Letting Schedule for Beaumont District (FY 2009)
Letting Schedule for Beaumont District (FY 2009) | ||||
Last Update: Monday, November 9, 2009 |
Beaumont District (FY 2009) |
Chambers | Hardin | Jasper | Jefferson | Liberty | Newton | Orange | Tyler | ||||||
Chambers County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0242-03-068 | SH 61 | Actual | APR 2009 | $814,457 | 1 | OVERLAY EXISTING ROADWAY & SEAL COAT |
0389-02-040 | SH 146 | Actual | MAY 2009 | $212,848 | 11 | ADD RIGHT TURN LANE |
0508-03-075 | IH 10 | Actual | AUG 2009 | $13,771,771 | 9 | CONSTRUCT TOURIST AND VISITOR CENTER, PARKING LOT AND |
0508-03-088 | SH 73 | Actual | JAN 2009 | $1,275,268 | 1 | BASE REPAIR AND OVERLAY |
0508-03-090 | IH 10 | Actual | APR 2009 | $813,244 | 1 | SPOT LEVEL UP & OVERLAY |
Hardin County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0784-01-043 | FM 418 | Actual | APR 2009 | $383,159 | 1 | OVERLAY EXISTING ROADWAY |
0811-01-010 | FM 420 | Actual | APR 2009 | $657,758 | 1 | RESTORE EXISTING ROADWAY |
1096-01-054 | FM 770 | Actual | MAR 2009 | $1,750,384 | 1 | OVERLAY EXISTING ROADWAY |
Jasper County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0064-07-038 | US 96 | Actual | DEC 2008 | $977,618 | 11 | UPGRADE BRIDGE RAIL |
0064-07-039 | US 96 | Actual | MAR 2009 | $1,533,636 | 1 | MILL AND OVERLAY EXISTING ROADWAY |
0064-08-051 | US 96 | Actual | MAR 2009 | $2,938,391 | 1 | OVERLAY EXISTING ROADWAY |
0784-02-010 | FM 1131 | Actual | MAY 2009 | $1,104,127 | 1 | RESTORE & OVERLAY EXISTING ROADWAY |
0784-03-014 | FM 1131 | Actual | APR 2009 | $2,569,366 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
Jefferson County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0028-06-069 | US 90 | Actual | DEC 2008 | $10,326,586 | 1 | SEAL COAT |
0028-07-051 | US 90 | Actual | NOV 2008 | $1,408,453 | 10 | LANDSCAPING AND OTHER SCENIC BEAUTIFICATION |
0508-04-152 | SH 73 | Actual | MAR 2009 | $294,559 | 5 | INSTALL TRAFFIC SIGNALS |
0508-04-154 | SH 73 | Actual | APR 2009 | $4,097,311 | 1 | OVERLAY EXISTING ROADWAY AND BASE REPAIRS |
0667-01-108 | SH 347 | Actual | SEP 2008 | $878,738 | 6 | REPLACE BRIDGE AND APPROACHES |
0667-01-110 | SH 347 | Actual | APR 2009 | $3,516,358 | 1 | OVERLAY EXISTING ROADWAY |
0920-00-072 | VA | Actual | JUN 2009 | $722,870 | 5 | INSTALL AN INTELLIGENT TRANSPORTATION SYSTEM |
0920-00-076 | VA | Actual | DEC 2008 | $900,000 | 5 | PROVIDE A PEAK - HOUR MOTORIST ASSISTANCE SERVICE ON MAJOR |
0920-00-088 | VA | Actual | DEC 2008 | $525,000 | 5 | AREAWIDE RIDESHARE PROGRAM |
0920-00-089 | VA | Actual | DEC 2008 | $450,000 | 5 | IMPLEMENT AN OZONE ALERT PROGRAM (OFF - SYSTEM) |
0920-00-090 | VA | Actual | MAR 2009 | $705,952 | 1 | STRIPING |
Liberty County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0389-01-036 | SH 146 | Actual | APR 2009 | $11,450,611 | 4 | WIDEN ROADWAY FROM 2 LANES TO 4 LANES |
0593-01-106 | SH 321 | Actual | APR 2009 | $452,456 | 8 | ADD LEFT TURN LANE |
Newton County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0304-08-012 | FM 1415 | Actual | APR 2009 | $1,043,652 | 1 | UPGRADE BRIDGE RAIL |
0920-06-025 | CR | Actual | OCT 2008 | $320,373 | 6 | REPLACE BRIDGE AND APPROACHES |
0920-06-027 | CR | Actual | JUN 2009 | $242,030 | 6 | REPLACE BRIDGE AND APPROACHES |
0920-06-028 | CR | Actual | AUG 2009 | $271,656 | 6 | REPLACE BRIDGE AND APPROACHES |
Orange County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0710-02-059 | FM 105 | Actual | AUG 2009 | $304,485 | 5 | OVERLAY EXISTING ROADWAY |
0784-05-034 | FM 1132 | Actual | APR 2009 | $525,420 | 1 | MILL & OVERLAY EXISTING ROADWAY, SEAL COAT |
0882-02-052 | FM 1006 | Actual | SEP 2008 | $1,245,232 | 1 | REHABILITATE EXISTING ROADWAY |
0920-30-055 | CS | Actual | FEB 2009 | $2,247,749 | 5 | IMPROVE INTERSECTIONS |
1286-01-015 | FM 1078 | Actual | MAY 2009 | $874,258 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
Tyler County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0200-07-049 | US 69 | Actual | APR 2009 | $2,393,603 | 1 | OVERLAY EXISTING ROADWAY |
|
|