SEP 2000 | OCT 2000 | NOV 2000 | DEC 2000 | JAN 2001 | FEB 2001 | MAR 2001 | APR 2001 | MAY 2001 | JUN 2001 | JUL 2001 | AUG 2001 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0748-05-030 | Atascosa/ San Antonio |
FM 140 | Actual | $3,338,733 | 4F | RECONSTRUCT & WIDEN EXISTING ROADWAY |
1740-03-012 | Atascosa/ San Antonio |
FM 1333 | Actual | $354,460 | 8A | REHAB & WIDEN NARROW PAVEMENT & SHOULDER |
0114-04-056 | Bastrop/ Austin |
US 290 | Actual | $1,018,430 | 11 | ADD CONTINUOUS LEFT TURN LANE |
0322-01-037 | Bastrop/ Austin |
SH 95 | Actual | $1,051,579 | 11 | REMOVE CONCRETE MEDIANS & ADD LT BAYS |
2686-01-010 | Bastrop/ Austin |
FM 2571 | Actual | $51,000 | 16B | REPAIR FLOOD DAMAGE |
0184-04-036 | Bell/ Waco |
LP 363 | Actual | $429,882 | 11 | REALIGN WESTBOUND FRONTAGE ROAD AND REALIGN RAMP |
0291-09-024 | Bexar/ San Antonio |
SH 16 | Actual | $2,906,900 | 7 | SEAL COAT & PAVEMENT MARKINGS |
0849-01-035 | Bexar/ San Antonio |
FM 471 | Actual | $592,790 | 11 | DRAINAGE REVISIONS |
0915-00-090 | Bexar/ San Antonio |
VA | Actual | $412,961 | 10A | UPGRADING ROADSIDE FLASHING BEACONS |
0915-12-347 | Bexar/ San Antonio |
CS | Actual | $528,836 | 13D | RESTORING EXISTING STREET (INCLUDES UTILITIES) |
1437-01-033 | Bexar/ San Antonio |
FM 1346 | Actual | $617,648 | 7 | ADDING 2' SHOULDERS, LEVEL-UP & SEAL COAT |
2255-01-028 | Bexar/ San Antonio |
FM 1937 | Actual | $1,709,310 | 7 | SEAL COAT & PAVEMENT MARKINGS |
0253-02-023 | Blanco/ Austin |
US 281 | Actual | $87,760 | 4A | IMPROVE GUARDRAIL AND ADD LEFT TURN LANE |
0912-31-081 | Brazoria/ Houston |
CS | Actual | $3,787,513 | 6B | REPLACE BRIDGE |
0251-07-018 | Burnet/ Austin |
US 281 | Actual | $512,480 | 4A | SAFETY TREAT DRAINAGE STRUCTURES |
0029-03-051 | Caldwell/ Austin |
US 90 | Actual | $127,800 | 16B | REPAIR FLOOD DAMAGE |
0286-02-023 | Caldwell/ Austin |
SH 80 | Actual | $186,875 | 4F | CONSTRUCT LEFT TURN LANE |
0575-01-007 | Caldwell/ Austin |
FM 20 | Actual | $50,700 | 16B | REPAIR FLOOD DAMAGE |
0515-03-037 | Calhoun/ Yoakum |
FM 1090 | Actual | $918,105 | 14 | RESTORE ROADWAY |
0275-02-054 | Carson/ Amarillo |
IH 40 | Actual | $15,998,849 | 2 | CONCRETE UPGRADE |
0191-04-005 | Cherokee/ Tyler |
FM 2493 | Actual | $323,017 | 10A | INSTALL TURN LANE AT HIGH SCHOOL ENTRANCE |
0069-05-024 | Coke/ San Angelo |
US 87 | Actual | $1,895,000 | 4B | RECONSTRUCTION OF SAFETY REST AREA |
0008-08-065 | Dallas/ Dallas |
SH 180 | Actual | $1,159,675 | 7 | REPAIR OF EXISTING CONCRETE PAVEMENT |
0009-03-040 | Dallas/ Dallas |
SH 66 | Actual | $301,978 | 16S | LANDSCAPE DEVELOPMENT |
0918-45-459 | Dallas/ Dallas |
VA | Actual | $3,009,680 | 4C | CONSTRUCT TRANSIT CENTER PEDESTRIAN CONNECTION |
0918-45-488 | Dallas/ Dallas |
CS | Actual | $40,455 | 13D | RECONSTRUCT CITY STREET |
0918-45-489 | Dallas/ Dallas |
CS | Actual | $60,000 | 13D | RECONSTRUCT CITY STREET |
0918-45-490 | Dallas/ Dallas |
CS | Actual | $52,000 | 13D | RECONSTRUCT CITY STREET |
0918-45-559 | Dallas/ Dallas |
VA | Actual | $1,103,750 | 5 | PUBLIC FLEET ALTERNATIVE FUELS PROGRAM |
2374-01-069 | Dallas/ Dallas |
IH 635 | Actual | 260,900,383 | 3A | CONSTRUCTION OF INTERCHANGE |
0143-08-080 | Dewitt/ Yoakum |
US 87 | Actual | $5,049,137 | 7 | ASPHALTIC CONCRETE PAVEMENT |
0913-00-057 | Dewitt/ Yoakum |
VA | Actual | $159,120 | 10A | TRAFFIC CONTROL DEVICES |
0913-00-058 | Dewitt/ Yoakum |
VA | Actual | $678,710 | 10A | TRAFFIC CONTROL DEVICES |
0007-03-075 | Eastland/ Brownwood |
IH 20 | Actual | $1,187,753 | 2 | BASE OVERLAY, CURB & GUTTER, SURFACE, SAFETY TRT STRUCTURES |
0906-00-064 | Ector/ Odessa |
VA | Actual | $863,942 | 7 | PREVENTIVE MAINTENANCE |
0906-00-074 | Ector/ Odessa |
VA | Actual | $339,454 | 10A | FLASHING BEACONS |
0001-04-077 | El Paso/ El Paso |
US 62 | Actual | $7,767,070 | 7 | OVERLAY |
0815-08-022 | Ellis/ Dallas |
FM 663 | Actual | $2,994,748 | 14 | RECONSTRUCT AND WIDEN ROADWAY |
0202-03-032 | Fannin/ Paris |
US 69 | Actual | $2,086,648 | 7 | PLANING, SEAL AND HMAC OVERLAY |
0192-04-092 | Galveston/ Houston |
SH 6 | Actual | $203,760 | 7 | JOINT CRACK SEAL AND SPOT BASE REPAIR |
0367-04-069 | Galveston/ Houston |
SH 87 | Actual | $705,497 | 11 | INSTALL LIGHTING |
0389-06-086 | Galveston/ Houston |
SH 146 | Actual | $583,951 | 11 | INSTALL MARINE FENDER SYSTEM |
2523-03-005 | Galveston/ Houston |
FM 646 | Actual | $88,860 | 7 | JOINT CRACK SEAL AND SPOT REPAIR |
0275-11-069 | Gray/ Amarillo |
IH 40 | Actual | $16,848,488 | 4B | RECONSTRUCT SAFETY REST AREA |
0909-29-021 | Hamilton/ Waco |
CR | Actual | $427,956 | 6B | REPLACE BRIDGES AND APPROACHES |
0028-02-073 | Harris/ Houston |
US 90 | Actual | $9,147,140 | 4E | GRADE SEPARATION |
0500-03-497 | Harris/ Houston |
IH 45 | Actual | $218,487 | 7 | JOINT SEPARATION REPAIR |
0912-71-536 | Harris/ Houston |
CS | Actual | $1,999,994 | 6B | REPLACE BRIDGE |
0912-71-733 | Harris/ Houston |
VA | Actual | $2,168,835 | 11 | CR /PM-FULL DEPTH REPAIR OF LONGITUDINAL JOINT SEPARATION, |
1685-05-080 | Harris/ Houston |
SH 6 | Actual | $192,343 | 7 | 2" PLANING, 2" ACP OVERLAY AND PAVEMENT MARKINGS |
1575-02-025 | Harrison/ Atlanta |
FM 968 | Actual | $648,733 | 8A | REHABILITATE EXISTING 2-LANE RURAL HIGHWAY |
2340-02-017 | Harrison/ Atlanta |
FM 9 | Actual | $2,401,190 | 4F | REHABILITATE EXISTING 2-LANE RURAL HIGHWAY |
0921-00-050 | Hidalgo/ Pharr |
VA | Actual | $1,522,908 | 11 | NON-SITE SPECIFIC TRAFFIC SIGNALS |
1429-01-026 | Hidalgo/ Pharr |
FM 2557 | Actual | $1,833,563 | 4F | WIDEN TO 4 LANE |
1490-03-013 | Hidalgo/ Pharr |
FM 490 | Actual | $1,294,361 | 8A | RESTORE AND ADD SHOULDERS |
0902-51-011 | Hood/ Fort Worth |
CR | Actual | $296,626 | 6B | REPLACE BRIDGE AND APPROACHES |
0901-22-030 | Hunt/ Paris |
PW | Actual | $1,369,317 | 9 | MISC CONST |
0739-02-123 | Jefferson/ Beaumont |
IH 10 | Actual | $9,021,536 | 12 | CONSTRUCT FRONTAGE ROADS AND RAMPS |
0019-01-121 | Johnson/ Fort Worth |
SH 174 | Actual | $116,000 | 16C | TRAFFIC SIGNAL INSTALLATION (NEW SIGNAL) |
1094-03-011 | Johnson/ Fort Worth |
FM 731 | Actual | $5,134,274 | 14 | REALIGN EXISTING FM ROADWAY AND WIDEN FROM 2 TO 4 LANE |
0033-04-057 | Jones/ Abilene |
US 83 | Actual | $1,329,290 | 3C | EXCAVATION, STORM SEWER, CURB & GUTTER, SIDEWALK, FLEX |
1278-01-008 | Kleberg/ Corpus Christi |
FM 1118 | Actual | $516,152 | 11 | REAHBILITATE ROADWAY |
0922-20-009 | La Salle/ Laredo |
CS | Actual | $125,795 | 6B | FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING |
1032-01-024 | Lampasas/ Brownwood |
FM 580 | Actual | $2,728,434 | 4E | RECONSTRUCT ROADWAY |
0643-01-042 | Leon/ Bryan |
FM 39 | Actual | $36,848 | 4A | MISCELLANEOUS WORK CONSISTING OF THE INSTALLATION OF A |
0542-06-036 | Live Oak/ Corpus Christi |
US 59 | Actual | $1,679,007 | 14 | REPAIR PAVEMENT FAILURE: TWO COURSE UNDERSEAL & 2" TY'C' OVERLA |
1378-05-023 | Llano/ Austin |
RM 1431 | Actual | $170,743 | 4A | INSTALL INTERSECTION FLASHING BEACON |
0905-06-048 | Lubbock/ Lubbock |
VA | Actual | $219,268 | 2 | MISCELLANEOUS CONSTRUCTION |
0905-06-054 | Lubbock/ Lubbock |
CS | Actual | $1,294,528 | 4E | WIDEN NON-FREEWAY |
0014-10-054 | McLennan/ Waco |
BU 77-L | Actual | $84,399 | 16S | LANDSCAPE DEVELOPMENT CONSISTING OF AN IRRIGATION SYSTEM |
0909-00-037 | McLennan/ Waco |
VA | Actual | $1,344,759 | 10A | DISTRICTWIDE GUIDE SIGNS |
0024-06-057 | Medina/ San Antonio |
US 90 | Actual | $2,197,158 | 7 | OVERLAY |
0110-03-046 | Montgomery/ Houston |
SH 75 | Actual | $735,161 | 14 | ADD LEFT TURN LANE AND TRAFFIC SIGNAL |
0338-03-084 | Montgomery/ Houston |
SH 105 | Actual | $2,391,853 | 7 | BASE AND ASPHALT REPAIR, ONE COURSE SURFACE TREATMENT AND |
0523-10-024 | Montgomery/ Houston |
FM 1488 | Actual | $455,160 | 10A | WIDEN PAVEMENT FOR LEFT AND RIGHT TURN CHANNELIZATION AND |
0911-04-032 | Polk/ Lufkin |
CR | Actual | $157,750 | 6B | REPLACE BRIDGE AND APPROACHES |
0041-05-042 | Potter/ Amarillo |
US 87 | Actual | $4,720,464 | 7 | OVERLAY |
0904-00-076 | Potter/ Amarillo |
VA | Actual | $174,700 | 11 | PAVEMENT MARKERS |
0203-04-026 | Rains/ Paris |
US 69 | Actual | $86,845 | 4A | INSTALL FLASHING BEACON W /ILL |
0371-02-062 | Refugio/ Corpus Christi |
US 77 | Actual | $8,256,236 | 3C | REHABILITATE ROADWAY |
0907-13-005 | Runnels/ San Angelo |
VA | Actual | $724,081 | 11 | TRANSPORTATION ENHANCEMENT -- HUTCHINS AVENUE PEDESTRIAN IMP |
0738-03-024 | San Patricio/ Corpus Christi |
FM 3284 | Actual | $617,422 | 6A | REPLACE BRIDGE AND APPROACHES |
0259-03-046 | Somervell/ Fort Worth |
US 67 | Actual | $581,739 | 7 | OVERLAY |
0106-06-029 | Stonewall/ Abilene |
SH 283 | Actual | $1,528,545 | 14 | EXCAVATION, EMBANKMENT, EXTEND AND SAFETY TREAT CULVERTS, |
0159-06-021 | Sutton/ San Angelo |
US 277 | Actual | $2,696,705 | 14 | REHABILITATE EXISTING ROADWAY |
0008-13-198 | Tarrant/ Fort Worth |
IH 20 | Actual | $1,450,648 | 2 | PAVEMENT REPAIR, FABRIC UNDERSEAL, OVERLAY, PAVEMENT MARKINGS |
0902-48-455 | Tarrant/ Fort Worth |
CS | Actual | $4,000 | 5 | RIGHT OF WAY ACQUISITION |
2266-02-107 | Tarrant/ Fort Worth |
SH 360 | Actual | $175,600 | 10A | TRAFFIC SIGNALS |
0113-13-127 | Travis/ Austin |
LP 360 | Actual | $2,079,533 | 7 | 1-CST, LEVEL-UP, OV |
3136-01-121 | Travis/ Austin |
LP 1 | Actual | $92,054 | 11 | ADD RIGHT TURN LANE |
0200-05-037 | Tyler/ Beaumont |
US 69 | Actual | $462,496 | 7 | ROTOMILL EXISTING ASPHALT AND OVERLAY |
2563-01-007 | Uvalde/ San Antonio |
FM 1023 | Actual | $1,195,392 | 8A | REHAB PAVEMENT & SHOULDERS (SDWLKS) |
0088-05-078 | Victoria/ Yoakum |
US 59 | Actual | $4,433,660 | 7 | ASPHALTIC CONCRETE PAVEMENT |
2350-01-026 | Victoria/ Yoakum |
LP 463 | Actual | $21,022,609 | 16C | CONSTRUCT GRADE SEPARATION INTERCHANGES, MAIN LANES AND |
0114-11-073 | Waller/ Houston |
US 290 | Actual | $1,938,969 | 7 | BS RP, PLN, ASPH REHAB O /L, SHLDR TX, PM |
0523-02-024 | Waller/ Houston |
FM 362 | Actual | $1,089,239 | 4F | PAVE SHOULDER AND ACP OVERLAY |
0922-33-042 | Webb/ Laredo |
VA | Actual | $895,913 | 13C | ITS DEPLOYMENT |
0137-03-036 | Wichita/ Wichita Falls |
SH 25 | Actual | $1,173,857 | 7 | HMAC OVERLAY |
0903-03-059 | Wichita/ Wichita Falls |
CS | Actual | $618,261 | 4D | REHABILITATION OF EXISTING ROAD |
0043-06-068 | Wilbarger/ Wichita Falls |
US 287 | Actual | $4,117,781 | 14 | REHABILITATION OF EXISTING ROAD |
0320-03-079 | Williamson/ Austin |
SH 95 | Actual | $116,685 | 16B | LANDSCAPING DEVELOPMENT |
0922-48-001 | Zavala/ Laredo |
VA | Actual | $174,440 | 4B | FOR THE CONSTRUCTION OF A HIKE AND BIKE TRAIL ON ABANDONED |