Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HARRIS |
Highway | IH0610 |
From | VARIOUS HWYS IN HOUSTON METRO AREA |
To | VARIOUS HWYS IN HOUSTON METRO AREA |
CSJ | 6430-57-001 |
Proj ID | RMC - 643057001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 2617739.76 | | 3290039.73 | 99.9 |
Work Order | 00-00-00 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 09-01-23 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 366 |
Percent Time Used | 100 |
Contractor(s) |
SWEEPING CORPORATION OF AMERICA, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6430-57-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234207 |
| Totals | 2617739.76 | 0.00 | 3290039.73 | 99.9 |
|
County | GALVESTON |
Highway | FM0518 |
From | VARIOUS HWYS IN GALVESTON COUNTY |
To | VARIOUS HWYS IN GALVESTON COUNTY |
CSJ | 6430-61-001 |
Proj ID | RMC - 643061001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 853913.00 | | 594995.08 | 69.6 |
Work Order | 00-00-00 |
Work Began | 09-28-23 |
Work Completed | |
Time Computed | 07-01-23 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 483 |
Percent Time Used | 66 |
Contractor(s) |
MB WESTERN INDUSTRIAL CONTRACTING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 6430-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234210 |
| Totals | 853913.00 | 0.00 | 594995.08 | 69.6 |
|
County | HARRIS |
Highway | SL0008 |
From | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
To | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
CSJ | 6430-71-001 |
Proj ID | RMC - 643071001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 2738450.00 | | 2482788.64 | 90.6 |
Work Order | 00-00-00 |
Work Began | 07-20-23 |
Work Completed | |
Time Computed | 06-26-23 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 488 |
Percent Time Used | 66 |
Contractor(s) |
FORDE CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6430-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234011 |
| Totals | 2738450.00 | 401253.35 | 2482788.64 | 90.6 |
|
County | BRAZORIA |
Highway | SH0288 |
From | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
To | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
CSJ | 6431-64-001 |
Proj ID | RMC - 643164001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 1197381.23 | | 590061.83 | 49.2 |
Work Order | 00-00-00 |
Work Began | 10-09-23 |
Work Completed | |
Time Computed | 10-09-23 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 353 |
Percent Time Used | 48 |
Contractor(s) |
SWEEPING CORPORATION OF AMERICA, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6431-64-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234615 |
| Totals | 1197381.23 | 9014.32 | 590061.83 | 49.2 |
|
County | GALVESTON |
Highway | SH0146 |
From | VARIOUS HWYS IN GALVESTON COUNTY |
To | VARIOUS HWYS IN GALVESTON COUNTY |
CSJ | 6432-02-001 |
Proj ID | RMC - 643202001 |
Work Type | REFLECTIVE PAVEMENT MARKINGS (GRAPHICS) |
|
| 0.010 | 697655.71 | | 535459.54 | 76.7 |
Work Order | 00-00-00 |
Work Began | 10-16-23 |
Work Completed | |
Time Computed | 12-01-23 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 452 |
Percent Time Used | 61 |
Contractor(s) |
TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6432-02-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05234017 |
| Totals | 697655.71 | 51897.85 | 535459.54 | 76.7 |
|
County | WALLER |
Highway | US0290 |
From | VARIOUS ROADWAYS IN WALLER COUNTY |
To | VARIOUS ROADWAYS IN WALLER COUNTY |
CSJ | 6432-82-001 |
Proj ID | RMC - 643282001 |
Work Type | BRIDGE DECK REPAIR |
|
| 0.010 | 739900.00 | | 945312.61 | 99.9 |
Work Order | 00-00-00 |
Work Began | 11-06-23 |
Work Completed | |
Time Computed | 08-01-23 |
Contract Working Days | 365 |
Addl Days Granted | 60 |
Working Days Charged | 428 |
Percent Time Used | 100 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6432-82-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05234018 |
| Totals | 739900.00 | 128850.01 | 945312.61 | 99.9 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6433-48-001 |
Proj ID | RMC - 643348001 |
Work Type | REFLECTIVE PAVEMENT MARKINGS (GRAPHICS) |
|
| 0.010 | 1835234.00 | | 1093357.97 | 59.5 |
Work Order | 10-13-23 |
Work Began | 11-01-23 |
Work Completed | |
Time Computed | 11-01-23 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 360 |
Percent Time Used | 49 |
Contractor(s) |
TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6433-48-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05234020 |
| Totals | 1835234.00 | 16589.48 | 1093357.97 | 59.5 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS BRIDGES IN MONTGOMERY COUNTY |
To | VARIOUS BRIDGES IN MONTGOMERY COUNTY |
CSJ | 6434-72-001 |
Proj ID | RMC - 643472001 |
Work Type | BRIDGE REPAIR |
|
| 0.010 | 1794500.00 | | 1530233.58 | 85.2 |
Work Order | 01-01-24 |
Work Began | 01-01-24 |
Work Completed | |
Time Computed | 01-01-24 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 299 |
Percent Time Used | 40 |
Contractor(s) |
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6434-72-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10234018 |
| Totals | 1794500.00 | 202210.75 | 1530233.58 | 85.2 |
|
County | FORT BEND |
Highway | US0059 |
From | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
To | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
CSJ | 6435-54-001 |
Proj ID | RMC - 643554001 |
Work Type | CONCRETE STRUCTURE REPAIR |
|
| 0.010 | 628825.00 | | 451032.23 | 71.7 |
Work Order | 00-00-00 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 09-01-23 |
Contract Working Days | 366 |
Addl Days Granted | 365 |
Working Days Charged | 421 |
Percent Time Used | 57 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6435-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234030 |
| Totals | 628825.00 | 0.00 | 451032.23 | 71.7 |
|
County | BRAZORIA |
Highway | SH0288 |
From | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
To | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
CSJ | 6435-66-001 |
Proj ID | RMC - 643566001 |
Work Type | CONCRETE SPALL REPAIR |
|
| 0.010 | 1467925.30 | | 104575.00 | 7.1 |
Work Order | 00-00-00 |
Work Began | 06-13-24 |
Work Completed | |
Time Computed | 06-13-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 105 |
Percent Time Used | 28 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6435-66-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244210 |
| Totals | 1467925.30 | 0.00 | 104575.00 | 7.1 |
|
County | BRAZORIA |
Highway | SH0288 |
From | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
To | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
CSJ | 6435-93-001 |
Proj ID | RMC - 643593001 |
Work Type | PUMP STATION & DRAINAGE SYSTEM CLEANING |
|
| 0.010 | 260750.00 | | 285648.25 | 99.9 |
Work Order | 00-00-00 |
Work Began | 08-14-23 |
Work Completed | |
Time Computed | 08-14-23 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 439 |
Percent Time Used | 60 |
Contractor(s) |
AIMS COMPANIES |
SUBCONTRACTOR(S) FOR CCSJ: 6435-93-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234032 |
| Totals | 260750.00 | 12827.25 | 285648.25 | 99.9 |
|
County | HARRIS |
Highway | US0290 |
From | VARIOUS HIGHWAYS IN THE WEST HARRIS CO. |
To | VARIOUS HIGHWAYS IN THE WEST HARRIS CO. |
CSJ | 6436-03-001 |
Proj ID | RMC - 643603001 |
Work Type | BRIDGE JOINT CLEANING AND SEALING |
|
| 0.010 | 1468500.00 | | 2640439.63 | 99.9 |
Work Order | 00-00-00 |
Work Began | 11-20-23 |
Work Completed | |
Time Computed | 11-20-23 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 341 |
Percent Time Used | 46 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6436-03-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234020 |
| Totals | 1468500.00 | 614628.73 | 2640439.63 | 99.9 |
|
County | HARRIS |
Highway | SL0008 |
From | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
To | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
CSJ | 6436-64-001 |
Proj ID | RMC - 643664001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 1849109.00 | | 1836593.55 | 99.3 |
Work Order | 00-00-00 |
Work Began | 09-12-23 |
Work Completed | |
Time Computed | 09-01-23 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 421 |
Percent Time Used | 57 |
Contractor(s) |
ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6436-64-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234616 |
| Totals | 1849109.00 | 72686.50 | 1836593.55 | 99.3 |
|
County | HARRIS |
Highway | SH0249 |
From | SH249 ETC. VARIOUS ROADWAYS IN N. HARRIS |
To | SH249 ETC. VARIOUS ROADWAYS IN N. HARRIS |
CSJ | 6436-75-001 |
Proj ID | RMC - 643675001 |
Work Type | STORM SEWER SYSTEM CLEANING |
|
| 0.010 | 267562.50 | | 299166.80 | 99.9 |
Work Order | 00-00-00 |
Work Began | 10-01-23 |
Work Completed | |
Time Computed | 10-01-23 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 361 |
Percent Time Used | 98 |
Contractor(s) |
AIMS COMPANIES |
SUBCONTRACTOR(S) FOR CCSJ: 6436-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234421 |
| Totals | 267562.50 | 11283.60 | 299166.80 | 99.9 |
|
County | HARRIS |
Highway | IH0610 |
From | IH-610, ETC |
To | IH-610, ETC |
CSJ | 6437-04-001 |
Proj ID | RMC - 643704001 |
Work Type | BRIDGE REPAIR |
|
| 0.010 | 3560810.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6437-04-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08244001 |
| Totals | 3560810.00 | 0.00 | 0.00 | 0.0 |
|
County | MONTGOMERY |
Highway | SH0105 |
From | SL 336 |
To | IH 45 |
CSJ | 6438-76-001 |
Proj ID | RMC - 643876001 |
Work Type | ACP OVERLAY |
|
| 0.010 | 1704616.38 | | 1567884.67 | 100.0 |
Work Order | 03-01-24 |
Work Began | 03-01-24 |
Work Completed | 09-20-24 |
Time Computed | 03-01-24 |
Contract Working Days | 45 |
Addl Days Granted | 0 |
Working Days Charged | 44 |
Percent Time Used | 97 |
Contractor(s) |
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6438-76-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234033 |
| Totals | 1704616.38 | 0.00 | 1567884.67 | 100.0 |
|
County | HARRIS |
Highway | IH0069 |
From | IH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS |
To | IH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS |
CSJ | 6439-70-001 |
Proj ID | RMC - 643970001 |
Work Type | REFLECTIVE PAVEMENT MARKINGS (GRAPHICS) |
|
| 0.010 | 630506.11 | | 309798.93 | 49.1 |
Work Order | 00-00-00 |
Work Began | 10-16-23 |
Work Completed | |
Time Computed | 10-16-23 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 346 |
Percent Time Used | 94 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6439-70-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234221 |
| Totals | 630506.11 | 3734.87 | 309798.93 | 49.1 |
|
County | HARRIS |
Highway | US0290 |
From | VARIOUS LOCATIONS IN WEST HARRIS COUNTY |
To | VARIOUS LOCATION IN WEST HARRIS COUNTY |
CSJ | 6439-86-001 |
Proj ID | RMC - 643986001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 1979425.00 | | 2690516.66 | 99.9 |
Work Order | 00-00-00 |
Work Began | 10-02-23 |
Work Completed | |
Time Computed | 10-02-23 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 390 |
Percent Time Used | 53 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6439-86-001 STRUCTURAL INTEGRITY GROUP LLC (13.59)
|
Contract # | 08234028 |
| Totals | 1979425.00 | 0.00 | 2690516.66 | 99.9 |
|
County | HARRIS |
Highway | IH0610 |
From | VARIOUS HWYS IN HOUSTON DISTRICT |
To | VARIOUS HWYS IN HOUSTON DISTRICT |
CSJ | 6441-04-001 |
Proj ID | RMC - 644104001 |
Work Type | TRAFFIC SIGNAL MAINTENANCE |
|
| 0.010 | 1051548.00 | | 770857.00 | 73.3 |
Work Order | 09-27-23 |
Work Began | 09-27-23 |
Work Completed | |
Time Computed | 09-27-23 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 395 |
Percent Time Used | 54 |
Contractor(s) |
LINDSEY ELECTRIC, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6441-04-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234029 |
| Totals | 1051548.00 | 94074.00 | 770857.00 | 73.3 |
|
County | BRAZORIA |
Highway | SH0288 |
From | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
To | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
CSJ | 6441-51-001 |
Proj ID | RMC - 644151001 |
Work Type | REFLECTIVE PAVEMENT MARKINGS (GRAPHICS) |
|
| 0.010 | 1085306.16 | | 255801.48 | 23.5 |
Work Order | 00-00-00 |
Work Began | 07-03-24 |
Work Completed | |
Time Computed | 07-03-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 85 |
Percent Time Used | 23 |
Contractor(s) |
STRIPE LINES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6441-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05244011 |
| Totals | 1085306.16 | 81422.39 | 255801.48 | 23.5 |
|