Letting Schedule for Lubbock District (FY 2010)
| Letting Schedule for Lubbock District (FY 2010) | ||||
| Last Update: Tuesday, November 2, 2010 | 
| Lubbock District (FY 2010) | 
| Crosby | Hale | Hockley | Lamb | Lubbock | Lynn | ||||||
Crosby County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
|---|---|---|---|---|---|---|
| 0453-04-021 | SH 207 | Actual | SEP 2009 | $1,022,626 | 1 | SEAL COAT | 
Hale County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0067-09-031 | BI 27-U | Actual | NOV 2009 | $10,384,468 | 1 | SEAL COAT | 
| 0905-12-036 | CS | Actual | SEP 2009 | $365,085 | 8 | CONSTRUCT SIDEWALKS - SAFE ROUTES TO SCHOOL PROJECT | 
Hockley County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0227-05-019 | US 385 | Actual | APR 2010 | $1,268,452 | 11 | MISCELLANEOUS CONSTRUCTION | 
| 3126-04-004 | FM 1585 | Actual | OCT 2009 | $687,169 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | 
Lamb County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0563-03-011 | FM 54 | Actual | AUG 2010 | $1,528,665 | 8 | HAZARD ELIMINATION SAFETY | 
| 1291-02-012 | FM 1055 | Actual | AUG 2010 | $1,350,742 | 1 | REHABILITATION OF EXISTING ROAD | 
Lubbock County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0053-01-090 | US 82 | Actual | SEP 2009 | $47,756,837 | 11 | CONVERT NON - FREEWAY TO FREEWAY | 
| 0053-01-115 | FM 835 | Actual | FEB 2010 | $3,387,881 | 1 | SEAL COAT | 
| 0068-01-064 | US 87 | Actual | JUL 2010 | $567,295 | 8 | HAZARDOUS ELIMINATION AND SAFETY | 
| 0130-05-069 | US 62 | Actual | JUL 2010 | $9,592,014 | 1 | REHABILITATION OF EXISTING ROAD | 
| 0783-01-093 | LP 289 | Actual | JUN 2010 | $1,561,338 | 1 | OVERLAY | 
| 0783-02-065 | LP 289 | Actual | JAN 2010 | $17,056,766 | 7 | WIDEN FREEWAY TO 6 MAIN LANES | 
| 0905-00-048 | VA | Actual | JAN 2010 | $771,313 | 10 | CONSTRUCTION CURB RAMPS | 
| 0905-00-053 | VA | Actual | MAR 2010 | $899,635 | 1 | FY 2010 DISTRICT WIDE STRIPING | 
| 0933-01-033 | FM 835 | Actual | FEB 2010 | $417,993 | 8 | HAZARD ELIMINATION SAFETY | 
| 1344-02-021 | FM 1730 | Actual | AUG 2010 | $1,325,000 | 1 | REHABILITATION OF EXISTING ROADWAY | 
| 1867-01-023 | FM 1264 | Actual | JUN 2010 | $118,261 | 8 | HAZARD ELIMINATION SAFETY | 
Lynn County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 2184-01-008 | FM 179 | Actual | AUG 2010 | $1,096,474 | 1 | REHABILITATION OF EXISTING ROAD | 
  | 
|   |