Monthly State Let Maintenance Report For Houston District As Of Mar 10, 2023 Page 4 Of 6

Last Update: Friday, March 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH0069
FromIH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS
ToIH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS
CSJ6392-48-001
Proj IDRMC - 639248001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0102509840.00788391.0031.4
Work Order00-00-00
Work Began04-04-22
Work Completed
Time Computed04-04-22
Contract Working Days730
Addl Days Granted0
Working Days Charged328
Percent Time Used44
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6392-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224015
Totals2509840.00101320.00788391.0031.4

CountyGALVESTON
HighwayFM0517
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6392-96-001
Proj IDRMC - 639296001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010630870.00613321.1997.2
Work Order00-00-00
Work Began04-22-22
Work Completed
Time Computed04-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged330
Percent Time Used45
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6392-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224007
Totals630870.0072504.04613321.1997.2

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6392-97-001
Proj IDRMC - 639297001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010415170.00263656.5163.5
Work Order00-00-00
Work Began05-01-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged300
Percent Time Used82
Contractor(s)
S6 INTERSTATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6392-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224008
Totals415170.0061415.00263656.5163.5

CountyWALLER
HighwayUS0290
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6393-30-001
Proj IDRMC - 639330001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010527898.26274670.3352.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged269
Percent Time Used36
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224016
Totals527898.260.00274670.3352.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6393-43-001
Proj IDRMC - 639343001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101763985.001622154.9091.9
Work Order00-00-00
Work Began04-11-22
Work Completed
Time Computed04-11-22
Contract Working Days730
Addl Days Granted0
Working Days Charged322
Percent Time Used44
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224217
Totals1763985.00152364.501622154.9091.9

CountyHARRIS
HighwaySH0249
FromSH 249 ETC VARIOUS LOCATIONS
ToSH 249 ETC VARIOUS LOCATIONS
CSJ6393-51-001
Proj IDRMC - 639351001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.0101157658.96134986.2211.6
Work Order00-00-00
Work Began10-31-22
Work Completed
Time Computed10-31-22
Contract Working Days314
Addl Days Granted0
Working Days Charged8
Percent Time Used2
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224215
Totals1157658.960.00134986.2211.6

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6393-60-001
Proj IDRMC - 639360001
Work TypePUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.010345000.00379952.9099.9
Work Order00-00-00
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged269
Percent Time Used73
Contractor(s)
AIMS COMPANIES
SUBCONTRACTOR(S) FOR CCSJ: 6393-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224013
Totals345000.0053252.30379952.9099.9

CountyHARRIS
HighwaySH0249
FromSH 249 ETC VARIOUS LOCATIONS
ToSH 249 ETC VARIOUS LOCATIONS
CSJ6393-86-001
Proj IDRMC - 639386001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101743010.00596386.4734.2
Work Order00-00-00
Work Began04-15-22
Work Completed
Time Computed04-15-22
Contract Working Days730
Addl Days Granted0
Working Days Charged317
Percent Time Used43
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6393-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224216
Totals1743010.00121243.61596386.4734.2

CountyGALVESTON
HighwayFM1764
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6394-14-001
Proj IDRMC - 639414001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010821795.00429042.5052.2
Work Order00-00-00
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged269
Percent Time Used73
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6394-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224014
Totals821795.0081070.00429042.5052.2

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6394-16-001
Proj IDRMC - 639416001
Work TypeREFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.010417285.31311783.9074.7
Work Order00-00-00
Work Began05-01-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged299
Percent Time Used81
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6394-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224012
Totals417285.3120723.83311783.9074.7

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6395-26-001
Proj IDRMC - 639526001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101176491.00290173.0024.6
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged179
Percent Time Used24
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224010
Totals1176491.0053100.50290173.0024.6

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON METRO AREA
ToVARIOUS HWYS IN HOUSTON METRO AREA
CSJ6395-37-001
Proj IDRMC - 639537001
Work TypeTOTAL MAINTENANCE
 
0.0108390099.873745493.3244.6
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged178
Percent Time Used48
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224006
Totals8390099.87817183.963745493.3244.6

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN S BRAZORIA COUNTY
To.
CSJ6395-76-001
Proj IDRMC - 639576001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010744554.46361922.3448.6
Work Order00-00-00
Work Began06-06-22
Work Completed
Time Computed06-06-22
Contract Working Days232
Addl Days Granted0
Working Days Charged77
Percent Time Used33
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224216
Totals744554.4637624.15361922.3448.6

CountyHARRIS
HighwayIH0069
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6396-27-001
Proj IDRMC - 639627001
Work TypeBRIDGE JOINT CLEANING AND SEALING
 
0.0101081556.251342569.8699.9
Work Order00-00-00
Work Began05-26-22
Work Completed
Time Computed05-26-22
Contract Working Days100
Addl Days Granted0
Working Days Charged78
Percent Time Used78
Contractor(s)
STRUCTURAL INTEGRITY GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224213
Totals1081556.250.001342569.8699.9

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6396-50-001
Proj IDRMC - 639650001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0101719552.50453046.2326.3
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged178
Percent Time Used24
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224220
Totals1719552.5090835.83453046.2326.3

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6396-68-001
Proj IDRMC - 639668001
Work TypeBRIDGE DECK REPAIR
 
0.010821200.00617609.8575.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-03-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224017
Totals821200.00280938.70617609.8575.2

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON METRO AREA
ToVARIOUS HWYS IN HOUSTON METRO AREA
CSJ6397-21-001
Proj IDRMC - 639721001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0103396060.331727145.5850.8
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged178
Percent Time Used48
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6397-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224207
Totals3396060.33357201.411727145.5850.8

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN METRO HOUSTON AREA
ToVARIOUS HWYS IN METRO HOUSTON AREA
CSJ6397-62-001
Proj IDRMC - 639762001
Work TypeASPHALT PAVEMENT REPAIR
 
2633600.00249424.609.4
Work Order00-00-00
Work Began12-03-22
Work Completed
Time Computed12-03-22
Contract Working Days365
Addl Days Granted0
Working Days Charged85
Percent Time Used23
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6397-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224208
Totals2633600.000.00249424.609.4

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6398-68-001
Proj IDRMC - 639868001
Work TypeASPHALT PAVEMENT REPAIR
 
0.010523275.00523209.1299.9
Work Order00-00-00
Work Began10-10-22
Work Completed
Time Computed10-03-22
Contract Working Days365
Addl Days Granted0
Working Days Charged148
Percent Time Used40
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6398-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224007
Totals523275.0038201.00523209.1299.9

CountyFORT BEND
HighwayUS0059
FromVARIOUS HIGHWAYS IN FORT BEND COUNTY
ToVARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ6398-92-001
Proj IDRMC - 639892001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.010931200.00584777.4462.7
Work Order00-00-00
Work Began09-14-22
Work Completed
Time Computed09-14-22
Contract Working Days365
Addl Days Granted0
Working Days Charged166
Percent Time Used45
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224008
Totals931200.000.00584777.4462.7