Letting Schedule for August, 2002 (FY 2002)
![]() |
![]() |
![]() |
![]() |
![]() |
Letting Schedule for August, 2002 (FY 2002) | ||||
Last Update: Thursday, September 5, 2002 | ||||
Updated from Design & Construction Information System (DCIS) on: August 30, 2002 | |
August, 2002 (FY 2002) | (see Links) |
SEP 2001 | OCT 2001 | NOV 2001 | DEC 2001 | JAN 2002 | FEB 2002 | MAR 2002 | APR 2002 | MAY 2002 | JUN 2002 | JUL 2002 | AUG 2002 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0123-01-031 | Anderson/ Tyler |
US 84 | Actual | $3,768,420 | 1 | REHABILITATE EXISTING ROADWAY AND ADD SHOULDERS |
0576-02-054 | Angelina/ Lufkin |
FM 1818 | Actual | $467,743 | 8 | MODERNIZE BRIDGE RAIL & APPROACH GUARDRAIL & SAFETY TREAT |
1795-02-012 | Angelina/ Lufkin |
FM 1819 | Actual | $2,038,088 | 1 | REHABILITATION OF EXISTING ROAD |
0357-03-020 | Armstrong/ Amarillo |
FM 1151 | Actual | $3,124,143 | 1 | OVERLAY |
0025-02-162 | Bexar/ San Antonio |
IH 10 | Actual | $149,866 | 8 | TEXTURIZE SHOULDERS (MILLED) |
0025-02-163 | Bexar/ San Antonio |
IH 10 | Actual | $2,375,178 | 1 | RECONFIGURATION OF INTERSECTION |
0915-12-263 | Bexar/ San Antonio |
VA | Actual | $206,000 | 7 | ALAMO AREA COMMUTE SOLUTION PGM - FY2002 |
0061-02-026 | Bowie/ Atlanta |
SH 8 | Actual | $2,882,386 | 1 | REHABILITATE AND WIDEN EXISTING 2 - LANE RURAL HIGHWAY |
0598-02-037 | Brazoria/ Houston |
SH 288 | Actual | $1,775,801 | 1 | CONSTRUCTION OF ACCELERATION AND DECELERATION LANES AT |
0847-03-030 | Brazoria/ Houston |
FM 521 | Actual | $2,577,736 | 1 | ACP OVERLAY, WIDEN SHOULDERS AND LENGTHEN STRUCTURES |
0049-12-066 | Brazos/ Bryan |
SH 6 | Actual | $926,325 | 1 | OVERLAY CONSISTING OF PLACING MICROSURFACING, PAVEMENT |
0923-06-038 | Brown/ Brownwood |
CR | Actual | $912,642 | 6 | REPLACE BRIDGE AND APPROACHES |
0923-06-046 | Brown/ Brownwood |
VA | Actual | $1,260,496 | 10 | CONSTRUCT NEW URBAN STREET |
0116-06-007 | Burleson/ Bryan |
LP 83 | Actual | $570,135 | 11 | REHABILITATE EXISTING ROAD CONSISTING OF GRADING, BASE, |
0252-01-056 | Burnet/ Austin |
US 281 | Actual | $418,887 | 1 | BASE REPAIR, MILL, SEAL & OVERLAY |
0220-05-059 | Cameron/ Pharr |
SH 48 | Actual | $1,315,325 | 11 | DRAINAGE IMPROVEMENTS |
1140-03-015 | Cameron/ Pharr |
FM 802 | Actual | $2,727,469 | 8 | WIDEN TO 4 LANE DIVIDED |
0199-01-067 | Cherokee/ Tyler |
US 69 | Actual | $1,570,234 | 1 | CONSTRUCT CURBED MEDIAN WITH PROTECTED LEFT TURN BAYS |
0450-01-008 | Cherokee/ Tyler |
SH 204 | Actual | $2,694,685 | 11 | REPLACE BRIDGES AND APPROACHES |
0047-14-054 | Collin/ Dallas |
US 75 | Actual | $235,825 | 1 | TRAFFIC SIGNAL INSTALLATION |
0619-03-051 | Collin/ Dallas |
FM 544 | Actual | $72,694 | 1 | TRAFFIC SIGNAL INSTALLATION |
0027-02-029 | Colorado/ Yoakum |
FM 102 | Actual | $3,595,806 | 8 | SEFETY TREAT FIXED OBJECTS |
0009-11-189 | Dallas/ Dallas |
IH 30 | Actual | $2,568,947 | 10 | RECONSTRUCT INTERCHANGE |
0095-02-091 | Dallas/ Dallas |
US 80 | Actual | $1,123,044 | 1 | MICROSURFACING AND PAVEMENT MARKINGS |
0197-02-092 | Dallas/ Dallas |
US 175 | Actual | $1,497,414 | 1 | MILL AND OVERLAY EXISTING MAIN LANES AND SHOULDERS |
0581-01-116 | Dallas/ Dallas |
LP 12 | Actual | $42,256 | 8 | REMOVE TURN DOWNS & METAL BARRELS & INSTALL MBGF & SGT'S |
0918-00-061 | Dallas/ Dallas |
VA | Actual | $1,849,177 | 1 | UPGRADE GUARDRAIL END TREATMENTS |
0918-00-066 | Dallas/ Dallas |
VA | Actual | $4,160,000 | 5 | SIP IMPLEMENTATION |
0918-45-462 | Dallas/ Dallas |
CS | Approved | $391,630 | 5 | 1 OFF SYSTEM INTERSECTION IMPROVEMENT |
0918-45-607 | Dallas/ Dallas |
VA | Actual | $111,250 | 7 | TRANSPORTATION MANAGEMENT ASSOCIATION |
0918-45-624 | Dallas/ Dallas |
CS | Actual | $79,901 | 5 | RIGHT OF WAY ACQUISITION |
0918-45-650 | Dallas/ Dallas |
VA | Actual | $2,311,730 | 5 | INSTAL OF POCKET TRACK IN VICINITY OF CONVENTION CENTER TO |
0918-45-651 | Dallas/ Dallas |
VA | Actual | $7,019,152 | 5 | RAIL TRANSIT |
0918-45-652 | Dallas/ Dallas |
VA | Actual | $18,979,786 | 5 | CONSTRUCT MISC DOUBLE TRACK SEGMENTS FOR THE TRINITY |
1068-04-083 | Dallas/ Dallas |
IH 30 | Actual | $96,841,618 | ROW | WIDEN 6 TO 8 LANES AND ADD INTERCHANGES |
1068-04-110 | Dallas/ Dallas |
IH 30 | Actual | $35,540,701 | 7 | WDN 6 TO 10 LANES AND NOISE WALL |
0182-01-011 | Eastland/ Brownwood |
SH 36 | Actual | $3,944,229 | 11 | BASE OVERLAY, SEAL COAT, AND STRIPING |
0924-06-133 | El Paso/ El Paso |
VA | Actual | $1,827,145 | 13D | CONCRETE PAVEMENT INTERSECTIONS |
0048-05-037 | Ellis/ Dallas |
US 77 | Actual | $1,444,455 | 6 | REPLACE BR & APPRS |
0172-04-028 | Ellis/ Fort Worth |
US 287 | Actual | $16,624,700 | 7 | WIDEN TO 4 LANE DIVIDED RURAL |
0172-05-095 | Ellis/ Dallas |
US 287 | Actual | $2,355,622 | 11 | WIDEN US 287 TO REDUCE QUEUES |
0260-02-033 | Ellis/ Dallas |
US 67 | Actual | $169,176 | 6 | REPLACE BR & APPRS |
1051-01-031 | Ellis/ Dallas |
FM 664 | Actual | $107,959 | 8 | TRAFFIC SIGNAL INSTALLATION, ADD LEFT TURN BAY, OVERLAY, AND |
0902-49-029 | Erath/ Fort Worth |
CR | Actual | $435,030 | 6 | REPLACE BRIDGES AND APPROACHES |
1440-01-015 | Fayette/ Yoakum |
FM 957 | Actual | $928,685 | 1 | RESTORE ROADWAY |
0027-12-112 | Fort Bend/ Houston |
US 59 | Actual | $2,234,665 | 1 | REALIGN SB MAINLANES |
0912-34-101 | Fort Bend/ Houston |
CS | Actual | $143,426 | 5 | SYNCHRONIZATION AND INTERCONNECTION OF TRAFFIC SIGNALS |
0421-03-011 | Frio/ San Antonio |
SH 173 | Actual | $4,640,678 | 1 | REHABILITATE AND WIDEN NARROW PAVEMENT AND SHOULDER |
0051-03-088 | Galveston/ Houston |
SH 3 | Actual | $648,953 | 1 | CRACK SEAL AND BASE REPAIR |
0192-04-093 | Galveston/ Houston |
SH 6 | Actual | $5,595,387 | 1 | FULL DEPTH REPAIR, BASE REPAIR, RAISE MBGF RAIL, |
0500-04-109 | Galveston/ Houston |
IH 45 | Actual | $916,963 | 1 | FULL DEPTH CONCRETE REPAIR, SLOPE REPAIR AND REPAIR BRIDGE |
0113-01-035 | Gillespie/ Austin |
US 290 | Actual | $629,377 | 1 | BASE REPAIR, MILL, SEAL, OVERLAY & SIGNAL |
0069-02-020 | Glasscock/ San Angelo |
US 87 | Actual | $12,588,460 | 3 | RECONSTRUCT AND UPGRADE 2 - LANE HIGHWAY TO 4 - LANE DIVIDED |
0393-01-076 | Gregg/ Tyler |
US 259 | Actual | $894,452 | 8 | INSTALL TRAFFIC SIGNAL |
0338-01-040 | Grimes/ Bryan |
SP 515 | Actual | $1,033,485 | 1 | REHAB EXISTING ROADWAY |
2233-02-004 | Guadalupe/ San Antonio |
FM 539 | Actual | $3,654,953 | 11 | RECONSTRUCT EXISTING ROADWAY |
0909-29-026 | Hamilton/ Waco |
CR | Actual | $689,638 | 6 | REPLACE BRIDGE AND APPROACHES |
0790-05-025 | Hansford/ Amarillo |
SH 15 | Actual | $978,911 | 1 | OVERLAY |
0027-13-171 | Harris/ Houston |
US 59 | Actual | $71,109,488 | 2 | RECONSTRUCT ROADWAY AND EXTEND HOV LANE |
0028-01-086 | Harris/ Houston |
BU 90-U | Actual | $802,646 | 5 | INSTALL ATMS |
0050-09-060 | Harris/ Houston |
US 290 | Actual | $1,189,856 | 1 | CRACK & SPALL REPAIR, CTB ALIGNMENT, FULL DEPTH CONCRETE |
0051-02-080 | Harris/ Houston |
SH 3 | Actual | $155,197 | 5 | INSTALL ARTERIAL TRAFFIC MANAGEMENT SYSTEM |
0500-03-509 | Harris/ Houston |
IH 45 | Actual | $1,447,813 | 1 | SHOULDER REPLACEMENT |
0720-03-110 | Harris/ Houston |
SH 249 | Actual | $27,268,003 | 12 | CONSTRUCT 3 DC'S (EB - NB, WB - NB, SB - EB) AND RELOCATE EXISTING |
0912-00-221 | Harris/ Houston |
VA | Actual | $749,412 | 1 | TRAFFIC SIGNALS (NON - SITE SPECIFIC) |
0912-71-816 | Harris/ Houston |
VA | Actual | $1,486,812 | 5 | FY 2002: TROLLEY / ACTIVITY CENTER SHUTTLES |
0912-71-817 | Harris/ Houston |
VA | Actual | $3,957,533 | 5 | FY 2002: ADDITION OF 8 NEW SERVICE ROUTES (OP ASSISTANCE - YR1) |
0912-71-818 | Harris/ Houston |
VA | Actual | $551,516 | 5 | FY 2002: 2ND YR FUNDING FOR OP ASSIST. OF THE 11 SERVICE |
2941-02-039 | Harris/ Houston |
FM 2920 | Actual | $899,246 | 5 | INSTALL ARTERIAL TRAFFIC MANAGEMENT SYSTEM |
0062-07-071 | Harrison/ Atlanta |
US 59 | Actual | $384,117 | 1 | IMPROVE TRAFFIC SIGNAL |
0030-07-014 | Hemphill/ Amarillo |
US 83 | Actual | $1,236,314 | 1 | REHABILITATE EXISTING ROADWAY |
0255-07-101 | Hidalgo/ Pharr |
US 281 | Actual | $14,549,173 | 11 | CONSTRUCT 4 LANE CONTROLLED ACCESS FACILITY WITH FRONTAGE |
0921-00-051 | Hidalgo/ Pharr |
VA | Actual | $735,994 | 1 | FLASHING BEACON REFURBISHING |
2059-01-011 | Hill/ Waco |
FM 1304 | Actual | $5,322,617 | 1 | REHABILITATION OF EXISTING ROADWAY AND ADD SHOULDERS |
0005-06-104 | Howard/ Abilene |
IH 20 | Actual | $350,090 | 8 | TEXTURIZE SHOULDERS (MILLED) |
0068-08-050 | Howard/ Abilene |
US 87 | Actual | $272,859 | 1 | TRAFFIC SIGNAL UPGRADE |
0791-03-016 | Hutchinson/ Amarillo |
SH 136 | Actual | $2,825,832 | 6 | REPLACE BRIDGE AND APPROACHES |
0014-13-004 | Johnson/ Fort Worth |
BI 35-V | Actual | $1,267,971 | 6 | REPLACE RAILROAD UNDERPASS |
0902-50-072 | Johnson/ Fort Worth |
VA | Actual | $161,418 | 1 | SMALL SIGNS REPLACEMENT |
1181-04-032 | Johnson/ Fort Worth |
FM 917 | Actual | $258,576 | 1 | WIDEN ROAD WAY TO INCLUDE LEFT TURN LANE |
0908-24-022 | Jones/ Abilene |
CR | Actual | $345,789 | 6 | REPLACE BRIDGE AND APPROACHES |
0908-24-028 | Jones/ Abilene |
CR | Actual | $1,097,526 | 6 | REPACE BRIDGE AND APPROACHES |
0522-01-018 | Kaufman/ Dallas |
SH 243 | Actual | $5,355,376 | 1 | RESURFACE ROADWAY |
0324-02-018 | Lavaca/ Yoakum |
SH 95 | Actual | $1,688,859 | 1 | REHABILITATE ROADWAY |
2349-02-009 | Lavaca/ Yoakum |
FM 2437 | Actual | $2,475,658 | 1 | RESTORE ROADWAY |
0205-04-024 | Leon/ Bryan |
US 79 | Actual | $9,651,559 | 3 | WIDEN TO FOUR LANE DIVIDED RURAL SECTION |
0426-03-034 | Leon/ Bryan |
FM 542 | Actual | $889,599 | 6 | REPLACEMENT OF AN EXISTING BRIDGE FACILITY CONSISTING OF |
0388-02-056 | Liberty/ Beaumont |
SH 146 | Actual | $3,874,161 | 4 | RECONSTRUCT ROADWAY AND ADD SHOULDERS |
0569-03-015 | Marion/ Atlanta |
SH 43 | Actual | $937,910 | 1 | RESURFACE EXISTING 2 - LANE RURAL HWY |
0346-03-027 | Matagorda/ Yoakum |
SH 111 | Actual | $4,483,495 | 4 | WIDEN ROADWAY AND ACP |
0870-06-013 | McCulloch/ Brownwood |
FM 765 | Actual | $552,237 | 11 | REPLACE STRUCTURE AND APPROACHES |
0015-21-006 | McLennan/ Waco |
FM 3476 | Actual | $973,548 | 11 | WIDEN FROM 2 LANE TO 4 LANE DIVIDED WITH CONTINUOUS |
0055-08-094 | McLennan/ Waco |
US 84 | Actual | $1,559,275 | 11 | REPLACE BRIDGE AND APPROACHES |
0909-22-107 | McLennan/ Waco |
CS | Approved | $510,008 | 13D | RECONSTRUCT EXISTING PAVEMENT |
0017-05-078 | Medina/ San Antonio |
IH 35 | Actual | $162,935 | 8 | TEXTURIZE SHOULDERS (MILLED) |
0849-02-032 | Medina/ San Antonio |
FM 471 | Actual | $1,725,996 | 1 | DRAINAGE IMPROVEMENT |
0906-32-031 | Midland/ Odessa |
VA | Actual | $4,048,948 | 9 | ENHANCEMENT - - ADD TRANSPORTATION WING |
0209-05-040 | Milam/ Bryan |
US 77 | Actual | $102,850 | 1 | MISCELLANEOUS CONSTRUCTION CONSISTING OF INSTALLING |
0006-01-083 | Mitchell/ Abilene |
IH 20 | Actual | $1,677,291 | 1 | PLANE EXIST PAVEMENT, ACP OVERLAY |
0908-21-011 | Mitchell/ Abilene |
CR | Actual | $148,223 | 6 | REPLACE BRIDGE AND APPROACHES |
0013-03-027 | Montague/ Wichita Falls |
US 81 | Actual | $2,176,557 | 1 | EXTENDING STRUCTURES AND ASPHALTIC CONCRETE PAVEMENT OVERLAY |
0013-05-049 | Montague/ Wichita Falls |
US 81 | Actual | $355,582 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS |
0044-06-067 | Montague/ Wichita Falls |
US 82 | Actual | $371,638 | 1 | ACP OVERLAY |
0675-08-087 | Montgomery/ Houston |
IH 45 | Actual | $1,516,232 | 8 | INSTALL MEDIAN BARRIER |
0912-37-142 | Montgomery/ Houston |
CR | Actual | $2,280,000 | 9 | WOODLANDS TOWN CENTER PEDESTRIAN CORRIDOR SOUTH SIDE - |
0912-37-143 | Montgomery/ Houston |
CS | Actual | $250,000 | 5 | PRELIMINARY ENGINEERING & ENVIRONMENTAL ANALYSIS |
0912-37-144 | Montgomery/ Houston |
CS | Actual | $1,150,000 | 5 | CONSTRUCT RESEARCH FOREST P & R EXPANSION |
0066-04-060 | Moore/ Amarillo |
US 287 | Actual | $5,915,390 | 1 | CONCRETE UPGRADE |
0066-05-060 | Moore/ Amarillo |
US 87 | Actual | $276,956 | 11 | TURN LANE AND RAMP |
0059-01-048 | Nacogdoches/ Lufkin |
SH 7 | Actual | $6,029,190 | 1 | REHABILITATE EXISTING MAINLANES & ADD 10 FT SHOULDERS |
0893-01-026 | Nacogdoches/ Lufkin |
FM 226 | Actual | $1,216,015 | 1 | WIDEN, LEVEL - UP, & SEAL |
0163-01-053 | Navarro/ Dallas |
SH 31 | Actual | $1,348,861 | 1 | MILL, SEALCOAT AND OVERLAY |
0305-01-030 | Newton/ Beaumont |
SH 87 | Actual | $2,413,448 | 1 | REHABILITATE EXISTING ROADWAY |
0373-01-037 | Nueces/ Corpus Christi |
US 77 | Actual | $23,691,410 | 7 | CONSTRUCT 4 LANE FREEWAY WITH FRONTAGE ROADS |
1088-03-012 | Nueces/ Corpus Christi |
FM 1889 | Actual | $6,436,564 | 1 | REHABILITATE ROADWAY & ADD SHOULDERS |
0028-14-095 | Orange/ Beaumont |
IH 10 | Actual | $1,522,992 | 1 | PLANE AND OVERLAY ROADWAY |
0063-12-012 | Panola/ Atlanta |
BU 59-D | Actual | $1,233,679 | 1 | FILL RUTS AND MICROSURFACE URBAN ROADWAY |
0171-03-056 | Parker/ Fort Worth |
SH 199 | Actual | $106,750 | 11 | INSTALLATION OF TRAFFIC SIGNALS |
0313-02-042 | Parker/ Fort Worth |
FM 51 | Actual | $847,378 | 1 | REPLACE BRIDGE AND APPROACHES |
0213-13-009 | Polk/ Lufkin |
FM 2457 | Actual | $3,655,359 | 1 | REHABILITATE EXISTING PAVEMENT AND ADD SHOULDERS |
0275-15-003 | Potter/ Amarillo |
FM 2575 | Actual | $286,199 | 1 | OVERLAY |
2635-01-026 | Potter/ Amarillo |
LP 335 | Actual | $3,898,439 | 1 | REHAB EXISTING ROADWAY |
0108-10-019 | Rains/ Paris |
SH 19 | Actual | $1,684,254 | 1 | MICROSURFACING |
1246-02-008 | Randall/ Amarillo |
FM 1062 | Actual | $3,978,875 | 1 | REHAB AND WIDEN EXISTING ROADWAY |
0554-02-015 | Real/ San Angelo |
FM 1120 | Actual | $1,157,637 | 1 | REPAIR FLOOD DAMAGED STREAM CROSSING |
0907-13-006 | Runnels/ San Angelo |
VA | Actual | $9,022 | 10 | LANDSCAPE ESTABLISHMENT - - COST SHARING |
0064-05-046 | Sabine/ Lufkin |
US 96 | Actual | $982,800 | 6 | REPLACE BRIDGE AND APPROACHES |
0304-03-021 | Sabine/ Lufkin |
SH 87 | Actual | $106,114 | 10 | LANDSCAPING |
1679-01-010 | Sabine/ Lufkin |
FM 276 | Actual | $294,292 | 8 | SAFETY TREAT FIXED OBJECTS |
0074-03-032 | San Patricio/ Corpus Christi |
IH 37 | Actual | $557,379 | 1 | LOWER ROADWAY |
0063-06-080 | Shelby/ Lufkin |
SH 87 | Actual | $1,251,789 | 1 | MILL & INLAY |
0424-01-040 | Smith/ Tyler |
SH 31 | Actual | $5,970,995 | 1 | OVERLAY |
0492-01-029 | Smith/ Tyler |
FM 14 | Actual | $1,790,645 | 1 | WIDEN ROADWAY |
0038-06-032 | Starr/ Pharr |
US 83 | Actual | $5,446,501 | 3B | UPGRADE AND WIDEN TO FOUR LANES DIVIDED URBAN WITH SHOULDERS |
0141-03-055 | Sutton/ San Angelo |
IH 10 | Actual | $4,477,410 | 1 | ASPHALTIC CONCRETE PAVEMENT OVERLAY |
0080-07-078 | Tarrant/ Fort Worth |
US 377 | Actual | $233,179 | 1 | INSTALL TRAFFIC SIGNAL |
0081-02-060 | Tarrant/ Fort Worth |
US 377 | Actual | $96,643 | 10 | PURCHASE LANDSCAPE MATERIAL |
0171-04-062 | Tarrant/ Fort Worth |
SH 199 | Actual | $106,750 | 11 | INSTALLATION OF TRAFFIC SIGNALS |
0172-01-035 | Tarrant/ Fort Worth |
BU 287P | Actual | $5,339,230 | 2 | RECONSTRUCT 2 LANE TO 4 LANE WITH CONTINUOUS LEFT TURN LANE |
0172-02-063 | Tarrant/ Fort Worth |
BU 287P | Actual | $103,999 | 1 | TRAFFIC SIGNALS |
0172-06-067 | Tarrant/ Fort Worth |
US 287 | Actual | $2,689,437 | 6 | REPLACE BRIDGES |
0902-00-086 | Tarrant/ Fort Worth |
VA | Actual | $484,636 | 1 | SMALL SIGN REPLACEMENT NON - INTERSTATE |
0902-00-088 | Tarrant/ Fort Worth |
VA | Actual | $646,537 | 1 | SMALL SIGN REPLACEMENT |
0902-48-385 | Tarrant/ Fort Worth |
CS | Actual | $324,551 | 6 | REPLACE BRIDGE - CLASS CULVERT |
0902-48-461 | Tarrant/ Fort Worth |
VA | Actual | $543,982 | 1 | SMALL SIGN REPLACEMENT |
0902-48-466 | Tarrant/ Fort Worth |
VA | Actual | $311,501 | 5 | SIGNAL COORDINATION - SPREAD SPECTRUM TECH. |
0902-48-470 | Tarrant/ Fort Worth |
VA | Actual | $95,800 | 5 | CLEAN VEHICLE PUBLIC FLEET IN EULESS |
0902-48-471 | Tarrant/ Fort Worth |
VA | Actual | $341,600 | 5 | CLEAN VEHICLE PUBLIC FLEET IN FORT WORTH |
0902-48-472 | Tarrant/ Fort Worth |
VA | Actual | $1,728,000 | 5 | CLEAN VEHICLE PUBLIC FLEET FWTA |
1068-02-111 | Tarrant/ Fort Worth |
IH 30 | Actual | $7,492,876 | 6 | RAMP REVISIONS |
2208-01-060 | Tarrant/ Fort Worth |
SP 303 | Actual | $116,561 | 11 | SAFETY LIGHTING |
0006-17-004 | Taylor/ Abilene |
BI 20-P | Actual | $318,606 | 11 | REALIGNMENT OF EXISTING INTERSECTION |
0699-01-041 | Taylor/ Abilene |
FM 89 | Actual | $3,212,583 | 1 | RESTORATION OF AN EXISTING ROADWAY |
0908-00-050 | Taylor/ Abilene |
VA | Actual | $410,882 | 1 | PAVEMENT MARKINGS |
1070-01-006 | Taylor/ Abilene |
FM 382 | Actual | $871,784 | 1 | REHABILITATE AND WIDEN EXIST ROADWAY |
0610-03-070 | Titus/ Atlanta |
IH 30 | Actual | $3,695,006 | 11 | WIDEN GRADE SEPARATION & APPROACHES TO IMPROVE SIGHT |
0015-13-244 | Travis/ Austin |
IH 35 | Actual | $3,427,658 | 1 | INSTALL CONDUIT & DETECTION AND FREEWAY TRAFFIC MGMT SYSTEM |
0015-13-288 | Travis/ Austin |
IH 35 | Actual | $429,087 | 1 | REMOVE US183 RAMP & EXT US290 / US183 RAMP |
0015-13-308 | Travis/ Austin |
IH 35 | Actual | $1,107,605 | 1 | REPAIR & BOLT DOWN ARMOR JOINTS |
0757-02-011 | Travis/ Austin |
FM 685 | Actual | $6,243,821 | 1 | UPGRADE TO 4 LANE DIVIDED URBAN ROADWAY WITH MEDIAN |
0914-00-156 | Travis/ Austin |
VA | Actual | $88,556 | 1 | REFURBISH GUIDE SIGNS |
0914-04-099 | Travis/ Austin |
VA | Actual | $242,948 | 7 | CREATE BIKE TRAIL |
1018-02-011 | Upshur/ Atlanta |
FM 555 | Actual | $3,079,439 | 6 | REPLACE 3 BRIDGES AND APPROACHES ON 2 LANE HIGHWAY |
0370-04-025 | Victoria/ Yoakum |
US 77 | Actual | $12,073,055 | 4 | ADD 2 LANES FOR 4 LANE DIVIDED HWY |
0675-06-079 | Walker/ Bryan |
IH 45 | Actual | $820,271 | 1 | CONSTRUCT NEW SOUTHBOUND ENTRANCE RAMP FOR TDCJ |
0271-04-076 | Waller/ Houston |
IH 10 | Actual | $1,174,809 | 1 | PLANING, ACP REHAB AND OVERLAY AND PAVEMENT MARKINGS |
0271-09-014 | Waller/ Houston |
US 90 | Actual | $224,195 | 5 | INSTALL ARTERIAL TRAFFIC MANAGEMENT SYSTEM |
0409-03-009 | Waller/ Houston |
FM 1488 | Actual | $824,012 | 1 | BASE REPAIR, PLANING, SURF REHAB, ACP OVERLAY AND |
0114-10-085 | Washington/ Bryan |
US 290 | Actual | $1,479,331 | 1 | OVERLAY CONSISTING OF A ONE COURSE SURFACE TREATMENT, AN HMA |
1261-02-021 | Wharton/ Yoakum |
FM 1299 | Actual | $1,155,766 | 1 | RESTORE ROADWAY |
0043-09-102 | Wichita/ Wichita Falls |
IH 44 | Actual | $7,104,214 | 1 | REHABILITATION OF EXISTING ROAD |
0137-03-035 | Wichita/ Wichita Falls |
SH 25 | Actual | $1,921,817 | 6 | REPLACE BRIDGE AND APPROACHES |
1587-01-015 | Willacy/ Pharr |
FM 1761 | Actual | $3,014,073 | 1 | RECONSTRUCT AND ADD SHOULDERS |
Top... Back... Letting Schedule Doing Business with TxDOT |