Detail Letting Schedule for Harrison County (FY 2001)
![]() |
![]() |
![]() |
![]() |
![]() |
Detail Letting Schedule for Harrison County (FY 2001) | ||||
Last Update: Friday, August 31, 2001 | ||||
Updated from Design & Construction Information System (DCIS) on: August 31, 2001 |
Harrison County (FY 2001) |
CCSJ: 0063-01-067 | |||
District: | Atlanta | Let Date: | MAY 2001 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2001(436)R | CSJ: | 0063-01-067 |
Description: | REHABILITATE EXISITING 6-LANE URBAN HIGHWAY | Handling Code: |
|
Limits From: | .2 MI NORTH OF SH 43 | Fund Cat: | 4F |
Limits To: | .1 MI SOUTH OF US 80 | Estimate: | $457,658 |
Length: | 1.1 Miles | Actual: | $469,056 |
Back... |
Totals for 0063-01-067 | ||
---|---|---|---|
Length: | 1.1 Miles | ||
Estimate: | $457,658 | ||
Actual: | $469,056 | ||
CCSJ: 0096-09-065 | |||
District: | Atlanta | Let Date: | JAN 2001 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | CPM 96-9-65 | CSJ: | 0096-09-065 |
Description: | RESURFACE EXISTING 2-LANE RURAL HIGHWAY | Handling Code: |
|
Limits From: | 0.2 MI E. OF LP 390 | Fund Cat: | 7 |
Limits To: | IH 20 | Estimate: | $1,477,598 |
Length: | 7.9 Miles | Actual: | $1,216,708 |
Back... |
Totals for 0096-09-065 | ||
Length: | 7.9 Miles | ||
Estimate: | $1,477,598 | ||
Actual: | $1,216,708 | ||
CCSJ: 0495-08-072 | |||
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | IM 20-7(56) | CSJ: | 0495-08-072 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | GREGG COUNTY LINE | Fund Cat: | 2 |
Limits To: | 0.5 MI. W. OF SH 43 | Estimate: | $305,631 |
Length: | 16.9 Miles | Actual: | $278,427 |
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | IM 20-7(56) | CSJ: | 0495-09-041 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | 0.5 MI. W. OF SH 43 | Fund Cat: | 2 |
Limits To: | E. END EIGHT MILE CREEK BRIDGE | Estimate: | $139,008 |
Length: | 6.9 Miles | Actual: | $103,742 |
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | IM 20-7(56) | CSJ: | 0495-10-065 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | E. END EIGHT MILE CREEK BRIDGE | Fund Cat: | 2 |
Limits To: | LOUISIANA STATE LINE | Estimate: | $317,191 |
Length: | 15.5 Miles | Actual: | $254,518 |
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | IM 30-3(110) | CSJ: | 0610-03-068 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | FRANKLIN COUNTY LINE | Fund Cat: | 2 |
Limits To: | MORRIS COUNTY LINE | Estimate: | $354,884 |
Length: | 23.5 Miles | Actual: | $276,079 |
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | IM 30-3(110) | CSJ: | 0610-04-028 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | TITUS COUNTY LINE | Fund Cat: | 2 |
Limits To: | BOWIE COUNTY LINE | Estimate: | $83,172 |
Length: | 7.3 Miles | Actual: | $63,452 |
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | IM 30-3(110) | CSJ: | 0610-05-041 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | MORRIS COUNTY LINE | Fund Cat: | 2 |
Limits To: | SH 98 | Estimate: | $177,856 |
Length: | 17.1 Miles | Actual: | $145,930 |
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | IM 30-3(110) | CSJ: | 0610-06-069 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | SH 98 | Fund Cat: | 2 |
Limits To: | 0.5 MI. W. OF SP 74 | Estimate: | $267,166 |
Length: | 13.7 Miles | Actual: | $203,175 |
District: | Atlanta | Let Date: | OCT 2000 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | IM 30-3(110) | CSJ: | 0610-07-076 |
Description: | REFURBISH LARGE AND SMALL SIGNS | Handling Code: |
|
Limits From: | 0.5 MI. W. OF SP 74 | Fund Cat: | 2 |
Limits To: | ARKANSAS STATE LINE | Estimate: | $421,765 |
Length: | 11.9 Miles | Actual: | $356,842 |
Back... |
Totals for 0495-08-072 | ||
Length: | 112.8 Miles | ||
Estimate: | $2,066,673 | ||
Actual: | $1,682,165 | ||
CCSJ: 0495-08-074 | |||
District: | Atlanta | Let Date: | FEB 2001 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | IM 20-7(57) | CSJ: | 0495-08-074 |
Description: | REHABILITATE INTERSTATE MAINLANES AND RAMPS | Handling Code: |
|
Limits From: | 0.5 MI W OF FM 3251 | Fund Cat: | 2 |
Limits To: | 0.5 MI W OF SH 43 | Estimate: | $3,037,079 |
Length: | 3.5 Miles | Actual: | $3,187,242 |
Back... |
Totals for 0495-08-074 | ||
Length: | 3.5 Miles | ||
Estimate: | $3,037,079 | ||
Actual: | $3,187,242 | ||
CCSJ: 0495-08-075 | |||
District: | Atlanta | Let Date: | SEP 2000 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | IM 20-7(55) | CSJ: | 0495-08-075 |
Description: | INSTALL CONCRETE TRAFFIC BARRIER AND CRASH CUSHIONS | Handling Code: |
|
Limits From: | GREGG COUNTY LINE | Fund Cat: | 2 |
Limits To: | 0.5 MI. W OF SH 43 | Estimate: | $864,719 |
Length: | 16.9 Miles | Actual: | $805,817 |
District: | Atlanta | Let Date: | SEP 2000 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | IM 20-7(55) | CSJ: | 0495-09-043 |
Description: | INSTALL CONCRETE TRAFFIC BARRIER AND CRASH CUSHIONS | Handling Code: |
|
Limits From: | 0.5 MI. W OF SH 43 | Fund Cat: | 2 |
Limits To: | E. END EIGHT MILE CREEK BRIDGE | Estimate: | $237,271 |
Length: | 6.8 Miles | Actual: | $173,230 |
District: | Atlanta | Let Date: | SEP 2000 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | IM 20-7(55) | CSJ: | 0495-10-067 |
Description: | INSTALL CONCRETE TRAFFIC BARRIER AND CRASH CUSHIONS | Handling Code: |
|
Limits From: | E. END EIGHT MILE CREEK BRIDGE | Fund Cat: | 2 |
Limits To: | LOUISIANA STATE LINE | Estimate: | $927,369 |
Length: | 15.4 Miles | Actual: | $727,668 |
Back... |
Totals for 0495-08-075 | ||
Length: | 39.1 Miles | ||
Estimate: | $2,029,359 | ||
Actual: | $1,706,715 | ||
CCSJ: 1575-02-025 | |||
District: | Atlanta | Let Date: | APR 2001 |
Highway: | FM 968 | Let Status: | Actual |
Project ID: | AR 1575-2-25 | CSJ: | 1575-02-025 |
Description: | REHABILITATE EXISTING 2-LANE RURAL HIGHWAY | Handling Code: |
|
Limits From: | US 80 | Fund Cat: | 8A |
Limits To: | FM 3251 | Estimate: | $576,600 |
Length: | 2.5 Miles | Actual: | $648,733 |
Back... |
Totals for 1575-02-025 | ||
Length: | 2.5 Miles | ||
Estimate: | $576,600 | ||
Actual: | $648,733 | ||
CCSJ: 1575-03-013 | |||
District: | Atlanta | Let Date: | MAY 2001 |
Highway: | FM 2625 | Let Status: | Actual |
Project ID: | STP 2001(437)R | CSJ: | 1575-03-013 |
Description: | REHABILITATE EXISTING 2-LANE RURAL HIGHWAY | Handling Code: |
|
Limits From: | FM 968 | Fund Cat: | 4F |
Limits To: | FM 3251 | Estimate: | $3,005,738 |
Length: | 8.4 Miles | Actual: | $2,995,686 |
Back... |
Totals for 1575-03-013 | ||
Length: | 8.4 Miles | ||
Estimate: | $3,005,738 | ||
Actual: | $2,995,686 | ||
CCSJ: 2340-02-017 | |||
District: | Atlanta | Let Date: | APR 2001 |
Highway: | FM 9 | Let Status: | Actual |
Project ID: | STP 2001(345)R | CSJ: | 2340-02-017 |
Description: | REHABILITATE EXISTING 2-LANE RURAL HIGHWAY | Handling Code: |
|
Limits From: | 4.5 MI. N. OF US 80 | Fund Cat: | 4F |
Limits To: | FM 1999 | Estimate: | $2,563,614 |
Length: | 5.1 Miles | Actual: | $2,401,190 |
Back... |
Totals for 2340-02-017 | ||
Length: | 5.1 Miles | ||
Estimate: | $2,563,614 | ||
Actual: | $2,401,190 |