Monthly State Let Construction Report For Fort Worth District As Of Jul 11, 2014 Page 4 Of 5

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyJOHNSON
Highway CR
From AT KING BRANCH
To ON CR 519
CSJ 0902-50-108
Proj ID BR 2012(761)
Work Type GR, BS, STRUCTURE
 
0.083 392475.80 644.21 400108.88 99.9
Work Order 09-16-13
Work Began 12-03-13
Work Completed  
Time Computed 10-02-13
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 128
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-50-108
STRIPING TECHNOLOGY, L.P.(0.80%)
GJ SEEDING, LLC(3.76%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
PEACHTREE CONSTRUCTION, LTD. (6.35%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (3.66%)
FORTSON CONTRACTING, INC.(2.34%)
Contract # 08133046
Totals 392475.80 644.21 400108.88 99.9

CountyTARRANT
Highway IH 30
From AT UPRR
To IN GRAND PRAIRIE
CSJ 1068-02-129
Proj ID IM 0304(100)
Work Type BRIDGE REPAIRS
 
0.100 98730.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-129
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143036
Totals 98730.00 0.00 0.00 0.0

CountyTARRANT
Highway IH 30
From COOPER_STREET
To FIELDER_ROAD
CSJ 1068-02-140
Proj ID IM 0304(097)
Work Type GR, BS AND SURFACE
 
0.999 639953.15 0.00 632534.52 99.9
Work Order 08-19-13
Work Began 09-30-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 64
Addl Days Granted 1
Working Days Charged 100
Percent Time Used 153
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-140
BRENDA PRICE TRUCKING(0.00%)
CROSSROADS, L.P. (0.75%)
DUSTROL, INC.(2.47%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(9.29%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.98%)
STRIPING TECHNOLOGY, L.P.(3.07%)
PEACHTREE CONSTRUCTION, LTD. (9.72%)
W.O.E. CONSTRUCTION(0.16%)
Contract # 06133215
Totals 639953.15 0.00 632534.52 99.9

CountyTARRANT
Highway IH 30
From IH 820
To W OF COOPER STREET
CSJ 1068-02-141
Proj ID IM 0304(099)
Work Type HMAC OVERLAY
 
5.681 5418484.81 673416.11 673416.11 12.4
Work Order 04-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 26
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-141
DUSTROL, INC.( 10.85%)
PRIMATE CONSTRUCTION, INC. (3.47%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.09%)
BRENDA PRICE TRUCKING(0.90%)
COWBOY TRUCKING(2.10%)
Contract # 02143222
Totals 5418484.81 673416.11 673416.11 12.4

CountyTARRANT
Highway SS 341
From SH-183/IH-30 INTERCHANGE
To N WHITE SETTLEMENT RD INTERCHANGE
CSJ 1068-03-021
Proj ID STP 2013(288)
Work Type LANDSCAPE ENHANCEMENT
 
1.905 124997.55 2878.00 109154.98 87.3
Work Order 09-17-13
Work Began 10-17-13
Work Completed  
Time Computed 10-03-13
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 86
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-03-021
ALTUS TRAFFIC MANAGEMENT LLC (2.08%)
Contract # 08133024
Totals 124997.55 2878.00 109154.98 87.3

CountyPARKER
Highway IH 30
From IH 20, AT WALSH RANCH PARKWAY
To TARRANT COUNTY LINE
CSJ 1068-05-009
Proj ID IM 0304(092)
Work Type GRADING, DRAINAGE, STRUCTURE & PAVE
 
1.541 14593117.40 317120.31 5341948.19 36.6
Work Order 09-03-13
Work Began 10-01-13
Work Completed  
Time Computed 09-19-13
Contract Working Days 225
Addl Days Granted 95
Working Days Charged 181
Percent Time Used 56
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-05-009
DALLAS LITE AND BARRICADE INC. (0.22%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.80%)
SCOTT DERR PAINTING CO (0.23%)
COWBOY TRUCKING(3.09%)
W.O.E. CONSTRUCTION(0.41%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(5.28%)
T-BAR FENCE, INC.(0.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
PEACHTREE CONSTRUCTION, LTD. (9.14%)
BUYERS BARRICADES, INC.(0.33%)
DUSTROL, INC.(0.53%)
HJC FARMS, INC.(1.45%)
ATS DRILLING, INC. (0.60%)
BREDA COMPANY, INC.(1.31%)
FORTSON CONTRACTING, INC.(0.05%)
Contract # 04133201
Totals 14593117.40 317120.31 5341948.19 36.6

CountyWISE
Highway FM 718
From SH 114
To NORTH END OF DERRETT CREEK BRIDGE
CSJ 1098-01-020
Proj ID STP 2011(599)
Work Type GRADING, DRAINAGE AND PAVEMENT
 
5.649 4598915.86 716334.70 2036009.31 44.2
Work Order 12-03-13
Work Began 02-18-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 45
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1098-01-020
LANCO TURF & SEEDING, INC. (0.64%)
PEACHTREE CONSTRUCTION, LTD. (4.20%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.86%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.41%)
TEX OP CONSTRUCTION, LP(0.21%)
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
TRANSPORT TRUST(0.54%)
NORTH TEXAS CONTRACTING, INC.( 10.34%)
STORM WATER MANAGEMENT, INC. (0.51%)
STRIPING TECHNOLOGY, L.P.(1.70%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.93%)
Contract # 08133272
Totals 4598915.86 716334.70 2036009.31 44.2

CountyPALO PINTO
Highway FM 919
From AT PANTHER CREEK RELIEF BRIDGE
To .
CSJ 1178-01-026
Proj ID BR 2007(290)
Work Type REPLACE BRIDGE
 
0.104 391234.00 58750.00 58750.00 15.0
Work Order 05-29-14
Work Began 06-25-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 6
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1178-01-026
BICK"S CONSTRUCTION, INC.( 22.02%)
FORTSON CONTRACTING, INC.(3.43%)
TRP CONSTRUCTION GROUP, LLC(0.00%)
Contract # 04143015
Totals 391234.00 58750.00 58750.00 15.0

CountyWISE
Highway FM 920
From TRINITY RIVER
To 3.174 MI N OF SH 199
CSJ 1179-01-039
Proj ID STP 2013(900)
Work Type GR, BS AND PAVEMENT
 
12.795 5559330.74 483065.47 2569543.32 46.2
Work Order 11-14-13
Work Began 02-14-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 54
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1179-01-039
FORTSON CONTRACTING, INC.(0.88%)
NORTHEASTERN PAVERS, INC.( 15.58%)
CROSSROADS, L.P. (0.97%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.82%)
STRIPING TECHNOLOGY, L.P.(2.57%)
BRENDA PRICE TRUCKING(0.00%)
J.V. CONCRETE CONSTRUCTION ( 12.23%)
Contract # 08133251
Totals 5559330.74 483065.47 2569543.32 46.2

CountyJOHNSON
Highway FM 917
From SH 171 IN GODLEY
To SH 174 IN JOSHUA
CSJ 1181-02-035
Proj ID STP 2014(394)
Work Type HMAC OVERLAY
 
8.950 2080434.45 0.00 0.00 0.0
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 04-27-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1181-02-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143214
Totals 2080434.45 0.00 0.00 0.0

CountyJOHNSON
Highway FM 2738
From FM-2738 IN LILIAN
To FM-917
CSJ 1181-04-043
Proj ID STP 2014(940)
Work Type SEAL COAT AND OVERLAY
 
0.761 186503.99 0.00 0.00 0.0
CountyJOHNSON
Highway FM 2738
From TARRANT COUNTY LINE
To FM-2738 IN LILLIAN
CSJ 3010-02-013
Proj ID STP 2014(940)
Work Type SEAL COAT AND OVERLAY
 
4.435 1570885.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3010-02-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143249
Totals 1757389.21 0.00 0.00 0.0

CountyJACK
Highway FM 1156
From FM 1156 OVER BEANS CREEK
To .
CSJ 1309-01-029
Proj ID BR 2014(771)
Work Type REPL BRIDGE AND APPROACHES
 
0.174 930482.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1309-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143022
Totals 930482.24 0.00 0.00 0.0

CountyTARRANT
Highway FM 1187
From NEWT PATTERSON
To BU 287P
CSJ 1330-02-034
Proj ID STP 2010(399)ES
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
1.503 6895052.12 99360.84 12446447.89 99.9
Work Order 05-05-10
Work Began 06-17-11
Work Completed  
Time Computed 11-01-10
Contract Working Days 427
Addl Days Granted 325
Working Days Charged 706
Percent Time Used 93
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-034
UNDERGROUND COALITION, INC.(2.92%)
INLET STRUCTURE SPECIALTIES LTD. (2.88%)
DURABLE SPECIALTIES, INC.(2.04%)
BANDA TRUCKING COMPANY (0.10%)
STORM WATER MANAGEMENT, INC. (0.31%)
INDUS CONSTRUCTION, L.P. (8.05%)
AUSTIN BRIDGE & ROAD, LP ( 17.43%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.34%)
DUSTROL, INC.(0.53%)
JM MATERIALS, INC. (0.32%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.83%)
Contract # 03103004
Totals 6895052.12 99360.84 12446447.89 99.9

CountyJACK
Highway FM 1191
From US 380
To YOUNG COUNTY LINE
CSJ 1333-03-018
Proj ID STP 2014(664)HRR
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
6.980 5404940.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 00-00-00
Work Completed  
Time Computed 07-04-14
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1333-03-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143217
Totals 5404940.22 0.00 0.00 0.0

CountyHOOD
Highway FM 167
From FM-51
To FM-3450
CSJ 1598-01-020
Proj ID STP 2014(976)
Work Type GR, BS, DR STRUCTURE & HMAC PAVEMENT
 
2.928 2079661.57 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1598-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143056
Totals 2079661.57 0.00 0.00 0.0

CountyPARKER
Highway FM 1884
From B.B. FIELDER ROAD
To TO END OF FM 1884
CSJ 1601-02-023
Proj ID STP 2012(685)
Work Type GR, DRAINAGE, STRUCTURES, & PAVEMEN
 
6.305 6349600.35 109753.14 6301648.34 99.2
Work Order 11-01-12
Work Began 01-21-13
Work Completed  
Time Computed 11-17-12
Contract Working Days 299
Addl Days Granted 15
Working Days Charged 300
Percent Time Used 95
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1601-02-023
COWTOWN TRAFFIC CONTROL, INC.(0.23%)
DUSTROL, INC.(0.30%)
FORTSON CONTRACTING, INC.(1.36%)
MCL CONTRACTING, LLC (0.11%)
NORTHEASTERN PAVERS, INC.( 36.29%)
SCOTT DERR PAINTING CO (0.04%)
STRIPING TECHNOLOGY, L.P.(0.90%)
SOUTHEAST GRINDING & GROOVING, LLC (0.04%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33%)
TEXAS SHAFTS, INC. (0.78%)
USA EROSION, INC.(1.18%)
INLET STRUCTURE SPECIALTIES LTD. (3.54%)
BRENDA PRICE TRUCKING(1.23%)
Contract # 08123234
Totals 6349600.35 109753.14 6301648.34 99.2

CountyTARRANT
Highway FM 1709
From UP RAILROAD, WEST OF US 377
To ELM STREET; IN KELLER
CSJ 1603-03-033
Proj ID CM 2011(928)
Work Type GR, DR, STRUCT AND PAVEMENT
 
0.226 879231.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143210
Totals 879231.70 0.00 0.00 0.0

CountyTARRANT
Highway FM 1709
From PEARSON LANE; WEST CITY LIMITS
To SH 114; EAST CITY LIMITS
CSJ 1603-03-034
Proj ID STP 2011(228)TE
Work Type GRADING, DRAINAGE, INSTALL SIDEWALKS
 
6.100 1320757.45 2121.00 1446798.88 99.9
Work Order 12-03-12
Work Began 01-28-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 149
Addl Days Granted 46
Working Days Charged 198
Percent Time Used 101
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-034
ENVIRONMENTAL STANDARDS, INC.(3.97%)
CONCRETE PAVER SYSTEMS, INC. (0.26%)
CROSSROADS, L.P. (0.71%)
HIGHWAY TECHNOLOGIES, INC. (0.52%)
MIKE ALBERT, INC.( 34.12%)
WOODLAKE OUTDOOR, INC. (2.37%)
BUYERS BARRICADES, INC.(0.28%)
BUZZ SERVICES, L.L.C.(3.76%)
Contract # 11123021
Totals 1320757.45 2121.00 1446798.88 99.9

CountyPARKER
Highway FM 1886
From FM 730
To TARRANT COUNTY LINE
CSJ 1605-01-014
Proj ID STP 2014(478)
Work Type GR.BS, DR, STRUC AND PAVEMENT
 
5.748 4834822.79 17961.20 17961.20 0.3
Work Order 05-07-14
Work Began 06-12-14
Work Completed  
Time Computed 05-23-14
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 3
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1605-01-014
RAMBO CONTRACTING, INC.(4.85%)
BICK"S CONSTRUCTION, INC.( 16.34%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.93%)
MARCOM"S MOWING SERVICE, LLC (0.53%)
WEST TEXAS RUMBLE STRIP(0.08%)
AAA DRILLING FOUNDATION CO., INC.(0.36%)
LIRA ELECTRIC(1.57%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.81%)
Contract # 03143221
Totals 4834822.79 17961.20 17961.20 0.3

CountyWISE
Highway FM 2123
From AT SALT CREEK
To AND AT COTTONWOOD CREEK
CSJ 1606-02-013
Proj ID BR 1102(297)
Work Type REPL BRIDGES
 
0.099 1968338.24 0.00 1872436.82 99.9
Work Order 09-14-11
Work Began 12-08-11
Work Completed  
Time Computed 09-30-11
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 253
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-013
COWTOWN TRAFFIC CONTROL, INC.(0.36%)
BROCK ENVIRONMENTAL, LLC (0.39%)
DUSTIN ALLEN, INC. (1.70%)
GORRONDONA & ASSOCIATES, INC.(0.50%)
HIGHWAY TECHNOLOGIES, INC. (1.28%)
RG PAINTING(0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
PRIMATE CONSTRUCTION, INC. (0.54%)
TEX OP CONSTRUCTION, LP(0.78%)
PEACHTREE CONSTRUCTION, LTD. (8.23%)
EW WELLS GROUP LLC (2.13%)
W. W. FOUNDATION DRILLING, LTD.(8.30%)
J.L. STEEL REINFORCING, LLC(0.33%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.95%)
JUST GROOVING, LTD.(0.29%)
JTM MATERIALS, INC.(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
KYLE ERWIN CONSTRUCTION, LLC (0.13%)
Contract # 08113260
Totals 1968338.24 0.00 1872436.82 99.9

page 1 | page 2 | page 3 | page 4 | page 5