133.46 25092.10 835081.12 12.0

CountyJOHNSON
Highway FM 1807
From FM 1706
To JOHNSON/ELLIS COUNTY LINE.
CSJ 1600-02-017
Proj ID STP 1502(545)HES
Work Type GR, BS, DR, STR, PAV
 
8.886 8282797.47 940620.89 2440620.03 29.4
Work Order 10-30-15
Work Began 01-04-16
Work Completed  
Time Computed 11-30-15
Contract Working Days 278
Addl Days Granted 22
Working Days Charged 123
Percent Time Used 41
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1600-02-017
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(7.54%)
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
STRIPING TECHNOLOGY, L.P.(1.61%)
DIAMOND SURFACE, INC.(0.11%)
SYNERGY SIGNS & SERVICES, LLC(0.53%)
J & M CONTRACTING, COMPANY ( 16.28%)
TEX OP CONSTRUCTION, LP(0.11%)
TX TINMAN ENTERPRISES, LLC.(2.84%)
DUSTROL, INC.(1.03%)
Contract # 08153033
Totals 8282797.47 940620.89 2440620.03 29.4

CountyPARKER
Highway FM 730
From US 180
To SH 199
CSJ 1601-01-029
Proj ID STP 1602(123)
Work Type HMAC OVERLAY
 
30.685 4868689.67 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1601-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163221
Totals 4868689.67 0.00 0.00 0.0

CountyWISE
Highway FM 1655
From 2.0 MILES N OF BU 81-C
To 1.1 MILES N OF BU 81-C
CSJ 1604-02-016
Proj ID STP 1602(328)HES
Work Type SMALL SIGNS, LED LIGHTS
 
1.500 299998.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1604-02-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163016
Totals 299998.00 0.00 0.00 0.0

CountyPARKER
Highway FM 1886
From FM 730
To TARRANT COUNTY LINE
CSJ 1605-01-014
Proj ID STP 2014(478)
Work Type GR.BS, DR, STRUC AND PAVEMENT
 
5.748 4834822.79 153881.16 4260707.48 88.6
Work Order 05-07-14
Work Began 06-12-14
Work Completed  
Time Computed 05-23-14
Contract Working Days 256
Addl Days Granted 77
Working Days Charged 359
Percent Time Used 107
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1605-01-014
RAMBO CONTRACTING, INC.(4.85%)
BICK"S CONSTRUCTION, INC.( 16.34%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.93%)
MARCOM"S MOWING SERVICE, LLC (0.53%)
WEST TEXAS RUMBLE STRIP(0.08%)
AAA DRILLING FOUNDATION CO., INC.(0.36%)
LIRA ELECTRIC(1.57%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.79%)
ELLIS-MCGINNIS CONSTRUCTION CO.(1.86%)
Contract # 03143221
Totals 4834822.79 153881.16 4260707.48 88.6

CountyWISE
Highway FM 2123
From FM 51
To CR 3585
CSJ 1606-02-019
Proj ID STP 2014(884)
Work Type GRADING, BASE, DRAIN.STRUCT. AND PAVE
 
3.078 2779919.35 0.00 21060.39 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-28-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163020
Totals 2779919.35 0.00 21060.39 0.7

CountyTARRANT
Highway FM 1938
From 0.2 MILE SOUTH OF FM 1709
To RANDOL MILL RD/WESTLAKE C/L
CSJ 1978-01-050
Proj ID STP 1402(039)MM
Work Type GR, BS, DR, STRUCTURES & PAVEMENT
 
1.743 20575236.87 682418.20 11106710.19 53.9
Work Order 01-16-15
Work Began 03-23-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 554
Addl Days Granted 63
Working Days Charged 331
Percent Time Used 53
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-050
DALLAS LITE AND BARRICADE INC. (0.38%)
GJ SEEDING, LLC(0.59%)
THELIN RECYCLING COMPANY, L.P. (0.25%)
AUSTCO, INC. (0.05%)
NORTH TEXAS CONTRACTING, INC.( 20.99%)
LIRA ELECTRIC(2.47%)
FARR FOUNDATION, INC.(0.60%)
BREDA COMPANY, INC.(0.50%)
W.O.E. CONSTRUCTION(8.79%)
TEXAS SHAFTS, INC. (0.76%)
CROSSROADS DECORATIVE PAVEMENT (0.09%)
USA SWPPP INSPECTIONS, INC.(2.75%)
SCOTT DERR PAINTING CO, LLC(0.06%)
TRP CONSTRUCTION GROUP, LLC(0.67%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.68%)
A & A CONSTRUCTION (0.06%)
MARCOM"S MOWING SERVICE, LLC (0.32%)
BRENDA PRICE TRUCKING(0.68%)
INLET STRUCTURE SPECIALTIES LTD. (3.12%)
JM MATERIALS, INC. (0.50%)
KLP COMMERCIAL, LLC(8.05%)
TEX OP CONSTRUCTION, LP(0.41%)
Contract # 08143005
Totals 20575236.87 682418.20 11106710.19 53.9

CountyPALO PINTO
Highway FM 2201
From FM 4
To US 281
CSJ 1993-01-015
Proj ID STP 1502(334)
Work Type GR, BS, DR, STRUC & PAVEMENT
 
6.427 4655964.11 0.00 0.00 0.0
Work Order 08-20-15
Work Began 00-00-00
Work Completed  
Time Computed 09-19-15
Contract Working Days 277
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1993-01-015
LUZ LERMA CONSTRUCTION, INC. ( 12.17%)
NORTHEASTERN PAVERS, INC.( 10.87%)
WEST TEXAS RUMBLE STRIP(0.09%)
DURABLE SPECIALTIES, INC.(0.58%)
MARCOM"S MOWING SERVICE, LLC (1.80%)
FARR FOUNDATION, INC.(1.89%)
Contract # 06153024
Totals 4655964.11 0.00 0.00 0.0

CountyTARRANT
Highway FM 1220
From EAGLE MOUNTAIN ELEM SCHOOL
To 1,100 FT. NORTH OF BAILEY BOSWELL
CSJ 2079-01-041
Proj ID STP 2013(901)
Work Type GRADING, BASE AND PAVEMENT
 
2.879 5878132.94 0.00 114642.11 1.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 06-09-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-041
BRENDA PRICE TRUCKING(0.72%)
DALLAS LITE AND BARRICADE INC. (0.31%)
FARR FOUNDATION, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.46%)
LAYFIELD CONSTRUCTION, INC (4.47%)
J. E. GUZMAN CONSTRUCTION, INC.(5.59%)
TEX OP CONSTRUCTION, LP(2.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.43%)
W.O.E. CONSTRUCTION(4.76%)
NORTH TEXAS CONTRACTING, INC.( 14.65%)
STRIPING TECHNOLOGY, L.P.(1.26%)
Contract # 08133064
Totals 5878132.94 0.00 114642.11 1.9

CountyTARRANT
Highway FM 1220
From EAGLE MOUNTAIN ELEM SCHOOL
To 1,100 FT. NORTH OF BAILEY BOSWELL
CSJ 2079-01-043
Proj ID STP 2013(901)
Work Type GRADING, BASE AND PAVEMENT
 
2.879 8350775.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-31-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 278
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163037
Totals 8350775.03 0.00 0.00 0.0

CountyJOHNSON
Highway FM 1902
From TARRANT COUNTY LINE
To FM 917
CSJ 2118-02-019
Proj ID STP 1502(547)HES
Work Type GR, BS, DR, STR, & PVT
 
7.669 6740440.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 354
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2118-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163207
Totals 6740440.33 0.00 0.00 0.0

CountyTARRANT
Highway SH 360
From SOUTH OF MIDWAY
To TRINITY RIVER
CSJ 2266-02-138
Proj ID NH 2016(594)
Work Type MILL AND OVERLAY
 
2.106 2126639.61 187345.35 1462563.72 68.7
Work Order 03-12-16
Work Began 04-05-16
Work Completed  
Time Computed 04-05-16
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 93
Contractor(s)
DIAMOND SURFACE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-138
PEACHTREE CONSTRUCTION, LTD. ( 12.85%)
STRIPING TECHNOLOGY, L.P.(6.54%)
ALTUS TRAFFIC MANAGEMENT LLC (5.00%)
DUSTROL, INC.(1.88%)
STRIPING SYSTEMS, INC. (0.05%)
PAVEMENT MARKINGS INC. (1.04%)
TEXAS STAR CONCRETE SERVICES, LLC(0.30%)
Contract # 01163205
Totals 2126639.61 187345.35 1462563.72 68.7

CountyPALO PINTO
Highway FM 2353
From SH-16
To PR-36
CSJ 2290-01-009
Proj ID STP 1502(335)
Work Type GR, BS, STRUCTURE AND PAVEMENTS
 
5.880 5278946.23 382043.24 2656907.16 50.3
Work Order 07-31-15
Work Began 10-12-15
Work Completed  
Time Computed 08-29-15
Contract Working Days 299
Addl Days Granted 35
Working Days Charged 116
Percent Time Used 34
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2290-01-009
LUZ LERMA CONSTRUCTION, INC. ( 16.74%)
HJC FARMS, INC.(1.98%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
STRIPING TECHNOLOGY, L.P.(1.83%)
Contract # 06153243
Totals 5278946.23 382043.24 2656907.16 50.3

CountyPARKER
Highway FM 1187
From FM 5
To TARRANT COUNTY LINE
CSJ 2291-01-013
Proj ID STP 2014(772)
Work Type GR, BS, STR, SURFACE, SIGNING & MARKING
 
7.204 6785848.59 3000.00 1703720.79 25.1
Work Order 08-08-14
Work Began 12-10-14
Work Completed  
Time Computed 08-24-14
Contract Working Days 374
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 29
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2291-01-013
RAMBO CONTRACTING, INC.( 20.05%)
TEXAS ALTERNATIVE GRASSER, INC.(0.90%)
NORTHEASTERN PAVERS, INC.( 14.31%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.49%)
HJC FARMS, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.07%)
TRP CONSTRUCTION GROUP, LLC(1.08%)
Contract # 06143231
Totals 6785848.59 3000.00 1703720.79 25.1

CountyTARRANT
Highway RM 2871
From SOUTH OF RR CROSSING
To US-377
CSJ 2855-01-021
Proj ID STP 2014(319)
Work Type OVERLAY
 
1.387 2072283.33 0.00 1759883.11 85.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-19-14
Work Began 04-28-14
Work Completed  
Time Computed 03-07-14
Contract Working Days 167
Addl Days Granted 15
Working Days Charged 184
Percent Time Used 101
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2855-01-021
PEACHTREE CONSTRUCTION, LTD. ( 38.67%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.53%)
FORTSON CONTRACTING, INC.(1.20%)
ENVIRONMENTAL STANDARDS(1.13%)
DURABLE SPECIALTIES, INC.(0.48%)
MARCOM"S MOWING SERVICE, LLC (0.30%)
TEXAS ALTERNATIVE GRASSER, INC.(0.33%)
Contract # 01143023
Totals 2072283.33 0.00 1759883.11 85.1

CountyPARKER
Highway FM 3028
From FM 3028 AT ROCKY CREEK
To .
CSJ 2930-02-011
Proj ID BR 1502(336)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 1561559.71 160379.80 1058633.43 67.9
Work Order 08-13-15
Work Began 09-22-15
Work Completed  
Time Computed 09-12-15
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 134
Percent Time Used 103
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2930-02-011
WOLFE CONSTRUCTION GROUP, INC. (0.47%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.95%)
STORM WATER MANAGEMENT, INC. (0.55%)
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
PEACHTREE CONSTRUCTION, LTD. (3.78%)
FORTSON CONTRACTING, INC.(2.02%)
TEXOP CONSTRUCTION (0.47%)
STRIPING TECHNOLOGY, L.P.(0.47%)
Contract # 06153053
Totals 1561559.71 160379.80 1058633.43 67.9

CountyJOHNSON
Highway FM 3136
From 5.213 MILES EAST OF FM 4
To 10.343 MILES EAST OF FM 4
CSJ 3348-01-019
Proj ID STP 1502(549)HES
Work Type GR, BS, DR, STR, & PAVT
 
5.192 6829235.17 63616.55 63616.55 0.9
Work Order 03-28-16
Work Began 00-00-00
Work Completed  
Time Computed 04-28-16
Contract Working Days 384
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3348-01-019
DUSTROL, INC.(0.12%)
Contract # 01163018
Totals 6829235.17 63616.55 63616.55 0.9

CountyJOHNSON
Highway FM 3391
From AT STONE ROAD
To IN BURLESON
CSJ 3372-01-014
Proj ID CC 3372-1-14
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.123 137750.00 26428.10 26428.10 19.1
Work Order 03-16-16
Work Began 06-16-16
Work Completed  
Time Computed 06-14-16
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 26
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3372-01-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153027
Totals 137750.00 26428.10 26428.10 19.1

CountyPARKER
Highway FM 3325
From IH 20
To FM 1886
CSJ 3516-01-015
Proj ID STP 2013(675)
Work Type GR, BS, DR, STRUC AND PAVEMENT
 
7.160 3283284.20 0.00 3282155.53 99.9
Work Order 01-06-14
Work Began 01-28-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 256
Addl Days Granted 64
Working Days Charged 381
Percent Time Used 119
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 3516-01-015
RAMBO CONTRACTING, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.40%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.29%)
NORTHEASTERN PAVERS, INC.( 37.58%)
STRIPING TECHNOLOGY, L.P.(1.71%)
JM MATERIALS, INC. (2.37%)
TEXAS ALTERNATIVE GRASSER, INC.(0.71%)
ODUM SERVICES, L.P.(0.87%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.91%)
Contract # 08133054
Totals 3283284.20 0.00 3282155.53 99.9

page 1 | page 2 | page 3 | page 4