Letting Schedule for Houston District (FY 2002)

Texas Department of Transportation Logo (Registered Trademark)
 
 
Last Update: Thursday, September 5, 2002
 
Updated from Design & Construction Information System (DCIS) on: August 30, 2002
Houston District (FY 2002)
Brazoria | Fort Bend | Galveston | Harris | Montgomery | Waller

Brazoria County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0111-09-035 BS 288B Actual DEC 2001 $823,333 1 ACP OVERLAY WITH PAVEMENT MARKINGS
0192-02-047 SH 6 Actual JAN 2002 $9,634,058 11 WIDEN TO 6 - LANE DIVIDED RURAL SECTION
0598-02-037 SH 288 Actual AUG 2002 $1,775,801 1 CONSTRUCTION OF ACCELERATION AND DECELERATION LANES AT
0598-03-019 SH 288 Actual DEC 2001 $3,774,598 12 GRADE SEPARATION
0598-04-017 SH 288 Actual NOV 2001 $7,144,443 11 GRADE SEPARATION OF MAIN LANES ON SH 288 OVER FM 2004
0598-04-019 SH 288 Actual JUL 2002 $4,399,049 12 GRADE SEPARATION
0847-03-030 FM 521 Actual AUG 2002 $2,577,736 1 ACP OVERLAY, WIDEN SHOULDERS AND LENGTHEN STRUCTURES
0912-31-128 VA Actual JAN 2002 $375,000 9 HISTORIC RAILROAD DEPOT
1003-01-082 FM 523 Actual FEB 2002 $2,007,326 1 ACP OVERLAY, STRUCTURE AND PAVEMENT

Fort Bend County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0027-12-107 US 59 Actual NOV 2001 $2,176,151 11 CONSTRUCT FRONTAGE ROADS FOR ACCESS TO RIVER PARK
0027-12-112 US 59 Actual AUG 2002 $2,234,665 1 REALIGN SB MAINLANES
0027-12-117 US 59 Actual JUN 2002 $979,283 1 REHABILITATE PAVEMENT SHOULDERS, ACP OVERLAY, SIGNING AND
0111-03-039 FM 521 Actual OCT 2001 $1,176,436 4 RAISE ROADWAY ELEVATION
0111-03-045 FM 521 Actual APR 2002 $38,738 10 RAILROAD GRADE CROSSING REPLANKING
0187-05-046 SP 10 Actual JUN 2002 $16,589,355 4 CONSTRUCT GRADE SEPARATION
0188-02-033 SH 36 Actual DEC 2001 $7,325,697 1 SPOT BASE REPAIR, SURFACE REPAIR, PLANING, ACP OVERLAY &
0192-01-063 SH 6 Actual FEB 2002 $16,091,646 4 WIDEN TO 6 - LANE DIVIDED RURAL SECTION
0192-01-078 SH 6 Actual MAR 2002 $15,197,718 1 WIDEN TO 6 - LANE DIVIDED RURAL SECTION
0912-34-080 CS Actual MAR 2002 $7,234,105 7 CONSTRUCT 4 LANE DIVIDED ROADWAY ON NEW LOCATION
0912-34-086 CS Actual OCT 2001 $1,267,977 5 CONSTRUCT PARK AND RIDE
0912-34-101 CS Actual AUG 2002 $143,426 5 SYNCHRONIZATION AND INTERCONNECTION OF TRAFFIC SIGNALS
1685-06-025 SH 6 Actual JUN 2002 $1,653,820 1 CONSTRUCT CROSS DRAINAGE STRUCTURE, STORM SEWER & CLEAN DITCH
3510-04-018 SH 99 Actual SEP 2001 $216,900 1 INSTALLATION OF A FULL - ACTUATED TRAFFIC SIGNAL WITH SAFETY

Galveston County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0051-03-088 SH 3 Actual AUG 2002 $648,953 1 CRACK SEAL AND BASE REPAIR
0192-04-093 SH 6 Actual AUG 2002 $5,595,387 1 FULL DEPTH REPAIR, BASE REPAIR, RAISE MBGF RAIL,
0389-07-031 SH 146 Actual SEP 2001 $159,224 11 REHABILITATE HIGH MAST
0500-04-109 IH 45 Actual AUG 2002 $916,963 1 FULL DEPTH CONCRETE REPAIR, SLOPE REPAIR AND REPAIR BRIDGE
0912-73-066 CR Actual JUL 2002 $445,858 6 REPLACE BRIDGE

Harris County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0027-13-171 US 59 Actual AUG 2002 $71,109,488 2 RECONSTRUCT ROADWAY AND EXTEND HOV LANE
0027-13-174 US 59 Actual JUL 2002 $988,975 7 CONSTRUCT NORTHBOUND EXIT RAMP
0027-13-176 US 59 Actual NOV 2001 $6,200 10 LANDSCAPE DEVELOPMENT
0027-13-177 US 59 Actual APR 2002 $60,160 10 RAILROAD GRADE CROSSING REPLANKING
0027-13-178 US 59 Actual APR 2002 $60,160 10 RAILROAD GRADE CROSSING REPLANKING
0028-01-086 BU 90-U Actual AUG 2002 $802,646 5 INSTALL ATMS
0028-01-089 US 90 Actual JUN 2002 $16,800 10 REPAIR AND / OR REPLACE DAMAGED ILLUMINATION ELECTRICAL
0050-09-060 US 290 Actual AUG 2002 $1,189,856 1 CRACK & SPALL REPAIR, CTB ALIGNMENT, FULL DEPTH CONCRETE
0051-02-080 SH 3 Actual AUG 2002 $155,197 5 INSTALL ARTERIAL TRAFFIC MANAGEMENT SYSTEM
0177-11-138 US 59 Actual JUN 2002 $35,000 11 FRENCHTOWN HISTORICAL MARKER AND LANDSCAPING
0177-11-140 US 59 Actual JUN 2002 $5,000 10 REPAIR COLLAPSED PUMPHOUSE BASKET TO ORIGINAL CONDITION
0271-07-223 IH 10 Actual OCT 2001 $1,162,101 5 INSTALL COMPUTERIZED TRANSPORTATION MANAGEMENT SYSTEM
0271-07-256 IH 10 Actual JAN 2002 $4,693,966 1 FOR THE CONSTRUCTION OF ASPHALTIC CONCRETE PAVEMENT OVERLAY
0271-07-259 IH 10 Actual MAR 2002 $97,119 11 CONSTRUCT SECURITY BARRIER
0271-07-267 IH 10 Actual JUN 2002 $70,276 10 REMOVE BROKEN AND RELAID ASPHALT PAVEMENT ON TRANSITION TO
0271-07-268 IH 10 Actual JUN 2002 $57,124 10 RESTORE FILL AND REPLACE ERODED CONCRETE RIPRAP AROUND
0271-07-269 IH 10 Actual JUN 2002 $17,048 10 FILL IN EROSION UNDER CONCRETE RIPRAP AND REPAIR DAMAGED
0271-16-113 IH 610 Actual OCT 2001 $5,753,388 1 REPLACE BRIDGE RAIL
0271-16-115 IH 610 Actual JUL 2002 $5,373,276 1 GRIND EXIST PAVEMENT, ADD BONDED CONC OVERLAY, RECONSTR 5
0271-16-116 IH 610 Actual DEC 2001 $4,860,447 1 GRIND EXIST PAVEMENT ADD BONDED CONC OVERLAY F.R.'S
0271-16-117 IH 610 Actual APR 2002 $5,434,594 1 GRIND EXIST PAVEMENT ADD BONDED CONCRETE O / L, RECONSTRUCT
0271-17-126 IH 610 Actual JUL 2002 $80,946,695 1 TSM, RECONSTRUCT 8 - LANE FREEWAY, TMS AND PROVISION FOR
0271-17-132 IH 610 Actual SEP 2001 $1,046,245 10 LANDSCAPING AND SIDEWALKS
0271-17-140 IH 610 Actual FEB 2002 $869,884 1 HIGH MAST LIGHTING
0389-05-090 SH 146 Actual APR 2002 $165,440 10 RAILROAD GRADE CROSSING REPLANKING
0389-05-093 SH 146 Actual JUN 2002 $562,907 1 ACP REHABILITATION MEDIAN AND SHOULDER
0389-12-084 SH 146 Actual MAR 2002 $465,000 11 INSTALL ACOUSTIC MONITORING SYSTEM FOR CABLE STAYED BRIDGE
0389-15-013 BS 146D Actual SEP 2001 $362,610 1 JT SEP REP, MILL & ACP O / L, SURF TREATMENT OF ML CENT MED,
0500-03-482 IH 45 Actual DEC 2001 $2,709,173 6 WIDEN BRIDGE
0500-03-501 IH 45 Actual SEP 2001 $202,677 11 CONSTRUCT NOISE WALL
0500-03-507 IH 45 Actual SEP 2001 $190,903 1 REPAIR AND ENCAPSULATE SUPPORT COLUMNS AT STR. # 89 & 337
0500-03-509 IH 45 Actual AUG 2002 $1,447,813 1 SHOULDER REPLACEMENT
0508-01-306 IH 10 Actual JUN 2002 $13,685 10 REMOVE BROKEN ASPHALT PAVEMENT ON SHOULDER AND RELAY WITH
0508-07-021 SP 330 Actual MAR 2002 $23,293,364 12 CONSTRUCT 6 MAIN LANES (PHASE 2)
0598-01-067 SH 288 Actual APR 2002 $1,863,939 1 FULL DEPTH CONCRETE REPAIR AND CRACK & JOINT SEAL MAINLANES
0598-01-068 SH 288 Actual JUN 2002 $78,830 10 FILL ERODED CONCRETE RIPRAP SLOPE AREAS AND REPLACE CONCRETE
0720-03-110 SH 249 Actual AUG 2002 $27,268,003 12 CONSTRUCT 3 DC'S (EB - NB, WB - NB, SB - EB) AND RELOCATE EXISTING
0912-00-179 VA Actual SEP 2001 $1,861,192 11 INSTALL OVERHEAD SIGNS W / HIGH INTENSITY SHEETING
0912-00-219 VA Actual OCT 2001 $453,105 1 FOR WORK CONSISTING OF TRAFFIC SIGNALS (NON - SITE SPECIFIC)
0912-00-221 VA Actual AUG 2002 $749,412 1 TRAFFIC SIGNALS (NON - SITE SPECIFIC)
0912-00-222 VA Actual OCT 2001 $200,000 1 UPGRADE SCHOOL ZONE FLASHERS (250 LOCATIONS)
0912-00-225 VA Actual MAY 2002 $1,696,550 1 REPLACE RAISED REFLECTIVE PAVEMENT MARKERS AND BUTTONS
0912-00-226 VA Actual MAY 2002 $887,933 1 RETRACE PAVEMENT MARKINGS AND INSTALL RAISED REFLECTIVE
0912-00-230 VA Actual MAY 2002 $898,114 1 REPLACE PAVEMENT MARKINGS AND INSTALL RAISED REFLECTIVE
0912-00-231 VA Actual JUL 2002 $555,962 1 REPLACE PAVEMENT MARKINGS AND INSTALL RAISED REFLECTIVE
0912-00-232 VA Actual JAN 2002 $1,500,000 5 55 MPH SIGNAGE INSTALLATION (TXDOT & HCTRA)
0912-00-234 VA Actual JUN 2002 $168,500 10 PROVIDE TRAFFIC CONTROL AND DEBRIS REMOVAL
0912-00-235 VA Actual JUN 2002 $27,288 10 REPAIR AND / OR REPLACE DAMAGED TRAFFIC SIGNAL CONTROLLERS
0912-00-236 VA Actual JUN 2002 $13,311 10 REPAIR AND / OR REPLACE DAMAGED TRAFFIC SIGNAL CONTROLLERS
0912-00-239 VA Actual JUL 2002 $2,247,000 7 FY 2003 CAPITAL UPGRADE (FUNDING FOR PURCHASE OF SOFTWARE /
0912-71-549 VA Actual NOV 2001 $1,688,000 9 SAN JACINTO MONUNENT RESTORATION PHASE 2
0912-71-650 VA Actual MAY 2002 $1,599,372 9 ACCESS ON - STREET BIKEWAY NETWORK - PHASE 2
0912-71-652 CR Actual NOV 2001 $407,867 10 REMOVE DEBRIS, EROSION REPAIR, REBUILD ROADWAY AND RAISE
0912-71-765 VA Actual JUL 2002 $295,175 1 RETRACE PAVEMENT MARKINGS AND INSTALL RAISED REFLECTIVE
0912-71-771 VA Actual JUL 2002 $707,628 1 REPLACE PAVEMENT MARKINGS AND INSTALL RAISED REFLECTIVE
0912-71-772 VA Actual JUL 2002 $1,019,955 1 REPLACE PAVEMENT MARKINGS AND INSTALL RAISED REFLECTIVE
0912-71-774 CS Actual JAN 2002 $240,000 8 RR SIGNAL AND WARNIFN DEVICES
0912-71-775 CS Actual JAN 2002 $240,000 8 SIGNAL AND WAINING DEVICES
0912-71-776 CS Actual JAN 2002 $170,000 8 RR SIGNALS AND WARNING DEVICES
0912-71-777 CS Actual JAN 2002 $240,000 8 RR SIGNAL AND WARNING DEVICES
0912-71-778 CS Actual JAN 2002 $240,000 8 RR SIGNAL AND WARNING DEVICES
0912-71-779 CR Actual JUN 2002 $65,000 10 REMOVE DEBRIS, REPLACE WASHED OUT ASPHALT PAVED ROADWAY,
0912-71-780 VA Actual JUN 2002 $6,264 10 REPLACE ASPHALT PAVEMENT
0912-71-784 VA Actual JUN 2002 $20,612 10 REPAIR AND / OR REPLACE DAMAGED TRAFFIC SIGNAL CONTROLLERS
0912-71-785 VA Actual JUN 2002 $33,600 10 REPAIR AND / OR REPLACE DAMAGED ILLUMINATION ELECTRICAL
0912-71-786 VA Actual JUN 2002 $16,800 10 REPAIR AND / OR REPLACE DAMAGED ILLUMINATION ELECTRICAL
0912-71-787 VA Actual JUN 2002 $58,544 10 REPAIR AND / OR REPLACE DAMAGED TRAFFIC SIGNAL CONTROLLERS
0912-71-788 VA Actual JUN 2002 $11,200 10 REPAIR AND / OR REPLACE DAMAGED ILLUMINATION ELECTRICAL
0912-71-813 VA Actual JUN 2002 $317,117 10 REPAIR TRAFFIC SIGNAL CONTROLLERS AND ELECTRONIC COMPONENTS
0912-71-815 VA Actual JUN 2002 $31,096 10 REPAIR CONCRETE RIPRAP ON SLOPES
0912-71-816 VA Actual AUG 2002 $1,486,812 5 FY 2002: TROLLEY / ACTIVITY CENTER SHUTTLES
0912-71-817 VA Actual AUG 2002 $3,957,533 5 FY 2002: ADDITION OF 8 NEW SERVICE ROUTES (OP ASSISTANCE - YR1)
0912-71-818 VA Actual AUG 2002 $551,516 5 FY 2002: 2ND YR FUNDING FOR OP ASSIST. OF THE 11 SERVICE
0981-01-098 NASA 1 Actual MAY 2002 $200,000 10 LANDSCAPE DEVELOPMENT
1258-04-051 FM 1093 Actual JAN 2002 $3,075,575 1 PLANING, FULL DEPTH CONCRETE REPAIR, ACP O / L, PAVE MARKS AND
1685-02-035 FM 1960 Actual MAR 2002 $22,885,623 2 WIDEN TO 6 - LANE DIVIDED, FLUSH MEDIAN, SHOULDERS AND OPEN
1743-01-007 FM 1876 Actual SEP 2001 $785,917 1 REPAIR EXISTING FLEX PAV STRCT, FULL DEPTH CONCRETE REPAIR,
2941-02-039 FM 2920 Actual AUG 2002 $899,246 5 INSTALL ARTERIAL TRAFFIC MANAGEMENT SYSTEM
3256-01-080 BW 8 Actual MAY 2002 $60,000 10 LANDSCAPE DEVELOPMENT
3256-02-062 BW 8 Actual SEP 2001 $900,864 11 INSTALL CONTINUOUS LIGHTING
3256-02-065 BW 8 Actual MAY 2002 $1,669,661 1 THIN BONDED CONCRETE OVERLAY AND PAVEMENT MARKINGS

Montgomery County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0110-03-048 SH 75 Actual MAY 2002 $1,945,392 1 PLANE, O.C.S.T., AND ACP OVERLAY
0110-04-156 IH 45 Actual JUN 2002 $2,044,286 5 INSTALL COMPUTERIZED TRANSPORTATION MANAGEMENT SYSTEM
0110-04-172 IH 45 Actual MAR 2002 $450,000 10 LANDSCAPE DEVELOPMENT
0110-04-173 IH 45 Actual MAY 2002 $8,000 10 REPAIR WASHOUT AT SHOULDER AND RESET OVERTURNED CTB
0110-04-174 IH 45 Actual JUN 2002 $16,800 10 REPAIR AND / OR REPLACE DAMAGED ILLUMINATION ELECTRICAL
0177-14-021 LP 494 Actual APR 2002 $615,029 11 ADD LEFT TURN LANES
0338-03-085 SH 105 Actual OCT 2001 $134,170 1 FOR WORK CONSISTING OF INSTALLATION OF A FULL - ACTUATED
0675-08-087 IH 45 Actual AUG 2002 $1,516,232 8 INSTALL MEDIAN BARRIER
0912-37-114 VA Actual SEP 2001 $1,558,979 1 RETROFIT BRIDGE RAIL, MILLING AND ACP OVERLAY
0912-37-136 CS Actual JAN 2002 $160,000 8 RR SIGNALS AND WARNING DEVICES
0912-37-137 VA Actual JUN 2002 $25,843 10 REP SHOULDER WASHOUTS, GUARDRAIL & ASPHALT PAVEMENT, REPAIR
0912-37-139 VA Actual JUN 2002 $16,240 10 REPAIR AND / OR REPLACE DAMAGED TRAFFIC SIGNAL CONTROLLERS
0912-37-142 CR Actual AUG 2002 $2,280,000 9 WOODLANDS TOWN CENTER PEDESTRIAN CORRIDOR SOUTH SIDE -
0912-37-143 CS Actual AUG 2002 $250,000 5 PRELIMINARY ENGINEERING & ENVIRONMENTAL ANALYSIS
0912-37-144 CS Actual AUG 2002 $1,150,000 5 CONSTRUCT RESEARCH FOREST P & R EXPANSION
1416-03-010 FM 1486 Actual JUN 2002 $22,136 10 RAILROAD GRADE CROSSING REPLANKING
1986-01-048 FM 1314 Actual JUL 2002 $1,000 11 ENVIRONMENTAL CLEARANCE AND INTERSECTION IMPROVEMENT PERMIT
3538-01-025 SH 242 Actual OCT 2001 $181,116 1 FOR WORK CONSISTING OF THE INSTALLATION OF AN EMER FIRE RUN
3538-01-028 SH 242 Actual MAR 2002 $750,000 10 LANDSCAPE DEVELOPMENT FOR MATERIALS ONLY

Waller County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0271-04-076 IH 10 Actual AUG 2002 $1,174,809 1 PLANING, ACP REHAB AND OVERLAY AND PAVEMENT MARKINGS
0271-09-014 US 90 Actual AUG 2002 $224,195 5 INSTALL ARTERIAL TRAFFIC MANAGEMENT SYSTEM
0409-03-009 FM 1488 Actual AUG 2002 $824,012 1 BASE REPAIR, PLANING, SURF REHAB, ACP OVERLAY AND
0523-01-023 FM 1488 Actual JAN 2002 $608,649 1 BASE REPAIR, PLANING, ASPHALTIC CONCRET REMIX, OVERLAY AND
0523-04-014 FM 1488 Actual JAN 2002 $2,447,478 1 BASE REPAIR, PLANING, ASPHALTIC CONCRET REMIX, OVERLAY AND
0543-01-056 FM 359 Actual JUL 2002 $3,978,137 1 BASE REPAIR, PLANING, ASPHALTIC CONCRETE REHAB AND OVERLAY


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract