Monthly State Let Maintenance Report For Houston District As Of Jun 10, 2024 Page 2 Of 8

Last Update: Monday, June 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6391-51-001
Proj IDRMC - 639151001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.0101075694.54539941.4050.1
Work Order06-06-22
Work Began06-06-22
Work Completed
Time Computed06-06-22
Contract Working Days264
Addl Days Granted0
Working Days Charged116
Percent Time Used43
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224218
Totals1075694.541.00539941.4050.1

CountyHARRIS
HighwaySH0099
FromFT BEND CL IH 10 TO SH 249
ToSH 249 TO IH 69 (N)
CSJ6391-55-001
Proj IDRMC - 639155001
Work TypeBUNDLED BID
 
0.0109152121.6214167974.4999.9
Work Order00-00-00
Work Began07-20-22
Work Completed
Time Computed07-20-22
Contract Working Days730
Addl Days Granted0
Working Days Charged676
Percent Time Used92
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224015
Totals9152121.62592715.0814167974.4999.9

CountyHARRIS
HighwayIH0069
FromIH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS
ToIH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS
CSJ6392-48-001
Proj IDRMC - 639248001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0102509840.002159956.7787.7
Work Order00-00-00
Work Began04-04-22
Work Completed
Time Computed04-04-22
Contract Working Days730
Addl Days Granted0
Working Days Charged783
Percent Time Used107
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6392-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224015
Totals2509840.0054570.752159956.7787.7

CountyWALLER
HighwayUS0290
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6393-30-001
Proj IDRMC - 639330001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010527898.26535021.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged728
Percent Time Used99
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224016
Totals527898.260.00535021.5099.9

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6393-43-001
Proj IDRMC - 639343001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101763985.004694555.1599.9
Work Order00-00-00
Work Began04-11-22
Work Completed
Time Computed04-11-22
Contract Working Days730
Addl Days Granted730
Working Days Charged776
Percent Time Used53
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224217
Totals1763985.00167245.204694555.1599.9

CountyHARRIS
HighwaySH0249
FromSH 249 ETC VARIOUS LOCATIONS
ToSH 249 ETC VARIOUS LOCATIONS
CSJ6393-51-001
Proj IDRMC - 639351001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.0101157658.96612221.6352.8
Work Order00-00-00
Work Began10-31-22
Work Completed
Time Computed10-31-22
Contract Working Days314
Addl Days Granted0
Working Days Charged85
Percent Time Used27
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224215
Totals1157658.9669457.80612221.6352.8

CountyHARRIS
HighwaySH0249
FromSH 249 ETC VARIOUS LOCATIONS
ToSH 249 ETC VARIOUS LOCATIONS
CSJ6393-86-001
Proj IDRMC - 639386001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101743010.002075423.7199.9
Work Order00-00-00
Work Began04-15-22
Work Completed
Time Computed04-15-22
Contract Working Days730
Addl Days Granted0
Working Days Charged711
Percent Time Used97
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6393-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224216
Totals1743010.0052534.722075423.7199.9

CountyGALVESTON
HighwayFM1764
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6394-14-001
Proj IDRMC - 639414001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010821795.001936627.26100.0
Work Order00-00-00
Work Began06-01-22
Work Completed05-10-24
Time Computed06-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged695
Percent Time Used95
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6394-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224014
Totals821795.00151868.001936627.26100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6395-26-001
Proj IDRMC - 639526001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101176491.001460930.9399.9
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted731
Working Days Charged633
Percent Time Used43
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224010
Totals1176491.0090820.001460930.9399.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN S BRAZORIA COUNTY
To.
CSJ6395-76-001
Proj IDRMC - 639576001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010744554.46757393.0699.9
Work Order00-00-00
Work Began06-06-22
Work Completed
Time Computed06-06-22
Contract Working Days232
Addl Days Granted232
Working Days Charged140
Percent Time Used30
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224216
Totals744554.460.00757393.0699.9

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6396-50-001
Proj IDRMC - 639650001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0101719552.501570388.7291.3
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged633
Percent Time Used86
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224220
Totals1719552.5069877.751570388.7291.3

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6396-68-001
Proj IDRMC - 639668001
Work TypeBRIDGE DECK REPAIR
 
0.010821200.00758079.2892.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-03-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224017
Totals821200.000.00758079.2892.3

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN METRO HOUSTON AREA
ToVARIOUS HWYS IN METRO HOUSTON AREA
CSJ6397-62-001
Proj IDRMC - 639762001
Work TypeASPHALT PAVEMENT REPAIR
 
2633600.004210150.1499.9
Work Order00-00-00
Work Began12-03-22
Work Completed
Time Computed12-03-22
Contract Working Days365
Addl Days Granted183
Working Days Charged505
Percent Time Used92
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6397-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224208
Totals2633600.000.004210150.1499.9

CountyFORT BEND
HighwayUS0059
FromVARIOUS HIGHWAYS IN FORT BEND COUNTY
ToVARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ6399-21-001
Proj IDRMC - 639921001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010406463.63606451.3899.9
Work Order00-00-00
Work Began08-08-22
Work Completed
Time Computed08-08-22
Contract Working Days185
Addl Days Granted0
Working Days Charged163
Percent Time Used88
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224009
Totals406463.636300.36606451.3899.9

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6399-26-001
Proj IDRMC - 639926001
Work TypeASPHALT PAVEMENT REPAIR
 
0.0101085050.001647650.1299.9
Work Order11-01-22
Work Began11-01-22
Work Completed
Time Computed11-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged574
Percent Time Used78
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224209
Totals1085050.000.001647650.1299.9

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6400-07-001
Proj IDRMC - 640007001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.010999743.95877997.8887.8
Work Order08-29-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged633
Percent Time Used86
Contractor(s)
SOUTHWEST SIGNAL SUPPLY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6400-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224210
Totals999743.9514700.53877997.8887.8

CountyHARRIS
HighwayIH0610
FromVARIOUS HIGHWAYS IN HOUSTON DISTRICT
ToVARIOUS HIGHWAYS IN HOUSTON DISTRICT
CSJ6400-67-001
Proj IDRMC - 640067001
Work TypeILLUMINATION MAINTENANCE
 
0.0102230105.002027040.2590.8
Work Order08-29-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged633
Percent Time Used86
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6400-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224608
Totals2230105.0076320.002027040.2590.8

CountyHARRIS
HighwayIH0610
FromMARKET ST
ToMCCARTY ST
CSJ6401-70-001
Proj IDRMC - 640170001
Work TypeROADSIGN ASSEMBLIES
 
0.010597485.50761163.4799.9
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed02-01-23
Contract Working Days40
Addl Days Granted0
Working Days Charged38
Percent Time Used95
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6401-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224011
Totals597485.500.00761163.4799.9

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY.
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY.
CSJ6403-24-001
Proj IDRMC - 640324001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.0101062525.001203409.4499.9
Work Order12-01-22
Work Began12-01-22
Work Completed
Time Computed12-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged544
Percent Time Used74
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6403-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224015
Totals1062525.00103543.241203409.4499.9

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6403-88-001
Proj IDRMC - 640388001
Work TypeDRAINAGE IMPROVEMENT AND/OR REPAIRS
 
0.010713974.001128402.0099.9
Work Order05-15-23
Work Began05-15-23
Work Completed
Time Computed05-15-23
Contract Working Days90
Addl Days Granted45
Working Days Charged87
Percent Time Used64
Contractor(s)
SHALOM SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6403-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234022
Totals713974.000.001128402.0099.9