Monthly State Let Maintenance Report For Houston District As Of Nov 10, 2024 Page 8 Of 8
Last Update: Sunday, November 10, 2024
 |
|
| Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
| County | HARRIS |
| Highway | IH0610 |
| From | VARIOUS HIGHWAYS IN HOUSTON METRO AREA |
| To | VARIOUS HIGHWAYS IN HOUSTON METRO AREA |
| CSJ | 6465-82-001 |
| Proj ID | RMC - 646582001 |
| Work Type | CONCRETE SPALL REPAIR |
| |
| 0.010 | 5629750.00 | | 247355.14 | 4.3 |
| Work Order | 00-00-00 |
| Work Began | 08-23-24 |
| Work Completed | |
| Time Computed | 08-23-24 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 34 |
| Percent Time Used | 9 |
| Contractor(s) |
| MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6465-82-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 07244208 |
| Totals | 5629750.00 | 142647.57 | 247355.14 | 4.3 |
|
| County | HARRIS |
| Highway | SL0008 |
| From | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
| To | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
| CSJ | 6466-59-001 |
| Proj ID | RMC - 646659001 |
| Work Type | TRAFFIC CONTROL SERVICES |
| |
| 0.010 | 1287900.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 10-28-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| REPUBLIC TRAFFIC SAFETY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6466-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08244011 |
| Totals | 1287900.00 | 0.00 | 0.00 | 0.0 |
|
| County | HARRIS |
| Highway | SH0099 |
| From | SH0099 |
| To | SH0099 |
| CSJ | 6467-71-001 |
| Proj ID | RMC - 646771001 |
| Work Type | BUNDLED BID |
| |
| 0.010 | 14959422.62 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6467-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08244210 |
| Totals | 14959422.62 | 0.00 | 0.00 | 0.0 |
|
| County | MONTGOMERY |
| Highway | IH0045 |
| From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
| To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
| CSJ | 6469-77-001 |
| Proj ID | RMC - 646977001 |
| Work Type | BRUSH REMOVAL |
| |
| 0.010 | 1000062.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 731 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| JACKSON EXCAVATION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6469-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 10244205 |
| Totals | 1000062.00 | 0.00 | 0.00 | 0.0 |
|
| County | MONTGOMERY |
| Highway | IH0045 |
| From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
| To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
| CSJ | 6469-78-001 |
| Proj ID | RMC - 646978001 |
| Work Type | DRAINAGE IMPROVEMENT AND/OR REPAIRS |
| |
| 0.010 | 1109686.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| JACKSON EXCAVATION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6469-78-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 10244002 |
| Totals | 1109686.00 | 0.00 | 0.00 | 0.0 |
|
| County | HARRIS |
| Highway | IH0010 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6472-95-001 |
| Proj ID | RMC - 647295001 |
| Work Type | DEBRIS REMOVAL |
| |
| 0.010 | 4984734.41 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| GLOBAL EMERGENCY SERVICES, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 6472-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 10244207 |
| Totals | 4984734.41 | 0.00 | 0.00 | 0.0 |
|