Monthly State Let Maintenance Report For Houston District As Of Mar 10, 2023 Page 3 Of 6

Last Update: Friday, March 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFORT BEND
HighwayUS0059
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6386-93-001
Proj IDRMC - 638693001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010462800.00217035.8046.8
Work Order00-00-00
Work Began03-07-22
Work Completed
Time Computed03-07-22
Contract Working Days730
Addl Days Granted0
Working Days Charged357
Percent Time Used48
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6386-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214013
Totals462800.000.00217035.8046.8

CountyFORT BEND
HighwayUS0059
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6386-94-001
Proj IDRMC - 638694001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010989468.00449931.2045.4
Work Order00-00-00
Work Began02-07-22
Work Completed
Time Computed02-04-22
Contract Working Days730
Addl Days Granted0
Working Days Charged389
Percent Time Used53
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6386-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214208
Totals989468.0062400.00449931.2045.4

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6388-06-001
Proj IDRMC - 638806001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010280998.9615575.745.5
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed02-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged27
Percent Time Used7
Contractor(s)
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6388-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224001
Totals280998.9615575.7415575.745.5

CountyHARRIS
HighwayIH0069
FromSL 8 AT HARDY
ToIH 610
CSJ6388-20-001
Proj IDRMC - 638820001
Work TypePAVEMENT MARKINGS
 
0.010518394.95558595.7599.9
Work Order00-00-00
Work Began07-14-22
Work Completed
Time Computed06-13-22
Contract Working Days60
Addl Days Granted0
Working Days Charged81
Percent Time Used135
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6388-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224009
Totals518394.9514105.50558595.7599.9

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6388-48-001
Proj IDRMC - 638848001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0101264800.00813530.0064.3
Work Order04-01-22
Work Began04-01-22
Work Completed
Time Computed04-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged333
Percent Time Used91
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6388-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214014
Totals1264800.0062400.00813530.0064.3

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6388-49-001
Proj IDRMC - 638849001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010536653.00271780.0050.6
Work Order07-01-22
Work Began07-01-22
Work Completed
Time Computed07-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6388-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224218
Totals536653.0042524.00271780.0050.6

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6388-70-001
Proj IDRMC - 638870001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.0101141643.00834189.0073.0
Work Order03-21-22
Work Began03-28-22
Work Completed
Time Computed03-28-22
Contract Working Days730
Addl Days Granted0
Working Days Charged336
Percent Time Used46
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6388-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224013
Totals1141643.0090782.00834189.0073.0

CountyMONTGOMERY
HighwayIH0069
FromI 69
ToFM 1314
CSJ6388-71-001
Proj IDRMC - 638871001
Work TypePAVEMENT MARKINGS
 
0.010738929.67240434.7232.5
Work Order09-19-22
Work Began09-19-22
Work Completed
Time Computed09-19-22
Contract Working Days180
Addl Days Granted0
Working Days Charged87
Percent Time Used48
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6388-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224011
Totals738929.67147074.74240434.7232.5

CountyFORT BEND
HighwayUS0059
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6388-88-001
Proj IDRMC - 638888001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010364440.00227175.4862.3
Work Order00-00-00
Work Began04-18-22
Work Completed
Time Computed04-18-22
Contract Working Days365
Addl Days Granted0
Working Days Charged315
Percent Time Used86
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6388-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224211
Totals364440.000.00227175.4862.3

CountyHARRIS
HighwayIH0069
FromFM 1960 LIBERTY CL
ToLEE RD. ETC.
CSJ6389-28-001
Proj IDRMC - 638928001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010718629.63430043.6559.8
Work Order00-00-00
Work Began03-28-22
Work Completed
Time Computed03-28-22
Contract Working Days730
Addl Days Granted0
Working Days Charged335
Percent Time Used45
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6389-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224212
Totals718629.630.00430043.6559.8

CountyWALLER
HighwayUS0290
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6389-42-001
Proj IDRMC - 638942001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010347440.00130036.0037.4
Work Order00-00-00
Work Began07-06-22
Work Completed
Time Computed07-06-22
Contract Working Days730
Addl Days Granted0
Working Days Charged237
Percent Time Used32
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6389-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224219
Totals347440.0021823.00130036.0037.4

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6389-50-001
Proj IDRMC - 638950001
Work TypePAVEMENT MARKINGS
 
0.010906749.60244795.7026.9
Work Order00-00-00
Work Began05-02-22
Work Completed
Time Computed05-02-22
Contract Working Days730
Addl Days Granted0
Working Days Charged300
Percent Time Used41
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6389-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224213
Totals906749.6047177.01244795.7026.9

CountyGALVESTON
HighwayFM0517
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6389-52-001
Proj IDRMC - 638952001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.0101676952.98859252.96100.0
Work Order00-00-00
Work Began04-01-22
Work Completed01-23-23
Time Computed04-01-22
Contract Working Days120
Addl Days Granted23
Working Days Charged131
Percent Time Used91
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6389-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224012
Totals1676952.980.00859252.96100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6389-98-001
Proj IDRMC - 638998001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101728375.001526468.3788.3
Work Order00-00-00
Work Began02-02-22
Work Completed
Time Computed02-02-22
Contract Working Days730
Addl Days Granted0
Working Days Charged389
Percent Time Used53
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6389-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214210
Totals1728375.00126016.851526468.3788.3

CountyBRAZORIA
HighwaySH0288
FromWITHIN BRAZORIA COUNTY
To.
CSJ6390-02-001
Proj IDRMC - 639002001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010834618.000.000.0
Work Order00-00-00
Work Began03-21-22
Work Completed
Time Computed03-21-22
Contract Working Days730
Addl Days Granted0
Working Days Charged342
Percent Time Used46
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6390-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214207
Totals834618.000.000.000.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6390-22-001
Proj IDRMC - 639022001
Work TypeASPHALT PAVEMENT REPAIR
 
0.010680800.00641330.7194.2
Work Order00-00-00
Work Began03-13-22
Work Completed
Time Computed03-13-22
Contract Working Days730
Addl Days Granted0
Working Days Charged351
Percent Time Used48
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6390-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214209
Totals680800.0025940.00641330.7194.2

CountyHARRIS
HighwayIH0010
FromVARIOUS LOCATIONS IN WEST HARRIS COUNTY
ToVARIOUS LOCATIONS IN WEST HARRIS COUNTY
CSJ6391-46-001
Proj IDRMC - 639146001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010464936.79331011.6371.1
Work Order00-00-00
Work Began06-13-22
Work Completed
Time Computed06-13-22
Contract Working Days120
Addl Days Granted0
Working Days Charged68
Percent Time Used56
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224211
Totals464936.7983911.57331011.6371.1

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6391-50-001
Proj IDRMC - 639150001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010797727.44134684.7616.8
Work Order12-01-22
Work Began12-01-22
Work Completed
Time Computed12-01-22
Contract Working Days486
Addl Days Granted0
Working Days Charged89
Percent Time Used18
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224015
Totals797727.4492428.87134684.7616.8

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6391-51-001
Proj IDRMC - 639151001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.0101075694.54278728.7525.9
Work Order06-06-22
Work Began06-06-22
Work Completed
Time Computed06-06-22
Contract Working Days264
Addl Days Granted0
Working Days Charged57
Percent Time Used21
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224218
Totals1075694.540.00278728.7525.9

CountyHARRIS
HighwaySH0099
FromFT BEND CL IH 10 TO SH 249
ToSH 249 TO IH 69 (N)
CSJ6391-55-001
Proj IDRMC - 639155001
Work TypeBUNDLED BID
 
0.0109152121.623042808.9533.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-20-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged221
Percent Time Used30
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224015
Totals9152121.62571528.233042808.9533.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6