Monthly State Let Maintenance Report For Houston District As Of May 10, 2023 Page 1 Of 6

Last Update: Wednesday, May 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
Highway0000000
From6810 OLD KATY ROAD, HOUTSON, TX. 77024
To6810 OLD KATY ROAD, HOUTSON, TX. 77024
CSJ4704-01-333
Proj IDCBC - 470401327
Work TypeADDITION TO FACILITY
 
0.0011353000.001295133.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-14
Work Began07-18-14
Work Completed
Time Computed07-18-14
Contract Working Days240
Addl Days Granted12
Working Days Charged252
Percent Time Used100
Contractor(s)
CONSTRUCTION LTD
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-333
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05144036
Totals1353000.000.001295133.1099.9

CountyGALVESTON
HighwaySH0087
FromGALVESTON FERRY LANDING
ToBOLIVAR FERRY LANDING
CSJ6195-11-001
Proj IDEMC - 619511001
Work TypeEMERGENCY DOLPHIN REPAIRS
 
1.0002872775.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6195-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06091240
Totals2872775.000.000.000.0

CountyBRAZORIA
HighwaySH0288
FromAT CR 220
To.
CSJ6319-73-001
Proj IDRMC - 631973001
Work TypeREHABILITATION OF EXISTING ROADWAY
 
779725.88834000.1199.9
Work Order00-00-00
Work Began07-12-22
Work Completed
Time Computed07-12-22
Contract Working Days38
Addl Days Granted6
Working Days Charged41
Percent Time Used93
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214015
Totals779725.880.00834000.1199.9

CountyHARRIS
HighwayIH0069
FromDUNLAVY ST
ToMANDELL ST
CSJ6327-98-001
Proj IDRMC - 632798001
Work TypeROUTINE MAINTENANCE PROJECT - SEALED
 
323749.50574413.8299.9
Work Order00-00-00
Work Began05-03-21
Work Completed
Time Computed05-03-21
Contract Working Days78
Addl Days Granted219
Working Days Charged297
Percent Time Used100
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6327-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01214016
Totals323749.500.00574413.8299.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HIGHWAYS IN BRAZORIA COUNTY
To.
CSJ6330-29-001
Proj IDRMC - 633029001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.010925700.00540502.1658.3
Work Order00-00-00
Work Began10-16-22
Work Completed
Time Computed10-16-22
Contract Working Days730
Addl Days Granted0
Working Days Charged192
Percent Time Used26
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224001
Totals925700.000.00540502.1658.3

CountyHARRIS
HighwayIH0010
FromVARIOUS COUNTIES IN THE HOUSTON DISTRICT
ToVARIOUS COUNTIES IN THE HOUSTON DISTRICT
CSJ6332-52-001
Proj IDRMC - 633252001
Work TypeREPLACE AND REFURBISH LARGE/OVH SIGNS
 
0.0011820450.172370905.57100.0
Work Order00-00-00
Work Began07-15-19
Work Completed04-25-23
Time Computed08-12-19
Contract Working Days360
Addl Days Granted45
Working Days Charged349
Percent Time Used86
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6332-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194215
Totals1820450.170.002370905.57100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6345-96-001
Proj IDRMC - 634596001
Work TypeGUARDRAIL REPAIR
 
0.0011994275.001053588.62100.0
Work Order00-00-00
Work Began10-26-19
Work Completed10-26-21
Time Computed10-28-19
Contract Working Days730
Addl Days Granted0
Working Days Charged701
Percent Time Used96
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6345-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08194206
Totals1994275.0033495.001053588.62100.0

CountyGALVESTON
HighwaySH0087
FromGALVESTON LANDING
ToBOLIVAR LANDING
CSJ6349-05-001
Proj IDRMC - 634905001
Work TypeLANDING MAINTENANCE
 
0.01016023070.0010650310.8566.4
Work Order00-00-00
Work Began09-08-20
Work Completed
Time Computed09-08-20
Contract Working Days450
Addl Days Granted365
Working Days Charged634
Percent Time Used77
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06204206
Totals16023070.00130498.9010650310.8566.4

CountyHARRIS
HighwayIH0010
FromIH 10 SAN JACINTO RIVER BRIDGE
ToIH 10 SAN JACINTO RIVER BRIDGE
CSJ6363-67-001
Proj IDRMC - 636367001
Work TypeFENDER SYSTEM CONSTRUCTION
 
0.00112567752.004165301.9133.1
Work Order00-00-00
Work Began12-12-22
Work Completed
Time Computed01-18-21
Contract Working Days512
Addl Days Granted0
Working Days Charged195
Percent Time Used38
Contractor(s)
BO-MAC CONTRACTORS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6363-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08204209
Totals12567752.00268904.904165301.9133.1

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6369-74-001
Proj IDRMC - 636974001
Work TypeBRIDGE REPAIR
 
1085109.50982620.1090.5
Work Order00-00-00
Work Began06-22-21
Work Completed
Time Computed06-22-21
Contract Working Days730
Addl Days Granted0
Working Days Charged673
Percent Time Used92
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6369-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04214209
Totals1085109.500.00982620.1090.5

CountyHARRIS
HighwayIH0610
FromVARIOUS AREAS IN METRO HOU AREA
ToVARIOUS AREAS IN METRO HOU AREA
CSJ6370-10-001
Proj IDRMC - 637010001
Work TypePAVEMENT MARKINGS
 
659051.00257675.3939.0
Work Order00-00-00
Work Began04-01-22
Work Completed
Time Computed04-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6370-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224014
Totals659051.000.00257675.3939.0

CountyHARRIS
HighwayIH0045
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6374-04-001
Proj IDRMC - 637404001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
1985138.001841175.7592.7
Work Order10-26-21
Work Began10-26-21
Work Completed
Time Computed10-26-21
Contract Working Days730
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6374-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09214017
Totals1985138.0080079.751841175.7592.7

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6374-23-001
Proj IDRMC - 637423001
Work TypeMOWING HIGHWAY RIGHT OF WAY_PROJECT
 
0.100420840.78255008.4560.5
Work Order00-00-00
Work Began11-01-21
Work Completed
Time Computed11-01-21
Contract Working Days190
Addl Days Granted0
Working Days Charged102
Percent Time Used53
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214211
Totals420840.780.00255008.4560.5

CountyHARRIS
HighwayIH0045
FromSH 87
ToSOUTHERN STREET
CSJ6375-52-001
Proj IDRMC - 637552001
Work TypeTOTAL MAINTENANCE
 
0.0104981840.175467799.9099.9
Work Order00-00-00
Work Began07-11-21
Work Completed
Time Computed07-11-21
Contract Working Days730
Addl Days Granted0
Working Days Charged654
Percent Time Used89
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6375-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05214013
Totals4981840.1748785.505467799.9099.9

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON METRO AREA
ToVARIOUS HWYS IN HOUSTON METRO AREA
CSJ6376-28-001
Proj IDRMC - 637628001
Work TypeTOTAL MAINTENANCE
 
0.01013849066.5513585902.78100.0
Work Order00-00-00
Work Began09-01-21
Work Completed01-30-23
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214212
Totals13849066.550.0013585902.78100.0

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6376-63-001
Proj IDRMC - 637663001
Work TypeREFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.010359157.30249078.9969.3
Work Order11-01-21
Work Began11-01-21
Work Completed
Time Computed11-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged541
Percent Time Used74
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6376-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214213
Totals359157.3012708.33249078.9969.3

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6379-57-001
Proj IDRMC - 637957001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101548871.001458053.8494.1
Work Order00-00-00
Work Began10-25-21
Work Completed
Time Computed10-25-21
Contract Working Days730
Addl Days Granted0
Working Days Charged517
Percent Time Used70
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6379-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214206
Totals1548871.00119849.501458053.8494.1

CountyHARRIS
HighwayIH0069
FromIH 69
To.1 MI N FM 525 TO MONTG CO. LINE ETC.
CSJ6379-66-001
Proj IDRMC - 637966001
Work TypeREFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.010379767.00348365.68100.0
Work Order00-00-00
Work Began10-26-21
Work Completed10-25-22
Time Computed10-26-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214009
Totals379767.0031022.27348365.68100.0

CountyHARRIS
HighwaySH0249
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6379-97-001
Proj IDRMC - 637997001
Work TypeBRIDGE JOINT CLEANING AND SEALING
 
0.010828900.001015850.2499.9
Work Order00-00-00
Work Began08-29-22
Work Completed
Time Computed08-29-22
Contract Working Days80
Addl Days Granted0
Working Days Charged61
Percent Time Used76
Contractor(s)
STRUCTURAL INTEGRITY GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224212
Totals828900.0035977.291015850.2499.9

CountyHARRIS
HighwayIH0610
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6380-30-001
Proj IDRMC - 638030001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.0101627457.001377864.3684.6
Work Order00-00-00
Work Began12-06-21
Work Completed
Time Computed12-06-21
Contract Working Days730
Addl Days Granted0
Working Days Charged506
Percent Time Used69
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6380-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09214018
Totals1627457.0091019.701377864.3684.6